Attachment A - EV Charging Station Specifications 03.27.2020.pdf

PDF 1 MB Posted

Attached to
WV-NCTC DIV OF FAC CAMPUS EV CHARGING ST
Solicitation number
140F0920B0004
Issued by

About this file

This document provides construction specifications for installing electric vehicle charging stations at the National Conservation Training Center in West Virginia. The specifications cover installing EV charging stations, panelboards, cabinets, transformers, disconnect switches, concrete pads, electrical wiring, distribution modifications, controls, branch circuits, grounding, and surge protection. Key details include installing Level 2 EV charging stations in the Blue and Green parking lots; providing underground ducts and wiring; using THHN-THWN insulated conductors; grounding all exposed and buried metal; testing installation work; and training facility staff on operating and maintaining the new systems.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

United States Fish and Wildlife Service

EV Charging Stations Shepherdstown, WV

EV Charging Stations

Construction Specifications

March 27, 2020

National Conservation Training Center 698 Conservation Way

Shepherdstown, WV 25443

EV Charging Stations Table of Contents National Conservation Training Center Engineer: Dubois & King, Inc. Section 00 01 10 - Page 1 of 1

IFC March 27, 2020

SECTION 00 01 10

TABLE OF CONTENTS

01 10 00 - Summary of Work

01 33 00 - Submittals

01 70 00 Project Closeout

26 05 00 - Basic Electrical Materials and Methods

26 05 20 - Conductors & Cables

26 05 26 - Grounding & Bonding

26 05 29 - Hangers and Supports for Electrical Systems

26 05 33 - Raceways and Boxes

26 05 43 - Underground Ducts and Utility Structures

26 05 75 - Electrical Identification

26 12 16 - Dry-Type Transformers

26 14 16 - Panelboards

26 26 53 - Electric Vehicle Charging Equipment

26 28 16 - Enclosed Switches and Circuit Breakers

26 43 13 - Transient Voltage Suppression

31 20 00 - Earthwork

31 25 00 - Erosion and Sediment Control

32 10 00 - Concrete Curbs Walk and Slabs

32 92 00 - Turf and Grasses

33 05 21 - Horizontal Directional Drilling

33 05 26 - Tracer Wire

EV Charging Stations Summary of Work

Training Center Engineer: Dubois & King, Inc. Section 01 10 00 - Page 1 of 4

IFC March 27, 2020

SECTION 01 10 00

SUMMARY OF WORK

PART 1 GENERAL

1.01 SUMMARY

A. Description of work: The work shall consist of providing all labor, equipment, supplies, and materials, to perform the following work at the National Conservation Training Center, Shepherdstown, West Virginia in accordance with these plans and specifications.

B. In general, this project consists of installing EV charging stations, panelboards, cabinets, transformers, disconnect switches, concrete pads, power wiring, power distribution modification, electrical controls, branch circuit wiring, grounding, surge protection and related electrical systems.

C. All work shall be installed in accordance with local, state and federal code requirements.

D. Installation location:

United States Department of the Interior

U.S. FISH & WILDLIFE SERVICE

National Conservation Training Center 698 Conservation Way Shepherdstown, WV 25443

E. Site visit: A site coordinated visit shall be scheduled with details included in the solicitation. Contractors are advised to visit the site and inspect existing conditions prior to submitting bids. See Federal Acquisition Regulation (FAR) clause 52.236-27 “Site Visit”.

F. The DESCRIPTION paragraph in each subsequent section is a statement or short word summary of the content of the section. This paragraph is only intended as a brief description of the significant items described in the section and is used to simplify the finding of specific information.

G. The "related work" paragraphs are also not meant to be all inclusive. They serve the function of assisting the reader in locating specific information.

1.02 REFERENCES

A. Referenced standards are listed in the applicable specification section.

1.03 DEFINITIONS

A. Approvals: Approval of submittals is an indication that the Contractor’s submittals have been reviewed and there are no objections, except as noted. Approval of deviations shall apply only to those deviations or omissions from the requirements of the drawings and specifications brought to the Contracting Officer Representative’s (COR) attention in writing.

1.04 SUBMITTALS

A. See Specification Section 01 33 00-Submittals for specific requirements on submittals.

Training Center Engineer: Dubois & King, Inc. Section 01 10 00 - Page 2 of 4

IFC March 27, 2020

1.05 CONFORMANCE

A. Submittals must show clearly that the product, sample or shop drawing conforms to the specifications.

1.06 QUALITY ASSURANCE

A. Codes and Standards: The work shall comply with codes and standards applicable to each type of work and as listed in the individual sections of these specifications. This contract incorporates materials, applications and tests by reference, with the same force and effects as if they were given in full test.

B. Conflict: Where a conflict occurs between reference documents, drawings, and project specifications, the most stringent requirement shall govern.

C. Product Basis: Where specifications or drawings call out a specific product or manufacturer, it is understood that an equal or better product is acceptable, as approved in the submittal process.

1.07 DELIVERY, STORAGE AND HANDLING

A. Delivery: Protect products incorporated into the work from damage while in transit to the site. Products must be delivered in original unopened containers with manufacturer’s name, brand designation, and contents legibly indicated. The containers shall bear the referenced specification number, type, and class as applicable.

