This is a Scope of Work for a federal construction project at the St. Cloud VA Health Care System. The project, numbered 656-22-342, requires the contractor to repair, remove, replace, and completely refurbish all windows in Building 10. The work encompasses demolition of existing windows including safe removal of lead and asbestos-containing materials in compliance with local and national regulations, installation of new or refurbished window frames and sashes, and restoration of walls, ceilings, trim, and millwork. The contractor must work in an occupied building with proper construction barriers and is responsible for moving, adjusting, and storing all disturbed furnishings. No VA-furnished equipment will be provided.

The anticipated project schedule begins with contract award (D) and progresses through pre-construction conference (D+7), Notice to Proceed (D+10), mobilization (D+57), construction start (D+60), and construction completion (D+475). Substantial completion is anticipated at 465 calendar days after Notice to Proceed. Contract working hours are 8:00 a.m. to 4:30 p.m., Monday through Friday, excluding Federal Holidays, though weekend and night work may be necessary in sensitive areas with Contracting Officer's Representative approval. The anticipated cost range for this project is between $2,000,000 and $5,000,000. Contractor trades anticipated include general contractor, general laborer, demolition contractor, abatement contractor, and painting contractor.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCOPE OF WORK

“PRESERVE BUILDING 10 WINDOWS”

PROJECT #656-22-342

ST CLOUD VA HEALTH CARE SYSTEM

A. PART I – GENERAL

1. Base Project: The Contractor shall furnish all labor, materials, tools and equipment required to repair, remove, replace and completely refurbish all windows in Building 10.

The contractor shall remove the existing internal and external window trim and wall finishes in order to successfully gain access to and cut out the existing wood windows.

Incorporated into the demolition of the windows will be the safe removal of both lead and asbestos containing material as guided by the local and national rules and regulations of lead and asbestos remediation. Additionally, the contractor will be responsible for the complete and satisfactory installation of the new/refurbished window frames and sashes. The window installation shall include the patching and painting of walls, ceiling installation and restoration, trim and millwork installation, and repair of all damaged in place items. This work will be completed in an occupied building; all construction activities shall be completed behind proper construction barriers as described in the specifications. The contractor shall return the worksite to the Veterans Affairs Health Care System after the work is completed, and all of the required work is satisfactorily completed and signed off by the assigned Contracting

Officer’s Representative. Refer to the contract specifications and drawings for details

All work completed in accordance with the specifications and contract drawings.

2. Deducts:

a. None

3. Work includes, but is not limited to:

a. Demolition:

b. Contractor shall remove from the VA site and dispose of all equipment and materials not scheduled to be reused.

c. Contractor shall remove Lead and Asbestos materials associated with windows

d. Contractor trades anticipated:

• General contractor

• General laborer

• Demolition contractor

• Abatement contractor

• Painting contractor

1. No VA furnished equipment

2. New construction consists of but is not limited to windows, doors, general construction and abatement.

3. Contractor is responsible for the movement, adjustment and storage of all furnishings disturbed during construction.

4. Contract working hours are 8 am to 4:30 pm Monday through Friday, excluding Federal

Holidays. Weekend and night work may be necessary in sensitive areas and shall be approved by the COR.

5. Phasing will be as listed on the contract documents

B. Anticipated Schedule:

Contract award* D

Pre-construction conference D+7

Notice to Proceed D+10

Start badging, submittals, and other pre-construction processes D+10

Mobilization D+57

Construction starts D+60

Construction completion D+475

The anticipated substantial completion of this project is 465 calendar days after “Notice to

Proceed” (NTP).

C. Cost Range

The anticipated cost range for this project is between $2,000,000 and $5,000,000.