This file consists of technical specifications and special provisions for a pavement preservation and highway maintenance project issued by the Oregon Department of Transportation (ODOT), Region 3, District 8, in Jackson County. The project scope includes grinding and inlaying pavement to a depth of two inches, with eight inches of paving for the first ten feet from the rail repair on Kirkland Road, durable striping, and safety edge installation where applicable. Work will be performed on Highway 140 (Lake of the Woods Highway) at two locations: Agate Road, where a 24-hour road detour will be maintained from May 30 to June 1, and Kirkland Road near Blackwell Road and the rail crossing, where work will be conducted nights only from June 2 to June 4 with flagging in alternating directions. The contractor is responsible for determining utility conflicts and coordinating with appropriate agencies at no additional cost to the project. All work must comply with the 2024 Oregon Standard Specifications for Construction, the State of Oregon Standard Conditions for Public Improvement Contracts, and the 2009 Manual on Uniform Traffic Control Devices. Estimated quantities for asphalt and striping materials are provided for bidding purposes only, with ODOT retaining the right to adjust quantities or modify work scope as needed. The project manager is Adam O. Stallsworth, reachable at 541-774-6328 office or 541-774-6349 fax.
The project specifications establish traffic control requirements including lane closures limited to one half-mile sections on Highway 140, permitted daily from 7:00 p.m. to 6:00 a.m. Sunday through Thursday and 8:00 p.m. to 6:00 a.m. Friday. Contractors must install advance warning signage including "TRUCKS LEAVING/ENTERING HIGHWAY" signs and "ROAD WORK AHEAD" signs with "FINES DOUBLE" riders, along with "END ROAD WORK" signs at project termination points. Cold plane pavement removal must not utilize heating devices, with machine forward speed limited to 2.5 feet per minute near bridge end panels, and paving must occur before allowing traffic on cold-planed surfaces. Safety edge installation is required except in sections with existing guardrails and must be constructed monolithically with the pavement using an approved device from manufacturers including Transtech Systems, Inc., AdvantEdge Paving Equipment, LLC., Carlson Paving Products, or Troxler Electronic Laboratories, Inc. Asphalt may be placed at depths of three inches with ODOT approval, and all excess asphalt must be disposed of at the end of each work shift in accordance with applicable permits. The contractor must coordinate with the rail contractor who will provide traffic control on the rail portion of the project, with potential for concurrent paving operations within ten feet of rail work upon coordination. No separate payment will be made for tack coat (approximately 0.3 tons estimated) or safety edge work, with these costs incorporated into base pavement items. The project allows for grinding of all sections prior to paving, with appropriate signage maintained until completion.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 00013850 ESB_RFCQ.docx | DOCX document | |
| Exhibit 2 Project Area Map and Details.pdf | ||
| ODOT Standard Drawing RD312.pdf | ||
| 00013850 ESB_RFCQ_Attachments.docx | DOCX document | |
| 00013850 Bid Results.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment A Specifications
DESCRIPTION OF WORK
Lake of the Woods Hwy 140 (270) Lake of the Woods Highway Jackson County
WORK TO BE DONE
Work to be done under this Contract consists of the following:
· Grind and Inlay Pavement preservation two inches deep.
· Note 8” (eight inches) of paving for the first ten feet from the rail repair on Kirkland.
· Butt grind at the beginning and end of the project.
· Durable Striping
· Safety edge is only required in those sections without a guardrail run.
· Asphalt and Striping quantiles are an estimate for Bidding.
· Hwy 140 sections will be in coordination with Rail as they will provide traffic control on the rail.
· Work will be on Agate road with a 24 hour road detour performed though this contract 5/30-6/1.
· Work at Kirkland Road will be 6/2-6/4 nights only one each direction flagging into the opposite direction.
Project area Kirkland Road Rail crossing near Blackwell Road and the Agate Road rail crossing.
