00012771 Intent To Award.xlsx

XLSX spreadsheet 26 KB Posted

Attached to
OR 82: Culvert Project, Minam to Wallowa
Solicitation number
S-73000-00012771
Issued by
Wasco County, Oregon

About this file

This document is an Intent to Award spreadsheet from the Oregon Department of Transportation (ODOT) for the OR 82 Culvert Repair Project, located between Minam and Wallowa in Union and Wallowa Counties. The bid solicitation was issued on 4/7/25 with a bid closing date of 04/02/2025 at 10:00 AM, targeting the rehabilitation of 22 culverts with pipe diameters ranging from 18" to 36". The project involves comprehensive infrastructure maintenance including work zone traffic control, temporary water management, culvert cleaning, CCTV inspection, CIPP liner installation, and paved invert work. The substantial completion date is set for September 12, 2025, with a final completion date of October 3, 2025, and in-water work strictly limited to July 15th through August 15th.

The bid tabulation reveals HP Civil Inc as the intended contract awardee, with a total bid of $879,907.77, which is the lowest among five bidders. Other bidders included JR Carlon Corp, Wildish Standard Paving Co, Jesse Rodriguez Construction LLC, and Whitaker Construction, with bids ranging from $955,085.02 to $1,499,573.00. The project is state-funded and subject to prevailing wage rates, with bidders required to possess Oregon Construction Contractors Board registration and DEQ Asbestos Abatement Contractor licenses. Performance and payment bonds are required at 100% of the contract price, with insurance requirements including $2,000,000 commercial general liability per occurrence and $5,000,000 annual aggregate. Liquidated damages are established at $700 per calendar day for failing to achieve substantial completion by the specified date.

View the file

Other files

File Type Posted
20252004_A2_IT Service Management Platform_Addendum 1.pdf PDF
00012771 Preliminary Results.xlsx XLSX spreadsheet
Invitation.To.Bid~12.docx DOCX document
Attachment A Plans~6.pdf PDF
Attachment C Bid Pricing Form~13.xlsx XLSX spreadsheet
Attachment B_Special Provisions and Specifications.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Date Issued:4/7/25
ITB No.S-73000-00012771BIDDER
NAME:HP Civil IncJR Carlon CorpWildish Standard Paving CoJesse Rodriguez Construction LLCWhitaker Construcion
Bid Closing:04/02/2025 @ 10:00 AM
Description:OR 82 Culvert Repair Project
This bid tabulation shall serve as ODOT's notice of intent to award a contract to (HP Civil INC). Aggrieved Bidders have 5 calendar days from the issued date shown above to protest the intent to award.
Bid Item #DescriptionEst
QTYUNITUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL

