Technical Specifications Summary
This is a technical specifications document for water system improvements at the Kansas Department of Wildlife and Parks (KDWP) Operations Headquarters in Pratt, Kansas, prepared by Schwab Eaton (civil engineer) and Orazem & Scalora Engineering, P.A. (MEP engineer), with a project number of 24.1.0274 and delivery date of February 2026. The scope of work includes 22 base bid items and 3 bid alternates: mobilization and demobilization (lump sum), demolition and removal (lump sum), earthwork (lump sum), concrete retaining wall (112 linear feet at unit price), PWS well extension (lump sum), ADA concrete sidewalk with rock base (lump sum), HDPE service lines in 3-inch, 2-inch, and 1-inch sizes (unit prices per linear foot), gate valves in 3-inch and 2-inch sizes (unit prices each), connections to existing water utility (unit price each), interior domestic water piping (lump sum), interior and exterior electrical improvements (lump sum each), 12-inch CMP culvert (unit price), 4-inch floor drain with French drain (unit price), seeding and mulching with erosion control (lump sum), and construction staking (lump sum). The three bid alternates include a pre-cast concrete chlorination building, a fiberglass chlorination building, and removal and replacement of the well pump, all at lump sum prices. The specifications address general requirements including measurement and payment procedures, RFI and ASI protocols, submittals, contract closeout procedures, site preparation, cast-in-place concrete work, plumbing systems, and electrical installations.
The specifications establish detailed requirements for materials, products, and execution across all divisions of work. Payment for unit price items is based on actual quantities verified by the engineer multiplied by the contracted unit price, while lump sum items are paid upon completion of all specified work. Mobilization and demobilization payments are phased at 50 percent when work reaches 10 percent of the original contract amount and 100 percent at 50 percent contract completion. All materials must comply with applicable standards including ASTM specifications for concrete, reinforcement, plumbing fixtures, and electrical components, and the work must conform to the 2021 International Plumbing Code, National Electrical Code, and all applicable local regulations. The contractor is responsible for obtaining all required permits and inspection fees, providing a certified independent testing agency for concrete testing, submitting shop drawings and product data in PDF format with two hard copies to the owner, maintaining project record documents marked as "As-Built," and furnishing a one-year warranty on all work unless longer manufacturer warranties apply to incorporated materials and equipment. Final payment requires submission of notarized lien waivers from the contractor and all subcontractors and suppliers, a notarized affidavit of payment of all debts, and written consent from the contractor's surety.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TECHNICAL SPECIFICATIONS
WATER SYSTEM IMPROVEMENTS
KDWP OPERATIONS HEADQUARTERS
PRATT, KANSAS
FEBRUARY 2026
SE #24.1.0274
Schwab Eaton Project No: 24.1.0274 WATER SYSTEM IMPROVEMENTS February 2026 KDWP Operations Headquarters – Pratt, KS
Schwab Eaton SEALS PAGE
SEALS PAGE
Civil Engineer Schwab Eaton 5410 Ledge Stone Drive, Suite 100 Manhattan, KS 66503 785-539-4687 Responsible for Divisions: 01 0000, 02 0000, 03 0000, 31 0000, 32 0000, 33 0000, 49 0000
MEP Engineer Orazem & Scalora Engineering, P.A.
2321 Anderson Ave.
Manhattan, KS 66502 785-537-2553 Responsible for Divisions: 22 0000, 26 0000
TABLE OF CONTENTS
Schwab Eaton TABLE OF CONTENTS 1
TABLE OF CONTENTS
DIVISION 01 – GENERAL REQUIREMENTS
01 2000 – MEASUREMENT AND PAYMENT
01 2600 – RFI, ASI AND CHANGE ORDER PROCEDURES
01 3300 – SUBMITTALS
01 7000 – CONTRACT CLOSEOUT
DIVISION 02 – EXISTING CONDITIONS
02 4105 – SITE PREPARATION
DIVISION 03 – CONCRETE
03 3000 – CAST-IN-PLACE CONCRETE
DIVISION 22 – PLUMBING
22 0000 – PLUMBING
DIVISION 26 – ELECTRICAL
26 0100 – BASIC ELECTRICAL REQUIREMENTS
26 1600 – POWER DISTRIBUTION EQUIPMENT
26 1700 – MOTOR AND CIRCUIT DISCONNECTS
26 5000 – LIGHTING
DIVISION 31 – EARTHWORK
31 2200 – EARTHWORK
31 2500 – EROSION AND SEDIMENTATION CONTROL
31 7000 – BORING AND TUNNELING
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 1100 – AGGREGATE PAVEMENT BASE
32 1300 – RIGID PAVING
32 1373 – RIGID PAVEMENT JOINT PROTECTION
32 9200 – SEEDING
DIVISION 33 – UTILITIES
33 1000 – WATER UTILITIES
33 1113 – WELL CONSTRUCTION
33 1136 – WELL PUMPS AND EQUIPMENT
33 1300 – CHLORINATION BUILDING AND EQUIPMENT
33 1419 – VALVES, HYDRANTS AND METERS
DIVISION 49 - MISCELLANEOUS
49 9999 – MISCELLANEOUS ITEMS OF WORK
DIVISION 01: GENERAL REQUIREMENTS
01 2000 – MEASUREMENT AND PAYMENT
Schwab Eaton MEASUREMENT AND PAYMENT 01 2000 - 1
SECTION 01 2000 – MEASUREMENT AND PAYMENT
PART 1 - GENERAL
1.1 SECTION INCLUDES:
A. Measurement and payment criteria applicable to portions of the Work performed under a unit price payment method. Progress payment for partial construction and/or performance of lump sum items shall be based on the Schedule of Values submitted by the Contractor at the beginning of construction.
B. Defect assessment and non-payment for rejected work.
1.2 AUTHORITY:
A. If measurement methods are delineated in the individual specification sections, said methods are intended to complement the criteria of this section. In the event of conflict, the requirements of this section shall govern.
B. Take all measurements and compute quantities. The Engineer will verify measurements and quantities.
C. Assist by providing necessary equipment, workers, and survey personnel as required.
1.3 UNIT QUANTITIES SPECIFIED:
A. Quantities and measurements indicated in the Bid Form are for bidding and contract purposes only. Quantities and measurements supplied or placed in the Work and verified by the Engineer shall determine payment.
