This is a Special Provisions and Specifications document for the Oregon Department of Transportation (ODOT) related to a culvert rehabilitation project on OR82 (Wallowa Lake Highway) between Minam and Wallowa. The project involves rehabilitating 22 culverts across multiple locations between mileposts 30.19 and 46.66, with pipe diameters ranging from 18" to 60"x84". Key rehabilitation activities include work zone traffic control, temporary water management, culvert cleaning, CCTV inspection, installing CIPP (cured-in-place pipe) liners, and installing paved inverts. The project has specific considerations for environmental protection, including in-water work periods from July 15th to August 15th and requirements for fish habitat preservation.

The project includes provisions for handling potentially asbestos-containing materials, with estimated disposal quantities of approximately 18 tons of contaminated soil and culvert materials. Contractors must have current Oregon DEQ Asbestos Abatement Contractor licenses and certifications. The contract references multiple supporting documents, including Minimal Assessment Memorandums and Asbestos Surveys dated February and January 2025. The project must also accommodate several local events, including the Wallowa Mountain Cruise Car Show, Wallowa Fourth of July Parade, and Chief Joseph Days, which will impact work zone traffic control and scheduling.

View the file

Other files

File Type Posted
20252004_A2_IT Service Management Platform_Addendum 1.pdf PDF
00012771 Preliminary Results.xlsx XLSX spreadsheet
Invitation.To.Bid~12.docx DOCX document
Attachment A Plans~6.pdf PDF
00012771 Intent To Award.xlsx XLSX spreadsheet
Attachment C Bid Pricing Form~13.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OR82: Culvert Project Minam to Wallowa

ATTACHMENT B

SPECIAL PROVISIONS AND SPECIFICATIONS FOR

OR82: CULVERT PROJECT, MINAM TO WALLOWA

SCOPE

The work to be done under this Contract, on OR82 (Wallowa Lake Highway) consists of supplying the materials, equipment, labor, and incidentals required to perform the following tasks as described in the Contract plans and specifications:

· Provide Work Zone Traffic Control

· Construct Temporary Water Management Facility as needed

· Clean and CCTV multiple culverts

· Install multiple CIPP liners

· Install paved invert

· Perform additional and incidental work as called for by the Contract plans and specifications and as directed.

The locations are as follows, OR82:

· Location #1Milepost 30.1924“diameter
· Location #2Milepost 30.9918” diameter
· Location #3Milepost 31.0718“diameter
· Location #4Milepost 34.3836“diameter
· Location #5Milepost 35.0818” diameter
· Location #6Milepost 35.4818“diameter
· Location #7Milepost 35.5024“diameter
· Location #8Milepost 36.3518“diameter
· Location #9Milepost 36.6018“diameter
· Location #10Milepost 36.9618"diameter
· Location #11Milepost 37.1724”diameter
· Location #12Milepost 39.4318“diameter
· Location #13Milepost 40.4524“diameter
· Location #14Milepost 41.5936“diameter
· Location #15Milepost 43.7124“diameter
· Location #16Milepost 44.0760”x 84” arch
· Location #17Milepost 44.2824“diameter
· Location #18Milepost 44.3918“diameter
· Location #19Milepost 44.6718”diameter
· Location #20Milepost 46.5224”diameter
· Location #21Milepost 46.5718“& 24”diameter
· Location #22Milepost 46.6636”diameter

PROJECT INFORMATION

General information pertaining to this project may be obtained from the following:

Wade Holaday, Senior Culvert Maintenance Engineer Oregon Department of Transportation Phone: 503.986.4046 Email: wade.holaday@odot.oregon.gov

APPLICABLE STANDARD SPECIFICATIONS AND SPECIAL PROVISIONS

STATE OF OREGON GENERAL CONDITIONS FOR PUBLIC IMPROVEMENT CONTRACTS: In addition to the solicitation laws and rules, this ITB and the resulting Contract are governed by the STATE OF OREGON GENERAL CONDITIONS FOR PUBLIC IMPROVEMENT CONTRACTS, January 1, 2012, Edition (“General Conditions”) which, although not physically attached, are incorporated herein by reference as an Attachment with the same force and effect as though fully set forth herein. The General Conditions can be obtained from the Department of Administrative Services, 1225 Ferry Street SE U140, Salem, OR 97301-4285, by telephone (503) 378-4642 or online at:

https://www.oregon.gov/das/Procurement/Guiddoc/GenCon4PI.pdf

2024 OREGON STANDARD SPECIFICATIONS FOR CONSTRUCTION: The 2024 Oregon Standard Specifications for Construction (Standard Specifications) include detailed technical specifications in Parts 00200 through 03000 inclusive (Technical Specifications) that apply to this ITB and the resulting Contract. Some sections of the Technical Specifications are identified and modified herein, Special Provisions and Specifications. Sections of the Technical Specifications not modified remain applicable to the Contract according to their original terms. Unless they are identified herein, Special Provisions and Specifications, sections of the Standard Specifications in Part 00100 (General Conditions) are not applicable to this Contract. Bidders can also access this information at the following Internet address:

https://www.oregon.gov/odot/Business/Specs/2024_STANDARD_SPECIFICATIONS.pdf

Silence of Specifications: The apparent silence of the Specifications as to any detail, or the apparent omission of a detailed description concerning any point, shall be regarded as meaning that the highest value commercial practices are to prevail and that only materials and workmanship of first quality are to be used.

PROFESSIONAL OF RECORD CERTIFICATION

The following Special Provisions were prepared and/or reviewed by the Engineer whose professional seal appears below. These Specifications are not valid unless the appropriate signed seal appears below and shall not be modified without the approval of the Engineer.

Oregon Department of Transportation Special Provisions For

OR82: MINAM TO WALLOWA CULVERT PROJECT

PROFESSIONAL OF RECORD CERTIFICATION(s):

Seal w/signature

I certify the Special Provision Section(s) listed below are applicable to the design for the subject project. Modified Special Provisions were prepared by me or under my supervision.