B. Storage: Provide temporary storage facilities for products. Storage shall comply with the manufacturer(s) instructions. The storage area shall permit access for inspection and handling.

C. Handling: Load and unload products protecting them from damage.

1.08 PROJECT/SITE CONDITIONS

A. The project site is a Training Campus operated by the United States Department of the Interior, U.S. FISH & WILDLIFE SERVICE. Work areas shall be protected and roped off to alert unauthorized personnel to work in progress.

B. Existing property not indicated for demolition shall be protected. All damage by Contractor activities shall be repaired by the Contractor at no additional cost to the Government.

C. Safety is paramount. Contractor is responsible for safety on the project site and shall take appropriate measures to maintain a safe area around the project site, which is used by Government employees and the public. Applicable OSHA regulations shall be adhered to by the Contractor. Contractor shall submit a safety plan prior to starting work.

D. Landscape Protection: Protect all vegetation inside work limits and outside work limits that Contractor has direct access to and utilizes in support of the project. All rutting caused by Contractor activities shall be filled and contoured to match adjacent areas.

Areas damaged by Contractor shall be repaired at no cost to the Government.

E. There are several elements of the project that require investigations and confirmation by contractor. For example, no soil borings have been obtained and it is assumed excavations to install sonotube-type foundations will be excavated in soils, and that bedrock will not be encountered. All installation and construction must be completed within local, State, and Federal codes. Furthermore, the project is to be constructed in

Training Center Engineer: Dubois & King, Inc. Section 01 10 00 - Page 3 of 4

IFC March 27, 2020 a coastal, windblown area and final selection of equipment, associated fasteners and connections, and other related materials and installation work shall be in consideration of this site condition.

1.09 SEQUENCING AND SCHEDULING

A. A bar chart type work schedule shall be submitted to the Contracting Officer

Representative (COR) within 15 days after the preconstruction conference. When requested, submit an updated schedule within 3 calendar days.

B. The Contractor is advised there is a separate, but concurrent project that will occur during this project. The separate project involves the installation of various emergency power systems within or adjacent to the project area at both federal facilities and at the same location, which may or may not be carried out by another contractor.

C. The Contractor shall be responsible to coordinate with the COR and understand general nature of any potential overlap or conflicts between this project and with other contractors to accommodate overlapping work and identify and resolve potential conflicts before they arise.

PART 2 PRODUCTS

2.01 TEMPORARY FACILITIES

A. The Contractor shall provide portable toilet facilities at the construction site.

B. Water is available at each Building.

C. Electrical power (120Vac-20Amp) is available at each building site.

D. The Contractor shall provide and maintain safe and suitable temporary barricades, obstructions, warning signs, tarpaulins and other temporary construction necessary for protection of the Work and the safety of persons and property.

E. The Contractor shall provide and maintain adequately equipped first aid facilities in a location or at locations, which are readily accessible to workmen, the Engineer, and visitors to the site. Provide at least one employee who is properly trained in first aid and who shall be available to render first aid whenever construction is in progress.

PART 3 EXECUTION

3.01 PROJECT MEETINGS

A. Preconstruction Conference: Will be scheduled through Contracting and General Services.

B. Progress Meetings: To be held at the project site(s) as required.

C. Inspections:

1. Routine inspections will be performed by the COR and the Engineer at critical points during construction. Inspection of items of work by the COR and Engineer will not relieve the Contractor of the requirement to meet project specifications.

The COR and Engineer shall be informed 24 hours in advance of work requiring his observation. After being informed in advance, the COR and Engineer’s non-attendance shall not prohibit the Contractor from proceeding with the work in the COR and Engineer’s absence.

2. For final inspection, notify the COR in writing at least 14 working days before the completion date so the Government can schedule final inspection. The superintendent shall be present during the final inspection.

Training Center Engineer: Dubois & King, Inc. Section 01 10 00 - Page 4 of 4

IFC March 27, 2020

3.02 DISPOSAL OF DEBRIS

A. Demolition debris shall be removed from the project site and disposed of in a legal disposal site by the contractor. Contractor shall pay all fees required for disposal.

3.03 AS-BUILT DRAWINGS

A. Contractor shall maintain a set of as-built drawings/ prints to be submitted to the COR before submitting final payment. As the job progresses, continuously maintain as-built drawings of the work. The changes shall be noted legibly in red pencil; or red ink.

Should final inspection reveal changes in the project not so noted on the as-built drawings, the contractor shall record these changes on the as-built drawings within 3 working days. Deliver as-built drawings to the COR before requesting final payment.

3.04 WARRANTY

A. All project construction shall be provided with a one-year warranty in accordance with

FAR 52.246-21. Refer to specific sections for extended warranty requirements.

B. With respect to warranties, expressed or implied, from manufacturer or suppliers for materials or equipment furnished under the contract, the Contractor shall:

1. Obtain the most favorable warranties that would be given by the Contractor in normal commercial practices, but in no case less than called for by the specifications.

