Attachment A-REGIONAL GENERATOR REPLACEMENT CONSTRUCTION DOCUMENTS SPECS.pdf

PDF 4 MB Posted

Attached to
OYA Regional Generator Replacement
Solicitation number
S-DASOBO-00008606
Issued by
Harney County, Jackson County, Lake County, Gladstone City, Amity City, Oregon

About this file

This document contains the construction specifications for the OYA Regional Generator Replacement project, which involves the removal and replacement of generators at three Oregon Youth Authority (OYA) correctional facilities located in Grants Pass, Burns, and Albany, Oregon. The project will be completed under a single prime contract and includes associated electrical, building, mechanical, roofing, and demolition work. Key milestones include submittal of critical path equipment within 30 days, delivery of generator equipment within 12 months, substantial completion within 60 days of equipment delivery, and final completion within 30 days of substantial completion. The contractor must comply with the OYA's safety and security requirements, including providing a temporary 8-foot security fence around the work area and following specific access and monitoring procedures.

The project will be awarded based on the base bid covering the work at the Grants Pass and Burns facilities, with an alternate for the work at the Albany facility. Pricing terms, set asides, and funding sources are not provided. The document outlines the administrative and procedural requirements for submitting shop drawings, product data, samples, and other submittals during the construction process.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NOTICE: These documents are instruments of professional service, and information contained therein is incomplete unless used in conjunction with DLR Group’s interpretations, decisions, observations and administrations. Use or reproduction of these documents in whole or in part without DLR Group’s consent is in violation of common law, copyrights, statutory and other reserved rights, which preempts state and local public records act.

© 2022 DLR Group inc., an Oregon corporation, ALL RIGHTS RESERVED.

OYA Regional Generator Replacement Burns, OR; Grants Pass, OR; Albany, OR

Construction Documents Specification Manual

DLR Group Project No. 74-23108-00

July 11, 2023

Project Manual

OYA Regional Generator Replacement Burns, OR; Grants Pass, OR; Albany, OR

Construction Documents Specification Manual

DLR Group Project No. 74-23108-00

May 19, 2023

DLR Group inc., an Oregon corporation Architecture Engineering Planning Interiors 110 SW Yamill Street, Suite 105 Portland, OR 97204 tel 503/274-2675

