WORK ORDER NO. 1599959

B-30 EOC Renovation

At the

Naval Station Norfolk, Norfolk, Virginia

DESIGNED BY:

NAVFAC MIDLANT; PWD NORFOLK; FACILITIES ENGINEERING

9742 MARYLAND AVENUE

NORFOLK, VIRGINIA 23511-3095

SPECIFICATION PREPARED BY:

Architectural: Lacie A Beemer, RA Mechanical/Plumbing: Bobby Kreie Electrical: C. Matt Hinson, PE Structural: Kim Davis, PE Fire Protection: Yong Kye, PE Civil: Luu Phu Interior Designer: Christine McKinley, CID

SPECIFICATION APPROVED BY:

Lead Discipline Branch Manager: Amanda L Pillo, RA Design Director: James M Smith, RA Engineering Director: Sean M Sweeney, P.E.

For Commander, NAVFAC MID-ATLANTIC:

Date:

EOC Renovation 1599959

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 01 15 LIST OF DRAWINGS

00 22 13.00 20 SUPPLEMENTARY INSTRUCTIONS TO OFFERORS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 SUMMARY OF WORK

01 14 00 WORK RESTRICTIONS

01 20 00.00 20 PRICE AND PAYMENT PROCEDURES

01 30 00 ADMINISTRATIVE REQUIREMENTS

01 30 01.00 22 DESIGN, PROCUREMENT AND INSTALLATION OF FURNITURE,

FIXTURES AND EQUIPMENT

01 31 23.13 20 ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT

MANAGEMENT SYSTEM

01 32 17.00 20 NETWORK ANALYSIS SCHEDULES (NAS)

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.10 20 QUALITY CONTROL FOR MINOR CONSTRUCTION

01 45 35 SPECIAL INSPECTIONS

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 57 19.01 20 SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS

01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT

01 78 00 CLOSEOUT SUBMITTALS

01 78 23 OPERATION AND MAINTENANCE DATA

DIVISION 02 - EXISTING CONDITIONS

02 41 00 DEMOLITION

02 82 00 ASBESTOS REMEDIATION

DIVISION 04 - MASONRY

04 20 00 UNIT MASONRY

DIVISION 05 - METALS

05 05 20.00 27 POST-INSTALLED CONCRETE ANCHORS

05 50 13 MISCELLANEOUS METAL FABRICATIONS

05 52 00.00 27 NON PENETRATING PERMANENT PERSONNEL GUARDRAIL

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 10 00 ROUGH CARPENTRY

06 41 16.00 10 PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS

06 61 16 SOLID SURFACING FABRICATIONS

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 21 16 MINERAL FIBER BLANKET INSULATION

07 84 00 FIRESTOPPING

07 92 00 JOINT SEALANTS

DIVISION 08 - OPENINGS

PROJECT TABLE OF CONTENTS Page 1

08 11 13 STEEL DOORS AND FRAMES

08 11 16 ALUMINUM DOORS AND FRAMES

08 14 00 WOOD DOORS

08 71 00 DOOR HARDWARE

08 81 00 GLAZING

DIVISION 09 - FINISHES

09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD

09 29 00 GYPSUM BOARD

09 65 00 RESILIENT FLOORING

09 68 00 CARPETING

09 90 00 PAINTS AND COATINGS

DIVISION 10 - SPECIALTIES

10 11 00 VISUAL DISPLAY UNITS

10 14 00.20 INTERIOR SIGNAGE

10 28 13 TOILET ACCESSORIES

10 44 16 FIRE EXTINGUISHERS

10 71 13.13 STORM SHUTTERS

DIVISION 12 - FURNISHINGS

12 21 00 WINDOW BLINDS

DIVISION 21 - FIRE SUPPRESSION

21 13 13.00 20 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS

23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS

23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC

23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS

23 81 00.00 20 UNITARY AIR CONDITIONING EQUIPMENT

DIVISION 26 - ELECTRICAL

26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS

26 20 00 INTERIOR DISTRIBUTION SYSTEM

26 51 00 INTERIOR LIGHTING

DIVISION 27 - COMMUNICATIONS

27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM

27 51 16 RADIO AND PUBLIC ADDRESS SYSTEMS

27 54 00.00 20 COMMUNITY ANTENNA TELEVISION (CATV) SYSTEMS

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

28 08 10 ELECTRONIC SECURITY SYSTEM ACCEPTANCE TESTING

28 10 05 ELECTRONIC SECURITY SYSTEMS (ESS)

28 31 76.00 22 INTERIOR FIRE ALARM SYSTEM, ADDRESSABLE

DIVISION 33 - UTILITIES

33 11 00 WATER UTILITY DISTRIBUTION PIPING

PROJECT TABLE OF CONTENTS Page 2

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 3

DOCUMENT 00 01 15

LIST OF DRAWINGS

02/11

PART 1 GENERAL

1.1 SUMMARY

This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings, Maps and Specifications."