2. Require warranties to be executed, in writing, for the benefit of the Government.

3. Submit warranties to the COR prior to final inspection.

END OF SECTION

EV Charging Stations Submittals

Training Center Engineer: Dubois & King, Inc. Section 01 33 00 - Page 1 of 5

IFC March 27, 2020

SECTION 01 3300

SUBMITTALS

PART 1 GENERAL

1.01 DESCRIPTION

A. This Section generally describes the types of submittals required during construction, procedures for making submittals, the preparation of submittals, and the times at which submittals are required.

B. Submittals shall include shop drawings, manufacturer’s literature, as-built drawings, samples, work schedule, schedule of values and other submittals as required herein.

C. The Contractor shall refer to specific specification sections for submittals required.

Additional submittals may be required by the Contracting Officer Representative

(COR).

1. Submittals shall be sent or delivered to the Contracting Officer at U.S. Fish and

Wildlife Service, National Conservation Training Center, 698 Conservation Way, Shepherdstown, WV 25443

D. Unless otherwise stated in the individual specification sections, provide four (4) paper copies of each submittal, of which three (3) copies will be retained for Government use and one (1) set will be returned to the Contractor. In lieu of paper copies, one copy of each electronic (i.e. PDF format) submittal is encouraged to be emailed to the Government COR for review, comment, and approval.

E. Allow at least 21 working days for review, plus transmittal time back and forth.

F. All printed materials shall be neat, clean, clear and legible, and of such quality that they can be easily reproduced. Copies not conforming to this paragraph may be returned to Contractor, without review.

G. Contractor shall not commence work, which requires review of any submittals until receipt of returned submittals with an acceptable action. The contractor will not allow submittals without an acceptable action marking to be used for the project.

1.02 IDENTIFICATION OF SUBMITTALS

A. Completely identify each submittal and resubmittal by showing at least the following information:

1. Name of project, drawing number and specification section number to which submittal applies.

2. Name, address, and telephone number of Contractor and Contractor's stamp of approval, indicating that the submission has been thoroughly checked by Contractor for conformance and fit.

3. Name, address and telephone number of individual, firm or organization who will be doing the fabrication, supplying or manufacturing of equipment and materials and the name of the individual who may be contacted for further information.

4. The location, service, equipment designation and other information to specifically indicate the item for which acceptance is requested. Clearly indicate any deviations from the Contract Documents.

5. Whether it is an original submittal or a resubmittal.

Training Center Engineer: Dubois & King, Inc. Section 01 33 00 - Page 2 of 5

IFC March 27, 2020

6. Each submittal shall clearly note the manufacturer’s name and address, trade name, product, lot, style, color, catalog designation or model number, and location of use.

1.03 COORDINATION OF SUBMITTALS

A. When preparing each submittal, Contractor shall fully coordinate all interrelated work, such as, but not limited to: Determine and verify all field dimensions and conditions, materials, catalog numbers and similar data; coordinate with all trades, subcontractors and secure all necessary approvals, in writing.

B. Make submittals in groups containing all associated items which in some way depend upon each other. This also applies to color charts, as one color may not be able to be selected without the selection of other colors so as to form a color-coordin-ated group.

The COR may elect not to review partial, incomplete submissions, whereupon he will return the incomplete submission to the Contractor for a resubmission of a complete submittal.

1.04 CONTRACTOR'S APPROVAL STAMP

A. The stamp shall have the following wording: "I hereby certify that I have carefully examined the enclosed submittal(s) and have determined and verified all field measurements, construction criteria, materials, catalog numbers and similar data, coordinated the submittal(s) with other submissions and the work of other trades and contractors, and that to the best of my knowledge and belief, the enclosed submittal(s) is/are in full compliance with the Contract requirements, except as follows (enter NONE if there are no exceptions):"

B. Each copy of every submittal shall be stamped with the Contractor's approved stamp.

1.05 GOVERNMENT’S REVIEW

A. The Government will review and comment on each submission and will only be for general conformance with the design concept of the Project and will be confined to general arrangement and compliance with the Contract Documents. Government’s review will not be for the purpose of checking dimensions, weights, clearances, fitting, tolerances, interferences, or coordination of trades or contractors. The acceptance of a separate item does not represent acceptance of an assembly in which the item functions. Government’s review and comments will in no way relieve Contractor of any of his responsibilities under the Contract.

B. Submittals will be marked as follows:

1. Accepted - Submittal appears to conform to Contract Documents and Contractor may proceed with ordering and installation.

2. Accepted As Corrected - Same as "Accepted", except it is accepted on the basis that the modifications or notes added to the submittal by COR will be complied with by Contractor.

3. Rejected, Revise and Resubmit - Submission is not acceptable and shall be revised and resubmitted by Contractor.

4. Rejected - Unacceptable - Submission is unacceptable, as it does not appear to conform to the Contract Documents. A completely new submission of other equipment or different materials is required.

C. No payment will be made on any item for which a submission is required if such submission:

Training Center Engineer: Dubois & King, Inc. Section 01 33 00 - Page 3 of 5

IFC March 27, 2020

1. has not been made.

2. has been made but was not stamped "Accepted" by the COR.

3. has been made and stamped "Accepted As Corrected", but Contractor has not complied with COR's notes marked on the submittal.

