This is a solicitation for repair work on an electrical system and substation at Marine Corps Base Quantico in Virginia. The scope of work includes replacing existing 15kV and 35kV switchgears with new pad mounted gas insulated switchgear equipped with microprocessor based interrupters. It will also reconnect existing 120-volt circuits currently fed from the 35kV switchgear enclosure. The solicitation is being conducted by the Department of the Navy Naval Facilities Engineering Command. The contractor will be responsible for providing all labor, materials, equipment, transportation and supervision to complete the work in accordance with applicable federal, state and local regulations.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Repair TBS Electric System - Substation 10 April 2020 Marine Corps Base Quantico, Virginia Final Design Submittal
PROJECT TABLE OF CONTENTS
DI VI SI ON 00 - PROCUREMENT AND CONTRACTI NG REQUI REMENTS
00 01 07 SEALS PAGE
00 01 15 LIST OF DRAWINGS
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 20 00.00 20 PRICE AND PAYMENT PROCEDURES
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 31 23.13 20 ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT
MANAGEMENT SYSTEM
01 32 17.00 20 COST-LOADED NETWORK ANALYSIS SCHEDULES (NAS)
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 20 QUALITY CONTROL
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 57 19.01 20 SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS
01 58 00 PROJECT IDENTIFICATION
01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
01 78 24.00 20 FACILITY ELECTRONIC OPERATION AND MAINTENANCE SUPPORT
INFORMATION (eOMSI)
01 91 00.15 TOTAL BUILDING COMMISSIONING
DI VI SI ON 03 - CONCRETE
03 30 00 CAST-IN-PLACE CONCRETE
DI VI SI ON 26 - ELECTRI CAL
26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS
26 05 19.10 10 INSULATED WIRE AND CABLE
26 08 00 APPARATUS INSPECTION AND TESTING
26 12 21 SINGLE-PHASE PAD-MOUNTED TRANSFORMERS
26 13 00 SF6/HIGH-FIREPOINT FLUIDS INSULATED PAD-MOUNTED SWITCHGEAR
DI VI SI ON 33 - UTI LI TI ES
33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1 Tracking # QU1810M & PWB # 2017137
THIS PAGE INTENTIONALLY LEFT BLANK
PROJECT TABLE OF CONTENTS Page 2
SECTION 00 01 07
SEALS PAGE
02/15
PART 1 SUMMARY
1.1 SEALS AND SIGNATURES
Professional Certification. I hereby certify that these documents were prepared or approved by me, and that I am a duly licensed Professional Engineer under the laws of the Commonwealth of Virginia.
License No. 0402058735.
Expiration Date: 08/25/2022.
Professional Certification. I hereby certify that these documents were prepared or approved by me, and that I am a duly licensed Professional Engineer under the laws of the State of North Carolina.
License No. 9761.
Expiration Date: 12/31/2020.
-- End of Section --
DOCUMENT 00 01 07 Page 1 Tracking # QU1810M & PWB # 2017137
4/10/20
SvobodaM New Stamp
SvobodaM New Stamp
THIS PAGE INTENTIONALLY LEFT BLANK
DOCUMENT 00 01 07 Page 2
DOCUMENT 00 01 15
LIST OF DRAWINGS
02/11
PART 1 GENERAL
1.1 SUMMARY
This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings, Maps and Specifications."
1.2 CONTRACT DRAWINGS
Contract drawings are as follows:
DRAWING NO. NAVFAC DWG NO. TITLE
G-001 3193066 COVER, LOCATION AND VICINITY MAPS, SITE LOCATION
PLAN
G-002 3193067 SHEET INDEX, SYMBOLS AND ABBREVIATIONS
G-003 3193068 SEQUENCE OF CONSTRUCTION
C-100 3193069 CIVIL PLAN AND DETAILS
E-100 3193070 SINGLE LINE DIAGRAM, NOTES, LEGEND
E-101 3193071 ELECTRICAL DETAILS
E-102 3193072 GROUNDING DETAILS
E-103 3193073 ELECTRICAL LAYOUT
E-104 3193074 ELECTRICAL LAYOUT - TEMPORARY EQUIPMENT
-- End of Document --
DOCUMENT 00 01 15 Page 1
THIS PAGE INTENTIONALLY LEFT BLANK
DOCUMENT 00 01 15 Page 2
SECTION 01 11 00
SUMMARY OF WORK
08/15
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Project Description
Work for this project includes replacement of the existing TBS’s 15 kV switchgears with pad mounted gas-insulated 15 kV switchgear with microprocessor based interrupters and the existing FBI Academy’s 35 kV switchgear with pad mounted gas insulated 35 kV switchgear with microprocessor based interrupters. This project will also reconnect existing 120 volt circuits currently fed from the 35 kV switchgear enclosure.
1.1.2 Location
The work is located at the Marine Corps Base - Quantico, approximately at the intersection of MCB 2 & MCB3. The exact location will be shown by the Contracting Officer.
1.2 OCCUPANCY OF PREMISES
Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches.
1.3 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
1.4 LOCATION OF UNDERGROUND UTILITIES
Obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities.
Contact local utility locating service a minimum of 14 days prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings, within area of work.