1.2 CONTRACT DRAWINGS

Contract drawings are as follows:

G-001 12,812,421 COVER SHEET

G-002 12,812,422 LIST OF SHEETS, GENERAL PROJECT NOTES AND SYMBOLS

GI101 12,812,423 FIRST FLOOR PLAN - LIFE SAFETY

HM101 12,812,424 PARTIAL FIRST FLOOR PLAN - HAZMAT ABATEMENT PLAN

C-100 12,812,425 CIVIL GENERAL NOTES, ABBREVIATIONS AND LEGEND

C-101 12,812,426 UTILITY LAYOUT

C-501 12,812,427 CIVIL DETAILS

S-001 12,812,428 GENERAL NOTES AND PLAN LEGEND

S-101 12,812,429 ROOF PLAN

A-001 12,812,430 ARCHITECTURAL SYMBOLS, LEGENDS, ABBREVIATIONS AND NOTES

AD101 12,812,431 PARTIAL FIRST FLOOR PLAN - DEMOLITION

AD102 12,812,432 ROOF PLAN - DEMOLITION

A-101 12,812,433 PARTIAL FIRST FLOOR PLAN - NEW

A-102 12,812,434 PARTIAL FIRST FLOOR REFLECTED CEILING PLAN

A-103 12,812,435 ROOF PLAN - NEW

A-201 12,812,436 PARTIAL EXTERIOR ELEVATIONS

A-301 12,812,437 WALL SECTIONS

A-401 12,812,438 ENLARGED PLANS AND DETAILS

A-402 12,812,439 PLAN DETAILS

A-501 12,812,440 DOOR SCHEDULE, FRAME TYPES AND DETAILS

A-502 12,812,441 DOOR DETAILS

A-601 12,812,442 INTERIOR FINISHES AND SIGNAGE

A-602 12,812,443 INTERIOR PARTITION TYPE SCHEDULE & DETAILS

IF-101 12,812,444 FURNITURE PLAN

FA001 12,812,445 FIRE ALARM SYMBOLS, LEGEND, ABBREVIATIONS AND NOTES

FD101 12,812,446 FIRST FLOOR PLAN - DEMOLITION FIRE ALARM

FA101 12,812,447 FIRST FLOOR PLAN - FIRE ALARM

FA102 12,812,448 SECOND FLOOR PLAN - FIRE ALARM

FA103 12,812,449 THIRD FLOOR PLAN - FIRE ALARM

FX001 12,812,450 FIRE SUPPRESSION SYMBOLS, LEGEND, ABBREVIATIONS

AND NOTES

FX101 12,812,451 FIRST FLOOR PLAN - FIRE SUPPRESSION, PART A

FX102 12,812,452 FIRST FLOOR PLAN - FIRE SUPPRESSION, PART B

FX103 12,812,453 SECOND FLOOR PLAN - FIRE SUPPRESSION, PART A

FX104 12,812,454 SECOND FLOOR PLAN - FIRE SUPPRESSION, PART B

DOCUMENT 00 01 15 Page 1

FX105 12,812,455 THIRD FLOOR PLAN - FIRE SUPPRESSION, PART A

FX106 12,812,456 THIRD FLOOR PLAN - FIRE SUPPRESSION, PART B

M-001 12,812,457 MECHANICAL LEGEND, ABREVIATIONS AND NOTES

MD101 12,812,458 PARTIAL FIRST FLOOR PLAN - DEMOLITION

M-101 12,812,459 PARTIAL FIRST FLOOR PLAN - NEW WORK

M-501 12,812,460 DETAILS

M-601 12,812,461 MECHANICAL SCHEDULES

E-001 12,812,462 ELECTRICAL SYMBOLS, LEGEND, ABBREVIATIONS AND NOTES

ED101 12,812,463 FLOOR PLAN - DEMOLITION

EL101 12,812,464 FLOOR PLAN - LIGHTING

EL601 12,812,465 LUMINAIRE SCHEDULES AND DETAILS

EP101 12,812,466 FLOOR PLAN - POWER

EP601 12,812,467 POWER RISER, SCHEDULES, AND DETAILS

TT101 12,812,468 FLOOR PLAN - TELECOMMUNICATIONS

TT501 12,812,469 DIAGRAMS AND DETAILS

TT502 12,812,470 DIAGRAM AND DETAILS

-- End of Document --

DOCUMENT 00 01 15 Page 2

DOCUMENT 00 22 13.00 20

SUPPLEMENTARY INSTRUCTIONS TO OFFERORS

02/14

PART 1 GENERAL

1.1 CONTRACT LINE ITEMS

The terms Offeror and Bidder and versions thereof (offer/bid) have the same definition as used within this contract.

Provide the Contract Line Item (CLIN) lump sum price for the following items:

CLIN 0001 - BASE PRICE. Price includes the following:

CLIN 0001AA. Price for the entire work for Facility B-30, complete to the 5 foot line outside of the building, in accordance with the drawings and specifications.

CLIN DESCRIPTION TOTAL PRICE FOR

CLIN 0001AA

0001AA All work associated with Building B-30, complete in accordance with the drawings and specifications, but excluding work described in Contract Line Item (CLIN) 0001AB thru 0001AG, CLIN 002, and CLIN 003.

The quantities in CLIN 0001AB thru CLIN 0001AG are above and beyond those indicated in the contract drawings for work to be completed at Building B-30.These items will only be performed at the direction of the Contracting Officer.