SECTION: 00210, 00220, 00294, 00295, 00410, 00412, 00413, 00414, 00415, 00445, 00470, 00490, 00495, 00842.

Date Signed: ____

SECTION 000210 - MOBILIZATION

Comply with Section 00210 of the Standard Specifications.

SECTION 00220 - ACCOMMODATIONS OF PUBLIC TRAFFIC

Comply with Section 00220 of the Standard Specifications modified as follows:

Add the following subsection:

00220.40(e)(1) Closed Lanes - Replace this subsection, except for the subsection number and title, with the following:

One Traffic Lane may be closed on the Wallowa Lake Highway (OR 82) when allowed, shown, or directed during the following periods of time except as indicated in 00220.40(e)(2):

· Lane closures resulting in a single lane of two-way traffic controlled by flaggers are allowed anytime to maximum length of closure to one mile.

00220.40(e)(2)(b) Special Events - Add the following to the end of this subsection:

The following special events will occur during this Project:

•Wallowa Mountain Cruise Car ShowJune 20-21, 2025
•Wallowa Fourth of July ParadeJuly 4, 2025
•Chief Joseph DaysJuly 24-27, 2025

SECTION 00221 – COMMON PROVISIONS FOR WORK ZONE TRAFFIC CONTROL

Comply with Section 00221 of the Standard Specifications.

SECTION 00222 – TEMPORARY TRAFFIC CONTROL SIGNS

Comply with Section 00222 of the Standard Specifications.

SECTION 00223 - WORK ZONE TRAFFIC CONTROL LABOR AND VEHICLES

Comply with Section 00223 of the Standard Specifications.

SECTION 00280 – EROSION AND SEDIMENT CONTROL

Comply with section 00280 of the Standard Specifications

SECTION 00290 - ENVIRONMENTAL PROTECTION

Comply with Section 00290 of the Standard Specifications modified as follows:

00290.10 Staging and Disposal Sites – Replace the paragraph that begins “Locate staging areas…” with the following paragraph:

Locate staging areas and disposal sites in previously improved or disturbed sites, including existing Roadways, pullouts, turnouts, parking lots, and storage yards that have been compacted, and graveled or paved, unless otherwise approved, in writing, by the Engineer.

00290.20(c)(2) Clean Fill - Add the following paragraph to the end of this subsection:

Manage all excavated soil that does not meet the definition of clean fill according to Section 00294.

Add the following subsection:

00290.30(a)(7) Water Quality:

Do not discharge water contaminated by pollutants including sediment, drilling fluids and waste, concrete, grout, or water contained within a work area isolation, into any waters of the State or U.S. or conveyances draining thereto until it has been treated using Materials such as those listed in 00280.15 or 00280.16 or by pumping to a vegetated upland location. Do not allow Project discharges to increase the concentration of any pollutant in the receiving water to a level that exceeds the limits prescribed by OAR 340‑041.

Do not use permanent stormwater quality treatment facilities to treat construction runoff unless prescribed by an ESCP approved under Section 00280.

If construction discharge water is released using an outfall or diffuser port, do not exceed velocities more than 4 feet per second, and do not exceed an aperture size of 1 inch.

Implement containment measures adequate to prevent pollutants from entering waters of the State or U.S. Such pollutants include but are not limited to construction and demolition materials, waste spoils, fuel or petroleum products, detergents, silt, welding slag and grindings, concrete saw cutting by-products and sandblasting abrasives.

Do not allow curing concrete or grout to be submerged within waters of the State or U.S. less than 24 hours after placement, except within work area isolation. Do not end-dump riprap into the waters of the State or U.S. Place riprap from above the ordinary high-water line.

Monitor weather and streamflow forecasts and conditions to anticipate high flows that may unintentionally inundate any portion of the Project Site.

If high flow conditions occur or are anticipated to occur that may unintentionally inundate any portion of the Project Site, remove all potentially affected Equipment, Materials, and debris from the potential inundation area. Cease Work in the area until water recedes, and the risk of further high-water events passes. The Engineer retains the authority to temporarily halt or modify the Work in case of excessive turbidity or damage to natural resources.

If Work in or around waters of the State or U.S. violate permit conditions or any requirement of this subsection, stop such Work and notify the Engineer.

00290.34 Protection of Fish and Fish Habitat - Add the following paragraph:

Meet with the Agency Biologist, Resource Representative, Engineer, and inspector on site, before moving equipment on-site or beginning any work, to ensure that all parties understand the locations of sensitive biological sites and the measures that are required to be taken to protect them.

00290.34(a) Regulated Work Areas - Add the following to the end of this subsection:

The regulated work area is the area at or below the ordinary high water (OHW) elevation shown on the plans.

Perform work within the regulated work area only during the in-water work period. The in‑water work period is from ___July 15th___ to ___August 15h___.

Submit a schedule to complete all work within the regulated work area within the in-water work period at least 10 Days prior to the preconstruction conference.

00290.34(c) Aquatic Species Protection Measures Required by Environmental Permits:

(1) General Requirements:

Do not install fish ladders (for example: pool and weirs, vertical slots, fishways) or fish trapping systems.

Do not apply surface fertilizer within 50 feet of any stream channel.

Use heavy equipment as follows:

Choice of equipment must have the least adverse effects on the environment (for example: minimally sized, low ground pressure).

Secure absorbent material around all stationary power equipment (for example: generators, cranes, drilling equipment) operated within 150 feet of wetlands, waters of the State, waters of the U. S., drainage ditches, or water quality facilities to prevent leaks, unless suitable containment is provided to prevent spills from entering waters of the State or waters of the U.S.

Do not cross directly through a stream for construction access, unless shown or approved. If shown or approved, cross perpendicular to the stream and do not block stream flow. When a crossing is no longer needed, completely remove the crossing and restore the soils and vegetation to the original condition.

Store fuel and maintain all equipment in staging areas that are at least 150 feet away from any waters of the State, waters of the U.S., or storm inlet or on an impervious surface that is isolated from any waters of the State, waters of the U.S., or storm inlet.

If temporary access roads are needed within 150 feet of any body of water, use existing routes unless new routes are shown or approved.

