This is a Project Specifications document from the Oregon Department of Transportation (ODOT) for the OR82 Bridge Resurfacing MBM 2025 Project managed by Project Manager Andy Adkins. The project involves resurfacing three bridges along Oregon Route 82 at mile posts 49.43, 54.11, and 63.19, requiring a combined total of 200 tons of asphalt concrete pavement (20 tons, 92 tons, and 88 tons respectively). Work is scheduled to commence within ten working days of a pre-work conference with the State Project Manager, with a tentative start date of June 2, 2025, substantial completion by July 1, 2025, and final completion by July 15, 2025. Site inspection is the sole responsibility of bidders prior to submission, and no pre-bid conference is required. The construction sequencing is dependent on ODOT District 13 Bridge Crew scheduling and follows a four-phase process: cold plane pavement removal by ODOT staff (day 1), contractor ACP base course paving (day 1-2), bridge deck membrane installation by ODOT (day 2-3), and contractor ACP wearing course paving (day 3-4).

The contract specifications require compliance with the 2024 Oregon Standard Specifications for Construction with specific modifications detailed in the document. Materials must include PG 64-28 grade asphalt cement, emulsified asphalt tack coat (approximately 0.4 tons), and properly tested asphalt concrete pavement meeting gradient and density requirements. Sampling and testing protocols require a CAT I to perform minimum testing for each 1,000 tons of placement, including asphalt content, gradation, mix moisture, maximum specific gravity, and field compacted gyratory specimens, with results provided to the Engineer by mid-shift of the following work day. Compaction compliance is determined through random nuclear gauge testing at one location per 100 tons placed with a minimum of three tests per shift. No separate payment is made for emulsified asphalt tack coat. The contractor must maintain a responsible representative on-site capable of making decisions and shall provide daily activity summaries to the State Project Manager upon request, with work continuing regardless of disputes unless otherwise agreed in writing.

View the file

Other files

File Type Posted
00013125_Bid Cover Sheet.docx DOCX document
00013125_Sample Contract.docx DOCX document
00013125_bid tab.xlsx XLSX spreadsheet
00013125_ITB.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT SPECIFICATIONS

OR82: Bridge Resurfacing MBM 2025 Project

State Highway Number

Route Number

Estimated Mile Post Location

Estimated Quantity (Tons) Project Manager Phone No.

OR82

49.43 54.11 63.19

20 Tons 92 Tons 88 Tons

Andy Adkins (see above)

541-910-6165

Tentative Start Date: June 2, 2025 (coordinate with State Project Manager, listed above) Substantial Completion: July 1, 2025 Final Completion Date: July 15, 2025

Description

Scope - This project scope consists of supplying all labor, equipment and machinery as necessary for resurfacing three bridges along OR82 according to the 2024 Oregon Standard Specifications for Construction and modifications listed in these contract documents.

2024 OREGON STANDARD SPECIFICATIONS FOR CONSTRUCTION: The 2024 Oregon Standard Specifications for Construction (“Standard Specifications”) include detailed technical specifications that apply to this Invitation To Bid and resulting Contract.

Some sections of the technical specifications are identified and modified below. Sections of the technical specifications not identified below remain applicable to the Contract according to their original terms. Part 00100 of the Standard Specifications (General Conditions) is not applicable to the Contract unless otherwise noted below; however, if a technical specification (Parts 200 and beyond) references a section from Part 00100, that section from Part 00100 applies to the Contract for purposes of supporting and giving full effect to the technical specification. The Standard Specifications are available online:

http://www.oregon.gov/ODOT/HWY/SPECS/Pages/standard_specifications.aspx

General - The Contractor shall always have a responsible party on the job while work is in progress, capable and with authority to make job-site decision as an official Contractor's representative. The Contractor shall provide the State Project Manager with a summarization of activities and work performed daily if requested.

The Contractor shall carry on the work and adhere to the contract schedule during all disputes or disagreements with the State. No work shall be delayed or postponed pending resolution of any disputes or disagreements, except as specifically permitted by the specifications or as Contractor and State may otherwise agree in writing.

The Contractor shall meet with the State Project Manager(s) for a pre-work conference at a time mutually agreed upon. Work shall commence within ten working days of this meeting, providing the Notice to Proceed has been issued. A pre-bid conference will not be required. Bidders are solely responsible for inspecting the sites prior to bidding. In no event shall failure to inspect the site constitute grounds for charges to the State more than the bid price. The Project Manager will be as listed above for the section they will be in.