CLIN 0001AB. Price for the removal and disposal of unidentified asbestos containing pipe elbow insulation in accordance with the following schedule:

CLIN ITEM UNIT UNIT PRICE NO. UNITS TOTAL PRICE

FOR CLIN

0001AB (UNIT

PRICE X NO.

UNITS)

0001AB Removal and Disposal of unidentified asbestos containing pipe elbow insulation

Each $ 200 $__________

DOCUMENT 00 22 13.00 20 Page 1

CLIN 0001AC. Price for the removal and disposal of unidentified asbestos containing pipe insulation up to 4" diameter in accordance with the following schedule:

CLIN ITEM UNIT UNIT PRICE NO. UNITS TOTAL PRICE

FOR CLIN

0001AB (UNIT

PRICE X NO.

UNITS)

0001AC Removal and Disposal of unidentified asbestos containing pipe insulation up to 4" diameter

Linear Feet

$ 1500 $__________

CLIN 0001AD. Price for the removal and disposal of unidentified asbestos containing pipe insulation up to 4" to 8" diameter in accordance with the following schedule:

CLIN ITEM UNIT UNIT PRICE NO. UNITS TOTAL PRICE

FOR CLIN

0001AB (UNIT

PRICE X NO.

UNITS)

0001AD Removal and Disposal of unidentified asbestos containing pipe insulation up to 4" to 8" diameter

Linear Feet

$ 1000 $__________

CLIN 0001AE. Price for removal and disposal of unidentified asbestos containing mastic in accordance with the following schedule:

DOCUMENT 00 22 13.00 20 Page 2

CLIN ITEM UNIT UNIT PRICE NO. UNITS TOTAL PRICE

FOR CLIN

0001AE (UNIT

PRICE X NO.

UNITS)

0001AE Removal and Disposal of unidentified asbestos containing mastic

Square Feet

$_______ 1000 $__________

CLIN 0001AF. Price for removal and disposal of unidentified asbestos containing floor tile with mastic in accordance with the following schedule:

CLIN ITEM UNIT UNIT PRICE NO. UNITS TOTAL PRICE FOR

CLIN 0001AF

(UNIT PRICE X

NO. UNITS)

0001AF Removal and Disposal of unidentifed asbestos containing floor tile with mastic

Square Feet

$_______ 500 $_______

CLIN 0001AG. Price for removal and disposal of unidentified asbestos containing duct insulation in accordance with the following schedule:

CLIN ITEM UNIT UNIT PRICE NO. UNITS TOTAL PRICE FOR

CLIN 0001AF

(UNIT PRICE X

NO. UNITS)

0001AG Removal and Disposal of unidentifed asbestos containing duct insulation

Square Feet

$_______ 1000 $_______

CLIN 0002 Planned Modification Item 1 - Price includes the following:

Price to procure and supervise installation of the Furniture, Fixtures, and Equipment (FF&E) complete in accordance with the plans and specifications and in accordance with the following schedule:

DOCUMENT 00 22 13.00 20 Page 3

CLIN ITEM GOVERNMENT

FF&E ESTIMATE

HAR

(NTE

5%)

HAR AMOUNT

(GOVT FF&E

ESTIMATE x

HAR%)

TOTAL FF&E

ESTIMATED AMOUNT

FOR CLIN 0004

(GOVT FF&E

ESTIMATE + HAR

AMOUNT)

0002 FF&E $122,000 % $_______ $_______

CLIN 0003 Planned Modification Item 2 - Price includes the following:

Price for providing work in connection with all labor, material, equipment, transportation and supervision required for the Audio/Visual (A/V) complete in accordance with the plans and specifications and the following schedule:

CLIN ITEM GOVERNMENT

A/V ESTIMATE

A/V

(HAR

NTE 5%)

HAR AMOUNT

(GOVT A/V

ESTIMATE x

HAR%)

TOTAL A/V

ESTIMATED AMOUNT

FOR CLIN 0005

(GOVT A/V

ESTIMATE + HAR

AMOUNT)

0003 Audio/Visual (A/V)

$25,346 % $_______ $_______

1.2 GENERAL BID NOTES

a. Award will be made on the total sum of Contract Line Item 0001AA.

1.3 PLANNED MODIFICATION BID NOTES

These notes apply to Planned Modification CLINs.

a. The estimated amount for FF&E and A/V has been supplied by the Government, to provide offerors with the projected magnitude of effort. The estimated amount includes the actual cost of the FF&E and A/V including freight and installation charges. The Government FF&E and A/V Estimate is only an estimated amount.

b. If awarded, line items will be funded separately after completion of FF&E and A/V design package review by the Government, and receipt of appropriate funding by the Government. Requirements and details are provided in Section 01 30 01.00 20 DESIGN PROCUREMENT AND INSTALLATION

OF FURNITURE, FIXTURES, AND EQUIPMENT.

c. Bonding is not required for the design, procurement and installation of FF&E and A/V equipment.

d. Offerors may propose a Handling and Administration Rate (HAR) for the FF&E and A/V not to exceed 5 percent. This fee will account for all administrative costs, overhead, bonding fees, administration of subcontracts, profit, and any other costs associated with and related to the coordination and processing of the procurement and installation of FF&E and A/V. The proposed HAR percentage will be incorporated into the contract award and will not be adjusted regardless of fluctuations from the estimate amount for the FF&E and A/V. The proposed HAR is a