Identify and mark all utilities not managed and located by the local utility companies. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are
SECTION 01 11 00 Page 1 discovered. Verify the elevations of existing piping, utilities,and any type of underground obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed.
Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
1.4.1 Notification Prior to Excavation
Notify the Contracting Officer at least 21 days prior to starting excavation work.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 2
SECTION 01 14 00
WORK RESTRICTIONS
11/11
PART 1 GENERAL
1.1 SPECIAL SCHEDULING REQUIREMENTS
a. The The Contractor must conduct his operations so as to cause the least possible interference with normal operations of the activity.
b. Permission to interrupt any Activity roads, railroads, and/or utility service must be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.
1.2 CONTRACTOR ACCESS AND USE OF PREMISES
1.2.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark Contractor equipment for identification.
1.2.1.1 Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.2.1.2 Access to Installation
All Contractor personnel shall obtain access to the installation through enrollment and registration into the Defense Biometric Identification System (DBIDS). The Contractor shall provide the KO with the name of their designated Service Contractor Administrator (SCA) for enrollment in DBIDS.
Once enrolled, the Contractor must provide the DBIDS Registrar with an approved employee list and then direct their employees to register into
DBIDS.
1.2.1.3 DBIDS Program
DBIDS is a voluntary program in which Contractor personnel who enroll, and are approved, are subsequently granted access to the installation for a period up to one year, or the length of the contract, whichever is less, and are not required to obtain a new pass from the Base Pass and Identification Office for each visit.
The Government performs background screening and credentialing. Throughout the year the Contractor employee must continue to meet background screening standards. Periodic background screenings are conducted to verify continued DBIDS participation and installation access privileges.
Under the DBIDS program, no commercial vehicle inspection is required, other than for Random Anti-Terrorism Measures (RAM) or in the case of an
SECTION 01 14 00 Page 1 elevation of Force Protection Conditions (FPCON).
The following is required to obtain a DBIDS credential:
a. Present a letter or official document from my government sponsoring organization that provides the purpose for your access.
b. Present valid identification, such as a passport or Real ID Act-compliant state driver's license.
c. Present a completed copy of the SECNAV 5512/1 form to obtain your background check.
d. Upon completion of the background check, the Visitor Control Center representative will complete the DBIDS enrollment process, which includes your photo, fingerprints, base restrictions, and several other assessments; after all this is done, you will be provided.
There is no cost to obtain a DBIDS credential. Information on requirements to participate and enroll in DBIDS is available at https://www.cnic.navy.mil/om/dbids.html or by calling 1-202-433-4784. For additional questions about obtaining a DBIDS card, contact your local base visitor control center.
DBIDS Paper Passes: Participation in the DBIDS is not mandatory, and if the Contractor chooses to not participate, the Contractor's personnel will have to obtain daily passes, be subject to daily mandatory vehicle inspection, and will have limited access to the installation. The Government will not be responsible for any cost or lost time associated with obtaining daily passes or added vehicle inspections incurred by non-participants in the DBIDS.
1.2.1.4 Identification Badges and Installation Access
Contractor Personnel: After Contract Award and at least 15 days prior to the desired date of worksite entry, and monthly thereafter no later than the 5th of each month, submit to the Contracting Officer and/or designated representative, an original alphabetical list of all personnel who require entry into Government property to perform work on the contract. The Contracting Officer designated representative will forward the alphabetical list to the Services Section of the Provost Marshall Office (PMO) for back-ground checks and clearances. All Contractor personnel employees will require screening, personnel approval, and clearance from the PMO Services Section. It is estimated PMO back-ground checks and clearances will take 3-5 days to complete. Final Approval of worksite entry for Contractor personnel will be by the Contracting Officer and/or designated representative upon receipt of clearances from PMO Services Section. POCs for the Contractor List of Employees or Representatives Form are Services Officer (703-784-4167) or Assistant Services Officer (703-784-4170). A Privacy Act Statement, DD Form 369, shall also be submitted for each contractor employee upon initial hire. Contractors that are screened using the Contractor Verification System (CVS) and issued a US Government identification credential are exempt from these screening requirements. MCBO 5530.2 is included after this section for reference.
The Contractor Employees or Representatives List for personnel screening shall be filled out in the "Name Block" and signed by the Contractor, and accompanied by Form I-9 for each employee. Furnish a completed EMPLOYMENT ELIGIBILITY VERIFICATION (DHS FORM I-9) form for
SECTION 01 14 00 Page 2 all personnel. This form is available at http://www.uscis.gov/files/form/I-9_IFR_02-02-09.pdf. Federal Contractors are required to use the E-verify program (www.dhs.gov/e-verify). Documentation for proof of citizenship identified on the MCINCR-MCBQ Screening Form, included after this section, are multiple representative samples. Provide only the acceptable source documents for proof of citizenship identified in MCBO 5530.2 and required for the DHS Form I-9. (refer to FAR E-Verify Clause: 52.222-54)
Immediately report any changes to the approved Contractor Employee List to the Contracting Officer and/or designated representative.
Provide the required employee information for any new employee change in order to obtain the appropriate Contractor Screening and approvals prior to entry to the work site.
