Attachment B - Bid Schedule.pdf

PDF 144 KB Posted

Attached to
Garfield County Coroner’s Office RTU Replacement
Solicitation number
IFB-GC-FM-07-25
Issued by
Gilpin County, Colorado

About this file

This document is a Bid Schedule (Attachment B) for the Garfield County Coroner's Office Roof Top Unit (RTU) Replacement project, solicited under the Invitation for Bid (IFB) number IFB-GC-FM-07-25. The project involves the replacement of two RTUs at the Garfield County Coroner's Office, with a defined completion deadline of December 31, 2025. The bid requires a comprehensive, turn-key solution that includes all necessary permits, inspections, labor, equipment, materials, payment and performance bonds, warranty, and services required for project initiation, construction, and completion.

The pricing for this project is to be submitted as a single lump sum, covering all aspects of the two RTU replacements as specified in the plans and specifications. The bid schedule provides space for bidders to enter their total bid amount in both numerical and written formats, and requires acknowledgment of any addendums. The document emphasizes that timing is of the essence, and the contractor must commit to diligent construction and completion by the specified deadline. Bidders are required to thoroughly review all bid documents, including the IFB, addendums, and attachments, and provide complete contact information and an authorized signature when submitting their proposal.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment B – Bid Schedule

IFB-GC-FM-07-25

Attachment B – Bid Schedule

IFB-GC-FM-07-25

Garfield County Coroner’s Office RTU Replacement

Pricing Price is to include, but not limited to, all permits, inspections, labor, equipment, materials, payment and performance bonds, warranty, and services as required to effect initiation, construction, and completion of a turn-key project per lump sum.

Item 1: Total Bid for Two (2) RTU Replacements per Plans & Specs

$ lump sum (in Numbers)

$ lump sum (in Words)

Acknowledgement of Addendum(s) #

Schedule The Contractor agrees that timing is of the essence in the performance of this contract. Once started, Contractor agrees to continue construction diligently and must complete all work by December 31, 2025.

By signing below, the undersigned affirmatively states that it has read and fully understands the requirements of IFB-GC-FM-07-25 and all addendum and attachments thereto and has familiarized itself with the requirements of that IFB. The undersigned submits the following bid to complete the Garfield County Coroner’s Office RTU Replacement at the prices and schedule quoted herein.

Firm Submitting Bid Address

Printed Name and Title of Signer City State Zip

Authorized Signature Telephone Number

Date Fax Number

Email Address

File details come from the government source that posted it. Updated .