12/31/2024

July 11, 2023

OYA REGIONAL GENERATOR REPLACEMENT DLRG PROJECT NO. 74-23108-00

OREGON YOUTH AUTHORITY JULY 11, 2023

BURNS, OR; GRANTS PASS, OR; ALBANY, OR CONSTRUCTION DOCUMENTS

TABLE OF CONTENTS 000110 - 1

TABLE OF CONTENTS

DIVISION 01 — GENERAL REQUIREMENTS

011000 SUMMARY

012300 ALTERNATES

012500 SUBSTITUTION PROCEDURES

012600 CONTRACT MODIFICATION PROCEDURES

012900 PAYMENT PROCEDURES

013100 PROJECT MANAGEMENT AND COORDINATION

013200 CONSTRUCTION PROGRESS DOCUMENTATION

013233 PHOTOGRAPHIC DOCUMENTATION

013300 SUBMITTAL PROCEDURES

014000 QUALITY REQUIREMENTS

014529 LABORATORY SERVICES

015000 TEMPORARY FACILITIES AND CONTROLS

016000 PRODUCT REQUIREMENTS

016001 EXECUTIVE ORDER 12-16

017300 EXECUTION

017419 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

017700 CLOSEOUT PROCEDURES

017823 OPERATION AND MAINTENANCE DATA

017839 PROJECT RECORD DOCUMENTS

017900 DEMONSTRATION AND TRAINING

DIVISION 02 — EXISTING CONDITIONS

024119 SELECTIVE DEMOLITION

DIVISION 03 — CONCRETE

032000 CONCRETE REINFORCING

033000 CAST-IN-PLACE CONCRETE

DIVISION 05 — METALS

054000 COLD-FORMED METAL FRAMING

055000 METAL FABRICATIONS

DIVISION 06 — WOOD, PLASTICS, AND COMPOSITES

061000 ROUGH CARPENTRY

061600 SHEATHING

DIVISION 07 — THERMAL AND MOISTURE PROTECTION

072100 THERMAL INSULATION

072500 WEATHER BARRIERS

072600 VAPOR RETARDERS

074646 FIBER-CEMENT SIDING

075419 POLYINYL-CHLORIDE (PVC) ROOFING

075423 THERMOPLASTIC-POLYOLEFIN (TPO) ROOFING

TABLE OF CONTENTS 000110 - 2

076200 SHEET METAL FLASHING AND TRIM

078413 PENETRATION FIRESTOPPING

079200 JOINT SEALANTS

DIVISION 08 — OPENINGS

089116 OPERABLE WALL LOUVERS

DIVISION 09 — FINISHES

099114 EXTERIOR PAINTING (MPI STANDARDS)

DIVISION 23 — HEATING VENTILATING AND AIR CONDITIONING

233723 HVAC GRAVITY VENTILATORS

DIVISION 26 — ELECTRICAL

260010 SUPPLEMENTAL REQUIREMENTS FOR ELECTRICAL

260011 FACILITY PERFORMANCE REQUIREMENTS FOR ELECTRICAL

260519 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES

260526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

260529 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

260533 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS

260548 VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS

260553 IDENTIFICATION FOR ELECTRICAL SYSTEMS

260800 COMMISSIONING OF ELECTRICAL SYSTEMS

262818 CIRCUIT BREAKERS

263213.13 DIESEL-ENGINE-DRIVEN GENERATOR SETS

263343 BATTERY CHARGERS

263600 TRANSFER SWITCHES

SUMMARY 011000 - 1

SECTION 011000 - SUMMARY

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Plans and general provisions of the Contract, including General Conditions and Supplemental

General Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes the following:

1. Project information.

2. Work covered by Contract Documents.

3. Phased construction.

4. Work by Owner.

5. Work under separate contracts.

6. Purchase contracts.

7. Owner-furnished products.

8. Contractor-furnished, Owner-installed products.

9. Access to site.

10. Coordination with occupants.

11. Work restrictions.

12. Specification and drawing conventions.

13. Miscellaneous provisions.

B. Related Sections include the following:

1. Division 01 Section "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.

1.3 PROJECT INFORMATION

A. Project Identification:

1. OYA Regional Generator Replacement

a. Project Locations:

1) Rogue Valley Youth Correctional Facility, Grants Pass, OR (RVYCF.)

2) Eastern Oregon Youth Correctional Facility, Burns, Or (EOYCF.)

3) Oak Creek Youth Correctional Facility, Albany, OR (EOYCF) – Alternate

No. 1.

B. Owner: Oregon Youth Authority

SUMMARY 011000 - 2

1. Owner's Authorized Representative: Stacy Davis

2. Owner's Authorized Field Representative:

a. Oak Creek Youth Correctional Facility: Mel Johnston

b. Eastern Oregon Youth Correctional Facility: Mel Johnston

c. Rogue Valley Youth Correctional Facility: Hara Miller

1.4 WORK COVERED BY CONTRACT DOCUMENTS

A. The Work is summarized as follows:

1. Remove and replace generators at each of the three project locations with associated electrical construction, building construction, mechanical construction, roofing construction and selective demolition.

B. Type of Contract:

1. Project will be constructed under a single prime contract.

1.5 SCHEDULE MILESTONES (PHASED CONSTRUCTION)

A. The Work shall be conducted to allow milestone completion for selected portions of the work, with each milestone substantially or finally complete as indicated:

1. Project Start Date: Date of notice to proceed.

2. Hold Preconstruction Conference: 7 calendar days after Notice to Proceed.

3. Milestone 1: 1st submittal for all critical path equipment no later than 30 days from date of notice to proceed.

4. Milestone 2: Completion of submittals for all critical path equipment no later than 30 days from completion date of Milestone 1.

5. Milestone 3: Delivery of generator equipment no later than 12 months from completion of submittals.

6. Substantial completion: Within 60 calendar days after delivery of generator equipment.

7. Final completion of remainder of work: Within 30 calendar days of Substantial

Completion date.

B. Before commencing Work of each phase, submit an updated copy of Contractor's construction schedule showing the sequence, commencement and completion dates including time periods specified for work by Owner and move-in dates of Owner's personnel for all phases of the

Work.

1.6 WORK BY OWNER

A. General: Cooperate fully with Owner so work may be carried out smoothly, without interfering with or delaying work under this Contract or work by Owner. Coordinate the Work of this

Contract with work performed by Owner.

SUMMARY 011000 - 3

1.7 ACCESS TO SITE

A. General: Contractor shall have limited use of Project site for construction operations as indicated on Drawings by the Contract limits and as indicated by requirements of this Section.

B. Use of Site: Limit use of premises to work in areas indicated. Do not disturb portions of

Project site beyond areas in which the Work is indicated.

1. Limits: Confine constructions operations to areas indicated and any additional areas mutually agreed to by Contractor and Owner.

2. Owner Occupancy: Allow for Owner occupancy of areas adjacent to work area.

3. Driveways and Entrances: Keep driveways, loading areas, and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

a. Schedule deliveries to minimize use of driveways and entrances.

b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

1.8 COORDINATION WITH OCCUPANTS

A. Partial Owner Occupancy: Owner will occupy the premises (adjacent rooms and parking lots) during entire construction period, with the exception of areas under construction. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage.

Perform the Work so as not to interfere with Owner's operations. Maintain existing exits, unless otherwise indicated.

1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and authorities having jurisdiction.