B. If the actual Work requires more or fewer quantities than those quantities indicated, provide the required quantities at the unit sum/prices contracted. However, if an increase in quantities is anticipated, obtain authorization of the Engineer prior to performing said additional Work.
1.4 MEASUREMENT OF QUANTITIES:
A. Measurement Devices:
1. Weigh Scales: Inspected, tested, and certified by the Kansas Department of Transportation within the past year.
2. Platform Scales: Of sufficient size and capacity to accommodate the conveying vehicle.
3. Metering Devices: Inspected, tested, and certified by the Kansas Department of
Transportation within the past year.
B. Measurement by Weight: Concrete reinforcing steel, rolled or formed steel or other metal shapes will be measured by handbook weights. Welded assemblies will be measured by handbook or scale weight.
C. Measurement by Volume: Measured by cubic dimension using mean length, width and height or thickness.
D. Measurement by Area: Measured by square dimension using mean length and width or radius.
E. Linear Measurement: Measured by linear dimension, at the item centerline or mean chord.
F. Stipulated Sum/Price Measurement: Items measured by weight, volume, area, or linear means
Schwab Eaton MEASUREMENT AND PAYMENT 01 2000 - 2 or combination, as appropriate, as a completed item or unit of the Work.
1.5 PAYMENT:
A. Payment includes: Full compensation for all required labor, products, tools, equipment, plant, transportation, services, and incidentals; erection, application, or installation of an item of the Work; overhead and profit.
B. Final payment for Work governed by unit prices will be made on the basis of the actual measurements and quantities accepted by the Engineer multiplied by the unit sum/price for Work which is incorporated in or made necessary by the Work.
1.6 SUBSIDIARY WORK:
A. Work or items specified to be constructed, installed, provided, etc. for which no Bid Item or manner of payment has been specified shall be considered as SUBSIDIARY or incidental to other Bid Items.
B. Work specifically identified in the Drawings or Specifications as "subsidiary" to particular Bid
Item(s) or portion(s) of Work, shall be so considered.
1.7 DEFECT ASSESSMENT:
A. Replace the Work, or portions of the Work, not conforming to specified requirements.
B. If, in the opinion of the Engineer, it is not practical to remove and replace the Work, the Engineer will direct one of the following remedies:
1. The defective Work may remain, but the unit sum/price will be adjusted to a new sum/price percent at the discretion of the Engineer.
2. The defective Work will be partially repaired to the instructions of the Engineer, and the unit sum/price will be adjusted to a new sum/price at the discretion of the Engineer.
3. The individual Specification Sections may modify these options or may identify a specific formula or percentage sum/price reduction.
1.8 NON-PAYMENT FOR REJECTED PRODUCTS:
A. Payment will not be made for any of the following:
1. Products wasted or disposed of in a manner that is not acceptable.
2. Products determined as unacceptable before or after placement.
3. Products not completely unloaded from the transporting vehicle.
4. Products placed beyond the lines and levels of the required Work.
5. Products remaining on hand after completion of the Work.
6. Loading, hauling, and disposing of rejected Products.
1.9 BASE BID ITEM DESCRIPTIONS:
A. The construction of this project shall be measured and paid in accordance with the Bid Form and the Base Bid Item descriptions below:
1. Mobilization and Demobilization: This item shall be paid for at the contract lump sum price for "Mobilization and Demobilization". This price shall include all labor, tools, equipment, and other incidentals necessary to complete the work. The term "Original Contract Amount" shall be construed to mean the total dollar value of the Original Contract, including all bid items shown in the Contract. Partial payments may be made
Schwab Eaton MEASUREMENT AND PAYMENT 01 2000 - 3 as follows:
a. When work amounting to 10 percent of the Original Contract Amount has been completed, 50 percent of the Contract amount for the item of mobilization and demobilization will be paid.
b. When work amounting to 50 percent of the Original Contract Amount has been completed, 100 percent of the Contract amount for the item for mobilization and demobilization will be paid.
2. Demolition and Removal: This item shall be paid for at the lump sum price bid for
“Demolition and Removal”, which price shall include the demolition/removal of existing pavement (concrete/asphalt), concrete curbs, and underlying aggregate base materials, including saw cutting, offsite disposal, capping, and any grading necessary to facilitate construction. The unit price shall also include removing the specified valve risers/vaults, disconnecting existing water utilities, and cutting and capping existing piping, in addition to all trenching and excavation (regardless of the nature of material encountered), sheeting and bracing, backfilling, handling, hauling, and all labor, equipment and materials necessary to complete the work.
3. Earthwork: This item shall be paid for at the lump sum price bid for “Earthwork”, which price shall include all materials, equipment, and labor necessary to construct the desired improvements. The work shall include all clearing and grubbing (tree and root removal and offsite disposal, vegetation stripping, etc.), excavation, hauling (importing offsite materials), embankment, dewatering, subgrade preparation, and other ancillary items necessary to complete the earthwork as shown on the drawings and specified herein.
4. Concrete Retaining Wall: This item shall be paid for at the contract unit price bid per linear foot of “Concrete Retaining Wall”, complete in place, which price shall include all formwork, steel reinforcement, concrete, geotextile fabric, granular backfill, weep holes, third party concrete testing and all labor, equipment, materials, appurtenances, and other incidentals associated with the concrete retaining wall.
5. PWS Well Extension: This item shall be paid for at the contract lump sum price bid for
“PWS Well Extension”, which price shall include the cost of removing and inspecting the existing well pump; furnishing and installing the well casing extension, new drop pipe, wellhead/well seal, vent, drawdown tubing, and associated appurtenances; and installing the existing pump (as applicable), complete with fittings, capping, sealing, and disinfecting; in addition to furnishing all labor, materials, and equipment necessary to complete the Work
6. 6” Concrete Sidewalk (ADA) (with 4” AB-3 Rock Base): This item shall be paid for at the contract lump sum price bid for “6” Concrete Sidewalk (ADA) (with 4” AB-3 Rock Base)”, which price shall include which price shall include any saw cutting and pavement removal deemed necessary; aggregate pavement base installation; formwork, steel reinforcement, concrete, third party concrete testing, jointing and joint sealants; and all labor, equipment, materials, appurtenances, and other incidentals associated with the cast-in-place concrete pavement.