4. has been made and stamped "Accepted", but item provided does not conform to the shop drawing nor to the Contract Documents.

1.06 RESUBMISSIONS

A. For any submittal that the Government requires a resubmission, Contractor shall make required corrections, and resubmit corrected copies until accepted. On or with resubmittals, clearly describe revisions and changes made, other than the corrections requested by COR, which did not appear on the previous submissions.

PART 2 SUBMITTALS

2.01 SCHEDULE OF VALUES

A. Within fifteen days after the signing of the Agreement, submit to the COR two (2) copies of a schedule of values of the various portions of the Work, including quantities aggregating the total Contract Price, and supported by such data to substantiate its correctness as COR may require. Each item in the schedule of values shall include its proper share of overhead and profit. This schedule, when accepted by the COR, shall only be used as a basis for Contractor's Periodic Estimate. No payments will be made to Contractor until such Schedule has been submitted and accepted by the COR.

B. Within 15 days after the signing of the Agreement, submit to the COR two (2) copies of a Cashflow Schedule including estimated monthly payment schedule for the Project.

C. On "unit price" items, the schedule of values shall contain unit prices for various stages of work, such as restoration of surfaces broken down into paved, unpaved, and other types of areas to be restored.

D. On "per each" or "lump sum" items, break prices down sufficiently to provide a convenient and realistic means for determining the amount of work done during various stages of progress.

E. Where prices are not broken down sufficiently to accurately determine the value of Work completed, the COR will estimate the value of the Work completed and will deduct some amount so as to arrive at a conservative value, which will allow Government to easily complete the Work with the unpaid balance. When the required detail in the Schedule of Values is not provided by the Contractor, the Contractor agrees to accept the COR's determinations.

2.02 CERTIFICATIONS

A. Submit in triplicate certifications of compliance whenever required by the

Specifications. Certifications shall be complete and exact, they shall be properly authenticated by the written signature, in ink, of an owner, officer or duly authorized representative of the person, firm or organization issuing such certification, and they shall guarantee that the materials or equipment are in complete conformance with the requirements of these Specifications. Submit an acceptable "Certificate of Compliance" for approval.

2.03 CONSTRUCTION SCHEDULE

A. Within fifteen days after the signing of the Agreement, submit for the COR's and

Government's information, a construction schedule showing, in detail, the proposed

Training Center Engineer: Dubois & King, Inc. Section 01 33 00 - Page 4 of 5

IFC March 27, 2020 sequence of the Work and the estimated date of starting and completing each stage of the Work in order to complete the Project within the Contract Time. Prepare the schedule in a manner so that the actual progress of the Work can be recorded and compared with the expected progress. Coordinate the construction schedule with the proposed schedules of other contractors, if any, engaged in work at, or adjacent to, the Project site.

B. Coordinate the Work and make every effort to maintain the construction schedule. In the event actual progress begins to lag the schedule, promptly employ additional means or methods of construction to make up the lost time.

C. Notify the COR in writing (1) 72 hours before commencing any work at the site, (2) 4 weeks before resuming work after a winter shutdown, and (3) at least 48 hours before resuming work in the case of a temporary suspension of work.

D. Keep the construction schedule current and revise or confirm the schedule as appropriate, and accurately reflect the conditions of the Work, past progress, and anticipated future progress.

E. Prepare and submit, with the Construction Schedule, a separate schedule listing dates for submission of major shop drawings, submittals, and material samples.

2.04 SHOP DRAWINGS

A. Submit shop drawings for all fabricated work, manufactured items and for all other items specifically required by the Specifications.

B. Subcontractors must submit shop drawings directly to the Contractor for the

Contractor’s review, approval and submission to the Government. Thoroughly check subcontractors' shop drawings for measurements, sizes of members, details, materials, and conformance with the Contract Documents. Return submittals which are found to be inaccurate or in error. Do not submit to the COR until corrections have been made.

C. Clearly show the relation of the various parts, and, where the Work depends upon field measurements, make measurements and include them on the shop drawings before submitting to the COR.

D. Reference all submissions to clearly indicate the Specification Section, location, service, and function of each particular item. Submissions for a single item, or group of related items shall be complete. When submitting manufacturers' catalogs, pamphlets or other data sheets, in lieu of prepared shop drawings, the contractor shall specifically identify in ink the items for which acceptance is being sought.

E. If the shop drawings contain any departures from the Contract requirements, specifically describe them in the Contractor's letter of transmittal. Where such departures require revisions to layouts or structural changes to the Work as shown, the Contractor shall, at his own expense, prepare and submit revised layout and structural drawings. Make drawings the same size as the Contract Drawings.

2.05 SAMPLES

A. Where required, submit sample or test specimens of materials to be used or offered for use. Samples shall be representative, in all respects, of the material offered or intended; shall be supplied in such quantities and sizes as may be required for proper examination and tests; and shall be delivered to the COR, prepaid, along with

Training Center Engineer: Dubois & King, Inc. Section 01 33 00 - Page 5 of 5

IFC March 27, 2020 identification as to their sources and types or grades. Submit samples well in advance of anticipated use to permit the making of tests or examinations.