2. Provide not less than 72 hours' notice to Owner of activities that will affect Owner's operations.

1.9 WORK RESTRICTIONS

A. On-Site work Hours: Work shall be performed during the hours indicated below unless otherwise mutually agreed to by Contractor and Owner.

1. Monday through Friday – 8 hour days typically 7:00 am to 3:30 pm

2. Work outside of secure building perimeter: 6:30 AM to 8:30 PM

3. Note: All work inside the secure perimeter shall comply with criteria established and accepted by Owner.

B. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

1. Notify Owner not less than two days in advance of proposed utility interruptions.

SUMMARY 011000 - 4

2. Do not proceed with utility interruptions without Owner's written permission.

1.10 SPECIFICATION FORMATS AND CONVENTIONS

A. Specification Format: The Specifications are organized into Divisions and Sections using the

50-division format and CSI/CSC's "MasterFormat" numbering system.

1. Section Identification: The Specifications use Section numbers and titles to help cross-referencing in the Contract Documents. Sections in the Project Manual are in numeric sequence; however, the sequence is incomplete because all available Section numbers are not used. Consult the table of contents at the beginning of the Project Manual to determine numbers and names of Sections in the Contract Documents.

2. Division 01: Sections in Division 01 govern the execution of the Work of all Sections in the Specifications.

B. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.

These conventions are as follows:

1. Abbreviated Language: Language used in the Specifications and other Contract

Documents is abbreviated. Words and meanings shall be interpreted as appropriate.

Words implied, but not stated, shall be inferred as the sense requires. Singular words shall be interpreted as plural, and plural words shall be interpreted as singular where applicable as the context of the Contract Documents indicates.

2. Imperative mood and streamlined language are generally used in the Specifications.

Requirements expressed in the imperative mood are to be performed by Contractor.

Occasionally, the indicative or subjunctive mood may be used in the Section Text for clarity to describe responsibilities that must be fulfilled indirectly by Contractor or by others when so noted.

a. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

1.11 MISCELLANEOUS PROVISIONS

A. Approved Applicators: Where specific instruction in the specifications or plans require that particular products, equipment or material be installed or applied by an approved applicator of the manufacturer, it shall be the Contractor’s responsibility to ensure that any entity or workers used for such work be an approved applicator, and shall be so documented in writing.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 011000

ALTERNATES 012300 - 1

SECTION 012300 - ALTERNATES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Plans and general provisions of the Contract, including General Conditions and Supplemental

General Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements for alternates.

1.3 DEFINITIONS

A. Alternate: An amount proposed by bidders and stated on the Bid Form for certain work defined in the bidding requirements that may be added to or deducted from the base bid amount if the

Owner decides to accept a corresponding change either in the amount of construction to be completed or in the products, materials, equipment, systems, or installation methods described in the Contract Documents.

1. Alternates described in this Section are part of the Work only if enumerated in the

Agreement.

2. The cost or credit for each alternate is the net addition to or deduction from the Contract

Sum to incorporate alternates into the Work. No other adjustments are made to the

Contract Sum.

1.4 PROCEDURES

A. Coordination: Revise or adjust affected adjacent work as necessary to completely integrate work of the alternate into Project.

1. Include, as part of each alternate, miscellaneous devices, accessory objects, and similar items incidental to or required for a complete installation, whether or not indicated as part of alternate.

B. Execute accepted alternates under the same conditions as other Work of the Contract.

C. Schedule: A Part 3 "Schedule of Alternates" Article is included at the end of this Section.

Specification Sections referenced in schedule contain requirements for materials necessary to achieve the work described under each alternate.

ALTERNATES 012300 - 2

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 SCHEDULE OF ALTERNATES

A. Alternate No. 1.

1. Base Bid: All Work at Rogue Valley Youth Correction Facility and all Work at Eastern

Oregon Youth Correctional Facility.

2. Alternate No. 1: All Work at Oak Creek Youth Correctional Facility.

END OF SECTION 012300

SUBSTITUTION PROCEDURES 012500 - 1

SECTION 012500 - SUBSTITUTION PROCEDURES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Plans and general provisions of the Contract, including General Conditions and Supplemental

General Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements for substitutions.

B. Related Sections:

1. Division 01 Section "Product Requirements" for requirements for submitting comparable product submittals for products by listed manufacturers.

2. Divisions 02 through 33 Sections for specific requirements.

1.3 DEFINITIONS

A. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents and proposed by Contractor.

1. Substitutions for Cause: Changes proposed by Contractor that are required due to changed Project conditions, such as unavailability of product, regulatory changes, or unavailability of required warranty terms.

2. Substitutions for Convenience: Changes proposed by Contractor or Owner that are not required in order to meet other Project requirements but may offer advantage to

Contractor or Owner.

1.4 SUBMITTALS

A. Substitution Requests: Submit three copies of each request for consideration. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.