Construction - Construction sequencing will be dependent on ODOT District 13 Bridge Crew scheduling, with each project site generally having the following timeline and sequencing:

1. ODOT District 13 Bridge crew completes cold plane pavement removal of existing asphalt surfacing over bridge deck (day 1)

2. Contractor paves and compacts ACP base course (day 1 or day 2, depending on schedules)

3. ODOT District 13 Bridge crew installs bridge deck membrane (day 2 or day 3, depending on schedules)

4. Contractor paves and compacts ACP wearing course (day 3 or day 4, depending on schedules)

Sequencing and durations listed above are approximate for bidding purposes only and shall be verified by coordinating with the Project Manager.

SECTION 00165 – QUALITY OF MATERIALS

Comply with Section 00165 of the Standard Specifications.

SECTION 00210 - MOBILIZATION

Comply with Section 00210 of the Standard Specifications.

SECTION 00290 – ENVIRONMENTAL PROTECTION

Comply with Section 00290 of the Standard Specifications.

SECTION 00730 - EMULSIFIED ASPHALT TACK COAT

Comply with Section 00730 of the Standard Specifications modified as follows:

00730.11 Emulsified Asphalt – Replace the sentence that begins “Furnish CSS-1, CSS-1h…” with the following sentence:

Furnish CSS-1, CSS-1h, CMS-2, CMS-2S, CMS-2h, CRS-1, CRS-2, HFRS-2, HFMS-2 or HPTC as selected by the Contractor.

00730.90 Payment - Replace this subsection, except for the subsection number and title, with the following:

No separate or additional payment will be made for Emulsified Asphalt tack coat. Approximately 0.4 Tons of Emulsified Asphalt in tack coat will be required on this Project.

SECTION 00744 - ASPHALT CONCRETE PAVEMENT

Comply with Section 00744 of the Standard Specifications modified as follows:

00744.11(a) Asphalt Cement - Add the following to the end of this subsection:

Provide PG 64-28 grade asphalt cement for this Project.

00744.16 Sampling and Testing - Replace this subsection, except for the subsection number and title, with the following:

For each 1,000 Tons of placement, have a CAT I perform a minimum of one of each of the following test methods as modified in the MFTP:

• Asphalt Content - AASHTO T 308 with ODOT TM 323 determined Calibration Factor

• Gradation - AASHTO T 30

• Mix Moisture - AASHTO T 329

• Maximum Specific Gravity - AASHTO T 209

• Field Compacted Gyratory Specimens - ODOT TM 326

When less than 1,000 Tons of mix is placed in a Day, perform a minimum of one series of tests per Day.

Provide test results to the Engineer by the middle of the following work shift. The Engineer may waive the requirement for any of AASHTO T 308, AASHTO T 30, AASHTO T 329, and ODOT TM 326 on a daily basis.

The Engineer may waive the requirement for AASHTO T 209 when less than 500 Tons of ACP is placed in a single work shift.

Provide samples or split samples to the Engineer when requested.

00744.17 Acceptance - Replace this subsection, except for the subsection number and title, with the following:

If the test result for each mix gradation constituent, asphalt content, and density measurement is within the specification limits, the material will be accepted. If the asphalt content, one or more gradation constituents, or the density measurement are not within the specification limits, the material that is not within the specification limits will be accepted according to 00150.25.

00744.41 Mixing Temperature - Replace the table with the following:

Temperature, °F Type Maximum Minimum Behind at Mixer Paver

HMAC 350 240

WMAC 350 215

00744.49 Compaction - Replace the paragraph that begins "Determine compliance with…" with the following paragraph:

Determine compliance with density Specifications by random testing of the compacted surface with calibrated nuclear gauges. Determine the density by averaging QC tests performed by a CDT with the nuclear gauge operated in the backscatter mode according to AASHTO T 335 at one random location for each 100 Tons of asphalt concrete placed, but take no less than three tests each shift. Do not locate the center of a density test less than 1 foot from the Panel edge. Calculate MAMD according to ODOT TM 305.

The Engineer may waive compaction testing requirements when less than 500 Tons of ACP is placed in a single work shift.