Contractor Personnel Requirements: Failure to obtain screening entry approval will not affect the contract price or time of completion.
The Contractor's worksite may be inspected periodically for compliance of MCBO 5530.2 by PMO and other Inspectors.
Citizenship Requirements: Contractor personnel will not be admitted to the work site without approval by Contracting Officer. Work under this contract is restricted to U.S. citizens and legal alien status in accordance with MCBO 5530.2 - CONTRACTOR SCREENING POLICY.
The Contractor shall not employ for any work required by this contract, any person who is a nonimmigrant as described in section 101(a)(15)(H)(ii) of the Immigration and Nationality Act (8 U.S.C.
1101(a)(15)(H)(ii), an alien having a residence in a foreign country which he has no intention of abandoning and who is coming to the United States to perform temporary services or labor.
Contractor Emergency Personnel Contacts: From the approved Contractor Employees List, furnish to the Contracting Officer and/or designated representative the contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency.
1.2.1.5 No Smoking Policy
Smoking is prohibited within and outside of all buildings on installations under the cognizance of NAVFAC except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
1.2.2 Working Hours
Regular working hours must consist of a period established by the Contractor Officer, between 7 a.m. and 4:00 p.m., Monday through Friday, excluding Government holidays.
1.2.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in
SECTION 01 14 00 Page 3 progress. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.
1.2.4 Occupied and Existing Buildings
The Contractor shall be working in and around existing buildings which are occupied. Do not enter the building without prior approval of the Contracting Officer.
The existing buildings and their contents must be kept secure at all times. Provide temporary closures as required to maintain security as directed by the Contracting Officer.
Keep driveways and entrances serving the premises clear and available at all times to the Government, Government employees and visitors. Do not use these areas for parking or storage of materials.
1.2.5 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in the paragraph "Work Outside Regular Hours."
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, and compressed air are considered utility cutovers pursuant to the paragraph entitled "Work Outside Regular Hours."
d. Operation of Station Utilities: The Contractor must not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor must notify the Contracting Officer giving reasonable advance notice when such operation is required.
1.3 SECURITY REQUIREMENTS
1.3.1 Marine Corps Base Quantico (MCBQ), Quantico, VA
All Contractor and its employees performing services on Marine Corps Base, Quantico (MCBQ) requiring physical access to the installation must be properly screened. Screening consists of identity proofing and vetting in accordance with the standards set forth in Marine Corps Base Order 5530.2.
This policy is attached at the end of this section for reference.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 14 00 Page 4
-- End of Section --
SECTION 01 14 00 Page 5
THIS PAGE INTENTIONALLY LEFT BLANK
SECTION 01 14 00 Page 6
UNITED STATES MARINE CORPS
MARINE CORPS INSTALLATIONS NATIONAL CAPITAL REGION
MARINE CORPS BASE QUANTICO
3250 CATLIN AVENUE
QUANTICO VIRGINIA 22134 5001
IN REPLY REFER TO
MCINCR-MCBQO 5530.2
B 033
21 Apr 16
MARINE CORPS INSTALLATIONS NATIONAL CAPITAL REGION–MARINE CORPS BASE QUANTICO
ORDER 5530.2
From: Commander
To: Distribution List
Subj: ACCESS CONTROL POLICY
Ref: (a) MARADMIN 533/08
(b) DTM 09-012
(c) 33 CFR Part 334.235
(d) MARADMIN 392/15
(e) AFO 5500.14B
Encl: (1) Identity Proofing
(2) Standards for Access
(3) Contractor Screening
(4) Commercial Vehicles
(5) Commissary Baggers
(6) Hunters Screening
(7) Role Player Screening
(8) USACE Waterfront Restricted Area
(9) MCINCR-MCBQ Screening Form
1. Situation. An effective access control policy is necessary to ensure the safety and security of Marine Corps Installations National Capital Region-
Marine Corps Base Quantico (MCINCR-MCBQ) personnel and property.
a. Access to MCINCR-MCBQ properties and facilities is limited for authorized purposes only. Authorized purposes include performance of official duties; performance of approved contractor and employment activities aboard
MCINCR-MCBQ; authorized dependent and guest access to family housing areas, medical facilities, and Department of Defense Schools; authorized patronage of
Marine Corps Community Services (MCCS) activities; the National Museum of the
Marine Corps (NMMC) and Marine Corps Heritage Center activities; and authorized participation in private organizations and conservation activities registered aboard MCINCR-MCBQ.
b. MCINCR-MCBQ is not a public forum, and protest and partisan political activities, of any kind, are not permitted.
c. Town of Quantico. Because the Town of Quantico is located within the geographical boundaries of MCINCR-MCBQ, Fuller Road, between Jefferson Davis
Highway (Route 1) and Potomac Avenue, is accessible to the public for the sole purpose of transiting to and from the Town of Quantico.
MCINCR-MCBO 5530.2
This limited public use does not allow any detour, deviation, or access to any other part of MCINCR-MCBQ, nor does it provide authority for any uses other than transit. Individuals who present appropriate identification may access the Town of Quantico via Fuller Road between Jefferson Davis Highway (Route 1) and Potomac Avenue. There is no right of public access via other Gates.