Before beginning work on temporary access routes that are not shown, submit a proposal to the Engineer for approval.

(2) Work Area Isolation - Provide work isolation according to Section 00245. Provide safe passage around or through the isolated work area for adult and juvenile migratory fish unless passage did not previously exist.

(3) Water Intake Screening - Install, operate, and maintain fish screens on each water intake used for project construction, including pumps used to isolate an in-water work area. When drawing or pumping water from any stream, protect fish by equipping intakes with screens having a minimum 27 percent open area and meeting the following requirements:

Perforated plate openings shall be 3/32 inch or smaller.

Mesh or woven wire screen openings shall be 3/32 inch or smaller in the narrowest direction.

Profile bar screen or wedge wire openings shall be 1/16 inch or smaller in the narrow direction.

Choose size and position of screens to meet the following criteria in Table 00290‑1:

Table 00290-1

Type
Approach Velocity 1

(Ft./Sec.)

Sweeping Velocity 2 (Ft./Sec.)

Wetted Area of Screen (Sq. Ft.)

Comments

Ditch Screen
≤ 0.4
Shall exceed approach velocity
Divide max. water flow rate (cfs) by

0.4 fps If screen is longer than 4 feet, angle 45° or less to stream flow

Screen with proven self-cleaning system
≤ 0.4
–
Divide max. water flow rate (cfs) by

0.4 fps

Screen with no cleaning system other than manual
≤ 0.2
–
Divide max. water flow rate (cfs) by

0.2 fps Pump rate 1 cfs or less

1 Velocity perpendicular to screen face at a distance of approximately 3 inches 2 Velocity parallel to screen

Provide ditch screens with a bypass system to transport fish safely and rapidly back to the stream.

(4) Special Aquatic Habitats - The following exploration or construction activities are not allowed in special aquatic habitats:

Use of pesticides and herbicides, unless allowed according to Section 01030.

Use of short pieces of plastic ribbon to determine flow patterns.

Temporary roads or drilling pads built on steep slopes, where grade, soil type, or other features suggest a likelihood of excessive erosion or slope failure.

Installation of a fish screen on any permanent water diversion or intake that is not already screened.

(5) Site Restoration - Restore damaged streambanks to a natural slope, pattern, and profile suitable for establishment of permanent woody vegetation unless precluded by pre‑project conditions (for example: natural rock substrate):

Replant all damaged streambanks before the first April 15 following construction.

If use of large wood, native topsoil, or native channel material is required for the site restoration according to the roadside development plans, stockpile all large wood, native vegetation, weed-free topsoil, and native channel material displaced by construction. Cut trees or large wood and trees into pieces of no less than 20 feet in length, or as shown on the roadside development plans or as directed. Stockpiled native wood and vegetation remain the property of the Agency.

Stabilize all disturbed soils, including obliteration of temporary access roads, following any break in work unless construction will resume in 4 Calendar Days.

(6) Surface Water Diversions - Surface water may be diverted to meet construction needs other than work area isolation, consistent with Oregon law, only if water from sources that are already developed, such as municipal supplies, small ponds, reservoirs, or tank trucks, is unavailable or inadequate, and meeting the following conditions:

When alternative surface sources are available, divert from the stream with the greatest flow.

Install, operate, and maintain a temporary fish screen.

Do not exceed a pumping rate and volume of 10 percent of the available flow. For streams with less than 5 cubic feet per second, do not exceed drafting of 18,000 gallons per Day. Do not use more than one pump for each site.

(9) Treated Wood - Treated wood includes any wood treated with any pesticide or wood preservatives. Do not use lumber, pilings, or other wood products that are treated or preserved with pesticidal compounds below the ordinary high water (OHW) or as part of an in-water or over-water structure, except as described below:

Store treated wood shipped to the Project out of contact with standing water and wet soil and protected from precipitation.

Visually inspect each load and piece of treated wood. Reject for use in or above aquatic environments if visible residues, bleeding of preservative, preservative-saturated sawdust, contaminated soil, or other matter is present.

Use pre-fabrication to the extent feasible. When field fabrication is necessary, all cutting and drilling of treated wood, and field preservative treatment of wood exposed by cutting and drilling, shall occur above the OHW. Use tarps, plastic tubs, or similar devices to contain the bulk of any fabrication debris and wipe off any excess field preservative.

All treated wood structures, including pilings, shall have design features to avoid or minimize impacts and abrasion by livestock, pedestrians, vehicles, vessels, and floats.

Treated wood may be used to construct a bridge, over-water structure or an in-water structure, with the exception of the work containment system, provided that all surfaces exposed to leaching by precipitation, overtopping waves, or submersion are coated with a water-proof seal or barrier are maintained. Apply and contain coatings and paint-on field treatment to prevent contamination. Surfaces that are not exposed to precipitation or wave attack, such as parts of a timber bridge completely covered by the bridge deck, are exempt from this requirement.

During demolition of treated wood, ensure that no treated wood debris falls into the water. If treated wood debris does fall into the water, remove it immediately.

Store removed treated wood debris in appropriate dry storage areas, at least 150 feet away from the regulated work area.

(11) Ditch and Culvert Cleaning - Complete ditch cleaning, culvert and trash rack cleaning by working from the top of bank, unless work area isolation would result in less habitat disturbance.

Do not work more than 20 feet upstream or downstream the culvert or trash rack.

Remove only the minimum amount of wood, sediment, or other natural debris necessary to maintain the facility’s function, without disturbing spawning gravel or changing the configuration of the original ditch, unless the new configuration is part of the project design.

Place all large wood, cobbles, and gravels recovered from during culvert and trash rack cleaning downstream from the structure.

Complete drift removal in the following priority, as directed:

Pull and release whole logs or trees downstream.

Pull whole logs and trees and place in the riparian area, as directed.

Remove whole logs or trees only if roadside development plans have been developed for replacement in-kind.

Pull, cut only as necessary, and release logs and trees downstream.