DOCUMENT 00 22 13.00 20 Page 4 fixed rate.

e. The Government is not obligated to award the Planned Modification line item(s). Should the Government choose to award the Planned Modification, the line item will be awarded as a negotiated modification to the contract/task order. The Contractor's proposed HAR will be applied to all vendor/supplier costs for the FF&E and A/V.

f. If awarded, the FF&E and A/V modification will be awarded at least six months prior to the contract completion date. A minimum of six months is required for the Contractor to purchase, deliver and install the FF&E and A/V without impacting the overall completion date of the project. The Contractor's schedule must assume the award of the FF&E and A/V as a modification. No schedule extensions will be granted if the modification is awarded at least six months prior to the contract completion date. If the Government decides to negotiate and award the furniture modification with less than six months prior to the contact completion date, the Contractor may be entitled to a contract extension and extended field overhead. A contract extension and extended field overhead will only be granted in those cases where the Contractor demonstrates that an accepted Final FF&E and A/V package was submitted within the approved schedule deadlines and sufficient lead time for the FF&E and A/V is not available and the Government's award of the modification is in the last six months of the contract.

g. Price for obtaining the services for an Interior Designer, certified by the National Council for Interior Design Qualification (NCIDQ), to prepare supporting plans and procurement data, in accordance with the design schedule. Tasks must include but are not limited to:

gathering the Activity's project FF&E, execution of the FF&E Best Value Determination process, coordination of the building's systems, and as-built conditions are identified and noted on the floor plans and construction drawings, devlopment of Final FF&E Package to include furniture/equipment plans, procurement data sheets, cost summary, 8.5" x 11" FF&E finish boards and any supplementary documentation, attend meetings with the Activity and NAVFAC MIDLANT, and perform final FF&E walk-through and punch list(s). Refer to specification section, 01 30 01.00 20 DESIGN, PROCUREMENT AND INSTALLATION OF FURNITURE, FIXTURES, AND EQUIPMENT in Administrative Requirements.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Document --

DOCUMENT 00 22 13.00 20 Page 5

SECTION 01 11 00

SUMMARY OF WORK

08/15

PART 1 GENERAL

1.1 WORK COVERED BY CONTRACT DOCUMENTS

1.1.1 Project Description

This project is a renovation of the north first floor wing of B-30 (Approx 5,225 sf). Renovated spaces are all interior and will include a kitchen, bunk room, conference room, storage, classroom for up to 40 people, EOC and ISAC spaces, and 4 offices. Fire Protection, HVAC, and Electrical will all be updated to work for the new layout. Fire sprinklers are being added to the entire building with required Civil work to accomodate.

1.1.2 Location

The work is located at Building B-30, Naval Station, Norfolk, VA approximately as indicated. The exact location will be shown by the Contracting Officer.

1.2 OCCUPANCY OF PREMISES

Building will be occupied during performance of work under this Contract.

Occupancy notifications will be posted in a prominent location in the work area.

Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.

1.3 EXISTING WORK

In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

1.4 LOCATION OF UNDERGROUND UTILITIES

Obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities.

Contact local utility locating service a minimum of 48 hours prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings, within area of work.

Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities,and any type of underground obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed.

Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.

1.4.1 Notification Prior to Excavation

Notify the Contracting Officer at least 48 hours prior to starting excavation work.

1.5 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT

Pursuant to Contract Clause FAR 52.245-1 Government Property, the Government will furnish the following materials and equipment for installation by the Contractor:

DESIGNATION NO. DESCRIPTION QUANTITY

46" MONITOR 2*

Printer/Copier Combo

1*

Digital Weather Radio

Digital Clock 2

Video Camera 2

CCTV

Camera/Door Bell

Video Projector

Quantities indicated for the above-listed items marked with an asterisk are estimates. It is the intention of the Government to furnish all quantities of the asterisk items required to complete the work as specified, and the various quantities will be adjusted when necessary. Quantities stated for the above items not marked with an asterisk are all that will be furnished by the Government. Provide any additional quantities that are required.

1.5.1 Delivery Schedule

Notify the Contracting Officer in writing at least 15 calendar days in advance of the date on which the materials and equipment are required. Pick up materials and equipment no later than 30 calendar days after such date.

When materials and equipment are not picked up by the 30th day, the Contractor will be charged for storage.

1.5.2 Delivery Location

The materials and equipment are located on the second floor of B-30 in the

EOC.