Personnel transiting MCINCR-MCBQ to the Town of Quantico are subject to routine and random security checks at access control points and in route.
d. Marine Corps Heritage Center (MCHC). The 135-acre MCHC is MCINCR-MCBQ property. Though the National Museum of the Marine Corps, which is part of the MCHC, is open to the public, MCINCR-MCBQ may establish access control points, as needed, to ensure compliance with this Order.
2. Mission. MCINCR-MCBQ executes comprehensive access control procedures in order to ensure the safety and security of installation personnel and property.
3. Execution
a. Commander’s Intent
(1) Purpose. To establish effective and efficient access control policy that ensures individuals granted access to MCINCR-MCBQ are properly identified and vetted in accordance with the references.
(2) Method. MCINCR-MCBQ will establish procedures that allow for scalable enforcement of access control procedures based on the threat, traffic/safety conditions and special event considerations.
(3) End-state. MCINCR-MCBQ access control policies and procedures ensure that base personnel and property are better protected by minimizing access to the base by unauthorized persons.
b. Concept of Operations
(1) All individuals that access MCINCR-MCBQ property are subject to access control measures that include identity proofing, vetting, vehicular searches, personnel searches, and other security regulations. Screening and vetting may take place at installation entry control points, as part of the application process for employment, as part of an application for a hunting license, during random checks of workplaces and job sites, and at other venues as determined by the base commander.
(a) Identity proofing consists of reviewing federally authorized documentation to ensure authenticity of an individual. Enclosure (1) identifies the credentials that are approved to identify persons seeking access to MCINCR-MCBQ.
(b) Vetting is an evaluation of an individual’s character and conduct, for approval, acceptance or denial onto the installation. MCINCR-
MCBQ conducts personnel vetting through law enforcement and other security databases. Enclosure (2) identifies the access standards required for base access.
(2) In addition to identity proofing and vetting, MCINCR-MCBQ has established specific access/screening procedures for contractors, commercial vehicles, commissary baggers, hunters, role players, and the USACE waterfront restricted area as identified in enclosures (3) through (8).
c. Tasks
(1) Assistant Chief of Staff, G-3 (Operations)
(a) Exercise staff cognizance for implementation of installation access control policies and procedures.
(b) Coordinate with tenant commands and activities to ensure compliance with the provisions of this order.
(c) Serve as the MCINCR-MCBQ point of contact with the US Army
Corps of Engineers for matters pertaining to the Potomac River Restricted
Area.
(d) Notify the Mayor of the Town of Quantico of any changes to
Access Control procedures that may impact town residents or visitors.
(e) Process requests for access control waivers.
(2) Assistant Chief of Staff, G-F (Installation & Environment)
(a) Conduct bi-annual background checks of all non-affiliated personnel requesting to hunt on MCBQ IAW the provisions identified in enclosure (6).
(b) Publish hunter screening requirements and procedures in the annual Fiscal Year Hunting Season Bulletin (MCINCR-MCBQBUL 11015).
(3) Command Inspector. Process recommendations for debarment for individuals that fail to meet/maintain access standards IAW enclosure (2).
(4) Director, Marine Corps Community Services. Ensure that signage identifying the provisions of the USACE Potomac River Restricted area are maintained/posted at the MCBQ Marina and all MCBQ boat launch facilities.
(5) Commanding Officer, Security Battalion
(a) Conduct background screening for contractors, commissary baggers, and non-affiliated hunters IAW the procedures identified in enclosures (3), (5), and (6). Provide the results of screening within ten days of initial receipt, to the government official that submitted the data.
(b) Add the names and biographical data of contractors that failed screening to the applicable physical access control system (PACS) database and provide a copy to the MCINCR-MCBQ Command Inspector General for possible debarment.
(c) Provide trained personnel and required equipment to operate the Commercial Vehicle Inspection (CVI) Lot IAW enclosure (4). Ensure a minimum of (1) armed law enforcement person is present at all times the CVI lot is operational.
(d) Conduct commercial vehicle screening at the installation Entry
Control Points (ECP) during hours that the CVI lot is not operational.
(e) Develop and publish written CVI procedures.
(f) Support registration in the RAPIDGate® program at the kiosk located at the CVI lot.
(g) Issue RAPIDGate® credentials to authorized patrons at the
Russell-Knox Building visitor control center.
(h) Coordinate with the Commanding Officer, MCAF to develop and publish procedures for enforcement of the restricted area IAW enclosure (8).
Enforcement shall include random patrols and procedures for both a shoreline/ground and waterborne response.
(i) Coordinate with the AC/S G-F (Environmental Law Enforcement
Section), NCIS Quantico, Charles County Sheriff, and other law enforcement/ mutual aid partners for assistance with enforcement of the restricted area.
(j) Appoint a Role Player Program Coordinator (RPPC) to manage the role player screening program IAW enclosure (7).
(6) Commanding Officer, Marine Corps Air Facility
(a) Coordinate with the Commanding Officers of Security Battalion and Presidential Helicopter Squadron-1 (HMX-1) to develop and publish procedures for a shoreline/ground enforcement of the USACE Potomac River
Restricted Area IAW enclosure (8).
(b) Publish and execute procedures for processing requests by commercial fisherman to access the restricted area.