1. Substitution Request Form: Use CSI Form 13.1A.

2. Documentation: Show compliance with requirements for substitutions and the following, as applicable:

a. Statement indicating why specified product or fabrication or installation cannot be provided, if applicable.

SUBSTITUTION PROCEDURES 012500 - 2

b. Coordination information, including a list of changes or modifications needed to other parts of the Work and to construction performed by Owner and separate

Contractors, that will be necessary to accommodate proposed substitution.

c. Detailed comparison of significant qualities of proposed substitution with those of the work specified. Include annotated copy of applicable specification section.

Significant qualities may include attributes such as performance, weight, size, durability, visual effect, sustainable design characteristics, warranties, and specific features and requirements indicated. Indicate deviations, if any, from the Work specified.

d. Product Data, including drawings and descriptions of products and fabrication and installation procedures.

e. Samples, where applicable or requested.

f. Certificates and qualification data, where applicable or requested.

g. List of similar installations for completed projects with project names and addresses and names and addresses of architects and Owners.

h. Material test reports from a qualified testing agency indicating and interpreting test results for compliance with requirements indicated.

i. Research reports evidencing compliance with building code in effect for Project, from ICC-ES.

j. Detailed comparison of Contractor's construction schedule using proposed substitution with products specified for the Work, including effect on the overall

Contract Time. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery.

k. Cost information, including a proposal of change, if any, in the Contract Sum.

l. Contractor's certification that proposed substitution complies with requirements in the Contract Documents except as indicated in substitution request, is compatible with related materials, and is appropriate for applications indicated.

m. Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.

3. Owner’s Action: If necessary, Architect will, on behalf of the Owner, request additional information or documentation for evaluation within seven days of receipt of a request for substitution. Architect will on behalf of the Owner notify Contractor of acceptance or rejection of proposed substitution within 5 days of receipt of request, or seven days of receipt of additional information or documentation, whichever is later.

a. Forms of Acceptance: Change Order.

b. Use product specified if Owner or Architect does not issue a decision on use of a proposed substitution within time allocated.

1.5 QUALITY ASSURANCE

A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage qualified testing agency to perform compatibility tests recommended by manufacturers.

SUBSTITUTION PROCEDURES 012500 - 3

1.6 PROCEDURES

A. Coordination: Modify or adjust affected work as necessary to integrate work of the approved substitutions.

PART 2 - PRODUCTS

2.1 SUBSTITUTIONS

A. Substitutions for Cause: Submit requests for substitution immediately upon discovery of need for change.

1. Conditions: Architect will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Architect will return requests without action, except to record noncompliance with these requirements:

a. Requested substitution is consistent with the Contract Documents and will produce indicated results.

b. Substitution request is fully documented and properly submitted.

c. Requested substitution will not adversely affect Contractor's construction schedule.

d. Requested substitution has received necessary approvals of authorities having jurisdiction.

e. Requested substitution is compatible with other portions of the Work.

f. Requested substitution has been coordinated with other portions of the Work.

g. Requested substitution provides specified warranty.

h. If requested substitution involves more than one Contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all Contractors involved.

B. Substitutions for Convenience: Architect will consider requests for substitution if received within 7 days after commencement of the Work. Requests received after that time may be considered or rejected at discretion of Architect.

1. Conditions: Architect will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Architect will return requests without action, except to record noncompliance with these requirements:

a. Requested substitution offers Owner a substantial advantage in cost, time, energy conservation, or other considerations, after deducting additional responsibilities

Owner must assume. Owner's additional responsibilities may include compensation to Architect for redesign and evaluation services, increased cost of other construction by Owner, and similar considerations.

b. Requested substitution does not require extensive revisions to the Contract

Documents.

c. Requested substitution is consistent with the Contract Documents and will produce indicated results.

SUBSTITUTION PROCEDURES 012500 - 4

d. Substitution request is fully documented and properly submitted.

e. Requested substitution will not adversely affect Contractor's construction schedule.

f. Requested substitution has received necessary approvals of authorities having jurisdiction.

g. Requested substitution is compatible with other portions of the Work.

h. Requested substitution has been coordinated with other portions of the Work.

i. Requested substitution provides specified warranty.

j. If requested substitution involves more than one Contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all Contractors involved.

END OF SECTION 012500

CONTRACT MODIFICATION PROCEDURES 012600 - 1

SECTION 012600 - CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Plans and general provisions of the Contract, including General Conditions and Supplemental

General Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements for handling and processing

Contract modifications.

B. Related Sections:

1. Division 01 Section "Product Requirements" for administrative procedures for handling requests for substitutions made after Contract award.

1.3 PROPOSAL REQUESTS

A. Owner-Initiated Proposal Requests: Architect will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Plans and Specifications.

1. Proposal Requests issued by Architect are not instructions either to stop work in progress or to execute the proposed change.