Standard Drawings RD610…………………….Asphalt Concrete Pavement (ACP) Details TM500……………………..Pavement Marking Standard Detail Blocks TM501……………………..Pavement Marking Standard Detail Blocks TM503……………………..Pavement Marking Standard Detail Blocks
| TM800 | Tables, Abrupt Edge and PCMS Details |
| TM810 | Temporary Pavement Markers |
TM820……………………..Temporary Barricades TM850……………………...2-Lane, 2-Way Roadways
It is the contractor’s responsibility to determine utility or facility conflicts and contact and coordinate with the appropriate utility company or government agency. All utility involvement shall be considered incidental to the project and no separate payment will be made.
Project Manager Adam O. Stallsworth Oregon Department of Transportation Region 3 District 8 100 Antelope Road White City, Oregon.
541-774-6328 OFC 541-774-6349 FAX
ESTIMATED QUANTITIES: All quantities are estimated and are for bidding purposes only. The Oregon Department of Transportation (ODOT) reserves the right to adjust quantities; add or delete items of work as needed.
Additional Specifications
Comply with the “State of Oregon Standard Conditions for Public Improvement Contracts.” Supplemental specifications which are applicable to the work on this project are the Oregon Department of Transportation’s Standard Specifications for Highway Construction 2024, or as modified by the Special Provisions.
2024 OREGON STANDARD SPECIFICATIONS FOR CONSTRUCTION. The 2024 Oregon Standard Specifications for Construction (“Standard Specifications”) include detailed technical specifications in Sections 00200 and beyond that apply to this ITB and any resulting Contract. Some sections of the technical specifications may be identified and modified in the Plans and Specifications. Sections of the technical specifications not identified in the Plans and Specifications remain applicable to the Contract according to their original terms.
Sections in Part 00100 of the Standard Specifications (General Conditions) are not applicable to the Contract unless they are specifically identified in an exhibit or attachment to the Contract or in the Plans and Specifications as being applicable. However, if a Part 00100 section that has been identified as being applicable references another section in Part 00100, or a technical specification (Parts 00200 and beyond) references a section from Part 00100, that section from Part 00100 applies to the Contract for purposes of supporting and giving full effect to the specification that referenced it. Bidders can access the Standard Specifications online at:
http://www.oregon.gov/ODOT/Business/Pages/Standard_Specifications.aspx
NOTE: The “State of Oregon Standard Conditions for Public Improvement Contracts” take precedence over all other specifications https://www.oregon.gov/das/Procurement/Guiddoc/GenCon4PI.pdf
Temporary Work Zone Traffic Control:
All traffic control devices and measures shall comply with the 2009 Manual on Uniform Traffic Control Devices (http://mutcd.fhwa.dot.gov/) and ODOT Standard Drawings (http://www.oregon.gov/ODOT/HWY/ENGSERVICES/standard_drawings_home.shtml).
SPECIAL PROVISIONS
SECTION 00210 - MOBILIZATION
Comply with Section 00210 of the Standard Specifications.
SECTION 00220 - ACCOMMODATIONS FOR PUBLIC TRAFFIC
Comply with Section 00220 of the Standard Specifications modified as follows:
00220.40(e-1) Closed Lanes - Replace this subsection, except for the subsection number and title, with the following:
One Traffic Lanes may be closed on the Lake of the Woods Highway (OR140) not exceeding a half miles in length when allowed, shown, or directed during the following periods of time except as indicated in 00220.40(e‑2):
Daily, Sunday through Thursday 7:00 p.m. to 6:00 a.m.
Friday Between 8:00 p.m. to 6:00 a.m.
SECTION 00225 - WORK ZONE TRAFFIC CONTROL
Comply with Section 00225 of the Standard Specifications modified as follows:
00225.01(c) Standards - Add the following bullet to the end of the bullet list:
ODOT "Traffic Control Plans Design Manual", available on the ODOT Traffic Control Plans Unit website.
00225.02 General Requirements - In the paragraph that begins "Work may be suspended…", replace the sentence that begins "Costs for work performed…" with the following sentence:
Costs for work performed by the Agency may be deducted from monies due the Contractor.
Add the following to the end of this subsection:
Install a 54 inch "TRUCKS LEAVING HIGHWAY XXXX FT" sign in advance of each entrance point to the work area at sign spacing “A” from the “TCD Spacing Table” shown on the standard drawings. Install a 54 inch "TRUCKS ENTERING HIGHWAY XXXX FT" sign in advance of each exit point from the work area at sign spacing “A” from the “TCD Spacing Table” shown on the standard drawings.