(c) Plan for required maintenance of restricted area buoys and barriers. Include buoy and barrier inspection, sustainment, repair, and replacement as part of annual MCAF budget submission.
(d) Publish Access Control Policy for MCAF Quantico identifying specific procedures as it relates to the air field and in accordance with reference (e).
(7) Director, Regional Contracting Office. Provide notice of the access control requirements identified in this order in all contract solicitations and awards for all contracts to be performed on MCBQ.
(8) Contracting Officers/Contracting Officer Representatives
(a) Submit the names of all applicable contractor employees to PMO
Services for background screening IAW enclosure (3) at the commencement of a contract and NLT the 5th of each month thereafter.
(b) Upon notification that an employee fails to meet access standards, immediately inform the contractor and ensure that the employee is not permitted to continue work on MCBQ.
(c) Forward requests for a waiver to contractor access control screening standards to the MCINCR-MCBQ G-3 for processing.
(9) Commissary Manager
(a) Ensure compliance with the provisions of enclosure (5) and that all commissary baggers have completed background screening prior to being allowed to work.
(b) Submit a roster that includes names and biographical data on all active commissary baggers to PMO Services NLT the 10th of each month.
(c) Ensure that all baggers are issued and wear an individual employee identification number at all times while working at the commissary.
d. Coordinating Instructions
(1) All personnel and vehicles entering MCINCR-MCBQ are subject to search. Searches may take place at the entry control point, commercial vehicle inspection lot, or other location as directed by the
Provost Marshal.
(2) Specific procedures for commercial vehicle processing are identified in Enclosure (4).
4. Administration and Logistics
a. Waiver Requests. The Commander, MCINCR-MCBQ or designee, may issue a waiver to allow access to an individual who fails the MCINCR-MCBQ vetting process or is prohibited from MCINCR-MCBQ access under this policy. Written requests for waiver shall be submitted to the MCINCR-MCBQ G-3 for processing.
Upon decision of the Commander, the individual submitting the waiver will be informed of the outcome.
b. Deviations. Requests to change or deviate from the provisions of the order will be submitted to the MCINCR-MCBQ G-3 (Attention: Director, Installation Protection Branch.
5. Command and Signal
a. Command
(1) This policy applies to all MCINCR-MCBQ tenant commands, organizations, activities, and military members, dependents, government employees, contractors, and private individuals who access MCINCR-MCBQ property.
(2) The Commanding Officer MCAF Quantico shall support the provisions of this order while maintaining additional access control policies and procedures designed to meet the security requirements of that installation.
b. Signal. This order is effective on the date signed and replaces MCBO
5530.1 (Access Control) and MCBO 4200.3 (Contractor Screening).
X
A. D. BROUGHTON
Chief of Staff
Signed by: BROUGHTON.ALLEN.DALE.1168122922
Enclosure (1)
Identity Proofing Requirements
1. In accordance with references (a) and (b), individuals requesting access to MCBQ must present appropriate identification. While identification alone will not guarantee MCBQ access, the following credentials are approved to identify personnel seeking access to MCBQ:
a. DoD issued Common Access Card (CAC);
b. DoD Uniformed Services Identification and Privileges Card;
c. U.S. Passport;
d. U.S. Government issued, authenticated, Federal Personal Identity
Verification (PIV) Credentials;
e. Transportation Workers Identification Credentials (TWIC);
f. Federal, State or local Law Enforcement Credentials (includes FBI and
DEA non-law enforcement employee credentials);
g. RAPIDGate Access Token when specifically authorized for MCINCR-MCBQ access;
h. Driver’s license issued by a State or outlying U.S. territory that comply with the provisions of the REAL ID Act, provided it contains a photograph and biographical information such as name, date of birth, gender, height, eye color, and address;
i. Identification card issued by Federal, state or local government agencies, provided it contains a photograph and biographical information such as name, date of birth, gender, height, eye color, and address;
j. School identification card with a photograph;
k. Permanent resident card or Alien Registration card (Form I-551);
l. Foreign passport with a temporary (I-551) stamp or temporary (I-551) printed notation on a machine readable immigrant visa;
m. Foreign passport with a current Arrival-Departure Record
(Form I-94) bearing the same names as the passport and containing an endorsement of the alien’s nonresident status and work authorization for employer with authorized purpose aboard the installation;
n. Employment Authorization Document (EAD) issued by the U.S. Immigration and Naturalization Service (INS) with a photograph (Form I-766).
2. Personnel who possess the credentials (a)-(g) may be granted access without further vetting, though must still have a legitimate reason for requiring access. Personnel who possess credentials (h)-(n) shall be vetted before access is granted.
Enclosure (2)
Standards for Access
1. Absent a valid and current waiver by the MCINCR-MCBQ Commander, individuals will generally be denied access to MCBQ property, if the individual is:
a. on a National Terrorist Watch List;
b. in the United States illegally;
c. subject of an outstanding warrant;
d. subject of a current debarment order from any military installation;
e. a prisoner on work-release or parole;
f. a registered sex offender; or
g. convicted of a felony within the previous two (2) years;
h. determined by the MCBQ Commander to be a detriment to the safety, security or good order and discipline of the installation.