B. Samples will be checked with reasonable promptness only for conformance with the design and for compliance with the information given in the Contract Documents.

C. The Work shall be in accordance with the accepted sample. The use of materials or equipment for which samples are required to be submitted for acceptance is not permitted until such acceptance has been given by the COR.

2.06 OPERATION AND MAINTENANCE DATA

A. Compile and submit all manufacturers recommended operations and maintenance manuals, procedures and other appropriate data.

2.07 SPARE PARTS

A. For each item, provide a list of parts and supplies that are normally furnished at no extra cost or are specified to be furnished under this Contract, and a separate list of additional items which the manufacturer recommends having "on hand" in order to assure efficient and proper operation for the first year of service.

2.08 INSTALLATION - APPLICATION INSTRUCTIONS

A. In addition to the installation instructions required, submit copies of all manufacturers' application instructions, all printed instructions and labels, which are attached to or shipped with equipment and materials.

2.09 MANUFACTURER'S AUTHORIZED DISTRIBUTORS

A. The product of a manufacturer who does not maintain an adequate distributors and a sufficient stock of spare parts in a reasonable vicinity of the Project, is subject to rejection by the COR solely on that basis. With each submission, submit information on manufacturer's facilities and give complete details of their service policies and capabilities, and a general idea of the stock of spare parts available.

2.10 TEST RESULTS AND INSTALLATION

A. Whenever tests are required on materials and equipment, such tests shall be performed and two (2) copies of the test results submitted to the COR. Do not deliver to the Project or incorporate into the Work any materials or equipment for which the COR has not issued a written acceptance of the required tests and test results.

EV Charging Stations Project Closeout

Training Center Engineer: Dubois & King, Inc. Section 01 70 00 - Page 1 of 3

IFC March 27, 2020

SECTION 01 70 00

PROJECT CLOSEOUT

PART 1 GENERAL

1.01 DESCRIPTION

A. This section provides instructions to the Contractor in scheduling the sequence of events and requirements leading to final acceptance of the Project, occupancy by the Government and the responsibilities of the respective parties.

1.02 REQUIREMENTS FOR SUBSTANTIAL CORMPLETION

A. The construction of the Project or a specified part thereof is sufficiently completed in accordance with the Contract Documents, so that the Project or specified part can be utilized for the purposes for which it is intended.

B. The Contractor shall:

1. Submit all appropriate electrical, building, health, and environmental certificates of compliance required by the Contractor to obtain in the performance of his work.

2. Submit all required test results and written certification that equipment and systems have been tested in presence of the COR and/or Engineer and are fully operational.

3. Provide keys of the facilities to the Facilities Manager.

4. Submit required Operation and Maintenance Manuals, data, materials, and spare parts to the Maintenance Staff.

5. Provide operator training to the Maintenance Staff.

6. Submit Project As-Built Drawings per requirements herein to the COR.

7. Meet other requirements of this Section and as stated elsewhere within these specifications.

1.03 SUBSTANTIAL CORMPLETION

A. The Contractor is advised that Substantial Completion must be attained at a reasonable time prior to the Contract Completion Date and attaining Final Completion.

Generally, this shall be at least 30 to 60 days prior to the Contract Completion Date to allow for the Contractor to complete all punch list and outstanding work items prior to arranging for a final completion inspection by the COR.

B. The Contractor shall:

1. Submit written certification to the COR that the Project or designated portion of the Project is substantially complete.

2. Submit a written request for a Substantial Completion inspection by the COR.

C. The COR will arrange for an inspection within ten days after receipt of certification.

D. Should the COR consider that Work is substantially complete, the COR will prepare and issue a Certificate of Substantial Completion, containing:

1. Effective date of Substantial Completion.

2. CO’s punch list of items to be completed or corrected.

3. The time within which Contractor shall complete or correct work of listed items.

4. Time and date Government will assume possession of Work or designated portion thereof.

5. Responsibilities of Government and Contractor for:

a. Insurance.

Training Center Engineer: Dubois & King, Inc. Section 01 70 00 - Page 2 of 3

IFC March 27, 2020

b. Utilities.

c. Operation of mechanical, electrical and other systems.

d. Maintenance and cleaning.

e. Security.

f. Warranties (list exceptions if any).

1) Signatures of:

(a) Contracting Officer (CO).

(b) Contractor.

E. Should the COR disagree with the Contractor's Certification that Work is substantially complete:

1. The COR will postpone inspection and will promptly notify the Contractor in writing, stating the reasons.

2. The Contractor shall complete the Work, and send second written notice to the

COR, certifying that the Project, or designated portion of the Project, is substantially complete and request re-inspection.

3. The COR will then schedule an inspection of the Work as above.

F. For Government occupancy of Project or Designated Portion of Project, the Contractor shall:

1. Perform final cleaning.

2. Program the lighting control panels as directed by the COR for each lighting circuit that includes time of day scheduling (on-off), holidays and weekends as directed.

1.04 FINAL INSPECTION

A. The Contractor is reminded that the status of Final Completion must be achieved on or before the Contract Completion Date to fully meet the conditions of this Contract.