Install "ROAD WORK AHEAD" (W20‑1‑48) signs with "FINES DOUBLE" (R2‑6‑36) rider on the Crater Lake Highway, according to the "TCD Spacing Table" shown on the standard drawings or as modified by the supplemental drawings except do not install the "FINES DOUBLE" rider on concrete barrier mounted signs.
Install beyond each end of the Project, facing outgoing traffic, an "END ROAD WORK" (CG20‑2A‑24) sign a distance of (A ÷ 2) according to the "TCD Spacing Table" shown on the standard drawings or as modified by the supplemental drawings.
When the horizontal clearance for the roadway is less than 19 feet, install horizontal clearance (CW21‑12‑48) signs, identifying the narrowest width of the roadway. Locate these horizontal clearance signs as shown or as directed.
00225.10 General - In the paragraph that begins "Evaluate the condition…", replace the first sentence with the following sentence:
Evaluate the condition of TCD using the criteria shown in the most current version in effect of the American Traffic Safety Services Association (ATSSA) publication titled "Quality Guidelines for Temporary Traffic Control Devices and Features", available from the ATSSA website at www.atssa.com.
00225.11(c-1) Temporary Signs - Replace the bullet that begins "Type 2 riprap geotextile…" with the following bullet:
Geotextile fabric
00225.29 Pilot Cars - Replace the bullet that begins " No smaller than…" with the following bullet:
No smaller than a compact pickup truck.
00225.32 Traffic Control Supervisor -
Replace the paragraph that begins "Do not designate the Project Superintendent…" with the following paragraph:
When the bid schedule includes an item for a TCS, do not designate the Project superintendent as the TCS.
00225.41(b-4) Temporary Sign Supports - Replace the bullet that begins "Do not tip over TSS…" with the following bullet:
Do not tip over any TSS that is exposed to traffic, unless approved by the Engineer or the TSS is protected from traffic by a barrier system.
00225.41(c) Sign Flag Boards and Sign Flags - Replace this subsection, including subsections 00225.41(c-1) and 00225.41(c-2), with the following subsection:
00225.41(c) Sign Flag Boards - Install two sign flag boards, as shown or specified.
00225.41(e) Inconsistent Temporary Signs - Replace the paragraph that begins "Ensure that all temporary…" with the following paragraph:
Ensure that all temporary signs are properly used and consistent with the work zone. Cover all inconsistent temporary signing until the sign messages are applicable to the Work that is beginning. When signage is no longer required for staging or shift Work, remove all temporary signs, sign flag boards, supports, sign covers, and ballast associated with the staging or shift Work.
SECTION 00290 - ENVIRONMENTAL PROTECTION
Comply with Section 00290 of the Standard Specifications modified as follows:
Add the following section:
00290.20 (c)(g): Asphalt: Dispose of excess asphalt at the end of each work shift according to applicable permits. Excess asphalt shall not be left within the project limits.
SECTION 00620 - COLD PLANE PAVEMENT REMOVAL
Comply with Section 00620 of the Standard Specifications modified as follows:
00620.40(a) General - Replace this subsection, except for the subsection number and title, with the following:
Remove the existing pavement to the depth, width, grade and cross section shown or as directed. The use of a heating device to soften the pavement is not allowed. When removing pavement from bridge end panels, limit the machine forward speed to 2.5 feet per minute.
00620.43 Maintenance Under Traffic - Replace this subsection, except for the subsection number and title, with the following:
Traffic is not allowed on the cold planed surface. Before opening the area to traffic, pave the surface according to 00745.51.
SECTION 00640 - AGGREGATE BASE AND SHOULDERS
Comply with Section 00640 of the Standard Specifications modified as follows:
00640.44 Surface Tolerance - Replace the paragraph that begins "The finished surface and the surface of each underlying…" with the following paragraph:
The finished surface and the surface of each underlying layer of the aggregate shall parallel the established grade and cross section for the finished surface within 0.04 foot.