Enclosure (3)
Contractor Screening
1. Policy. Contractor screening is a part of the overall installation access control and security program and requires that all contractors doing business aboard MCBQ are identity proofed IAW enclosure (1) and meet the requirements for access identified in enclosure (2).
2. Applicability. This policy applies to all commands, organizations and tenant activities that employ contractors on MCBQ and MCAFQ (contractors that require physical access to the installation). Duration of contract, contract source, or length of time that employees will perform services/work on MCBQ does not diminish or effect applicability of this policy.
3. Definition. A contractor is any individual gaining access to MCBQ for the purpose of performing services under a government contract or subcontract who is not a member of the Armed Forces or a direct employee of the U.S.
Government.
4. Procedures
a. Contractors with employees performing services on MCBQ shall provide, at the commencement of the contract and monthly thereafter, a list of all employees requiring base access.
b. A list of all contractor employees requiring access shall be submitted to the contracting officer representative (COR) utilizing enclosure (9), NLT the 5th of each month. The COR will then forward the list to MCBQ Security
Battalion for vetting. A Privacy Act Statement, DD Form 369, shall also be submitted for each contractor employee upon initial hire.
c. In addition to monthly submissions, contractors shall provide immediate updates to the COR, when new or additional employees require base
d. Security Battalion officials will validate the contractor list to ensure individuals meet access control standards and notify the COR of results.
e. Contractors that are screened using the Contractor Verification System
(CVS) and issued a US Government identification credential are exempt from these screening requirements.
5. Appeals
a. A contractor that desires to employ an individual that does not meet the access standards identified in enclosure (2) may submit an appeal to the
Commander, MCINCR-MCBQ for special consideration. Appeals will be in writing and processed through the contracting officer.
b. An individual that does not meet the access standards identified in enclosure (2) may submit an appeal to the Commander, MCINCR-MCBQ for special
Enclosure (3) consideration. Appeals will be in writing and processed through the MCINCR-
MCBQ G-3.
6. Enforcement
a. Contractors and their employees are subject to the Random
Antiterrorism Measures being employed at Installation Access Control Points to include identification verification and screening against law enforcement and other databases.
b. Contractors and their employees are subject to random security sweeps of work sites to verify contractor identification and eligibility.
c. Contractors may be subject to a wide range of contract and administrative actions for failure to comply with this policy to include termination of their contract and suspension or debarment from doing future business with the Federal Government. Contractors are responsible to ensure subcontractors are notified of and comply with this policy.
7. Notification. Contracting Officers shall provide notice of this policy in all contract solicitations and awards for all contracts to be performed on
MCBQ.
Enclosure (4)
Commercial Vehicles
1. Policy. All commercial vehicles will be screened prior to being granted access to MCBQ. Commercial vehicle screening includes identity proofing and vetting of the commercial vehicle operator and any passengers, and a physical inspection of the commercial vehicle.
2. Applicability. This policy applies to vendors, suppliers, contractors, subcontractors, and service providers requiring commercial vehicle access to
MCBQ. This policy also applies to commercial vehicles transiting MCBQ to gain access to the Town of Quantico.
3. Definition. A commercial vehicle is defined as any non-government vehicle, larger than a standard van (e.g. box truck or larger), accessing
MCBQ.
(a) The primary location for commercial vehicle screening is the
Commercial Vehicle Inspection (CVI) Lot located adjacent to the Ponderosa-Y
Gate on Russell Road (west of I-95). During non-duty hours (or whenever the
CVI lot is closed), commercial vehicle screening will take place at the installation entry control points (gates).
(b) Commercial vehicles with sustained, long-term access requirements (in excess of 30 days) may utilize streamlined access procedures by enrolling in the RAPIDGate® Program. Commercial vehicle operators with a current and valid
RAPIDGate® credential authorizing access to MCBQ, will be allowed to bypass the CVI lot and be granted access at the entry control points.
(c) All vehicles, to include commercial vehicles participating in the
RAPIDGate® Program, are subject to random security screening/ vehicle inspections at both the installation gates, and other locations aboard the installation.
Enclosure (5)
Commissary Baggers
1. Policy. Prior to being allowed to work at the MCBQ Commissary, all baggers shall be identity proofed and vetted.
2. Applicability. This policy applies to the MCBQ Commissary and personnel working at the commissary as baggers.
3. Definition. Commissary Baggers are self-employed persons who have the permission of the commissary store director to enter the commissary for the purpose of soliciting commissary customers to bag and carry out their groceries in return for a tip. Baggers can be present on the installation, pursuing their personal business for profit in the commissary only with the approval of the installation commander who exercises his/her, inherent authority of military command to allow the baggers to enter. Baggers are not employees of the Defense Commissary Agency or of the U.S. government, nor are they contract personnel.
a. The Store Manager of the MCBQ Commissary is responsible to ensure that all baggers are screened by the MCBQ Provost Marshals Office (PMO) before being allowed to work at the commissary store.
b. Biographical data, to include full name, address, date & place of birth, and SSN, for all new/prospective baggers shall be submitted to PMO for screening utilizing enclosure (9). Additionally, a Privacy Act Statement, DD
Form 369, shall be submitted for each prospective bagger.
c. PMO will screen the list of prospective baggers provided by the commissary using law enforcement databases to ensure DoD and MCBQ access standards are met. Upon completion of screening, the list of names will be returned to the commissary store manager with an annotation beside each name identifying “pass” or “fail”. Those identified as “fail”, do not meet access standards and are not authorized to work on MCBQ in any capacity unless a waiver from the commander is obtained. Up to 10 days should be allowed from submission of data to PMO, until release of screening results.