2. Within time specified in Proposal Request or 5 days, when not otherwise specified, after receipt of Proposal Request, submit a quotation estimating cost adjustments to the

Contract Sum and the Contract Time necessary to execute the change.

a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

c. Include costs of labor and supervision directly attributable to the change.

d. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.

e. Quotation Form: Use CSI Form 13.6B "Proposal Worksheet Summary" and 13.6C

"Proposal Worksheet Detail".

CONTRACT MODIFICATION PROCEDURES 012600 - 2

B. Contractor-Initiated Proposals: If latent or changed conditions require modifications to the

Contract, Contractor may initiate a claim by submitting a request for a change to Architect.

1. Include a statement outlining reasons for the change and the effect of the change on the

Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time.

2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

4. Include costs of labor and supervision directly attributable to the change.

5. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the

Contract Time.

6. Comply with requirements in Division 01 Section "Substitution Procedures" if the proposed change requires substitution of one product or system for product or system specified.

7. Proposal Request Form: Use CSI Form 13.6A "Change Order Request (Proposal)" with attachments CSI Form 13.6B "Proposal Worksheet Summary" and 13.6C "Proposal

Worksheet Detail".

1.4 CHANGE ORDER PROCEDURES

A. On Owner's approval of a Proposal Request, Architect will create change order document for signature of Architect, Owner and Contractor in a form approved by the Owner.

PART 2 - PRODUCTS (Not Used)

END OF SECTION 012600

PAYMENT PROCEDURES 012900 - 1

SECTION 012900 - PAYMENT PROCEDURES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Plans and general provisions of the Contract, including General Conditions and Supplemental

General Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section specifies administrative and procedural requirements necessary to prepare and process Applications for Payment.

B. Related Sections:

1. Section 012600 "Contract Modification Procedures" for administrative procedures for handling changes to the Contract.

2. Section 013200 "Construction Progress Documentation" for administrative requirements governing the preparation and submittal of the Contractor's construction schedule.

3. Section 013300 "Submittal Procedures" for administrative requirements governing the preparation and submittal of the submittal schedule.

1.3 DEFINITIONS

A. Schedule of Values: A statement furnished by Contractor allocating portions of the Contract

Sum to various portions of the Work and used as the basis for reviewing Contractor's

Applications for Payment.

1.4 SCHEDULE OF VALUES

A. Coordination: Coordinate preparation of the schedule of values with preparation of Contractor's construction schedule.

1. Correlate line items in the schedule of values with other required administrative forms and schedules, including the following:

a. Application for Payment forms with continuation sheets.

b. Submittal schedule.

c. Items required to be indicated as separate activities in Contractor's construction schedule.

2. Subschedules for Work associated with each of the three project locations: Provide subschedules showing values correlated with each of three project locations .Sub-

Subschedules for Separate Elements of the Work: Where the Contractor's construction

PAYMENT PROCEDURES 012900 - 2

schedule at each of the three project locations defines separate elements of the Work, provide subschedules showing values correlated with each element.

B. Format and Content: Use the Project Manual table of contents as a guide to establish line items for the schedule of values. Provide at least one line item for each Specification Section.

1. Identification: Include the following Project identification on the schedule of values:

a. Project name and location.

b. Name of Architect.

c. Architect's project number.

d. Contractor's name and address.

e. Date of submittal.

2. Arrange schedule of values consistent with format of AIA Document G703.

3. Arrange the schedule of values in tabular form with separate columns to indicate the following for each item listed:

a. Related Specification Section or Division.

b. Description of the work.

c. Name of Subcontractor.

d. Name of manufacturer or fabricator.

e. Name of supplier.

f. Change Orders (numbers) that affect value.

g. Dollar value of the following, as a percentage of the Contract Sum to nearest one-hundredth percent, adjusted to total 100 percent.

1) Labor.

2) Materials.

3) Equipment.

4. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of Applications for Payment and progress reports. Coordinate with the Project

Manual table of contents. Provide multiple line items for principal subcontract amounts in excess of five percent of Contract Sum.

a. Include separate line items under Contractor and principal subcontracts for project closeout requirements in an amount totaling five percent of the Contract Sum and subcontract amount.

5. Round amounts to nearest whole dollar; total shall equal the Contract Sum.

6. Provide a separate line item in the schedule of values for each part of the Work where

Applications for Payment may include materials or equipment purchased or fabricated and stored, but not yet installed.

a. Differentiate between items stored on-site and items stored off-site. If required, include evidence of insurance.

7. Provide separate line items in the schedule of values for initial cost of materials, for each subsequent stage of completion, and for total installed value of that part of the Work.

PAYMENT PROCEDURES 012900 - 3

8. Each item in the schedule of values and Applications for Payment shall be complete.

Include total cost and proportionate share of general overhead and profit for each item.

a. Temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown either as separate line items in the schedule of values or distributed as general overhead expense, at Contractor's option.

9. Schedule Updating: Update and resubmit the schedule of values before the next

Applications for Payment when Change Orders result in a change in the Contract Sum.