(13) Temporary Power, Communication and Water Lines - Before installing temporary power, communication, or water lines across streams or bodies of water, submit a proposed plan to the Engineer for approval. Do not begin installation before receiving approval from the Engineer. Proposed plans for installation of temporary power, communication, and water lines and stream crossings shall utilize the following design methods in the listed order of priority:

1. Aerial lines, including lines hung from existing bridges.

2. Directional drilling, boring and jacking that spans the channel migration zone and any associated wetland.

3. Trenching, which is restricted to intermittent streams and may only be used when the stream is naturally dry. For all sections of trenches below the ordinary high-water line, backfill with native material and cap with clean gravel suitable for fish use in the project area.

Align each crossing as perpendicular to the watercourse as possible. For drilled, bored, or jacked crossings, ensure that the line is below the total scour prism. Return any large wood displaced by trenching or plowing as nearly as possible to its original position, or otherwise arranged to restore habitat functions.

(14) Injured Fish Notification - If a dead or injured fish is found in the project area, immediately notify the Agency. If the injured fish is in a location where further injury or stress may take place, attempt to move the fish to a safer location, if one is available, near the capture site while keeping the fish in the water and reducing its stress as much as possible. Do not disturb the fish after it has been moved. If the fish is dead or dies while being captured or moved, save the fish and any tags. The Agency will notify appropriate regulatory agencies about the injured or dead fish and provide additional direction to the Contractor.

00290.36(a) Migratory Birds ‑ Add the following to the end of this subsection:

Do not disturb migratory bird nesting habitat (shrubs, trees, and structures), or clear vegetation from March 1 to September 1 of each year without prior written approval from the Engineer. Notify the Engineer, in writing, a minimum of 10 Calendar Days prior to starting activities that could harm nesting birds.

(1) Bird Management - Bird management activities to comply with the Migratory Bird Treaty Act (16 U.S.C. 703 712) will be performed by the Agency. Ensure that the Agency and its permitted agents have access to the project area, as needed to prevent migratory bird nesting. Nesting prevention may include daily bird harassment and the installation and maintenance of devices that exclude birds.

Do not disturb migratory bird nesting habitats (shrubs, trees, and structures), or clear vegetation from March 1 to September 1 of each calendar year without prior written approval from the Engineer. Notify the Engineer, in writing, a minimum of 10 Calendar Days prior to starting activities that could harm nesting birds.

00290.51 Protection of Sensitive Cultural Sites - Add the following to the end of this subsection:

There are sensitive cultural sites or areas of high probability for cultural resources on this Project. At the time of preparation of the Plans, ___1____ site was identified.

The Region Environmental Coordinator for this Project is ___Tayton Duby__________.

The Agency Archaeology Representative for this Project is _____ Alex New__________.

All contact with the Agency Archaeology Representative and the Region Environmental Coordinator shall be through the Engineer.

An Inadvertent Discovery Plan (IDP) has been developed for this project. The IDP is available from the Engineer.

Meet with the Engineer at least 10 Calendar Days prior to beginning ground disturbing activities to discuss sensitive cultural sites on the Project. Required attendees include:

The Contractor’s supervisory personnel.

Subcontractors, and supervisory personnel who will be involved in ground disturbing activities.

Agency archaeology representative or region environmental coordinator.

When applicable, tribal representative(s) or monitor(s).

Prior to beginning On-Site Work, install work zone fencing from section 00221.13 of the QPL, or lath and flagging, around no work zones, as shown or as directed.

00290.90 Payment - Add the following paragraph(s) to the end of this subsection:

No separate or additional payment will be made for work zone fencing.

SECTION 00294 - CONTAMINATED MEDIA

Section 00294, which is not a Standard Specification, is included in this Project by Special Provision.

Description

00294.00 Scope - In addition to the requirements of Section 00290 and the Specifications, this Work consists of the following:

Contain and dispose of materials removed during cleaning of culverts with required liner installation at the following locations that are presumed to contain asbestos, unless testing conducted according to SP00295 demonstrates that asbestos is not detected:

Contaminated Soil Location Table 00294-1

From Location/Station to Location/Station
Depth below grade (feet)
Approximate Quantity (tons)
Presumed Contaminants
OR82 MP 30.19
NA
3.8
Bituminous coating
OR82 MP 36.60
NA
1.6
Bituminous coating
OR82 MP 40.45
NA
5.3
Bituminous coating
OR82 MP 44.28
NA
6
Bituminous coating
OR82 MP 44.39
NA
1.5
Bituminous coating
Approximate Total Quantity
18tons
Quantity to be reused on Project
0tons
Quantity to be disposed at landfill
18tons

Contain and dispose of materials in pipe sections that are removed for replacement from the following locations and that are presumed to contain asbestos, unless testing conducting according to SP00925 demonstrates that asbestos is not detected:

Contaminated Soil Location Table 00294-2

From Location/Station to Location/Station
Depth below grade (feet)
Approximate Quantity (tons)
Presumed Contaminants
OR82 MP 30.990
NA
0.4
Bituminous coating and mortar
OR82 MP 35.48
NA
0.1
Mortar
OR82 MP 35.50
NA
0.02
Mortar
OR82 MP 36.35
NA
2.2
Mortar
OR82 MP 39.43
NA
1.6
Mortar
OR82 MP 41.59
NA
14
Mortar
Approximate Total Quantity
18tons
Quantity to be reused on Project
0tons
Quantity to be disposed at landfill
18tons

The following ODOT reports, documenting the contaminated media identified within the Project, is available from the Engineer:

Minimal Assessment Memorandum, Clean Fill Determination, and Asbestos Survey, dated February 6, 2024.

Minimal Assessment Memorandum, Clean Fill Determination, and Asbestos Survey Addendum, dated January 6, 2025.

00294.01 Definitions:

Contaminated Soil - Soil that does not meet the DEQ definition of "Clean Fill", as defined by OAR 340-093-0030(18). For this Project, Contaminated Soil is also defined to be materials removed during culvert cleaning and pipe replacement that contain fragments of bituminous coating and/or mortar that are ACM or presumed to be ACM by DEQ and require disposal in accordance with OAR 340-248-0280.