5. Enforcement. The following actions ensure compliance with bagger screening requirements and that commissary baggers have been screened/meet access standards before being allowed to work at the commissary:
a. Commissary baggers shall be issued (by the commissary), and wear, an easily recognizable identification number at all times while working at the commissary. The bagger identification number must be associated with that bagger’s name and cannot be transferred to another bagger.
b. The Commissary manager shall submit a report of all active baggers to
PMO no later than the 5th of each month. The report shall be submitted utilizing enclosure (9) and include Name (Last, First, MI); Date/Place of
Birth; Full SSN; current address; and date began work at the commissary.
Enclosure (5)
c. PMO shall conduct random, monthly, on-site, screening checks to ensure compliance with the provisions of this order.
Enclosure (6)
Hunter Screening
1. Policy. MCBQ conducts background screening of applicants prior to the issuance of base hunting licenses.
2. Applicability. This policy applies to individuals applying to participate in hunting activities on MCBQ. The following are exempt from hunter screening requirements:
a. Personnel who possess credentials identified in paragraph (a) through
(g) of enclosure (1).
b. Minors (under the age of 18 years) applying to hunt on MCBQ are not subject to background screening requirements, but must be accompanied by a licensed adult.
c. Personnel participating in Wounded Warrior and other command sponsored hunts are not subject to background screening requirements.
3. Purpose. Annually, a large number of personnel, both military and civilian, access MCBQ to participate in hunting activities. Though most hunters comply with the base hunting regulations, many have no DoD affiliation and are not vetted to determine suitability for base access. Unscreened personnel accessing the installation with firearms and ammunition present an unacceptable risk to the safety and security of the base population.
Therefore, unaffiliated personnel desiring to obtain a MCBQ hunting license shall undergo a background investigation to confirm they comply with MCBQ access requirements and are authorized to be in possession of a firearm in the
Commonwealth of Virginia prior to being issued a MCBQ hunting license or being allowed to hunt on MCBQ.
a. Screening of applicants for a base hunting license will be conducted at the Game Check Station (GCS) using a commercial, law enforcement database.
b. Background screening will be conducted at the time of application and requires that the applicant provide an approved source of identity as identified in enclosure (1), and biographical data to include full name, address, birth date, and full Social Security Number (SSN).
c. GCS personnel will enter the applicant biographical data into a commercial law enforcement database and review the retrieved data for compliance with MCBQ standards for access, as identified in enclosure (2), and
Virginia and federal firearm requirements. After review, if the applicant meets both MCBQ access requirements and is authorized to possess a firearm in the Commonwealth of Virginia, a MCBQ hunting license may be issued.
d. In those cases where an applicant does not meet the screening requirements or the results are questionable, a MCBQ Wildlife Enforcement
Officer will review the data and make a determination. If required, the applicant data will be forwarded to PMO for additional screening checks.
Enclosure (6)
e. Persons denied a MCBQ hunting license due to failure to meet screening criteria, may submit a written request for a waiver to the Commander, MCBQ.
Waivers shall be routed through the Conservation Law Enforcement Section.
f. Background checks are required bi-annually (successfully passing the background screening enables the applicant to apply for a hunting license for the year in which the check was conducted, as well as the following year).
Enclosure (7)
Role Player Screening
1. Policy. All cultural-based role players accessing MCBQ must be under a contract administered by the Program Manager for Training Systems (PM TRASYS) and must comply with the Role Player Threat Screening procedures identified in reference (d) and this order prior to being allowed access to MCBQ to participate in training events. Under no circumstances will an unscreened role player be permitted access to the installation.
2. Applicability. This policy applies to all commands/organizations conducting training with culture-based role players requiring physical access to MCBQ.
3. Definition: A culture-based role player is an individual who supports training (while under contract with the Marine Corps) by educating Marines in the customs, languages, wardrobe, religions, behaviors, and values of a specific population/geographic region. Role players utilize behaviors, combat patterns and tactics to replicate potential adversaries and scenarios faced by
Marine forces.
a. In accordance with reference (d), the Commanding Officer of Security
Battalion shall appoint a Role Player Program Coordinator (RPPC) to manage the role player screening program and ensure that any role player allowed access to MCBQ is in compliance with Marine Corps role player screening policies and the provisions of this order.
b. Tenant commands planning to utilize culture-based role players shall appoint a command Point of Contact (POC) for each training event and notify the MCINCR-MCBQ AC/S G-3 and the MCBQ RPPC at least 60 days prior to the start of the training.
c. The tenant command’s POC shall coordinate with the contractor providing the role players and obtain & submit the following information to the MCBQ RPPC at least 21 days prior to the start of the training.
(1) A list of the names of all role-players that will participate in the training. The list shall include the last name, first name, middle name, and date of birth.