7. 3” HDPE, SDR 9 Service Line: This item shall be paid for at the contract unit price bid per linear foot of “3” HDPE SDR 9 Service Line”, complete in place, which price shall include the cost of all trenching, excavation, and boring, regardless of the nature of the material encountered, sheeting, and bracing, backfilling, compaction of the backfill, site restoration, handling, hauling, and installing the pipe, and all labor, tools, and equipment necessary to complete the Work.
Schwab Eaton MEASUREMENT AND PAYMENT 01 2000 - 4
8. 2” HDPE, SDR 9 Service Line: This item shall be paid for at the contract unit price bid per linear foot of “2” HDPE SDR 9 Service Line”, complete in place, which price shall include the cost of all trenching, excavation, and boring, regardless of the nature of the material encountered, sheeting, and bracing, backfilling, compaction of the backfill, site
9. 1” HDPE, SDR 9 Service Line: This item shall be paid for at the contract unit price bid per linear foot of “1” HDPE SDR 9 Service Line”, complete in place, which price shall include the cost of all trenching, excavation, and boring, regardless of the nature of the material encountered, sheeting, and bracing, backfilling, compaction of the backfill, site
10. 3” MJ Gate Valve: This item shall be paid for at the contract unit price bid for each
“3” M.J. Gate Valve”, which price shall include furnishing and installing the valve, valve box, restrained joints, excavation and backfill, concrete work, and all materials, labor, equipment, and other incidentals necessary to complete each installation.
11. 2” MJ Gate Valve: This item shall be paid for at the contract unit price bid for each
“2” M.J. Gate Valve”, which price shall include furnishing and installing the valve, valve box, restrained joints, excavation and backfill, concrete work, and all materials, labor, equipment, and other incidentals necessary to complete each installation.
12. Connect to Existing Water Utility: This item shall be paid for at the contract unit price for each “Connect to Existing Water Utility”, which price shall include the cost of locating the existing infrastructure, furnishing and installing the necessary pipe and fittings, in addition to all trenching, and excavation regardless of the nature of material encountered, concrete thrust blocking, sheeting and bracing, backfilling, handling, hauling, and all labor, equipment and materials necessary to complete the work.
13. Interior Domestic Water Piping: This item shall be paid for at the contract lump sum price bid for “Interior Domestic Water Piping”, which price shall include all materials, including, but not limited to, all piping, fittings, valves, sleeves, insulation, and related appurtenances, in addition to all labor and equipment necessary to complete the internal piping improvements and provide a complete, working system.
14. Interior Electrical Improvements: This item shall be paid for at the contract lump sum price bid for “Interior Electrical Improvements”, which price shall include all materials, labor, and equipment necessary to complete the internal electrical improvements and provide a complete, working system.
15. Exterior Electrical Improvements: This item shall be paid for at the contract lump sum price bid for “Exterior Electrical Improvements”, which price shall include all materials, labor, and equipment associated with providing electrical service to the chlorination building and water well, and as necessary to complete the installation and make the system ready for service.
16. 12” CMP Culvert: This item shall be paid for at the contract unit price bid for “12” CMP
Culvert”, which price shall include furnishing the pipe, installation and field connections, excavating, backfilling, miscellaneous fittings, and all materials, labor, equipment, and appurtenances necessary to complete the work.
17. 4” Floor Drain with French Drain: This item shall be paid for at the contract unit price bid for “4” Floor Drain with French Drain”, which price shall include furnishing the piping and drainage materials, installation and field connections, excavating, backfilling, miscellaneous fittings, and all materials, labor, equipment, and appurtenances necessary to complete the work.
Schwab Eaton MEASUREMENT AND PAYMENT 01 2000 - 5
18. Seeding, Mulching, and Erosion Control: This item shall be paid for at the lump sum contract price bid for “Seeding, Mulching, and Erosion Control”, which price shall include all costs associated with installing, maintaining and removing erosion controls (BMPs);
seedbed preparation, temporary seeding (as applicable), permanent seeding and mulching; and all labor, tools, and equipment necessary to perform the work.
19. Construction Staking: This item shall be paid for at the lump sum contract price bid for
“Construction Staking”, which price shall include all costs associated with survey-grade staking and layout.
20. Pre-Cast Concrete Chlorination Building (complete) (BID ALTERNATE 1): This item shall be paid for at the lump sum price bid for the “Pre-Cast Concrete Chlorination Building”, which price shall include the procurement and installation of the new pre-cast concrete building, including interior firring and insulation; construction of the associated concrete footings/foundation, including formwork, steel reinforcement, concrete, and third-party concrete testing; and installation of the sand backfill. Such price shall also include furnishing and installing the internal infrastructure shown on the plans (including aboveground piping, buried piping to five feet outside of the building, valves, fittings, meter, chlorination equipment, lighting, electric heater, electrical wiring, etc.), and all materials, labor, and equipment necessary to complete the installation and make the unit ready for service.
21. Fiberglass Chlorination Building (complete) (BID ALTERNATE 2): This item shall be paid for at the lump sum price bid for the “Fiberglass Chlorination Building”, which price shall include the procurement and installation of the new fiberglass building, including interior firring and insulation; design and construction of the associated concrete footings/foundation, including formwork, steel reinforcement, concrete, and third-party concrete testing; and installation of the sand backfill. Such price shall also include furnishing and installing the internal infrastructure shown on the plans (including aboveground piping, buried piping to five feet outside of the building, valves, fittings, meter, chlorination equipment, lighting, electric heater, electrical wiring, etc.), and all materials, labor, and equipment necessary to complete the installation and make the unit ready for service.
22. Remove and Replace Well Pump (BID ALTERNATE 3): This item shall be paid for at the lump sum price bid for “Remove and Replace Well Pump” which price shall include procuring and installing the new submersible pump/motor concurrent with the well improvements, including all labor, materials, and equipment necessary to complete the installation.