Asbestos-Containing Material (ACM) – A Material containing more than 1% asbestos by weight (OAR 340-248-0010(8)).

Asbestos-Containing Waste Material – Waste that contains or is contaminated by ACM (OAR 340-248-0010(9)).

Shoulder Soil - Soil outside of the existing Highway Pavement and within Highway Right-of-Way generated during Highway maintenance or construction activities. This definition applies to excess Soil generated to a maximum depth of 1.5 feet below ground surface. This definition does not apply to Soil that is covered by existing impervious surfaces, including but not limited to curbs, sidewalks and parking lots constructed of asphalt or concrete.

ODOT Beneficial Use Determination (ODOT BUD) ‑ The statewide ODOT Beneficial Use Determination (ODOT BUD), approved by DEQ (No. BUD-20181204), outlines a series of pre-approved non-residential reuse options for excess Soil Materials that do not meet DEQ’s Clean Fill Standards in some circumstances. These options may vary based on project scope and location, and documentation may vary, as directed by the Engineer.

00294.03 Submittals - Submit the following documents:

Current employee training certificates and medical surveillance information before beginning Work within the contaminated areas.

· Completed and signed DEQ Waste Shipment Report Form according to the following:

· Send the form along with the Asbestos-Containing Waste Material to the disposal facility.

· Provide a copy of the form to the Engineer within 48 hours of transportation of the asbestos waste.

Obtain the final signed form from the disposal facility along with the disposal receipts and submit them to the Engineer within three Calendar Days after receiving them from the waste disposal facility.

Labor

00294.30 Personnel Qualifications - Provide employees meeting the following requirements:

A current Oregon DEQ Asbestos Abatement Contractor license.

A current Oregon DEQ Certified Supervisor meeting the requirements of OAR 340‑248‑0130.

Current Oregon DEQ Certified asbestos workers meeting the requirements of OAR 340‑248‑0130.

Ensure the DEQ Certified Supervisor is on site and overseeing work whenever Asbestos Containing Materials are disturbed or removed.

Construction

00294.40 Contaminated Soil (Culvert Cleanout Material) Removal and Disposal - If asbestos test results obtained per Section 00295 identify that bituminous coating and/or mortar in one or more culverts is ACM, or if no asbestos testing is conducted, then comply with 29 CFR 1910, 29 CFR 1926.1101, 40 CFR 61, 40 CFR 763, OAR 340 248, ORS 468A and the following:

Notify the Engineer 3 Calendar Days before beginning cleaning and repair activities within contaminated areas.

At culverts listed in Table 00294-1, contain and dispose of cleanout materials removed from culverts where a liner will be installed. Use collection and containment methods that minimize the release of asbestos fibers and minimize visible emissions.

At culverts listed in Table 00294-2, collect and dispose of materials in pipe sections that are removed and replaced, or throughout the entire culvert for those culverts where a liner will also be installed. Conduct pipe removal according to SP00295. Use collection and containment methods that minimize the release of asbestos fibers and minimize visible emissions.

Complete and sign all manifests and bill of lading forms for transporting and disposing the ACM.

Maintain the ACM in an undamaged and non-friable condition by keeping the Material wet during demolition or by using methods approved by DEQ.

Keep Material sealed during transport to the disposal facility. Transport and dispose of all ACM according to OAR 340-248-280.

Measurement

00294.80 Measurement - Work performed under this Section will be measured according to the following:

The quantities of Contaminated Soil (containing asbestos) Disposal will be measured on the weight basis, based on weigh tickets from the disposal facility.

Payment

00294.90 Payment - The accepted quantities of Work performed under this Section will be paid for at the Contract unit price, per unit of measurement, for the following items:

Pay Item Unit of Measurement

(e) Contaminated Soil (containing asbestos) Disposal Ton

Item (e) includes all costs involved with the disposal of Contaminated Soil at a recycling or disposal facility.

No separate or additional payment will be made for the excavation or reuse of Contaminated Soil or contaminated Shoulder Soil. Payment will be included in payment made for the appropriate items under which the excavation or reuse of Contaminated Soils or contaminated Shoulder Soil is required.

Payment will be payment in full for removing and disposing of all Materials, and for furnishing all Equipment, labor, Plans, test results, and Incidentals necessary to complete the Work as specified.

SECTION 00295 - ASBESTOS MATERIALS

Section 00295, which is not a Standard Specification, is included in this Project by Special Provision.

Description

00295.00 Scope - In addition to the requirements of Section 00290 and Section 00294, remove asbestos according to the following Specifications.

Remove and dispose of pipe sections coated with presumed ACM from the following locations in Table 00295-1A, unless testing conducted according to Section 00295.35 demonstrates that asbestos is not detected. Remove and dispose of culvert cleaning debris and debris from removed pipe sections according to 00294.

Table 00295-1A

Location/Address
Material Description
Quantity

(ft. or sq.ft.)

Percent Asbestos
Friable or

Non-Friable

OR82 MP 30.990
CMP with bituminous coating and concrete with mortar
56 ft.
Presumed ACM
Presumed Friable
OR82 MP 35.48
Concrete with mortar
6 ft.
Presumed ACM
Presumed Friable
OR82 MP 35.50
Concrete with mortar
3 ft.
Presumed ACM
Presumed Friable
OR82 MP 36.35
Concrete with mortar
3 ft.
Presumed ACM
Presumed Friable
OR82 MP 39.43
Concrete with mortar
9 ft.
Presumed ACM
Presumed Friable
OR82 MP 41.59
Concrete with mortar
9 ft.
Presumed ACM
Presumed Friable

Unless testing conducted according to Section SP00295.35 demonstrates that asbestos is not detected, remove and dispose of mortar as presumed ACM from the joint of the pipe section remaining in place from locations where one or more pipe sections will be removed and replaced as listed in Table 00295-1B.

Table 00295-1B

Location/Address
Material Description
Quantity

(ft. or sq.ft.)