(2) A completed I-9 Employment Eligibility form for each participating role player.
(3) Verification of enrollment in “E-Verify” and employment eligibility for each role player.
d. The tenant command POC shall coordinate with the MCBQ RPPC and the contractor providing the role players in order to establish a date, time and location for PMO to conduct biometric enrollment of all role players scheduled to participate in the training. Biometric data shall be collected from all
Enclosure (7) role players at least 24 hours prior to the start of training for submission to the Department of Justice.
e. The MCBQ RPPC shall notify the NCIS Resident Agent Quantico, the MCBQ
AC/S G3, and the POC for the tenant command conducting role player training if any role player is rejected for not meeting the standards for installation
f. Upon completion of role player screening, the tenant command POC will coordinate with the MCBQ RPPC for daily installation access. Daily access procedures will include detailed checks of all role players, equipment and vehicles. Once cleared for access, the tenant command POC is responsible for continuous observation of the role players while on MCBQ. Unescorted access is NOT permitted.
Enclosure (8)
USACE Waterfront Restricted Area
1. Policy. Reference (c) establishes a US Army Corps of Engineers (USACE)
Restricted Area in the waters of the Potomac River extending offshore from the
Marine Corps Air Facility Quantico (MCAF). The restricted area includes all of the navigable waters of the Potomac River extending approximately 500 meters from the high-water mark on the Eastern shoreline of the MCAF, bounded by the coordinates identified in reference (c) (including the Chopawamsic
Creek channel, but excluding Chopawamsic Island).
2. Applicability. All persons, vessels, or other craft are prohibited from entering, transiting, drifting, dredging, or anchoring within the restricted area without the permission of the Commander, MCINCR-MCB Quantico or his/her designated representatives. The restriction is in place 24 hours a day, seven days a week.
3. Procedures. The restricted area shall be enforced by the Commander, MCINCR-MCBQ or any such agencies he/she designates. Any person or vessel encroaching within the restricted area will be directed to immediately leave.
Failure to do so could result in forceful removal and/or criminal charges.
4. Exceptions. Commercial fishermen are authorized controlled access to the restricted area (with the exception of Chopawamsic Creek channel) after registering with MCAF and following specific access notification procedures.
MCINCR-MCBQ Screening Form
Enclosure (9)
Event Name Here Event Date Here
SSN Last Name First Name Middle Name Address Date of Birth Place of Birth Drivers License StateDrivers License NumberLicense Plate Number License Plate State
Contract Number
Contract Name/Location
Contract Start Date
Contract End Date
FEAD POC (ET)
FEAD POC's Email Address
FEAD POC's Phone Number
Name of PRIME or SUB-
CONTRACTOR SSN Last Name First Name Middle Name Address Date of Birth Place of Birth
Driver's
License
State
Driver's
License
Number
License Plate
Number
License
Plate
State
EXAMPLE Contractors, LLC 2 123-45-6789 Knows Goofy Who
227 Disney Channel Drive, Orlando, CA 12345 13-Aug-2024 Lost Soul, WI VA T1234-764W 424-85W VA
WARNING: This document includes information that is subject to the Privacy Act of 1974. Disclosure of this information to anyone other than the intended recipient is a violation of federal law AND MAY SUBJECT THE OFFENDER TO CRIMINAL PROSECUTION AND/OR CIVIL
PROCEEDINGS. If you are not the intended recipient, immediately inform [EIC Name] at [EIC e-mail address] or at [EIC Telephone No.]; then destroy this document in any and all forms, whether electronic, hard copy, or other. FOR OFFICIAL USE ONLY!!
TBD
TBD
High Temp Hot Water (HTHW) Distribution Repair @ Camp Barrett (TBS)
TBD
TBD
TBD
TBD
SECTION 01 20 00.00 20
PRICE AND PAYMENT PROCEDURES
11/11
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EP-1110-1-8 (2009) Construction Equipment Ownership and Operating Expense Schedule
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. The following shall be submitted in accordance with Section
01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Earned Value Report; G
1.3 EARNED VALUE REPORT
1.3.1 Data Required
This contract requires the use of a cost-loaded Network Analysis Schedule (NAS). The information required for the Schedule of Prices will be entered as an integral part of the Network Analysis Schedule. Within 15 calendar days of notice of award, prepare and deliver to the Contracting Officer a Schedule of Prices (construction contract) as directed by the Contracting Officer. Provide a detailed breakdown of the contract price, giving quantities for each of the various kinds of work, unit prices, and extended prices. Costs shall be summarized and totals provided for each construction category.
1.3.2 Schedule Instructions
Payments will not be made until the Earned Value Report from the cost-loaded NAS has been submitted to and accepted by the Contracting Officer. Identify the cost for site work, and include incidental work to the 5 ft line. Identify costs for the building(s), and include work out to the 5 ft line. Work out to the 5 ft line shall include construction encompassed within a theoretical line 5 ft from the face of exterior walls and shall include attendant construction, such as pad mounted HVAC cooling equipment, cooling towers, and transformers placed beyond the 5 ft line.
1.4 CONTRACT MODIFICATIONS
In conjunction with the Contract Clause "DFARS…