B. The Contractor shall submit written certification that:

1. Work has been completed in accordance with Contract Documents.

2. Project is completed, and ready for final inspection.

C. If the COR concurs with the Contractor's Certification, the COR will schedule a final inspection within ten (10) working days after receipt of the certification.

D. Should the COR disagree with the Contractor's certification that work is finally complete:

1. The COR will postpone inspection and will notify the Contractor in writing, stating the reasons.

2. The Contractor shall take immediate steps to remedy the stated deficiencies, and send second written notice to COR certifying that the Work is complete.

3. The COR will then schedule an inspection of the Work as above.

E. Should the COR consider that work is complete in accordance with requirements of the Contract Documents, he will request the Contractor to deliver the appropriate Project Closeout submittals and will prepare the Final Completion Certificate for execution by Contractor and COR.

1.05 REINSPECTION CORSTS

A. Should the COR be required to arrange for additional Government inspections because of failure of Work to comply with original certifications of the Contractor, the Government will deduct actual additional costs from final payment to the Contractor.

1. CLOSEOUT SUBMITTALS:

Training Center Engineer: Dubois & King, Inc. Section 01 70 00 - Page 3 of 3

IFC March 27, 2020

B. Guarantees and Bonds C. Evidence of Payments and Release of Liens

1. The Contractor shall submit:

2. a. Contractor's Affidavit of Payment of Debts and Claims.

3. b. Contractor's Affidavit indemnifying the Government harmless from all claims.

D. Final Periodic Estimate:

1. The Contractor shall submit final periodic estimate in accordance with requirements of General and Supplementary Conditions.

E. Meet other requirements of this section and by government agencies stated elsewhere within these Contract Documents.

1.06 FINAL CERTIFICATE OF PAYMENT

A. The COR will issue the final completion certificate.

1.07 POST-CONSTRUCTION INSPECTION

A. Prior to expiration of one year from Date of Substantial Completion, the COR will make visual inspection of Project in company of Contractor to determine whether correction of Work is required, in accordance with warranty requirements.

B. For warranties beyond one year, the COR will schedule inspections after notification to the Contractor.

C. The COR will promptly notify the Contractor, in writing, of any observed deficiencies, which shall be promptly corrected by the Contractor at his expense.

EV Charging Stations Basic Electrical National Conservation Materials and Methods Training Center Engineer: Dubois & King, Inc. Section 26 05 00 - Page 1 of 15

IFC March 27, 2020

SECTION 26 05 00

BASIC ELECTRICAL MATERIALS AND METHODS

PART 1 - GENERAL

1.01 WORK INCLUDED

A. Complying with the applicable provisions of the General Conditions, Supplementary Conditions, Special Conditions and other provisions of the Contract Documents that apply to the Work included in Division 26.

B. Install new electrical systems including but not limited to: EV charging stations, panelboards, cabinets, transformers, disconnect switches, concrete pads, power wiring, power distribution modification, electrical controls, branch circuit wiring, grounding, surge protection and related electrical systems.

C. Throughout construction Contractor shall provide upgraded schedules to accurately reflect time frame of work.

D. Complying with requirements of all codes and regulatory agencies. All equipment and materials furnished under the Electrical Sub-Contracts and labor performed herein shall be in complete accordance with the West Virginia State Building and Electrical Codes, the Town of Shepardstown, West Virginia and the National Fire Protection Association and regulations and requirements governing such work.

E. Shop Drawings: Electronic copies of the shop drawings shall be provided by the Contractor for review and comment by the Project Leader and Engineer, in addition to the normal A/E review as specified.

1.02 SUBMITTALS

A. Refer to procedures specified in Division 01. Submittal packages shall be provided in the formats listed in this section and on the drawings.

B. Apply Contractor's stamp on each copy of each submittal, signed or initialed certifying that the product is in accordance with the requirements of the Work and Contract Documents.

The stamp shall have the following wording: "I hereby certify that I have carefully examined the enclosed submittal(s) and have determined and verified all field measurements, construction criteria, materials, catalog numbers and similar data, coordinated the submittal(s) with other submissions and the work of other trades and contractors, and that to the best of my knowledge and belief, the enclosed submittal(s) is/are in full compliance with the Contract requirements, except as follows: (enter NONE if there are no exceptions)”.

C. Identify variations from Contract Documents and Product or system limitations which may be detrimental to successful performance of the completed work.

D. Items not clearly marked will be returned for corrections prior to the initial review. Clearly mark items for submission including part numbers, accessories, options, etc. Submittals

Training Center Engineer: Dubois & King, Inc. Section 26 05 00 - Page 2 of 15

IFC March 27, 2020 revised for resubmission shall clearly identify changes made since previous submission.

E. Engineer's acceptance of submittal(s) shall not relieve Contractor or responsibility for any deviation from the requirements of the Contract Documents unless Contractor has informed Engineer and COR in writing, of such deviation at the time of submission and Engineer has given written acceptance to the specific deviation, nor shall Engineer's acceptance relieve Contractor from responsibility for errors or omissions in the submittal.

F. Refer to other Division Sections for equipment and materials which require individual submittals.

Coordinate with, and provide direction for Firestopping requirements specific to Electrical, G. Submit submittals, shop drawings and product data by Specification Division or by Drawing Specified reference in single packaged submittals including complete submittals, related systems, products and all accessories.