PART 2 – PRODUCTS
Not Used
PART 3 – EXECUTION
END OF SECTION 01 2000
01 2600 – RFI, ASI AND CHANGE ORDER
PROCEDURES
Schwab Eaton RFI, ASI & CHANGE ORDER PROCEDURES 01 2600 - 1
SECTION 01 2600 – RFI, ASI & CHANGE ORDER PROCEDURES
A. RFI Procedures.
B. ASI Procedures.
C. Submittals.
D. Documentation of change in Contract Sum/Price and Contract Time.
E. Change procedures.
F. Construction Change Authorization.
G. Change order description.
H. Execution of change orders.
I. Correlation of Contractor submittals.
1.2 R.F.I. PROCEDURES:
A. The Contractor may submit to the Engineer a Request for Information (RFI) where the Engineer’s clarification or interpretation of the Contract Documents is warranted to enable the Contractor to effectively and accurately perform his Work in a manner ultimately satisfactory to the Engineer. If a subcontractor encounters the need to submit an RFI, he shall submit it to the Contractor who will forward such to the Engineer.
B. Each RFI shall include the following:
1. Numerical identification of the respective RFI.
2. Date of issuance.
3. Name of individual from whom the request originated.
4. Identify the subject matter.
5. Brief description of the clarification, interpretation or information required. Identify the specification section, page and paragraph, drawing name, sheet number or other description referencing the Contract Documents.
6. Note whether or not a change order will likely be required.
7. Indicate a date by which a response is necessary to avoid an undue hardship on the
Contractor.
8. Provide appropriate space for the Engineer to respond.
C. Issuance of valid RFIs is encouraged; however, frivolous or unnecessary RFIs will not be tolerated. The Contractor shall exercise due diligence to locate the required information within the Contract Documents prior to issuing an RFI. If, in the opinion of the Engineer, the Contractor has exhibited a pattern of issuing RFIs when such information was readily apparent from reasonable observation of field conditions or a review of the Contract Documents, or are reasonably inferable therefrom, the Contractor shall be responsible to the Owner for all reasonable costs charged by the Engineer to the Owner for time spent responding to such requests.
Schwab Eaton RFI, ASI & CHANGE ORDER PROCEDURES 01 2600 - 2
1.3 A.S.I. PROCEDURES:
A. The Engineer may issue a supplemental instruction (ASI) to the Contractor if the Engineer discovers a need to clarify or modify a requirement of the Contract Documents. The ASI will include the following:
1. Numerical identification of the respective ASI.
2. Date of issuance.
3. Name of individual from whom the ASI originated.
4. Identify the subject matter.
5. Brief description of the supplemental instruction. The specification section, page and paragraph, drawing name, sheet number or other description referencing the Contract Documents will be identified.
6. Space for the Contractor to acknowledge receipt and note whether or not a change order appears warranted.
B. The Contractor shall immediately advise the Engineer if a change order will be warranted as a result of the ASI and justification for such. If the Engineer concurs he may issue a proposal request and commence the change order process as described elsewhere in the Specification Section.
1.4 SUBMITTALS:
A. Submit name of the individual authorized to receive change documents and be responsible for informing others in Contractor's employ or Subcontractors of changes to the Work.
1.5 DOCUMENTATION OF CHANGE IN CONTRACT SUM/PRICE AND CONTRACT TIME:
A. Maintain detailed records of work done on a time and material basis. Provide full information required for evaluation of proposed changes, and to substantiate costs of changes in the Work.
B. Document each quotation for a change in cost or time with sufficient data to allow evaluation of the quotation.
1.6 CHANGE PROCEDURES:
A. The Engineer will advise of minor changes in the Work not involving an adjustment to Contract Sum/Price or Contract Time.
B. The Engineer may issue a Proposal Request which includes a detailed description of a proposed change with supplementary or revised Drawings and Specifications, and any change in Contract Time for executing the change.
C. The Contractor may propose a change by submitting a request for change to the Engineer, describing the proposed change and its full effect on the Work, with a statement describing the reason for the change, and the effect on the Contract Sum/Price and Contract Time with full documentation.
1.7 CONSTRUCTION CHANGE AUTHORIZATION:
A. The Engineer may issue a document, signed by the Owner, instructing the Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.
B. The document will describe changes in the Work and will designate method of determining any change in Contract Sum/Price and/or Contract Time.
Schwab Eaton RFI, ASI & CHANGE ORDER PROCEDURES 01 2600 - 3
C. Promptly execute the change in Work.
1.8 CHANGE ORDER DESCRIPTION:
A. Based on Proposal Request and Contractor's price quotation or Contractor's request for a Change Order as accepted by the Engineer.
B. When pre-determined unit prices are included in the original Bid Form, the Change Order will be executed on the respective fixed unit price for the change in quantities.
1.9 EXECUTION OF CHANGE ORDERS:
A. Execution of Change Orders: Engineer will issue Change Orders for signatures of parties as provided in the Conditions of the Contract.
1.10 CORRELATION OF CONTRACTOR SUBMITTALS:
A. Promptly revise Schedule of Values and Application for Payment forms to record each authorized Change Order as a separate line item and adjust the Contract Sum/Price.
B. Promptly revise progress schedules to reflect any change in Contract Time, revise sub-schedules to adjust time for other items of work affected by the change and resubmit.
C. Promptly enter changes in Project Record Documents.
PART 2 - PRODUCTS
PART 3 - EXECUTION
END OF SECTION 01 2600
01 3300 – SUBMITTALS
Schwab Eaton SUBMITTALS 01 3300 - 1
SECTION 01 3300 - SUBMITTALS
A. Submittal procedures.
B. Construction progress schedules.
C. Proposed subcontractors, suppliers, and products list.
D. Shop drawings and product data.
E. Manufacturers' instructions.
F. Manufacturers' certificates.
1.2 SUBMITTAL PROCEDURES:
A. Transmit each submittal with a Letter of Transmittal.
B. Identify Project, Contractor, subcontractor or supplier and submittal sequence number; pertinent
Drawing sheet and detail number(s), and Specification Section number, as appropriate.
A. Submittals shall be submitted to Engineer in PDF format. The Contractor shall provide two (2) hard copies of all Approved Submittals to the Owner. Provide in electronic format on a flash drive as well.
B. Apply Contractor's stamp to each submittal copy, signed or initialed certifying that review, verification of Products required, field dimensions, adjacent construction Work, and coordination of information, is in accordance with the requirements of the Work and Contract Documents.