SECTION 00730 - EMULSIFIED ASPHALT TACK COAT
Comply with Section 00730 of the Standard Specifications modified as follows:
00730.90 Payment - Replace this subsection, except for the subsection number and title, with the following:
No separate or additional payment will be made for Emulsified Asphalt tack coat. Approximately ___0.3__ tons of Emulsified Asphalt in tack coat will be required on this Project.
SECTION 00738 - SAFETY EDGE
Section 00738, which is not a Standard Specification, is included in this Project by Special Provision.
Description
00738.00 Scope - This work consists of furnishing and placing a consolidated sloped pavement edge treatment, known as a safety edge, constructed monolithically with the pavement as shown.
Materials
00738.10 Materials - Construct the safety edge using the same material used to construct the adjoining pavement.
Equipment
00738.20 Safety Edge Device - Attach a device to the asphalt concrete paver screed that confines the asphalt concrete at the end gate and extrudes the asphalt concrete in a wedge shape onto the roadway shoulder. The safety edge device compacts a wedge between the ratios 1:1 1/2 and 1:2, providing a uniform texture and shape, adjusts to varying paving thicknesses, and allow for transitions for cross roads, driveways, and obstructions. Brief stops of the paving machine to adjust the safety edge device at transitions are allowed. A single plate strike off is not allowed.
Use a safety edge device manufactured by Transtech Systems, Inc; Advant‑Edge Paving Equipment, LLC; Carlson Paving Products; Troxler Electronic Laboratories, Inc; or a similar device that produces the same wedge consolidation results. If a similar device is used, provide proof the device has been used on previous projects with acceptable results or construct a test section meeting the requirements of 00738.47
Construction
00738.40 Asphalt Concrete Density Adjacent to Safety Edge - Compact asphalt concrete pavement adjacent to the safety edge according to Sections 00743, 00744 or 00745. No additional compaction of the safety edge is required.
00738.43 Handwork - Short sections of handwork where the safety edge transitions at locations such as driveways, intersections, interchanges, and bridges are allowed.
00738.47 Test Section - At the beginning of the paving operation, construct one initial test strip of asphalt pavement at least 0.1 mile but not more than 0.2 mile in length at the specified paving width. Safety edge is evaluated for wedge ratio, compaction, texture, and shape to the satisfaction of the Engineer.
The initial test strip is waved if the safety edge device is manufactured by one of the companies listed in 00738.20 or a device that is proven to the satisfaction of the Engineer.
Measurement
00738.80 Measurement - No measurement of quantities will be made for safety edge.
Payment
00738.90 Payment - No separate or additional payment will be made for safety edge. Payment will be included in payment for the appropriate items under which this work is required.
SECTION 00740 - COMMERCIAL ASPHALT CONCRETE PAVEMENT (CACP)
Comply with Section 00740 of the Standard Specifications.
SECTION 00749 - MISCELLANEOUS ASPHALT CONCRETE STRUCTURES
Comply with Section 00749 of the Standard Specifications.
SECTION 00850 - COMMON PROVISIONS FOR PAVEMENT MARKINGS
Comply with Section 00850 of the Standard Specifications.
SECTION 00860 - LONGITUDINAL PAVEMENT MARKINGS - PAINT
Comply with Section 00860 of the Standard Specifications.
SECTION 00867 - TRANSVERSE PAVEMENT MARKINGS - LEGENDS AND BARS
Comply with Section 00867 of the Standard Specifications.
SECTION 02320 - GEOSYNTHETICS
Comply with Section 02320 of the Standard Specifications modified as follows:
SECTION 02640 – Shoulder Aggregate
Comply with Section 02640 of the Standard Specifications modified as follows:
ADDITIONAL SPECIAL PROVISIONS
· Asphalt may be placed at depths of 3 inches as approved by ODOT
· Grinding of all sections may occur before the start of paving with asphalt wedges and appropriate signage until paved if opened to traffic.
· The rail will be worked on at the same time as grinding for this work. Contractor shall work in conjunction with the rail contractor providing highway traffic control. Contractor may be able to pave within ten feet of the rail during rails work with their coordination.
· Work will take multiple days to complete.
· Please note that discrepancies in the documents of the contract will be determined in the order as noted in A 3.1 of the General Conditions for Public Improvement Contracts. What is called for one is intended to be complimentary to the others. See also A 3.2.