1.5 APPLICATIONS FOR PAYMENT

A. Each Application for Payment shall be consistent with previous applications and payments as certified by Architect and paid for by Owner.

1. Initial Application for Payment, Application for Payment at time of Substantial

Completion, and final Application for Payment involve additional requirements.

B. Payment Application Times: The period of construction work covered by each Application for

Payment will be one calendar month.

C. Application for Payment Forms: Use forms acceptable to Architect and Owner for Applications for Payment. Submit forms for approval with initial submittal of schedule of values.

D. Application Preparation: Complete every entry on form. Notarize and execute by a person authorized to sign legal documents on behalf of Contractor. Architect will return incomplete applications without action.

1. Entries shall match data on the schedule of values and Contractor's construction schedule.

Use updated schedules if revisions were made.

2. Include amounts for work completed following previous Application for Payment, whether or not payment has been received. Include only amounts for work completed at time of Application for Payment.

3. Include amounts of Change Orders and Construction Change Directives issued before last day of construction period covered by application.

4. Indicate separate amounts for work being carried out under Owner-requested project acceleration.

E. Stored Materials: Request for payment for stored materials will be accepted at the Owner’s discretion as indicated in the General Conditions.

F. Transmittal: Submit one signed and notarized original copies in PDF digital format of each

Application for Payment to Architect by a method ensuring receipt within 24 hours. Include waivers of lien and similar attachments if required.

1. Transmit each copy with a transmittal form listing attachments and recording appropriate information about application.

PAYMENT PROCEDURES 012900 - 4

G. Waivers of Mechanic's Lien: With each Application for Payment, submit waivers of mechanic's liens from Subcontractors, Sub-subcontractors, and suppliers for construction period covered by the previous application.

1. Submit partial waivers on each item for amount requested in previous application, after deduction for retainage, on each item.

2. When an application shows completion of an item, submit conditional final or full waivers.

3. Owner reserves the right to designate which entities involved in the Work must submit waivers.

4. Submit final Application for Payment with or preceded by conditional final waivers from every entity involved with performance of the Work covered by the application who is lawfully entitled to a lien.

5. Waiver Forms: Submit waivers of lien on forms, executed in a manner acceptable to

Owner.

H. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following:

1. List of Subcontractors.

2. Schedule of values.

3. Contractor's construction schedule (preliminary if not final).

4. Products list (preliminary if not final).

5. Schedule of unit prices.

6. Submittal schedule (preliminary if not final).

7. List of Contractor's staff assignments.

8. List of Contractor's principal consultants.

9. Copies of building permits.

10. Copies of authorizations and licenses from authorities having jurisdiction for performance of the Work.

11. Initial progress report.

12. Report of preconstruction conference.

13. Certificates of insurance and insurance policies.

14. Performance and payment bonds.

15. Data needed to acquire Owner's insurance.

I. Application for Payment at Substantial Completion: After issuing the Certificate of Substantial

Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete.

1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum.

2. This application shall reflect Certificates of Partial Substantial Completion issued previously for Owner occupancy of designated portions of the Work.

PAYMENT PROCEDURES 012900 - 5

J. Final Payment Application: Submit final Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following:

1. Evidence of completion of Project closeout requirements.

2. Insurance certificates for products and completed operations where required and proof that taxes, fees, and similar obligations were paid.

3. Updated final statement, accounting for final changes to the Contract Sum.

4. AIA Document G706, "Contractor's Affidavit of Payment of Debts and Claims."

5. AIA Document G706A, "Contractor's Affidavit of Release of Liens."

6. AIA Document G707, "Consent of Surety to Final Payment."

7. Evidence that claims have been settled.

8. Final meter readings for utilities, a measured record of stored fuel, and similar data as of date of Substantial Completion or when Owner took possession of and assumed responsibility for corresponding elements of the Work.

9. Final liquidated damages settlement statement.

PART 2 - PRODUCTS (Not Used)

END OF SECTION 012900

PROJECT MANAGEMENT AND COORDINATION 013100 - 1

SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Plans and general provisions of the Contract, including General Conditions and Supplemental

General Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. Owner’s safety and security requirements.

2. General project coordination procedures.

3. Administrative and supervisory personnel.

4. Coordination drawings.

5. Requests for Information (RFIs).

6. Project meetings.

B. Each Contractor shall participate in coordination requirements. Certain areas of responsibility are assigned to a specific Subcontractor or installer.

C. Related Sections:

1. Section 013200 "Construction Progress Documentation" for preparing and submitting

Contractor's construction schedule.

2. Section 017300 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

3. Section 017700 "Closeout Procedures" for coordinating closeout of the Contract.

1.3 DEFINITIONS

A. RFI: Request from Contractor seeking information from Architect, Construction Manger or

Owner during construction.

1.4 SAFETY AND SECURITY REQUIREMENTS

A. Employee Identification: Owner will provide identification tags for Contractor personnel working on Project site. Require personnel to use identification tags at all times.