1.6 GOVERNMENT-INSTALLED WORK

The EOC requires coordination and installation of equipement for functionality purposes. Contractor to coordinate with Contracting Officer when the schedule allows for final installation of Goverment-Installed items. These items include but are not limited too:

-Computer Consules for ISAC area -Printer/Copier Combinations -Vending Machines -Digital Weather Radio -Precision Digital Clock with TimeZone -Video Projector -WiFi Hotspot Charger -AMX 7" NXT-CV7 Touch Panel Terminal -Vantage Pro 2 Console -Extron RGB-190F Splitter -ATFP COI Zero Client -Camera Monitor -Mid-Atlantic Power Rach with Video Switching Equipment -Cox Cable Box -Motorola MC 3000 Repeater -Radio Charger Racks and Radios -NMCI TACLANE Cabinet -LENEL IDS Alarm Cabinet -LENEL Alarm -Video Cameras -Shredder

1.7 NAVY AND MARINE CORPS (NMCI) COORDINATION REQUIREMENTS

1.7.1 NMCI Contractor Access

Allow the NMCI Contractor access to the facility towards the end of construction (finishes 90 percent complete, rough-in 100 percent complete, Inside Plant (ISP)/Outside Plant (OSP) infrastructure in place) to provide equipment in the telecommunications rooms and make final connections.

Coordinate efforts with the NMCI Contractor to facilitate joint use of building spaces during the final phases of construction. After the Contracting Officer has facilitated coordination meetings between the two contractors, within one week, incorporate the effort of additional coordination with the NMCI Contractor into the construction schedule to demonstrate a plan for maintaining the contract duration.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

SECTION 01 14 00

WORK RESTRICTIONS

11/11

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00

SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

List of Contact Personnel; G

1.2 SPECIAL SCHEDULING REQUIREMENTS

a. Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the work.

b. The building will remain in operation during the entire construction period. The Contractor must conduct his operations so as to cause the least possible interference with normal operations of the activity.

c. Permission to interrupt any Activity roads, railroads, or utility service must be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.

e. The work under this contract requires special attention to the scheduling and conduct of the work in connection with existing operations. Identify on the construction schedule each factor which constitutes a potential interruption to operations.

1.3 CONTRACTOR ACCESS AND USE OF PREMISES

1.3.1 Activity Regulations

Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark Contractor equipment for identification.

1.3.1.1 Subcontractors and Personnel Contacts

Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

SECTION 01 14 00 Page 1

1.3.1.2 Additional Personnel Requirements

1.3.1.2.1 General Construction

General construction of the secure area must be performed by U.S. firms using U.S. citizens. General construction includes construction activities such as building sitework, utilities, foundations, structure, and enclosure or shell, including doors, windows and façade work. Utility work that penetrates the secure area and installation of doors in these areas are not general construction.

1.3.1.2.2 Finish Work

Finish Work within the secure area must be accomplished by U.S.

SECRET-cleared personnel. Finish Work includes construction activities such as insulation, floor/partition/ceiling systems, cabinet work, conveyor systems, specialties, building furnishings/fixtures/equipment, mechanical/electrical services and equipment including those specialized for fire protection, security, communication, control, energy conservation, safety, comfort, convenience, and similar purposes.

1.3.1.2.3 Electronic Security Systems Equipment

Electronic Security Systems equipment such as processing control units, workstations, field panels, sensors, card readers, cable installation, and system programing, testing and training must be performed by U.S. companies using U.S. citizens who have been subjected to a trustworthiness determination.

1.3.1.3 Installation Access

Obtain access to Navy installations through participation in the Defense Biometrics Identification System (DBIDS). Requirements for Contractor employee registration, and transition for employees currently under Navy Commercial Access Control System (NCACS), are available at https://www.cnic.navy.mil/om/dbids.html. No fees are associated with obtaining a DBIDS credential.

Participation in the DBIDS is not mandatory, and Contractor personnel may apply for One-Day Passes at the Base Visitor Control Office to access an installation.

1.3.1.3.1 Registration for DBIDS

Registration for DBIDS is available at https://www.cnic.navy.mil/om/dbids.html. Procedure includes:

a. Present a letter or official award document (i.e. DD Form 1155 or SF 1442) from the Contracting Officer, that provides the purpose for access, to the base Visitor Control Center representative.

b. Present valid identification, such as a passport or Real ID Act-compliant state driver's license.

c. Provide completed SECNAV FORM 5512/1 to the base Visitor Control Center representative to obtain a background check. This form is available for download at https://www.cnic.navy.mil/om/dbids.html.

d. Upon successful completion of the background check, the Government will

SECTION 01 14 00 Page 2 complete the DBIDS enrollment process, which includes Contractor employee photo, finger prints, base restriction and several other assessments.

e. Upon successful completion of the enrollment process, the Contractor employee will be issued a DBIDS credential, and will be allowed to proceed to worksite.

1.3.1.3.2 DBIDS Eligibility Requirements

Throughout the length of the contract, the Contractor employee must continue to meet background screen standards. Periodic background screenings are conducted to verify continued DBIDS participation and installation access privileges. DBIDS access privileges will be immediately suspended or revoked if at any time a Contractor employee becomes ineligible.

An adjudication process may be initiated when a background screen failure results in disqualification from participation in the DBIDS, and Contractor employee does not agree with the reason for disqualification. The Government is the final authority.

1.3.1.3.3 DBIDS Notification Requirements

a. Immediately report instances of lost or stolen badges to the Contracting Officer.

b. Immediately collect DBIDS credentials and notify the Contracting Officer in writing under the following circumstances:

(1) An employee has departed the company without having properly returned or surrendered their DBIDS credentials.

(2) There is a reasonable basis to conclude that an employee, or former employee, might pose a risk, compromise, or threat to the safety or security of the Installation or anyone therein.

