Attachment A_SOI_2.3.26_Cerro Pelado Roads Reconstruction .xlsx
XLSX spreadsheet 15 KB Posted
- Attached to
- Solicitation is Restricted to the Current Region 3 FERM BPA Holders - USDA Forest Service
- Solicitation number
- 127EAX26Q0056
- Issued by
-
Department of Agriculture Forest Service
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Schedule of Items | |||||
| Company: | Project Title: | Cerro Pelado Road Reconstruction | |||
| Date: | Representative: | ||||
| BASE Items | |||||
| Item No. | Description | Unit | Quantity | Unit Cost | Amount |
| 151(01) | Mobilization | LS | ALL | ||
| 201(01) | Clearing and Grubbing, <0.5 Ac., Disposal Method (b) Scattering | LS | ALL | ||
| 203(01) | Removal of Structures and Obstructions, CMP removal and disposal, 18" dia. CMP | LF | 26 | ||
| 203(02) | Removal of Structures and Obstructions, 24" dia. CMP removal and disposal | LF | 210 | ||
| 203(03) | Removal of Structures and Obstructions, 36" diam. CMP removal and disposal | LF | 30 | ||
| 203(04) | Removal of Structures and Obstructions, 24' Cattleguard, Remove and Salvage | EA | 1 | ||
| 204(01) | Excavation and Embankment, Recontuour Small areas, <1.0 Ac. Total, Compaction Method (d) | LS | ALL | ||
| 204(02) | Excavation and Embankment, Reconstruct Grade Dip, Compaction Method (d) | EA | 2 | ||
| 204(03) | Excavation and Embankment, Construct Rolling Dip, Compaction Method (d) | EA | 15 | ||
| 204(04) | Excavation and Embankment, Reconstruct Rolling Dip, Compaction Method (d) | EA | 74 | ||
| 204(05) | Excavation and Embankment, Place Common Backfill, Compaction Method (d) | TON | 280 | ||
| 207(01) | Earthwork Geosynthetics, Type 6 Non-woven geotextile, Install w/ 251(01) Check Dams | LS | ALL | ||
| 209(01) | Structure Excavation and Backfill, 24" dia. CMP Culverts, Compaction Method (d) | LF | 128 | ||
| 209(02) | Structure Excavation and Backfill, 36" dia. CMP Culverts, Compaction Method (d) | LF | 156 | ||
| 209(03) | Structure Excavation and Backfill, 48" dia. CMP Culverts, Compaction Method (d) | LF | 36 | ||
| 251(01) | Riprap, Class 2, Construct ~9 small Check Dams | TON | 20 | ||
| 251(02) | Riprap, Gov Furnished Class 1, Install ONLY | CY | 10 | ||
| 301(01) | Aggregate Courses, Spot Gravel, R3-G FS Specs, Compaction Method (d) | TON | 1400 | ||
| 301(02) | Aggregate Courses, 4" Compacted, 14' w, R3-G FS Specs, Compaction Method (d), w/ initial Road Reconditioning | MILE | 14.3 | ||
| 303(01) | Road Reconditioning, Compaction Method (d) | MILE | 8 | ||
| 418(01) | Asphalt Concrete Pavement Patching, Type 1 | SY | 15 | ||
| 602(01) | Culverts, Furnish/Install 24" CMP, 16 GA, Galvanized, Compaction Method (d) | LF | 278 | ||
| 602(02) | Culverts, Furnish/Install 36" CMP, 16 GA, Galvanized, Compaction Method (d) | LF | 30 | ||
| 602(03) | Culverts, Furnish/Install 48" CMP, 16 GA, Galvanized, Compaction Method (d) | LF | 36 | ||
| 619(01) | Cattleguard, Install 24' wide CG w/ wings and wing posts, U-80 Specs | EA | 1 | ||
| 619(02) | Cattleguard, Maintain | EA | 1 | ||
| 633(01) | Permanent Traffic Control, Install Type III Object Markers w/ Cattleguard installation, Contractor Furnished | EA | 4 | ||
| 635(01) | Temporary Traffic Control, w/ message boards, message boards NTE 3 Days | LS | ALL | ||
| 704(01) | Soil, Common Backfill, Contractor Furnished | TON | 500 | ||
| BASE Subtotal | |||||
| NMGRT | |||||
| BASE TOTAL |
| Option Item A | |||||
| Item No. | Description | Unit | Quantity | Unit Cost | Amount |
| 201(01)a | Clearing and Grubbing, <0.5 Ac., Disposal Method (b) Scattering | LS | ALL | ||
| 314(01)a | Stockpiled Aggregates, R3-G Specifications, within project boundary | TON | 500 | ||
| Option A Subtotal | |||||
| NMGRT | |||||
| Option A TOTAL |
| Option Item B | |||||
| Item No. | Description | Unit | Quantity | Unit Cost | Amount |
| 201(01)b | Clearing and Grubbing, <0.5 Ac., Disposal Method (b) Scattering | LS | ALL | ||
| 314(01)b | Stockpiled Aggregates, Class 0 Riprap, within project boundary | TON | 500 | ||
| Option B Subtotal | |||||