B. The superintendent and Project manager, if the Contractor utilizes a Project manager, shall be reviewed and approved by the Architect and Owner, and neither shall be changed except with the consent of the Architect and Owner. Any new superintendent or new Project manager must

PROJECT MANAGEMENT AND COORDINATION 013100 - 2

be satisfactory to the Architect and Owner. The superintendent, and any Project manager, shall represent the Contractor and all communications given to the superintendent or Project manager are deemed given to the Contractor. Important communications will be confirmed in writing.

C. Owner may request any person working on the project be removed for behavior and/or inappropriate conduct at the sole discretion of the Owner.

D. The project work areas are within youth correctional facilities. Contractor is responsible for the safety and security of the work site and any material and equipment staging areas. The contractor shall comply with all facility access requirements for personnel and vehicles. The contractor will provide as part of the work a temporary eight-foot-tall security fence around the work area to serve as a barrier to youth accessing the work area. The contractor will ensure the area is secure at all times. Personnel and vehicle gates will be kept closed when not in use.

1. Portable Chain-Link Fencing and Gates: Minimum 2-inch, 0.148-inch- thick, galvanized-steel, chain-link fabric fencing; minimum 8 feet high by 10 feet wide panels with galvanized-steel pipe posts and 1-5/8-inch- OD top and bottom rails. Provide 36-inch minimum base stands for supporting posts. Additionally, Contractor to install fabric on all sides of the construction fencing to block views into the construction site up to approximately 6 feet in height. Fabric to be Privacy Screen 100 Series Fence Block

Windscreen – 98% blockage or equal.

E. All Contractor and subcontractor personnel shall wear OSHA approved, high visibility vests at all times. This is to ensure not only the normal safety protocol and procedure but also to allow

OYA staff to quickly differentiate Contractor staff from residents and other visitors.

F. Gates and Building Doors are to be locked and monitored by Contractor. Gates and Building

Doors are to be posted with signage stating the following at a minimum (verify exact wording with Owner): “CONSTRUCTION AREA: AUTHORIZED PERSONNEL ONLY; HARD

HATS AND PROTECTION GEAR REQUIRED; WATCH FOR FALLING MATERIAL;

WATCH FOR MOVING EQUIPMENT; WATCH FOR UNEVEN SURFACES.”

G. Safety and Security Procedures:

1. Contractor shall have personnel monitoring all material movements through site or building secure perimeter.

2. Contractor shall have personnel provide end of work period jobsite sweeps.

3. End of work period Confirmation that all Construction personnel have exited the site.

4. Sweeps and monitoring to ensure construction materials, tools and supplies are 100% accounted for and secured to ensure youth do not take possession.

5. Contractor will comply with all security and safety requirements and requests from

Owner to ensure the security and safety of staff and youth.

6. Contractor shall immediately correct all security and safety matters the Owner identifies.

7. Contractor shall monitor and enforce clean-up, tool control activities, unlocking and locking vehicles and storage facilities inside the secure perimeter, and end of work period jobsite sweeps.

8. Gather and collect all tools and vehicle and equipment keys at day’s end as per requirements of the Oregon Youth Authority.

9. Secure all ladders and other materials or equipment that are not in use that could be used to aid youth escapes.

PROJECT MANAGEMENT AND COORDINATION 013100 - 3

10. Contractor shall monitor any temporary facilities including but not limited to temporary stairs, fencing, lifts or other temporary measures to ensure that no access is provided to residents.

11. Contractor shall observe and record that any temporary facility that is to remain in place

(such as a temporary scaffold or stair) is secured at end of each construction activity period.

1.5 GENERAL COORDINATION PROCEDURES

A. Coordination: Coordinate construction operations included in different Sections of the

Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, that depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

B. Coordination: Each contractor and subcontractor shall coordinate its construction operations with those of other contractors and entities to ensure efficient and orderly installation of each part of the Work. Each contractor and subcontractor shall coordinate its operations with operations, included in different Sections, that depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components with other contractors to ensure maximum performance and accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

C. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

1. Prepare similar memoranda for Owner and separate contractors if coordination of their

Work is required.

D. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors and Owner to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's construction schedule.

2. Preparation of the schedule of values.

3. Installation and removal of temporary facilities and controls.

PROJECT MANAGEMENT AND COORDINATION 013100 - 4

4. Delivery and processing of submittals.

5. Progress meetings.

6. Preinstallation conferences.

7. Project closeout activities.

8. Startup and adjustment of systems.

E. Conservation: Coordinate construction activities to ensure that operations are carried out with consideration given to conservation of energy, water, and materials. Coordinate use of temporary utilities to minimize waste.

1. Salvage materials and equipment involved in performance of, but not actually incorporated into, the Work. See other Sections for disposition of salvaged materials that are designated as Owner's property.