1.3.1.3.4 One-Day Passes

Personnel applying for One-Day passes at the Base Visitor Control Office are subject to daily mandatory vehicle inspection, and will have limited access to the installation. The Government is not responsible for any cost or lost time associated with obtaining daily passes or added vehicle inspections incurred by non-participants in the DBIDS.

1.3.1.4 No Smoking Policy

Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.

1.3.2 Working Hours

Regular working hours must consist of an 8 1/2 hour period established by the Contracting Officer, excluding Government holidays.

SECTION 01 14 00 Page 3

1.3.3 Work Outside Regular Hours

Work outside regular working hours requires Contracting Officer approval.

Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.

1.3.4 Occupied Building

The Contractor shall be working in an existing building which is occupied.

Do not enter the building without prior approval of the Contracting Officer.

The existing buildings and their contents must be kept secure at all times. Provide temporary closures as required to maintain security as directed by the Contracting Officer.

Provide dust covers or protective enclosures to protect existing work that remains and Government material located in the building during the construction period.

The Government will remove and relocate other Government property in the areas of the building scheduled to receive work.

1.3.5 Utility Cutovers and Interruptions

a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in paragraph WORK OUTSIDE REGULAR HOURS.

b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.

c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm and compressed air are considered utility cutovers pursuant to the paragraph WORK

OUTSIDE REGULAR HOURS.

d. Operation of Station Utilities: The Contractor must not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor must notify the Contracting Officer giving reasonable advance notice when such operation is required.

1.4 SECURITY REQUIREMENTS

1.4.1 Naval Base, Norfolk, VA

a. Contractor registration. Register with the Base Police Truck Investigation Team, located behind pass and ID Office (Bldg CD-9) on Hampton Boulevard, Naval Air Station, Norfolk, VA 23511-5000, telephone number (757) 322-2979.

SECTION 01 14 00 Page 4

b. Storage and office trailer registration. Register storage and office trailers to be used on base with the truck investigation team.

Trailers must meet State law requirements and must be in good condition.

(1) Trailers must be lockable and must be locked when not in use.

(2) Trailers must have a sign in the lower left hand corner of left door of trailer with the following information: Company name, address, registration number of trailer or vehicle identification number, location on base, duration of contract or stay on base, contract number, local on-base phone number, off-base phone number of main office, and emergency recall person and phone number.

c. Equipment markings. Equipment owned or rented by the company must have the company name painted or stenciled on the equipment in a conspicuous location. Rented equipment is to be conspicuously marked with a tag showing who rented the equipment. Register the equipment with the truck investigation team.

d. Procedure information. For additional information regarding registration procedures, contact the Officer in Charge of Construction at (757) 445-1463 or Base Police at (757) 444-8856.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 14 00 Page 5

SECTION 01 20 00.00 20

PRICE AND PAYMENT PROCEDURES

11/11

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EP 1110-1-8 (2016) Construction Equipment Ownership and Operating Expense Schedule

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00

SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Schedule of Prices; G

1.3 SCHEDULE OF PRICES

1.3.1 Data Required

This contract requires the use of a cost-loaded Network Analysis Schedule (NAS). The information required for the Schedule of Prices will be entered as an integral part of the Network Analysis Schedule. Within 15 calendar days of notice of award, prepare and deliver to the Contracting Officer a Schedule of Prices (construction contract) as directed by the Contracting Officer. Provide a detailed breakdown of the contract price, giving quantities for each of the various kinds of work, unit prices, and extended prices. Costs shall be summarized and totals provided for each construction category.

1.3.2 Schedule Instructions

Payments will not be made until the Schedule of Prices has been submitted to and accepted by the Contracting Officer. Identify the cost for site work, and include incidental work to the 5 ft line. Identify costs for the building, and include work out to the 5 ft line. Work out to the 5 ft line shall include construction encompassed within a theoretical line 5 ft from the face of exterior walls and shall include attendant construction, such as pad mounted HVAC cooling equipment, cooling towers, and transformers placed beyond the 5 ft line.

1.3.3 Schedule Requirements for HVAC TAB

The field work Section 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC shall be broken down in the Schedule of Prices and in the Construction

SECTION 01 20 00.00 20 Page 1

Progress Documentation by separate line items which reflect measurable deliverables. Specific payment percentages for each line item shall be determined on a case by case basis for each contract. The line items shall be as follows:

a. Approval of Design Review Report: The TABS Agency is required to conduct a review of the project plans and specifications to identify any feature, or the lack thereof, that would preclude successful testing and balancing of the project HVAC systems. The resulting findings shall be submitted to the Government to allow correction of the design. The progress payment shall be issued after review and approval of the report.

b. Approval of the pre-field engineering report: The TABS Agency submits a report which outlines the scope of field work. The report shall contain details of what systems will be tested, procedures to be used, sample report forms for reporting test results and a quality control checklist of work items that must be completed before TABS field work commences.

c. Season I field work: Incremental payments are issued as the TABS field work progresses. The TABS Agency mobilizes to the project site and executes the field work as outlined in the pre-field engineering report. The HVAC water and air systems are balanced and operational data shall be collected for one seasonal condition (either summer or winter depending on project timing).

d. Approval of Season I report: On completion of the Season I field work, the data is compiled into a report and submitted to the Government.