Percent Asbestos
Friable or

Non-Friable

OR82 MP 35.48
Mortar
2.2 sq.ft.
Presumed ACM
Presumed Friable
OR82 MP 35.50
Mortar
1.1 sq.ft.
Presumed ACM
Presumed Friable
OR82 MP 36.35
Mortar
1.1 sq.ft.
Presumed ACM
Presumed Friable
OR82 MP 39.43
Mortar
1.1 sq.ft.
Presumed ACM
Presumed Friable

The materials listed in Table 00295-2 were not sampled.

Table 00295-2

Location/Address
Material Description
Quantity

(ft. or sq.ft.)

Friable or Non-Friable

OR82 MP 30.19
Bituminous coating
117 ft.
Presumed Friable
OR82 MP 30.990
Bituminous coating and mortar
66 ft.
Presumed Friable
OR82 MP 35.48
Mortar

(work disturbs the joints at 2 pipe sections)

4.4 sq. ft.
Presumed Friable
OR82 MP 35.50
Mortar

(work disturbs the joints at 1 pipe section)

2.2 sq. ft.
Presumed Friable
OR83 MP 36.35
Mortar

(work disturbs the joints at 1 pipe section)

2.2 sq. ft.
Presumed Friable
OR82 MP 36.60
Bituminous coating
60 ft.
Presumed Friable
OR82 MP 39.43
Mortar

(work disturbs the joints at 3 pipe sections)

6.6 sq. ft.
Presumed Friable
OR82 MP 40.45
Bituminous coating
91 ft.
Presumed Friable
OR82 MP 41.59
Mortar

(work disturbs the joints at 3 pipe sections)

6.6 sq. ft.
Presumed Friable
OR82 MP 44.28
Bituminous coating
52 ft.
Presumed Friable
OR82 MP 44.39
Bituminous coating
46 ft.
Presumed Friable

The following ODOT reports, documenting the presumed asbestos identified within the Project is available from the Engineer:

Minimal Assessment Memorandum, Clean Fill Determination, and Asbestos Survey, dated February 6, 2024.

Minimal Assessment Memorandum, Clean Fill Determination, and Asbestos Survey Addendum, dated January 6, 2025.

Maintain a copy of these reports and all additional asbestos survey results on site at all times and readily available to employees and inspectors during demolition and repair activities.

00295.01 Definitions:

Asbestos Containing Material (ACM) ‑ Any material containing more than 1% asbestos.

00295.03 Submittals - The following forms and reports are required:

Asbestos survey report documenting sample locations and analytical results according to Oregon Administrative Rule (OAR) 340-248-0270 (3)(d).

Completed and signed DEQ Project Notification Form and an abatement plan to Agency and DEQ at least 10 Calendar Days before beginning friable asbestos removal.

Completed and signed DEQ Waste Shipment Report Form according to the following:

Send the form along with the asbestos waste to the disposal facility.

Provide a copy of the form to the Engineer within 48 hours of transportation of the asbestos waste.

Obtain the final signed form from the disposal facility along with the disposal receipts and submit them to the Engineer within 3 Calendar Days after receiving them from the waste disposal facility.

Disposal receipts within 72 hours of receipt from the waste disposal facility.

Labor

00295.30 Personnel Qualifications - Provide employees meeting the following requirements:

A current Oregon DEQ Asbestos Abatement Contractor license.

A current Oregon DEQ Certified Supervisor meeting the requirements of OAR 340‑248‑0130.

Current Oregon DEQ Certified asbestos workers meeting the requirements of OAR 340‑248‑0130

Ensure the DEQ Certified Supervisor is on site and overseeing work whenever asbestos containing materials are disturbed or removed.

A current AHERA Inspector Training Certification according to 40 CFR 763, Part 763, Appendix C - TSCA Tile II

Workers trained according to 29 CFR 1926.1101.

When a DEQ Certified Supervisor is required, ensure the supervisor is on site and overseeing the work whenever asbestos materials are disturbed or removed.

Materials Testing

00295.35 Testing of Suspect Asbestos Containing Material ‑ When additional testing is performed for suspected ACM listed in Table 00295-2, complete the following with an Asbestos Hazard Emergency Response Act (AHERA) Inspector prior to removal of material listed in the Table 00295-2:

Collect at least 2 samples of each material listed in the Table 00295-2 to determine if asbestos is present.

Submit samples to a National Voluntary Laboratory Accreditation Program (NVLAP) certified laboratory for analysis by polarized light microscopy (PLM) following EPA Method 600/R-93/116.

Submit the laboratory test results to Engineer for review.

If asbestos is detected in any material sample, then all similar material are considered asbestos containing material and all similar materials are to be removed according to 00295.40.

Construction

00295.40 Asbestos Removal - Comply with 29 CFR 1910, 29 CFR 1926.1101, 40 CFR 61, 40 CFR 763, OAR 340‑248, ORS 468A and the following for locations provided in Table 00295-1A and Table 00295-1B if those materials are found to contain asbestos after testing, or are not tested:

Before beginning asbestos removal work, sign and submit all notifications and pay all fees to DEQ. Provide copies to the Engineer.

Complete and sign all manifests and bill‑of‑lading forms for transporting and disposing the ACM.

Maintain the ACM in an undamaged and non-friable condition by keeping the material wet during demolition or by using methods approved by DEQ.

Keep material sealed during transport to the disposal facility. Transport and dispose of all ACM according to OAR 340-248-280 and OAR 340-248-290.

Remove and dispose of the materials identified as having less than 1% asbestos according to 29 CFR 1926.1101, where that regulation refers to "asbestos" rather than "asbestos containing material" or "ACM".

Measurement

00295.80 Measurement - The quantities of removing asbestos containing materials will be measured on either the length basis or the area basis.

No measurement of quantities will be made for bulk asbestos sampling, analytical testing, and reporting.

Materials containing 1% or less asbestos will not be measured.

Materials containing asbestos that cover less than 3 square feet will not be measured.