C. Schedule submittals to expedite the Project and deliver to Engineer. Coordinate submission of related items.
D. Identify variations from Contract Documents and product or system limitations which may be detrimental to successful performance of the completed Work.
E. Provide space for Contractor and Engineer review stamps.
F. Revise and resubmit submittals as required, identify all changes made since previous submittal.
G. Distribute copies of reviewed submittals to concerned parties. Instruct parties to promptly report any inability to comply with provisions.
1.3 CONSTRUCTION PROGRESS SCHEDULES:
A. Submit initial progress schedule in duplicate within 10 days after date of Owner-Contractor Agreement for Engineer review.
B. Revise and resubmit as required.
C. Submit revised schedules with each Application for Payment, identifying changes since previous version.
Schwab Eaton SUBMITTALS 01 3300 - 2
D. Submit a horizontal bar chart with separate line for each major section of Work or operation, identifying first work day of each week.
E. Indicate estimated percentage of completion for each item of Work at each submission.
F. Indicate submittal dates required for shop drawings, product data, samples, and product delivery dates, including those furnished by Owner.
1.4 PROPOSED SUBCONTRACTORS, SUPPLIERS, AND PRODUCTS LIST:
A. Within 10 days after date of Owner-Contractor Agreement, submit complete list of subcontractors, principal suppliers, and major products proposed for use, with name of manufacturer, trade name, and model number of each product.
B. For Products specified only by reference standards, give manufacturer, trade name, model or catalog designation, and reference standards.
1.5 SHOP DRAWINGS AND PRODUCT DATA:
A. Submit the number of copies which Contractor requires, plus three copies which will be retained by Engineer.
B. After review, distribute in accordance with Article on Procedures above and for Record
Documents described in Section 01700 - Contract Closeout.
1.6 MANUFACTURER'S INSTRUCTIONS:
A. When specified in individual Specification Sections, submit manufacturers' printed instructions for delivery, storage, assembly, installation, start-up, adjusting, and finishing, in quantities specified for Product Data.
B. Identify conflicts between manufacturers' instructions and Contract Documents.
1.7 MANUFACTURER'S CERTIFICATES:
A. When specified in individual Specification Sections, submit manufacturers' certificate to Engineer for review, in quantities specified for Product Data.
B. Indicate that material or product conforms to or exceeds specified requirements. Submit supporting reference date, affidavits, and certifications as appropriate.
C. Certificates may be recent or previous test results on material or Product but must be acceptable to Engineer.
END OF SECTION 01 3300
01 7000 – CONTRACT CLOSEOUT
Schwab Eaton CONTRACT CLOSEOUT 01 7000 - 1
SECTION 01 7000 – CONTRACT CLOSEOUT
A. Closeout procedures.
B. Final cleaning.
C. Project record documents.
D. Warranties.
1.2 CLOSEOUT PROCEDURES:
A. Submit written certification that Contract Documents have been reviewed, Work has been inspected, and that Work is complete in accordance with Contract Documents and ready for Engineer's inspection.
B. Provide submittals to Engineer that are required by governing or other authorities.
C. Submit final Application for Payment identifying total adjusted Contract Sum, previous payments, and sum remaining due.
D. Submit a notarized release or waiver of liens from Contractor and all subcontractors and suppliers as may be required by the Owner. Submit said release(s) along with final Application for Payment in a form acceptable to the Owner. The Contractor's release of liens shall be conditional upon final payment.
E. Submit a notarized affidavit of payment of all debts and claims arising out of the performance of the Work in this Contract. Said affidavit shall be submitted with final Application for Payment in a form acceptable to the Owner.
F. Submit a document from Contractor's surety consenting to final payment. Submit said document with final Application for Payment.
1.3 FINAL CLEANING:
A. Execute final cleaning prior to final inspection.
B. Clean debris from drainage systems.
C. Clean site; sweep paved areas, rake clean landscaped surfaces.
D. Remove waste and surplus materials, rubbish, and construction facilities from the site.
1.4 PROJECT RECORD DOCUMENTS:
A. Maintain on site, one set of the following record documents; record actual revisions to the Work:
1. Contract Drawings.
2. Specifications.
3. Addenda.
4. Change Orders and other Modifications to the Contract.
Schwab Eaton CONTRACT CLOSEOUT 01 7000 - 2
5. Reviewed shop drawings, product data, and samples.
B. Record information concurrent with construction progress.
C. Record Documents and Shop Drawings; legibly mark each item to record actual construction including:
1. Measured horizontal and vertical locations of underground utilities and appurtenances, referenced to permanent surface improvements.
2. Field changes of dimension and detail.
3. Details not on original Contract Drawings.
D. Mark documents "As-Built," recorded by Contractor.
E. Submit documents to Engineer with claim for final Application for Payment.
1.5 WARRANTIES:
A. Unless otherwise specified herein for a particular portion of the Work, all Work shall be under warranty for one year after date of final acceptance. Longer manufacturers warranties on materials, products, and equipment incorporated into the Work shall be so honored.
B. Provide duplicate notarized copies.
C. Execute and assemble documents from subcontractors, suppliers, and manufacturers.
D. Neatly assemble in three-ring binder.
E. Submit prior to final Application for Payment.
F. For items of Work delayed beyond date of Substantial Completion, provide updated submittal within ten days after acceptance of said Work, listing date of acceptance as start of warranty period.
END OF SECTION 01 7000
DIVISION 02: EXISTING CONDITIONS
02 4105 – SITE PREPARATION
Schwab Eaton SITE PREPARATION 02 4105 - 1
SECTION 02 4105 - SITE PREPARATION
1.1 SCOPE OF WORK:
A. Provide all labor, materials, and equipment necessary for all site preparation and incidental demolition Work.
1.2 SECTION INCLUDES:
A. Site clearing and topsoil stripping and stockpiling.
B. Removing above-grade improvements.
C. Removing below-grade improvements, D. Disconnecting and capping/removal of identified utilities.
1.3 SCHEDULE:
A. Coordinate Work with the respective utility owner(s) and all other contractors performing work on the jobsite.
1.4 QUALITY CONTROL:
A. Work shall be performed by personnel experienced in performing the type(s) of demolition Work specified herein.
1.5 REGULATORY REQUIREMENTS:
A. Conform to all applicable laws, regulations and codes having jurisdiction over the Work specified herein.
B. Do not close or obstruct roadways, sidewalks, emergency exits, and/or fire hydrants without permits.
C. Conform to applicable regulatory procedures when discovering hazardous or contaminated materials.
1.6 SALVAGED MATERIALS:
A. All topsoil stripping shall be salvaged for reuse.
B. Unless otherwise directed by the Owner, all other incidental demolition items will not be salvaged or remain the Owner’s property.