The Contractor shall submit to the COR a Proposed Submittals List for review and acceptance. The Submittal phase shall not commence until this proposed list has be returned. The COR manage the overall Submittal process and reserves the right to request additional submittals at any point within the construction phase of the project.

Timely submissions are essential; do not submit loose submittals; they will be returned without review for proper package submission.

Note: Items not clearly marked will be returned for corrections prior to the initial review.

Scheduling: Contractor shall allow for no more than 90 days to develop the coordination drawings and an additional 30 days for Engineer review period.

H. Submit shop drawings and product data grouped to include complete submittals or related systems, products and accessories in a single submittal.

I. Provide catalog cuts and shop drawings for all equipment, trim, devices and materials.

Submittals shall be project specific indicating all specialties and accessories intended to be provided. Clearly indicate the precise items submitted. Contractor shall not install any equipment or material without accepted submittal. Equipment purchased without submittal approval will be done so at the financial risk of the contractor.

J. Provide installation instructions and operation and maintenance manuals for all equipment. Manuals will be submitted for review before Engineer performs punch list.

See paragraph 1.08.

K. Provide copies of all required permits to the COR.

L. Test Reports: Provide complete copies of electrical systems and communication systems test reports. Contractor shall provide a draft copy of report with discrepancies from contract requirements clearly noted before Engineer performs punch list.

M. Scheduling: The Engineer shall review all correctly submitted Packages within a 21-day time frame beginning on day of receipt. The Contractor shall include this period in its overall Project Schedule.

Items not clearly marked will be returned for corrections prior to the initial review.

Submitted packages not in compliance with Paragraph ‘G’ (above) shall be returned for

Training Center Engineer: Dubois & King, Inc. Section 26 05 00 - Page 3 of 15

IFC March 27, 2020 corrections; re-submittal begins the review period timeframe again.

N. Electrical Performance Testing. When testing and if necessary re-testing, has been completed, and no issues are remaining, provide written confirmation of testing and successful completion has been achieved, to the COR.

All testing shall be witnessed by the COR or its Agent. Backfilling or covering shall not be permitted until tests have been witnessed and signed off by the COR or its Agent.

1.03 SUBMITTALS AND PRODUCT SUBSTITUTIONS

A. Submit in accordance with Division 01, Product Requirements and 1.03 (above).

B. Equipment listed in the equipment schedules on the drawings is the basis of design.

C. Accepted manufacturers generally considered equals are listed in this specification.

Because equipment of different manufacturers varies in physical and performance characteristics, it shall be the Contractor's sole responsibility to ensure that products proposed as substitution for use meet the intent and constraints of the project.

Changes in system performance, equipment size, layout, installation, conduit and wiring connections (above and underground), or performance requirements including any impact to the mechanical systems, structural, and architectural will be engineered and confirmed in writing to the COR by the Contractor. All changes shall be fully coordinated with the other applicable trades. All costs for system re-engineering (in whole or in part), impacts to other trades, and schedules are the sole responsibility of the Contractor. Proposed substitutions and subsequent modifications are at no additional cost to the COR.

D. Equipment not listed specifically on the Drawings or in the Specifications shall be considered substitutes. Substitutions will be processed in accordance with Division 01.

Products submitted as substitutions after the award of bid will be rejected, unless specific written pre-approval from the COR is obtained. It shall be the Contractor's responsibility to ensure that substitute items meet the intent and constraints of the project.

The Contractor shall compensate the Architect/Engineer for time spent reviewing submittals of substitute materials and equipment. The compensation shall be based on the Architect’s/Engineer's published hourly rate schedule for Senior Architect and/or Electrical Engineer’s service.

1.04 WORK NOT INCLUDED

A. Work specifically indicated to be done by GOVERNMENT or others.

1.05 REFERENCE STANDARDS

A. National Electrical Manufacturers Association (NEMA).

B. Underwriters' Laboratories (UL).

C. American National Standards Institute (ANSI).

D. National Environmental Policy Act (NEPA).

E. ANSI/NFPA 70-National Electrical Code (NEC).

Training Center Engineer: Dubois & King, Inc. Section 26 05 00 - Page 4 of 15

IFC March 27, 2020

F. Institute of Electrical and Electronics Engineers (IEEE).

G. American with Disabilities Act (ADA)

H. American Society for Testing and Material (ASTM)

I. Insulated Cable Engineers Association (ICEA)

J. National Electrical Code (NEC)

K. National Fire Protection Association (NFPA)

L. International Building Code®

M. Local ordinances and regulations

N. The Standard Specifications which are referred to herein shall be the latest revisions of such Specifications.

1.06 QUALITY ASSURANCE

A. Codes and standards:

1. Comply with NEC requirements for electrical materials and installations.

2. Provide products and components which have been third party certified including UL or other approved listed and labeled products, including UL or other marks indicating special type usage wherever applicable.

3. In each case, codes are minimum requirements.

4. It shall be understood that all codes and standards mentioned shall be those in force at the time the Contract is signed. If any code is changed during the construction period, these specifications may be changed by mutual agreement.

