This is a Statement of Work (SOW) for fire-rated door repairs and replacements at the Hopi Health Care Center. The contractor must complete all work within thirty (30) calendar days after contract award, performing services Monday through Friday, 8:00 a.m. to 5:00 p.m., excluding federal holidays. Any work outside normal business hours requires prior Government approval.
The scope of work includes replacing two (2) failed fire-rated housekeeping entrance doors with 45-minute rated wood door slabs, automatic flush bolts, door replacement kits, and performing required clearance corrections, door alignment and adjustments, removal and disposal of existing doors, and functional testing. The contractor must also repair twenty (20) existing fire-rated doors, which may include door adjustments, clearance corrections, gap correction kit installations, gravity coordinator replacements, strike replacements and shims, smoke seal replacements, defective hardware replacement, and operational testing. Upon completion, the contractor shall perform complete operational inspections of all repaired and replaced doors, verify proper hardware operation and door clearances, ensure compliance with NFPA 80 requirements and Joint Commission standards, and correct any deficiencies discovered during final inspection. The contractor is responsible for furnishing all labor, supervision, equipment, tools, and materials; employing qualified personnel; protecting Government property; maintaining safe work areas; and removing all construction debris. All work must comply with NFPA 80, OSHA safety requirements, applicable Federal, State, and Local Codes, hospital safety requirements, and Joint Commission Life Safety Standards. Two points of contact from Facilities Management are provided: Joseph Yoiwaima (928) 737-6033 and Wyatt Mase (928) 737-6023. Attachment A lists replacement hardware specifications including clearance corrections (NGP 9200C), door slabs, automatic flush bolts (Corner 2942-26D), and door replacement kits. Attachment B details repair hardware including adjustments, clearance corrections, gap correction kits, gravity coordinators, strikes, shims, and smoke seals with specific order quantities.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW)
Fire-Rated Door Repairs and Replacements
Project: Housekeeping Entrance Fire Door Repairs and Replacements Location: Hopi Health Care Center
1. PURPOSE
The purpose of this Statement of Work (SOW) is to obtain a qualified contractor to furnish all labor, supervision, materials, equipment, tools, transportation, and incidental services necessary to repair, replace, inspect, and certify fire-rated door assemblies at the Hopi Health Care Center. All work shall restore the designated fire doors to full operational condition and compliance with applicable life safety requirements.
2. PERIOD OF PERFORMANCE
The Contractor shall complete all work within thirty (30) calendar days after receipt of the contract award.
Work shall be performed during normal business hours:
• Monday through Friday
• 8:00 a.m. – 5:00 p.m.
• Excluding Federal holidays
Any work performed outside normal business hours shall require prior approval from the Government.
3. SCOPE OF WORK
The Contractor shall provide all labor, materials, equipment, supervision, transportation, permits (if required), and disposal necessary to complete the following work.
3.1 Fire Door Replacements
Replace two (2) failed fire-rated housekeeping entrance doors.
Replacement work shall include all materials and hardware necessary for complete installation, including but not limited to:
• Fire-rated wood door slabs (45-minute rated)
• Automatic flush bolt
• Door replacement kit
• Required clearance corrections
• Door alignment and adjustments
• Removal and disposal of existing doors
• Functional testing following installation
The replacement doors shall be installed in accordance with the manufacturer's recommendations and NFPA 80 requirements.
3.2 Fire Door Repairs
Repair twenty (20) existing fire-rated doors.
Repairs may include, but are not limited to:
• Door adjustments
• Clearance corrections
• Installation of gap correction kits
• Gravity coordinator replacement
• Strike replacement
• Strike shims
• Smoke seal replacement
• Replacement of defective fire door hardware
• Hardware adjustments and operational testing
The Contractor shall provide all replacement hardware identified during the inspection and listed in the attached schedule of required repair components.
3.3 Inspection and Testing
Upon completion of repairs and replacements, the Contractor shall:
• Perform a complete operational inspection of all repaired and replaced fire doors.
• Verify proper operation of all hardware.
• Verify proper door clearances.
• Ensure each fire-rated door assembly complies with NFPA 80 requirements.
• Ensure work satisfies applicable Joint Commission standards.
• Correct any deficiencies discovered during final inspection prior to project acceptance.
4. MATERIALS
The Contractor shall furnish all materials necessary to complete this project.
Replacement hardware shall be equivalent to the products identified in the attached hardware schedule unless otherwise approved by the Contracting Officer or Contracting Officer's Representative (COR).
No substitutions shall be made without prior Government approval.
5. CONTRACTOR RESPONSIBILITIES
The Contractor shall:
• Furnish all labor, supervision, equipment, tools, and materials.
• Employ qualified personnel experienced in fire-rated door installation and repair.
• Perform work in a professional, workmanlike manner.
• Protect Government property from damage.
• Repair or replace any Government property damaged by Contractor personnel at no additional cost.
• Maintain a clean and safe work area throughout the project.
• Remove and dispose of all construction debris off Government property.
• Coordinate work activities to minimize disruption to hospital operations.
6. CODES AND STANDARDS
All work shall comply with applicable editions of:
• NFPA 80 – Standard for Fire Doors and Other Opening Protectives
• OSHA Safety Requirements
• Applicable Federal, State, and Local Codes
• Hospital safety requirements
• Joint Commission Life Safety Standards
• Manufacturer installation requirements
7. QUALITY CONTROL
The Contractor shall perform quality control inspections throughout the project to ensure:
• Proper installation
• Correct operation of all hardware
• Compliance with fire door requirements
• Completion of all identified repairs prior to Government acceptance
8. SAFETY
The Contractor shall:
• Provide all required Personal Protective Equipment (PPE).
• Maintain a safe work environment.
• Comply with OSHA regulations.
• Prevent interference with hospital staff, patients, visitors, and emergency services.
• Maintain safe pedestrian and vehicle access throughout construction.
9. CLEANUP
At the completion of work, the Contractor shall:
• Remove all debris, packaging, and discarded materials.
• Clean the work area.
• Dispose of all waste at an approved off-site disposal facility.
• Leave the work area in a clean, safe, and operational condition.
10. GOVERNMENT ACCEPTANCE
Government acceptance will occur after:
• Completion of all repairs and replacements.
• Successful final inspection.
• Verification that all fire doors operate correctly.
• Confirmation that all work complies with NFPA 80 and Joint Commission requirements.
11. POINTS OF CONTACT
Facilities Management
• Joseph Yoiwaima – (928) 737-6033
• Wyatt Mase – (928) 737-6023
Attachments
Attachment A – Fire Door Replacement Hardware Schedule
• Clearance Corrections (NGP 9200C)
• 45-Minute Fire-Rated Wood Door Slabs
• Automatic Flush Bolt (Corner 2942-26D)
• Door Replacement Kit
Attachment B – Fire Door Repair Hardware Schedule
• Door Adjustments
• Clearance Corrections
• Gap Correction Kits
• Gravity Coordinators
• Top Strikes
• Strike Shims
• Smoke Seals
• Other required replacement hardware as identified in the attached parts list.