1.6 COORDINATION DRAWINGS

A. Coordination Drawings, General: Prepare coordination drawings according to requirements in individual Sections, and additionally where installation is not completely shown on Shop

Drawings, where limited space availability necessitates coordination, or if coordination is required to facilitate integration of products and materials fabricated or installed by more than one entity.

1. Content: Project-specific information, drawn accurately to a scale large enough to indicate and resolve conflicts. Do not base coordination drawings on standard printed data. Include the following information, as applicable:

a. Use applicable Drawings as a basis for preparation of coordination drawings.

Prepare sections, elevations, and details as needed to describe relationship of various systems and components.

b. Coordinate the addition of trade-specific information to the coordination drawings by multiple contractors in a sequence that best provides for coordination of the information and resolution of conflicts between installed components before submitting for review.

c. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.

d. Indicate space requirements for routine maintenance and for anticipated replacement of components during the life of the installation.

e. Show location and size of access doors required for access to concealed dampers, valves, and other controls.

f. Indicate required installation sequences.

g. Indicate dimensions shown on the Drawings. Specifically note dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Architect indicating proposed resolution of such conflicts. Minor dimension changes and difficult installations will not be considered changes to the Contract.

B. Coordination Drawing Organization: Organize coordination drawings as follows:

PROJECT MANAGEMENT AND COORDINATION 013100 - 5

1. Floor Plans and Reflected Ceiling Plans: Show architectural and structural elements, and mechanical, plumbing, fire-protection, fire-alarm, and electrical Work. Show locations of visible ceiling-mounted devices relative to acoustical ceiling grid. Supplement plan drawings with section drawings where required to adequately represent the Work.

2. Plenum Space: Indicate subframing for support of ceiling and wall systems, mechanical and electrical equipment, and related Work. Locate components within ceiling plenum to accommodate layout of light fixtures indicated on Drawings. Indicate areas of conflict between light fixtures and other components.

3. Mechanical Rooms: Provide coordination drawings for mechanical rooms showing plans and elevations of mechanical, plumbing, fire-protection, fire-alarm, and electrical equipment.

4. Structural Penetrations: Indicate penetrations and openings required for all disciplines.

5. Slab Edge and Embedded Items: Indicate slab edge locations and sizes and locations of embedded items for metal fabrications, sleeves, anchor bolts, bearing plates, angles, door floor closers, slab depressions for floor finishes, curbs and housekeeping pads, and similar items.

6. Mechanical and Plumbing Work: Show the following:

a. Sizes and bottom elevations of ductwork, piping, and conduit runs, including insulation, bracing, flanges, and support systems.

b. Dimensions of major components, such as dampers, valves, diffusers, access doors, cleanouts and electrical distribution equipment.

c. Fire-rated enclosures around ductwork.

7. Electrical Work: Show the following:

a. Runs of vertical and horizontal conduit 1-1/4 inches in diameter and larger.

b. Light fixture, exit light, emergency battery pack, smoke detector, and other fire-alarm locations.

c. Panel board, switch board, switchgear, transformer, busway, generator, and motor control center locations.

d. Location of pull boxes and junction boxes, dimensioned from column center lines.

8. Fire-Protection System: Show the following:

a. Locations of standpipes, mains piping, branch lines, pipe drops, and sprinkler heads.

9. Review: Architect will review coordination drawings to confirm that the Work is being coordinated, but not for the details of the coordination, which are Contractor's responsibility. If Architect determines that coordination drawings are not being prepared in sufficient scope or detail, or are otherwise deficient, Architect will so inform

Contractor, who shall make changes as directed and resubmit.

10. Coordination Drawing Prints: Prepare coordination drawing prints according to requirements in Section 013300 "Submittal Procedures."

C. Coordination Digital Data Files: Prepare coordination digital data files according to the following requirements:

PROJECT MANAGEMENT AND COORDINATION 013100 - 6

1. Architect will furnish Contractor one set of digital data files of Drawings for use in preparing coordination digital data files.

a. Architect makes no representations as to the accuracy or completeness of digital data files as they relate to Drawings.

b. Digital Data Software Program: Drawings are available in REVIT 2022.

c. Contractor shall execute a data licensing agreement in the form of

AIA Document C106.

1.7 KEY PERSONNEL

A. Key Personnel Names: At the preconstruction meeting submit a list of key personnel assignments, including superintendent and other personnel in attendance at Project site. Identify individuals and their duties and responsibilities; list addresses and telephone numbers, office, and cellular telephone numbers and email addresses. Provide names, addresses, and telephone numbers of individuals assigned as standbys in the absence of individuals assigned to Project.

1. Post copies of list in project meeting room, in temporary field office, and by each temporary telephone. Keep list current at all times.

1.8 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.

1. Architect will return RFIs submitted to Architect by other entities controlled by

Contractor with no response.

2. Coordinate and submit RFIs in a prompt…

This is the start of the file's text. The full file is on GovTribe.