The report is reviewed, and approved, after ensuring compliance with the pre-field engineering report scope of work.

e. Completion of Season I field QA check: Contract QC and Government representatives meet the TABS Agency at the jobsite to retest portions of the systems reported in the Season I report. The purpose of these tests are to validate the accuracy and completeness of the previously submitted Season I report.

f. Approval of Season II report: The TABS Agency completes all Season II field work, which is normally comprised mainly of taking heat transfer temperature readings, in the season opposite of that under which Season I performance data was compiled. This data shall be compiled into a report and submitted to the Government. On completion of submittal review to ensure compliance with the pre-field engineering report scope, progress payment is issued. Progress payment is less than that issued for the Season I report since most of the water and air balancing work effort is completed under Season I.

1.4 CONTRACT MODIFICATIONS

In conjunction with the Contract Clause DFARS 252.236-7000 Modification Proposals-Price Breakdown, and where actual ownership and operating costs of construction equipment cannot be determined from Contractor accounting records, equipment use rates shall be based upon the applicable provisions of the EP 1110-1-8.

SECTION 01 20 00.00 20 Page 2

1.5 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT

1.5.1 Content of Invoice

Requests for payment will be processed in accordance with the Contract Clause FAR 52.232-27 Prompt Payment for Construction Contracts and FAR 52.232-5 Payments Under Fixed-Price Construction Contracts. The requests for payment shall include the documents listed below.

a. The Contractor's invoice, on NAVFAC Form 7300/30 furnished by the Government, showing in summary form, the basis for arriving at the amount of the invoice. Form 7300/30 shall include certification by Contractor and Quality Control (QC) Manager.

b. The Estimate for Voucher/ Contract Performance Statement on NAVFAC Form 4330/54 furnished by the Government, showing in detail: the estimated cost, percentage of completion, and value of completed performance for each of the construction categories stated in this contract. Use NAVFAC Form 43300/54 on NAVFAC contracts when a Monthly Estimate for Voucher is required.

c. Updated Project Schedule and reports required by the contract.

d. Contractor Safety Self Evaluation Checklist.

e. Other supporting documents as requested.

f. Updated copy of submittal register.

g. Invoices not completed in accordance with contract requirements will be returned to the Contractor for correction of the deficiencies.

1.5.2 Submission of Invoices

If DFARS Clause 5252.232-7006 is included in the contract, provide the documents listed in paragraph CONTENT OF INVOICE in their entirety as attachments in Wide Area Work Flow (WAWF) for each invoice submitted. The maximum size of each WAWF attachment is two megabytes, but there are no limits on the number of attachments. If a document cannot be attached in WAWF due to system or size restriction, provide it as instructed by the Contracting Officer.

1.5.3 Final Invoice

a. A final invoice shall be accompanied by the certification required by DFARS 252.247.7023 Transportation of Supplies by Sea, and the Contractor's Final Release. If the Contractor is incorporated, the Final Release shall contain the corporate seal. An officer of the corporation shall sign and the corporate secretary shall certify the Final Release.

b. For final invoices being submitted via WAWF, the original Contractor's Final Release Form and required certification of Transportation of Supplies by Sea must be provided directly to the respective Contracting Officer prior to submission of the final invoice. Once receipt of the original Final Release Form and required certification of Transportation of Supplies by Sea has been confirmed by the Contracting Officer, the Contractor shall then submit final invoice and attach a copy of the Final Release Form and required certification of Transportation of Supplies by Sea in WAWF.

SECTION 01 20 00.00 20 Page 3

c. Final invoices not accompanied by the Contractor's Final Release and required certification of Transportation of Supplies by Sea will be considered incomplete and will be returned to the Contractor.

1.6 PAYMENTS TO THE CONTRACTOR

Payments will be made on submission of itemized requests by the Contractor which comply with the requirements of this section, and will be subject to reduction for overpayments or increase for underpayments made on previous payments to the Contractor.

1.6.1 Obligation of Government Payments

The obligation of the Government to make payments required under the provisions of this contract will, at the discretion of the Contracting Officer, be subject to reductions and suspensions permitted under the FAR and agency regulations including the following in accordance with FAR 32.503-6 Suspension or Reduction of Payments:

a. Reasonable deductions due to defects in material or workmanship;

b. Claims which the Government may have against the Contractor under or in connection with this contract;

c. Unless otherwise adjusted, repayment to the Government upon demand for overpayments made to the Contractor; and

d. Failure to provide up to date record drawings not current as stated in Contract Clause "FAC 5252.236-9310, Record Drawings."

1.6.2 Payment for Onsite and Offsite Materials

Progress payments may be made to the contractor for materials delivered on the site, for materials stored off construction sites, or materials that are in transit to the construction sites under the following conditions:

a. FAR 52.232-5(b) Payments Under Fixed Price Construction Contracts.

b. Materials delivered on the site but not installed, including completed preparatory work, and off-site materials to be considered for progress payment shall be major high cost, long lead, special order, or specialty items, not susceptible to deterioration or physical damage in storage or in transit to the construction site. Examples of materials acceptable for payment consideration include, but are not limited to, structural steel, non-magnetic steel, non-magnetic aggregate, equipment, machinery, large pipe and fittings,precast/prestressed concrete products, plastic lumber (e.g., fender piles/curbs), and high-voltage electrical cable. Materials not acceptable for payment include consumable materials such as nails, fasteners, conduits, gypsum board, glass, insulation, and wall coverings.

c. Materials to be considered for progress payment prior to installation shall be specifically and separately identified in the Contractor's estimates of work submitted for the Contracting Officer's approval in accordance with Schedule of Prices requirement of this contract.