1.7 FEES AND PERMITS:
A. The Contractor shall pay for all required permits and inspection fees levied by governmental agencies having jurisdiction.
Schwab Eaton SITE PREPARATION 02 4105 - 2
PART 2 - MATERIALS
2.1 DEMOLITION MATERIALS:
A. Topsoil: Reusable topsoil stripped during site clearing, having the following characteristics:
1. Containing between 1% and 8% organic matter by weight.
2. Free of subsoil, heavy roots, grass, excessive weeds and gravel, large stones, broken glass, debris, and toxic substances.
B. Unless otherwise specified, all references to the type of materials to be removed are based on the best information available at the time of the Drawings. The Contractor shall be fully responsible for satisfying himself as to the type, depth, and thickness of demolition items and extent of reinforcement, if any, and basing his bid accordingly.
2.2 FILL MATERIALS:
A. Fill material required to backfill and restore excavations and depressions resulting from demolition Work shall be in accordance with Section 31 2316 – Excavation and Trenching.
3.1 PREPARATION AND CLEARING:
A. Verify all utility depths and locations prior to commencing Work.
B. Notify utility companies regarding abandonment of existing utilities and verify the status thereof.
C. Protect existing improvements to from damage during demolition/construction.
D. Protect existing trees (and their root zones) and other landscaping to remain from damage during demolition/construction.
E. Remove trees, shrubs, grass and other vegetation, improvements or obstructions that interfere with new construction. Removal includes new and old tree stumps and their roots. Fill and compact, to a density equal to adjacent original ground, all depressions caused by clearing and grubbing unless further excavation or earthwork is indicated.
F. Strip all topsoil from all areas to be disturbed by construction and located where stockpiling of future fill materials will be placed. Strip to whatever depths encountered, but not less than six (6") inches. Remove heavy growths of grass and herbaceous plant cover prior to stripping. Do not allow major intermingling of subsoils or other objectionable material during stripping operations.
G. Stockpile topsoil in area(s) on site where it will not interfere with drainage, construction, or utility operations. No topsoil shall be removed from site until restoration of topsoil to all landscape areas is completed and reviewed by the Engineer and/or Landscape Architect.
H. Provide, erect and maintain temporary barriers and security devices. Maintain at least one open lane when adjacent to or crossing road. For public safety, provide signage, flaggers, barricades, flashers and traffic control devices in accordance with local jurisdictional requirements and the latest edition of the U.S. Dept. of Transportation Manual on Uniform Traffic Control Devices.
I. Prevent movement or settlement of adjacent structures to remain. Provide bracing and shoring as required.
Schwab Eaton SITE PREPARATION 02 4105 - 3
3.2 SALVAGEABLE ITEMS:
A. Carefully remove items indicated to salvaged. Store and protect for reinstallation. Items indicated to salvaged but not specified for reinstallation shall be delivered to the Owner, unless otherwise specified.
3.3 DEMOLITION:
A. Conduct demolition in a manner as to minimize interference with adjacent structures.
B. Cease operations immediately if adjacent structures appear to be in danger. Notify Engineer.
Do not resume operations until directed.
C. Conduct operations with minimum interference to public or private accesses. Maintain protected egress and access at all times.
D. Obtain written permission from adjacent property owners when demolition equipment will traverse, infringe upon or limit access to their property.
E. Sprinkle Work with water to minimize dust. Provide hoses and water connections for this purpose.
F. Disconnect/remove and cap designated utilities within demolition areas in accordance with applicable codes and the respective utility owner’s standards.
G. Sawcut all limits of demolition Work to clean, neat lines.
H. Remove all incidental improvements located within the construction limits as shown on the
Drawings and as required to facilitate new construction. Incidental improvements generally include pavements, abandoned utilities, fences and similar items.
I. Backfill and compact depressions, open pits and holes caused as a result of demolition in accordance with Section 31 2316 – Excavation and Trenching.
J. Rough grade and compact areas affected by demolition to maintain drainage, site grades and contours.
K. Remove demolished materials from site, unless otherwise specified.
L. Do not burn or bury materials on site. Leave site in clean condition.
M. Remove temporary work, unless otherwise specified.
END OF SECTION 02 4105
DIVISION 03: CONCRETE
03 3000 – CAST-IN-PLACE CONCRETE
Schwab Eaton CAST-IN-PLACE CONCRETE 03 3000 - 1
SECTION 03 3000 – CAST-IN-PLACE CONCRETE
PART 1 – GENERAL
1.1 SCOPE OF WORK:
A. Provide all labor, materials and equipment necessary for performing all concrete Work as shown on Drawings and specified herein.
1.2 SECTION INCLUDES:
A. Formwork
B. Reinforcement
C. Accessories
D. Cast-in-place concrete
E. Finishing
F. Curing
1.3 SCHEDULE:
A. Perform Work under environmental conditions conducive for the specified Work. Protect Work when such conditions do not occur.
B. Coordinate Work with all other contractors performing work on the jobsite.
1.4 QUALITY ASSURANCE:
A. The Contractor shall employ certified independent testing agency approved by the Engineer for testing concrete work.
B. Construct and erect concrete formwork in accordance with ACI 301, and 318, unless specified otherwise in this Section.
C. Perform concrete reinforcing Work in accordance with ACI 301, 318 and CRSI 63, 65 unless specified otherwise in this Section.
D. Perform cast-in-place concrete Work in accordance with ACI 301, 302, 318, 304, 305, and 306, unless specified otherwise in this Section.
1.5 SUBMITTALS:
A. Submit concrete mix designs with certifications at least 15 days prior to start of Work.
B. Submit Shop Drawings of concrete structures indicating pertinent dimensioning, form materials, arrangement of joints and ties, and schedule of erection and stripping.