Payment

00295.90 Payment - The accepted quantities of Work performed under this Section will be paid for at the Contract unit price, per unit of measurement, for the following item(s):

· Pay Item Unit of Measurement

(a) Remove Asbestos Material, FriableFoot
(b) Remove Asbestos Material, FriableSquare Foot
(c) Bulk asbestos sampling, analytical testing, and reportingLump Sum

In item (a) and (b), the type of Material will be inserted in the blank.

Payment will be payment in full for furnishing all Equipment, labor, and Incidentals necessary to complete the Work as specified.

No separate or additional payment will be made for materials containing 1% or less asbestos.

No separate or additional payment will be made for asbestos covering less than 3 square feet.

SECTION 00410 - REHABILITATE EXISTING PIPE

Section 00410, which is not a Standard Specification, is included in this Project by Special Provision.

Description

00410.00 Scope ‑ This Work consists of rehabilitating existing pipes according to Section 00412, Section 00413, or Section 00414, as indicated in Table 00410-1 as shown and selected.

00410.01 Installation Options ‑ Choose one of the approved rehabilitation methods indicated in Table 00410-1.

00410.02 Submittals ‑ Submit a pipe rehabilitation summary indicating which method is selected for each location/station as indicated in Table 00410-1. Submit required documentation according to Section 00412, Section 00413, or Section 00414, for the renewal methods indicated in Table 00410-1.

Materials

00410.10 General ‑ Furnish Materials according to Section 00412 or Section 00413 as indicated in Table 00410-1 and selected.

00410.13 Location ‑ Rehabilitate existing pipe(s) according to Table 00410-1:

Table 00410-1

Location/Station
Pipe Size

(Dia.)

(Rise x Span) (Inches) Specification Section(s) Allowed

M.P. 30.19
24”
SP00412, SP00413
M.P. 34.38
36”
SP00412, SP00413
M.P. 36.35
18”
SP00412, SP00413
M.P. 36.60
18”
SP00412, SP00413
M.P. 39.43
18”
SP00412, SP00413
M.P. 40.45
24”
SP00412, SP00413
M.P. 40.96
24”
SP00412, SP00413
M.P. 41.59
36”
SP00412, SP00413
M.P. 43.71
24”
SP00412, SP00413
M.P. 44.28
24”
SP00412, SP00413
M.P. 44.39
18”
SP00412, SP00413
M.P. 46.57
18” & 24”
SP00412, SP00413

Construction

00410.40 General ‑ Construct pipe rehabilitation according to Section 00412 or Section 00413 as indicated in Table 00410-1 and selected.

Measurement

00410.80 Measurement ‑ The quantities of Work performed under this Section will be measured according to the following:

(a) Rehabilitate pipe ‑ The quantities of installed cured-in-place pipe (CIPP) liners will be measured on the length basis. The length will be measured, with no deduction for Structures or fittings, along the pipe flow line from center to center of manholes, inlets, Structures, special sections, or the ends of pipe, whichever is applicable.

(b) Service Line Reconnections ‑ The quantities of service line reconnections will be measured on the unit basis, regardless of size.

Payment

00410.90 Payment ‑ The accepted quantities of Work performed under this Section will be paid for at the Contract unit price, per unit of measurement, for the following items:

Pay Item Unit of Measurement

(a)Rehabilitate, ___18__ Inch pipeFoot
(a)Rehabilitate, ___24__ Inch pipeFoot
(a)Rehabilitate, ___36__ Inch pipeFoot

In item (a), the diameter of the host pipe will be inserted in the blanks.

Payment will be payment in full for furnishing and placing all Materials, and for furnishing all Equipment, labor, and Incidentals necessary to complete the Work as specified.

SECTION 00412 - CURED-IN-PLACE PIPE LINING

Comply with Section 00412 of the Standard Specifications modified as follows:

00412.01 Submittals ‑ Add the following paragraph before the sentence beginning “Upon liner system…

Submit the following for approval according to 00150.37 at least 10 Calendar Days before ordering tube(s):

· Verify Pipe length, rise and span, for each installation according to Section 00415 and include the corresponding tube size that will be ordered for each installation according to 00412.10. Do not order Material(s) until approval has been received.

00412.02 Design Parameters - Add the following to the end of this subsection:

Height of fill from invertM.P. 30.197 ft.
M.P. 34.3810 ft.
M.P. 36.358 ft.
M.P. 36.607 ft.
M.P. 39.437 ft.
M.P. 40.458 ft.
M.P. 40.967 ft.
M.P. 41.597 ft.
M.P. 43.716 ft.
M.P. 44.288 ft.
M.P. 44.396 ft.
M.P. 46.575 ft.

Groundwater Elevation above invert N/A

00412.71 Post Installation Video Inspection ‑ Replace this subsection, except for the subsection number and title, with the following:

After installation of the CIPP perform a post-installation video inspection of the pipe according to Section 00415.

00412.80 Measurement ‑ Replace this subsection, except for the subsection number and title, with the following:

CIPP Liner and Service Line Reconnections will be measured according to 00410.80.

00412.90 Payment ‑ Replace this subsection, except for the subsection number and title, with the following:

CIPP Liner and Service Line Reconnections will be paid for according to 00410.90.

SECTION 00413 - GRP CURED-IN-PLACE PIPE LINING & UV CURE

Comply with Section 00413 of the Standard Specifications modified as follows:

00413.01 Submittals ‑ Add the following paragraph to the end of this subsection:

Submit the following for approval according to 00150.37 at least 10 Calendar Days before ordering tube(s):

Verify Pipe length, rise and span, for each installation according to Section 00415 and include the corresponding tube size that will be ordered for each installation according to 00413.10. Do not order Material(s) until approval has been received.

00413.02 Design Parameters - Add the following to the end of this subsection:

Height of fill from invertM.P. 30.197 ft.
M.P. 34.3810 ft.
M.P. 36.358 ft.
M.P. 36.607 ft.
M.P. 39.437 ft.
M.P. 40.458 ft.
M.P. 40.967 ft.
M.P. 41.597 ft.
M.P. 43.716 ft.
M.P. 44.288 ft.
M.P. 44.396 ft.
M.P. 46.575 ft.