Requests for progress payment consideration for such items shall be supported by documents establishing their value and that the title requirements of the clause at FAR 52.232-5 Payments Under Fixed-Price

SECTION 01 20 00.00 20 Page 4

Construction Contracts have been met.

d. Materials are adequately insured and protected from theft and exposure.

e. Provide a written consent from the surety company with each payment request for offsite materials.

f. Materials to be considered for progress payments prior to installation shall be stored either in Hawaii, Guam, Puerto Rico, or the Continental United States. Other locations are subject to written approval by the Contracting Officer.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 20 00.00 20 Page 5

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

08/15

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00

SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

View Location Map; G

Progress and Completion Pictures; G

1.3 VIEW LOCATION MAP

Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.

1.4 PROGRESS AND COMPLETION PICTURES

Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color JPEG file format showing the sequence and progress of work. Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten views from points located by the Contracting Officer. Submit with the monthly invoice two sets of digital photographs, each set on a separate compact disc (CD) or data versatile disc (DVD), cumulative of all photos to date. Indicate photographs demonstrating environmental procedures.

Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch. Also provide the view location sketch on the CD or DVD as a digital file.

Include a date designator in file names. Cross reference submittals in the appropriate daily report. Photographs provided are for unrestricted use by the Government.

1.5 MINIMUM INSURANCE REQUIREMENTS

Provide the minimum insurance coverage required by FAR 28.307-2 Liability, SECTION 01 30 00 Page 1 during the entire period of performance under this contract. Provide other insurance coverage as required by State law.

1.6 FIRST TIER CONTRACTOR REQUIREMENTS FOR ASBESTOS CONTAINING MATERIALS

Accomplish all contract requirements of Section 02 82 00 ASBESTOS REMEDIATION, assigned to the Private Qualified Person, directly with a first tier subcontractor.

1.7 SUPERVISION

1.7.1 Minimum Communication Requirements

Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of contract work. In addition, if a Quality Control (QC) representative is required on the contract, then that individual must also have fluent English communication skills.

1.7.2 Superintendent Qualifications

The project superintendent must have a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.

For routine projects where the superintendent is permitted to also serve as the Quality Control (QC) Manager as established in Section 01 45 00.10 20 QUALITY CONTROL FOR MINOR CONSTRUCTION, the superintendent must have qualifications in accordance with that section.

1.7.2.1 Duties

The project superintendent is primarily responsible for managing and coordinating day-to-day production and schedule adherence on the project.

The superintendent is required to attend NAVFAC Red Zone meetings, partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.

1.7.3 Non-Compliance Actions

The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to insure timely completion. Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.

SECTION 01 30 00 Page 2

1.8 PRECONSTRUCTION MEETING

After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule of prices or earned value report, shop drawings, and other submittals, scheduling programming, prosecution of the work, and clear expectations of the "Interim DD Form 1354" Submittal. Major subcontractors who will engage in the work must also attend.

1.9 FACILITY TURNOVER PLANNING MEETINGS (NAVFAC Red Zone - NRZ)

Meet with the Government to identify strategies to ensure the project is carried to expeditious closure and turnover to the Client. Start the turnover process at the Pre-Construction Conference meeting with a discussion of the NAVFAC Red Zone (NRZ) process and convene at regularly scheduled NRZ Meetings. Include the following in the facility Turnover effort:

1.9.1 NRZ Checklist

a. Contracting Officer's Technical Representative (COTR) will provide the Contractor a copy of the NRZ Checklist template prior to 75 percent completion.

b. Prior to 75 percent completion add/delete critical activities to the NRZ Checklist template as necessary to match the project scope, and schedule critical activities and insert planned completion dates in the NRZ checklist for each critical activity. Present the NRZ Checklist to COTR and review during a regularly scheduled QC Meeting.

1.9.2 Meetings

a. Upon Government acceptance of the NRZ Checklist, the Project Superintendent is required to lead regular NRZ Meetings beginning at approximately 75 percent project completion, or three to six months prior to Beneficial Occupancy Date (BOD), whichever comes first.

b. The Contracting Officer will determine the frequency of the meetings, which is expected to increase as the project completion draws nearer.

c. Using the NRZ Checklist as a Plan of Action and Milestones (POAM) and basis for discussion, review upcoming critical activities and strategies to ensure work is completed on time.

d. Coordinate with the COTR any upcoming activities that require Government involvement.

e. Maintain the NRZ Checklist by documenting the actual completion dates as work is completed and update the NRZ Checklist with revised planned completion dates as necessary to match progress. Distribute copies of the current NRZ Checklist to attendees at each NRZ Meeting.

1.10 PARTNERING

To most effectively accomplish this contract, the Government requires the…