C. Indicate in Shop Drawings reinforcement sizes, spacings, locations, and quantities; bending and cutting schedules; and supporting and spacing devices.
Schwab Eaton CAST-IN-PLACE CONCRETE 03 3000 - 2
PART 2 – PRODUCTS
2.1 FORM MATERIALS:
A. Plywood: PS 1, C Grade Douglas Fir or Spruce species; CD grade; sound, undamaged sheets with clean true edges.
B. Lumber: Pine or Fir species; construction grade.
C. Prefabricated Steel or Fibrous Glass Reinforced Resin Type: matched, tight fitting, stiffened to support weight of concrete.
D. Tubular Column Type: Round, spirally wound laminated materials; inside surface treated with release agent; of size required.
E. Form Ties: Snap-off metal type of adjustable length, cone type.
F. Form Release Agent: Colorless mineral oil which will not stain concrete or impair natural bonding of coatings specified to be applied to concrete surface.
G. Formed Construction Joints for Slab-on Grade: Galvanized steel or extruded plastic, tongue and groove type profile, knockout holes to receive dowelling.
H. Slab Edge Joint Filler: ASTM D1751, premolded asphaltic board, ½ inch thick.
2.2 REINFORCEMENT MATERIALS:
A. Reinforcing Steel: ASTM A615, 60 ksi yield grade; deformed billet steel bars, plain finish.
B. Welded Steel Wire Fabric: ASTM A1064 / A1064M, plain type, in flat sheets or coiled rolls, plain finish.
C. Chairs, Bolsters, Bar Supports, Spacers: Sized and shaped for support of reinforcing.
D. Fabricate concrete reinforcing in accordance with ACI 318.
2.3 CONCRETE MATERIALS:
A. Cement: ASTM C150, Normal-Type I, Portland type.
B. Aggregates: All aggregate shall comply with the current Kansas Department of Transportation
(KDOT) Standard Specifications for State Road and Bridge Construction, Section 1102
1. Fine Aggregates: Free from materials with deleterious reactivity to alkali in cement
2. Coarse Aggregates: Maximum size of ¾” nominal
C. Water: Clean and not detrimental to concrete.
D. Air Entrainment Admixture: ASTM C260.
E. Bonding Agent: Polymer resin emulsion or latex emulsion.
F. Non-shrink Grout: Premixed compound consisting of non-metallic aggregate, cement, water reducing and plasticizing agents.
Schwab Eaton CAST-IN-PLACE CONCRETE 03 3000 - 3
2.4 COMPOUNDS, HARDENERS AND SEALERS:
A. Curing Compound: ASTM C309, Type 2, Class A; white.
B. Absorptive Mats: ASTM C171, burlap-polyethylene.
C. Hot Joint Sealers: Hot applied, non-tracking asphalt-rubber compound complying with ASTM
D6690 as manufactured by W.R. Meadows, Cary/Celotex, or acceptable equivalent, applied in accordance with manufacturer’s recommendations.
D. Expansion Joint Sealer: Single component, polyurethane-based, non-sag elastomeric joint sealant shall be Sikaflex-1a, as manufactured by Sika Corporation or acceptable equivalent.
2.5 CONCRETE MIX:
A. Mix and deliver concrete in accordance with ASTM C94.
B. Provide concrete of the following strength: Compressive Strength: 4,000 psi, 28 days.
C. Slump:
1. Flatwork: Three inches (3”) [+/- three-quarters inch (¾”)]. Subject to review and acceptance by the Engineer, the allowable slump may be increased with use of water-reducing agents to improve workability.
2. Curbs: Two and one-half inches (2½”) [+/- three-quarters inch (¾”)].
3. Slip-Form: Two and one-half inches (2½”) [+/- three-quarters inch (¾”)].
4. Foundations: Four inches (4”) [+/- one inch (1”)].
5. Walls: Four (4”) inches [+/- one inch (1”)].
6. Exterior Steps: Four (4”) inches, [+/- one inch (1”)].
D. Air Entrained:
1. Exterior: Six and one-half percent (6.5%) [+/- one percent (1%)].
2. Interior: Three percent (3%) maximum.
E. Water/cement ratio shall not exceed 0.50.
F. Select admixture proportions for normal weight concrete in accordance with ACE 301 & 302.
PART 3 – EXECUTION
3.1 FORMWORK ERECTION:
A. Erect formwork, shoring and bracing to achieve design requirements.
B. Camber slabs and framing to achieve ACI 301 tolerances.
C. Provide bracing to ensure stability of formwork.
D. Provide chamfer strips (three-quarters (¾”) inch triangular molding) on external corners of all exposed concrete structures, unless otherwise specified.
E. Apply form release agent to formwork in accordance with manufacturer's instructions, prior to placing for accessories and reinforcement.
F. Do not apply form release agent where concrete surfaces will receive special finishes, which are
Schwab Eaton CAST-IN-PLACE CONCRETE 03 3000 - 4 affected by agent.
G. Clean forms as erection proceeds, to remove foreign matter.
H. Forms shall be set plumb, properly aligned, to provide smooth, even layout.
3.2 INSERTS, EMBEDDED COMPONENTS, AND OPENINGS:
A. Provide formed openings where required for Work to be embedded in and passing through concrete members.
B. Coordinate Work of other Sections in forming and setting openings, slots, recesses, chases, sleeves, bolts, anchors, and other inserts.
C. Install concrete accessories at proper elevation, straight, level, and plumb.
D. Place formed construction joint device in slab pattern pouring sequence.
E. Install void forms in accordance with manufacturer's instructions. Protect forms from moisture before concrete placement and from crushing during concreting operations.
3.3 REINFORCEMENT PLACEMENT:
A. Place reinforcement supported and secured against displacement. Use the appropriate chairs, spacers, and other devices to support reinforcement.
B. Ensure reinforcing is clean, free of loose scale, dirt, or other foreign coatings.
3.4 PLACING CONCRETE:
A. Prepare previously place concrete by cleaning with steel brush and applying bonding agent.
Apply bonding agent in accordance with manufacturer's instructions.
B. Concrete shall be placed in the forms in a way which will prevent segregation. It shall not be allowed to have a fall of more than five feet unless through a closed pipe which not only prevents segregation but will also prevent splattering of the forms with mortor.
