This is an Attachment A requirements document for Montana State University Bozeman's comprehensive snow removal and ice control services contract across multiple campus locations. The scope encompasses four primary service areas: Commuter Lots, Residential Lots, Family/Graduate Housing Streets, Parking Garage, and Museum of the Rockies. Snow removal operations are required between 6:00 PM and 6:00 AM daily, with extended hours on weekends and during scheduled events as needed. The Contractor must respond to one-inch snowfall accumulation throughout drive lanes and parking stalls by monitoring snow conditions continuously. Traction control materials must be applied during service hours as conditions require. The Museum of the Rockies requires exception handling with trace-level snowfall response to ensure 7:00 AM daily opening accessibility. MSU crews will handle plowing and traction control between 6:00 AM and 6:00 PM. Equipment used within the Parking Garage is limited to a maximum height of 6 feet, 11 inches due to roof clearance restrictions, with all snow disposal directed through the designated West Snow Chute only.
Snow hauling services and snow melter assistance shall be performed at the direction of MSU's Director of Facilities Services or designee at any time throughout the winter season. The Contractor may be requested to provide loaders and qualified operators to feed snow into the university's snow melter equipment, which shall be operated solely by authorized MSU representatives; contractor assistance is billed at contracted hourly equipment and operator rates. Pre-treatment applications must be performed when weather forecasts indicate a 70 percent or greater probability of precipitation with temperatures remaining below freezing for four hours or longer. Bare pavement operations during Winter Break in residential lots and snow scraping/hauling from Family/Graduate Housing Streets require coordination with MSU Parking Services and MSU Facilities Services. Skid steer snow removal services shall be provided upon university request and compensated at applicable rates identified in the Equipment and Application Rates Table. No undisclosed costs are reimbursable, and all pricing must be fully transparent.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment A – Requirements by Location
1. Commuter Lots
a. Snow removal operations in these areas shall occur between 6:00 PM and 6:00 AM daily, with extended hours on weekends if required. Scheduled events may require modified service schedules in certain lots.
b. MSU crews will plow and apply traction control to drive lanes only between 6:00 AM and
6:00 PM.
c. A one inch (1") snowfall response shall occur throughout drive lanes and parking stalls. The Contractor is responsible for monitoring snow conditions and responding when snowfall accumulation reaches one inch (1") or greater.
d. The Contractor shall provide and apply traction control materials during service hours as conditions require.
e. Snow hauling operations / snow melter assistance feeding melter may be directed by MSU and performed in these lots at any time throughout the winter season as needed.
f. Museum of the Rockies Exception: On trace snowfall callouts, the Museum of the Rockies shall be maintained as an exception to standard MOR requirements and must be cleared and fully accessible for a 7:00 AM daily opening.
2. Residential Lots
a. Snow removal operations in drive lanes and vacant parking stalls shall occur between 6:00 PM and 6:00 AM daily, with potential extended hours and weekends if required.
b. MSU crews will plow and apply traction control to drive lanes only between 6:00 AM and
6:00 PM.
c. One inch (1") snowfall response shall occur throughout drive lanes. The Contractor is responsible for monitoring snow conditions and responding when snowfall accumulation reaches one inch (1") or greater.
d. The Contractor shall provide and apply traction control materials during service hours as conditions require.
e. Snow hauling from designated snow storage locations may be directed by MSU Director of Facilities Services, or their designee to be performed at any time throughout the season as needed.
f. Bare pavement operations shall be directed by MSU Director of Facilities Services, or their designee to be completed during Winter Break. During severe or exceptional winter conditions, additional clearing operations may be required. Coordination for vehicle movement shall be managed through MSU Parking Services and MSU Facilities Services.
3. Family/Graduate Housing Streets
a. Snow removal operations in drive lanes shall occur between 6:00 PM and 6:00 AM daily, with potential extended hours and on weekends if required.
b. MSU crews will plow and apply traction control to drive lanes only between 6:00 AM and
6:00 PM.
c. One inch (1") snowfall response shall occur throughout drive lanes. The Contractor is responsible for monitoring snow conditions and responding when snowfall accumulation reaches one inch (1") or greater.
d. The Contractor shall provide and apply traction control materials during service hours as conditions require.
e. Snow hauling from designated snow storage locations may be directed by MSU Director of Facilities, or their designee to be performed at any time throughout the season as needed.
f. Snow scraping and/or snow hauling from streets and parking stalls may require coordination with Parking Services and Family/Graduate Housing through MSU Facilities Services.
4. Parking Garage
a. Snow removal operations in these areas shall occur between 6:00 PM and 6:00 AM daily, with potential extended hours if required. Scheduled events may require modified service schedules.
b. A one inch (1") snowfall response shall occur throughout drive lanes and parking stalls. The Contractor is responsible for monitoring snow conditions and responding when snowfall accumulation reaches one inch (1") or greater.
c. The Contractor shall provide and apply traction control materials during service operations as conditions require. Traction control applications shall be limited to the upper garage level and ramp driving lanes.
d. Continuous snow hauling operations shall be required, as all snow is deposited at designated “West Snow Chute” location. Snow shall be hauled as necessary to prevent accumulation that could compromise facility operations or safety.
e. Snow hauling operations from designated storage locations may be directed and performed at any time throughout the season as deemed necessary by MSU.
f. The Parking Garage Upper Deck (4th Floor) presents unique operating conditions, as all snow removal is conducted via designated snow chute (refer to attached map). The east chute is no longer available; therefore, only the west chute shall be used for snow disposal. The Contractor shall exercise special precautions to protect the work zone, with particular attention to chute dumping locations and associated safety hazards.
g. All snow removal and traction control equipment used within the parking garage shall not exceed a maximum overall height of six feet, eleven inches (6’11”) due to roof clearance limitations.
h. Skid steer snow removal services shall be provided upon request by the University. Work will be compensated at the applicable skid steer rate identified in the Equipment and Application Rates Table
5. Museum of the Rockies
a. Museum of the Rockies Exception: On trace snowfall callouts, the Museum of the Rockies shall be maintained as an exception to standard MOR requirements and must be cleared and fully accessible for a 7:00 AM daily opening.
b. Lots covered will be East side including entrance from Kagy and West side including parking service drive.
c. Trace response will occur throughout drive lanes and stalls. The contractor is expected to monitor snow conditions and respond when snowfall is trace level or greater.
d. Contractor shall supply traction control measures during their service hours as needed.
e. Snow hauling duties can be directed and carried out in these lots anytime needed throughout the season.
6. Snow Hauling and Snow Melter Operations
a. Snow hauling services shall be performed at the direction of the Owner. Primary parking lot snow storage piles shall be prioritized for removal utilizing the MSU snow melter system.
b. The Contractor may be requested to assist the Owner with snow recovery operations by providing loaders and qualified operators to feed snow into the snow melter. The snow melter equipment shall be operated solely by the Owner. Contractor assistance provided for these operations shall be billed at the contracted hourly equipment and operator rates.
c. Under no circumstances shall the Contractor operate the snow melter without an authorized Owner representative present onsite.
7. Pre-Treatment Applications
a. Pre-treatment applications shall be performed when weather forecasts indicate a seventy percent (70%) or greater probability of precipitation followed by temperatures remaining below freezing for four (4) hours or longer.
b. The Contractor shall monitor weather conditions and apply approved de-icing or anti-icing materials as necessary to maintain safe surface conditions.
| 6. Snow Hauling and Snow Melter Operations |