Groundwater Elevation above Invert N/A

00413.80 Measurement ‑ Replace this subsection, except for the subsection number and title, with the following:

CIPP Liner will be measured according to 00410.80.

00413.90 Payment ‑ Replace this subsection, except for the subsection number and title, with the following:

CIPP Liner will be paid for according to 00410.90.

SECTION 00415 - VIDEO PIPE INSPECTION

Comply with Section 00415 of the Standard Specifications modified as follows:

Description

00415.00 Scope ‑ This Work consists of inspecting pipes by video accompanied by a recorded narrative and written report of the findings.

Equipment

00415.20 Mainline Inspection Equipment ‑ Use the following Equipment unless otherwise approved.

(a) Video Camera ‑ Use a digital color video camera with the ability to rotate 360 degrees, tilt to a 90-degree angle to the axis of the pipe and a zoom ration of at least 40:1. A light source that provides a clear image of the full pipe circumference and all areas of concern. Provide a camera and lighting system capable of operating in 100% humidity conditions.

(b) Transporter ‑ Use an all-wheel drive or track mounted transporter capable of inspecting pipes ranging in size from 12 to 60 inches and does not obstruct the camera view. A vertical and horizontal adjustable camera to maintain the camera along the approximate center of the pipe at all times. The transporter will have an adjustable operating speed while recording not to exceed 30 feet per minute.

(c) Recording Device ‑ Provide a device capable of recording video with the pipe identification, a remote meter counter displaying length along the profile in tenths of feet and indicating the camera’s position from the starting point. Calibrate the meter counter to be accurate within 0.5 percent over the length of pipe being inspected. The device must be capable of recording a digital video with a minimum resolution of 720 x 480.

Construction

00415.40 Video Inspection:

(a) Notice and Access ‑ Notify the Engineer a minimum of 48 hours before beginning cleaning or video inspection. Allow the Engineer access at all times, to observe the video monitor and all other operations.

(b) Cleaning ‑ Clean the pipe by removing all debris, sediment, and other accumulated material that would adversely impact the liner installation and function. Remove and dispose of all debris according to 00290.20.

00415.41 Liner Pre Installation Video Inspection ‑ Perform a pre-installation video inspection 5 Calendar Days before beginning Work. Begin Inspection at one end of the pipe and proceed through the entire pipe length at a speed not greater than 30 feet per minute. Move the camera through the pipe and provide a continuous 360 degree pan of each pipe joint. Stop and record all cracks, deformities, and defects to document the pipe condition, including the location of all lateral connections to the mainline.

Provide a verbal narrative on each video inspection recording. Include the company name, operator’s name, date and time of the inspection, site location, description of the pipe type, size and length, and direction of travel. As part of the recorded audio portion of the video, include a description of all observed defects, deformities, location of lateral connections and locations where digital photographs are taken.

If, during the inspection operation, the camera will not pass through the entire segment, set up Equipment so that the inspection can be performed from the opposite access point back to the obstruction.

(a) Mainline Inspection Use video inspection equipment meeting the requirements of 0415.20. Each video inspection will display and record an on-screen header containing location, pipe type, size, date and time of inspection, direction of travel, distance and owner.

00415.42 Liner Post Installation Video Inspection ‑ Perform post construction video inspection according to 00415.40 and 00415.41.

Finishing and Cleaning Up

00415.70 Video Inspection Recording and Written Inspection Report ‑ Furnish two copies of all preconstruction and post construction inspection video and reports within three Calendar Days after completing the inspections. If inspection video or audio recording quality is poor, the Engineer has the right to reject the recording and request new video inspection at no additional cost to the Agency.

(a) Inspection Report ‑ Provide an inspection report that includes each defect, deformity, and joint along with the distance from the inspection starting point. Provide still digital images in the report along with a reference and description of each defect, deformity and joint.

00415.71 Corrections to Deficiencies in Work ‑ Submit a repair plan to the Engineer for approval of all detrimental pipe deficiencies that are revealed in the recording and written report. Repair all deficiencies within 48 hours after receiving notification. Re-perform the video inspection, submit the new video, and update the written report at no additional cost to the Agency.

Measurement

00415.80 Measurement ‑ The quantities of Work performed under this Section will be measured according to the following:

(a) Mainline Video Inspection ‑ Mainline video inspection will be measured on the length basis. The length will be measured, with no deduction for Structures or fittings, along the pipe flow line from center to center of manholes, inlets, special sections, or the ends of pipe, whichever is applicable. Pipes with sloped ends will be measured from the top of the sloped end section.

Payment

00415.90 Payment ‑ The accepted quantities of Work performed under this Section will be paid for at the Contract unit price, per unit of measurement, for the following items:

Pay Item Unit of Measurement

(a) Mainline Video Inspection Foot

Payment will be payment in full for furnishing all Equipment, labor, and Incidentals necessary to complete the Work as specified.

SECTION 00440 - COMMERCIAL GRADE CONCRETE

Comply with Section 00440 of the Standard Specifications

SECTION 00445 – SANITARY, STORM, CULVERT, SIPHON, AND IRRIGATION PIPE

Comply with Section 00445 of the Standard Specifications.

SECTION 00490 - WORK ON EXISTING SEWERS AND STRUCTURES

Comply with Section 00490 of the Standard Specifications.

SECTION 00495 - TRENCH RESURFACING

Comply with Section 00495 of the Standard Specifications.

SECTION 00530 – STEEL REINFORCEMENT FOR CONCRETE

Comply with Section 00530 of the Standard Specifications.

SECTION 00540 – STRUCTURAL CONCRETE

Comply with Section 00540 of the Standard Specifications.

SECTION 00547 - PIPE INVERT PAVING

Section 00547, which is not a Standard Specification, is included in this Project by Special Provision.

Description

00547.00 Scope – This work consists of preparing the existing culvert, lining the invert of the existing culvert with reinforced concrete.

Materials

00547.10 General - Provide materials meeting the applicable requirements of Section 00396, 00440, 00530, 00540, 00560, and this section.

Construction

00547.40 General - Construct…