C. Separate slabs-on-grade from vertical surfaces with joint filler, extended from bottom of slab to within three-quarters (¾”) inch (unless otherwise specified) of finished slab surface.
D. Place concrete continuously between predetermined expansion, control and construction joints.
Do not break or interrupt successive pours such that cold joints occur.
E. Where new concrete is dowelled to existing work, drill holes in existing concrete, insert steel dowels and pack with non-shrink grout.
F. Screed floors and slabs-on-grade uniformly, maintaining surface flatness of maximum one-quarter (¼”) inch in 10 ft. to prevent unevenness and the formation of "birdbaths."
G. Consolidate concrete as required by mechanical vibrator supplemented by rodding, spading, or tamping. Do not vibrate forms or reinforcement. Do not over-vibrate, segregate concrete mix, or transport concrete in forms by use of vibrator.
Schwab Eaton CAST-IN-PLACE CONCRETE 03 3000 - 5
3.5 FORM REMOVAL:
A. Do not remove forms or bracing until concrete has gained sufficient strength to carry its own weight and imposed loads.
B. Remove formwork progressively and in accordance with code requirements.
3.6 CONCRETE FINISHING:
A. Finish concrete floor surfaces in accordance with ACI 301 and 302.
B. Uniformly spread, screed, and float concrete.
C. Heavy broom finish exterior slab surfaces.
D. Maintain surface flatness, with maximum variation of one-quarter (¼”) inch in 10 ft.
E. Grout voids left after form removal where acceptable to Engineer.
F. Provide vertical concrete surfaces to be left exposed with smooth rubbed finish; grout voids;
remove fins, form marks, and rough surfaces.
3.7 CURING:
A. Place absorptive matting and dampen as required.
B. Immediately after placement, protect concrete from premature drying, excessively hot or cold temperatures, and mechanical damage.
C. Apply curing compound in accordance with the manufacturer's recommendations.
D. Maintain concrete with minimal moisture loss at relatively constant temperature for period necessary for hydration of cement and hardening of concrete.
E. Prior to sealant application, clean all joints by lightly sandblasting and/or another acceptable method to remove curing compound, loose material, and other deleterious substances hindering proper sealant application. Do not damage appearance of joint finish.
F. Apply joint sealants after cleaning. Avoid overfilling or spilling sealant on surrounding surfaces.
Any such spillage shall be cleaned up immediately.
3.8 TESTING:
A. Testing Frequency: ASTM 172; one composite sample test samples shall be taken for each day's pour exceeding five (5) cu. yds. plus additional for each 50 cu. yds. over and above the first 25 cu. yds. of each concrete class placed in one day. Test samples shall be taken in middle of a loading during concrete placement (not at beginning).
B. Slump: ASTM C143; one test at point of placement for each composite sample but not less than one test for each day’s pour of each concrete mixture. Perform additional tests when concrete consistency appears to change.
C. Air Content: ASTM C231; pressure method, for normal weight concrete; one test for each composite sample but not less than one test for each day’s pour of each concrete mixture.
D. Density (Unit Weight): ASTM C138; for normal weight concrete; one test for each composite
Schwab Eaton CAST-IN-PLACE CONCRETE 03 3000 - 6 sample but not less than one test for each day’s pour of each concrete mixture.
E. Concrete Temperature: ASTM C1064; one test hourly when air temperature is 40 degrees F and below or 80 degrees F and above, and one test for each composite sample.
F. Compressive Test Specimens: ASTM C31; minimum four (4) specimens per sample.
G. Compressive Strength Test: ASTM C39; test one laboratory cured specimen at 7 days and two specimens at 28 days. Hold one specimen for additional testing if required.
H. Reporting: Test results shall be reported in writing to Engineer, concrete manufacturer, and
Contractor within 48 hours of testing. Reports of compressive strength tests shall contain Project identification name and number, date of concrete placement, name of concrete testing and inspecting agency, location of concrete batch in Work, design compressive strength at 28 days, concrete mixture proportions and material, compressive breaking strength and type of break for both 7 and 28 day tests.
END OF SECTION 03 3000
DIVISION 22: PLUMBING
22 0000 – PLUMBING
Orazem & Scalora Engineering, P.A. PLUMBING 22 0000 - 1
SECTION 22 0000 - PLUMBING
PART 1 - GENERAL
1.1 WORK INCLUDED:
A. This Section of the Specification includes the furnishing and installation of complete drainage, water supply, plumbing fixtures and other equipment as described herein and as indicated on the Drawings.
1.2 SUBMITTALS:
A. Submit complete printed catalog and descriptive data for each major piece of equipment, clearly indicating exactly what features, options and accessories are being provided.
B. See Section 23 0100.
1.3 SEWER AND WATER CONNECTIONS:
A. Connections to on-site water services shall be in accordance with the requirements of the 2021 International Plumbing Code and the respective Utility Company. Pay all associated fees including tap charges and cost of meter installations.
B. Before any new sewer work is done, the Contractor shall uncover the sewer line where connection is to be made and shall determine the actual elevation. If the actual elevation of the sewer at the point of connection is such that the new drainage line cannot be installed with the required slope to the new fixtures, the matter shall be referred to the Architect as soon as possible.
PART 2 - PRODUCTS
2.1 GENERAL
A. Compliance with the Reduction of Lead in Drinking Water Act (2014) is required and all applicable products must meet the lead-free requirements and conform to NSF 372.
B. All pipes, fittings, valves, coatings, gaskets, lubricants, adhesives, Teflon tape, thread sealer, suitable joint compound, and other appurtenances and materials in contact with raw, partially treated, or treated potable water must be NSF 61 produce certified, as applicable.
2.2 UNDERGROUND WATER PIPING:
A. Underground domestic water piping outside the building shall be as specified by the Civil Engineer.
2.3 ABOVEGROUND WATER PIPING:
A. Aboveground domestic water piping 3-inches in size and smaller, shall be copper tubing, Type L, hard drawn, ASTM B-88. Fittings shall be one of the following:
1. Recessed solder- joint type of either wrought copper or cast brass. Adapters for connection to threaded valves, fittings, meters and other equipment shall be cast brass.