PRICE

1Mobilization1LS$ 87,990.77$ 87,990.77$110,000.00$ 110,000.00$98,558.00$ 98,558.00$ 110,000.00$ 110,000.00$322,500.00$ 322,500.00$ - 0$ - 0$ - 0
2Temporary Protection and Direction of Traffic1LS$ 90,000.00$ 90,000.00$ 49,680.00$ 49,680.00$ 100,000.00$ 100,000.00$ 155,976.00$ 155,976.00$ 89,800.00$ 89,800.00$ - 0$ - 0$ - 0
3Temporary Signs236SQFT$ 25.00$ 5,900.00$ 75.00$ 17,700.00$ 40.00$ 9,440.00$ 12.00$ 2,832.00$ 170.00$ 40,120.00$ - 0$ - 0$ - 0
4Flaggers432HOURS$ 72.00$ 31,104.00$ 123.25$ 53,244.00$ 70.00$ 30,240.00$ 95.00$ 41,040.00$ 97.00$ 41,904.00$ - 0$ - 0$ - 0
5Automated Flagger Assistance Device2EACH$ 3,500.00$ 7,000.00$ 4,060.00$ 8,120.00$ 1,000.00$ 2,000.00$ 1,300.00$ 2,600.00$ 5,450.00$ 10,900.00$ - 0$ - 0$ - 0
6Flagger station lighting2EACH$ 800.00$ 1,600.00$ 600.00$ 1,200.00$ 500.00$ 1,000.00$ 500.00$ 1,000.00$ 5,950.00$ 11,900.00$ - 0$ - 0$ - 0
7Temporary Water Management, MP 40.451LS$ 5,000.00$ 5,000.00$ 8,500.00$ 8,500.00$ 7,000.00$ 7,000.00$ 8,900.00$ 8,900.00$ 8,180.00$ 8,180.00$ - 0$ - 0$ - 0
8Temporary Water Management, MP 41.591LS$ 5,000.00$ 5,000.00$ 8,500.00$ 8,500.00$ 7,000.00$ 7,000.00$ 8,900.00$ 8,900.00$ 8,180.00$ 8,180.00$ - 0$ - 0$ - 0
9Temporary Water Management, MP 44.071LS$ 35,000.00$ 35,000.00$ 23,018.85$ 23,018.85$ 35,000.00$ 35,000.00$ 20,000.00$ 20,000.00$ 15,000.00$ 15,000.00$ - 0$ - 0$ - 0
10Erosion Control1LS$ 5,000.00$ 5,000.00$ 1,500.00$ 1,500.00$ 5,000.00$ 5,000.00$ 3,295.00$ 3,295.00$ 13,700.00$ 13,700.00$ - 0$ - 0$ - 0
11Pollution Control Plan1LS$ 500.00$ 500.00$ 1,500.00$ 1,500.00$ 1,000.00$ 1,000.00$ 1,250.00$ 1,250.00$ 3,590.00$ 3,590.00$ - 0$ - 0$ - 0
12Contaminated Soil Disposal37TON$ 90.00$ 3,330.00$ 300.00$ 11,100.00$ 50.00$ 1,850.00$ 350.00$ 12,950.00$ 3,720.00$ 137,640.00$ - 0$ - 0$ - 0
13Remove Asbestos Material, Non-Friable86FOOT$ 45.00$ 3,870.00$ 211.00$ 18,146.00$ 50.00$ 4,300.00$ 177.00$ 15,222.00$ 1,620.00$ 139,320.00$ - 0$ - 0$ - 0
14Remove Asbestos Material, Non-Friable6SQFT$ 200.00$ 1,200.00$ 1,200.00$ 7,200.00$ 50.00$ 300.00$ 518.00$ 3,108.00$ 2,320.00$ 13,920.00$ - 0$ - 0$ - 0
15Bulk Asbestos Sampling, Analytical Testing, and Reporting1LS$ 4,000.00$ 4,000.00$ 8,500.00$ 8,500.00$ 2,000.00$ 2,000.00$ 24,975.00$ 24,975.00$ 19,100.00$ 19,100.00$ - 0$ - 0$ - 0
16Class 100 loose riprap15CY$ 175.00$ 2,625.00$ 200.00$ 3,000.00$ 300.00$ 4,500.00$ 225.00$ 3,375.00$ 270.00$ 4,050.00$ - 0$ - 0$ - 0
17Rehabilitate 18" culvert354FOOT$ 350.00$ 123,900.00$ 393.30$ 139,228.20$ 400.00$ 141,600.00$ 403.00$ 142,662.00$ 390.00$ 138,060.00$ - 0$ - 0$ - 0
18Rehabilitate 24" culvert412FOOT$ 375.00$ 154,500.00$ 420.90$ 173,410.80$ 450.00$ 185,400.00$ 435.00$ 179,220.00$ 390.00$ 160,680.00$ - 0$ - 0$ - 0
19Rehabilitate 36" culvert212FOOT$ 575.00$ 121,900.00$ 579.60$ 122,875.20$ 625.00$ 132,500.00$ 523.00$ 110,876.00$ 570.00$ 120,840.00$ - 0$ - 0$ - 0
20Mainline Video Inspection1956FOOT$ 10.50$ 20,538.00$ 14.40$ 28,166.40$ 15.00$ 29,340.00$ 23.00$ 44,988.00$ 4.00$ 7,824.00$ - 0$ - 0$ - 0
2118 inch culvert Pipe, 5 ft depth76FOOT$ 500.00$ 38,000.00$ 325.00$ 24,700.00$ 360.00$ 27,360.00$ 875.00$ 66,500.00$ 535.00$ 40,660.00$ - 0$ - 0$ - 0
2218 inch culvert Pipe, 10 ft depth35FOOT$ 500.00$ 17,500.00$ 810.00$ 28,350.00$ 500.00$ 17,500.00$ 1,275.00$ 44,625.00$ 765.00$ 26,775.00$ - 0$ - 0$ - 0
2324 inch culvert pipe, 5 ft depth13FOOT$ 715.00$ 9,295.00$ 600.00$ 7,800.00$ 600.00$ 7,800.00$ 975.00$ 12,675.00$ 840.00$ 10,920.00$ - 0$ - 0$ - 0
2436 inch culvert pipe, 5 ft depth9FOOT$ 820.00$ 7,380.00$ 900.00$ 8,100.00$ 900.00$ 8,100.00$ 1,275.00$ 11,475.00$ 1,170.00$ 10,530.00$ - 0$ - 0$ - 0
25Invert Paving of Existing Culvert1LS$ 65,000.00$ 65,000.00$ 47,120.57$ 47,120.57$ 100,000.00$ 100,000.00$ 72,999.00$ 72,999.00$ 38,500.00$ 38,500.00$ - 0$ - 0$ - 0
26Filling Abandon structures1EACH$ 15,000.00$ 15,000.00$ 7,850.00$ 7,850.00$ 7,000.00$ 7,000.00$ 13,500.00$ 13,500.00$ 8,200.00$ 8,200.00$ - 0$ - 0$ - 0
27Remove and reinstall guardrail16FOOT$ 80.00$ 1,280.00$ 650.00$ 10,400.00$ 200.00$ 3,200.00$ 50.00$ 800.00$ 1,100.00$ 17,600.00$ - 0$ - 0$ - 0
28Trench resurfacing32SQYD$ 170.00$ 5,440.00$ 300.00$ 9,600.00$ 200.00$ 6,400.00$ 375.00$ 12,000.00$ 690.00$ 22,080.00$ - 0$ - 0$ - 0
29Permanent Seeding0.2ACRE$ 9,600.00$ 1,920.00$ 1,500.00$ 300.00$ 9,000.00$ 1,800.00$ 9,600.00$ 1,920.00$ 37,200.00$ 7,440.00$ - 0$ - 0$ - 0
30Culvert Drainage Markers, Type 121EACH$ 200.00$ 4,200.00$ 275.00$ 5,775.00$ 200.00$ 4,200.00$ 200.00$ 4,200.00$ 230.00$ 4,830.00$ - 0$ - 0$ - 0
31Culvert Drainage Markers, Type 221EACH$ 235.00$ 4,935.00$ 500.00$ 10,500.00$ 200.00$ 4,200.00$ 200.00$ 4,200.00$ 230.00$ 4,830.00$ - 0$ - 0$ - 0
TOTAL$ 879,907.77$ 955,085.02$ 985,588.00$ 1,138,063.00$ 1,499,573.00$ - 0$ - 0$ - 0