5. Work shall be in accordance with regulations and rulings of all authorities having jurisdiction over the work. Any changes required to accomplish the intent of these specifications shall be the Contractor's responsibility as to accomplishment and any extra cost for performing work.

1.07 DEFINITIONS

A. Definitions used in this Section are not intended to change the meaning of other terms used in the Contract Documents, such as specialties, systems, structures, finishes, accessories, and similar terms. Such terms are self-explanatory and have well-recognized meanings in the construction industry.

6. Products are items purchased for incorporation in the Work, whether purchased for the Project or taken from previously furnished stock. The term product includes the terms material, equipment, system, and terms of similar intent.

Training Center Engineer: Dubois & King, Inc. Section 26 05 00 - Page 5 of 15

IFC March 27, 2020

a. Named Products are items identified by manufacturer’s product name, including make or model designation, indicated in the manufacturers published product literature, which is current as of the date of the Contract Documents.

7. Materials are products that are substantially shaped; cut, worked, mixed, finished, refined or otherwise fabricated, processed, or installed to form a part of the Work.

8. Equipment is a product with operational parts, whether motorized or manually operated, that requires service connections such as wiring or piping.

9. Installer: An “Installer” is the Contractor or another entity engaged by the Contractor, either as an employee, subcontractor, or contractor of lower tier, for performance of a particular construction activity, including installation, erection, application, and similar operations. Installers are required to be experienced in the operations they are engaged to perform.

10. The term “experienced,” when used with the term “Installer,” means having a minimum of five previous projects similar in size and scope to this Project, being familiar with the special requirements indicated, and having complied with requirements of the authority having jurisdiction.

11. Trades: Using terms such as “carpentry” is not intended to imply that certain construction activities must be performed by accredited or unionized individuals of a corresponding generic name, such as “carpenter.” It also does not imply that requirements specified apply exclusively to tradespersons of the corresponding generic name.

1.08 PRODUCT DELIVERY, STORAGE AND HANDLING

A. Protection: Use all means necessary to protect electrical system materials before, during and after installation and to protect the installed work and materials of all other trades.

B. Replacements: In the event of damage, immediately make all repairs and replacements necessary to the acceptance by the Government and at no additional cost. If any apparatus has been subject to possible injury by water, it shall be thoroughly dried out and put through such special tests as directed, at the cost and expense of the Contractor, or shall be replaced by the Contractor at his own expense.

C. Protect the work of other trades. Restore any damage caused to other trades to the condition existing prior to damage at no additional cost to the GOVERNMENT.

1.09 PROJECT CONDITIONS

A. Existing conditions:

1. Prior to all work of this Section, carefully inspect the site and verify that conditions are such that this installation may properly commence.

Training Center Engineer: Dubois & King, Inc. Section 26 05 00 - Page 6 of 15

IFC March 27, 2020

2. Verify that the electrical installation may be made in complete accordance with all pertinent codes and regulations and the original design.

3. In the event of discrepancy, immediately notify the Government’s COR.

4. Do not proceed with installation in areas of discrepancy until all such discrepancies have been fully resolved.

5. Coordinate the layout of the electrical panels, generators, transfer switches, control panels, etc. and related electrical conduits so that the installation is well planned with equipment; this to make certain that no removal or modifications of the proposed equipment, conduits and supporting devices shown on the documents will be required.

B. Coordination:

1. Coordinate the installation of electrical items with the schedules for work of other trades to prevent unnecessary delays in the total work.

2. Coordinate with all utility companies and make all installations or modifications for their services in accordance with all utility company requirements.

3. Any changes shall be done at the Contractor's expense.

4. Remove: The term “remove” means to take away, to extract, do away with and eliminate from the Project Site. All removed materials, hardware, equipment, devices, poles and related items shall be disposed of in an approved and legal manner.

5. Any work installed contrary to or without approval shall be subject to change as directed, and no extra compensation will be allowed the Contractor for making these changes.

C. Related Work.

1. Earthwork and concrete.

2. Trenching, excavation and backfill.

D. Accuracy of data:

1. The drawings are diagrammatic and functional only, and are not intended to show exact number of fittings, or other installation details. Furnish all labor and materials necessary to install conduit system ready for use by others. Furnish all labor and materials necessary to install and place in satisfactory operation all power, lighting, and other electrical systems shown. Install additional circuits wherever needed to conform to the specific requirements of the equipment.

2. The locations of equipment and similar devices shown on the Drawings are approximate only. Field measurements shall take precedence over scaled

Training Center Engineer: Dubois & King, Inc. Section 26 05 00 - Page 7 of 15

IFC March 27, 2020 dimensions from Drawings. Exact locations shall be as approved by the Engineer during construction. Obtain in the field all information relevant to the placing of electrical work and, in case of any interference with other work, proceed as directed by the Engineer and furnish all labor and materials necessary to complete the work in an approved manner. Verify sizes and ratings of motors and other electrically operated devices supplied by others.

3. Before installation of work for all items not clearly noted on the Contract Documents but required for a complete installation as to exact locations for work that interferes with other trades or existing conditions.

E. General:

1. Drawings and specifications are based on available information. Utility data, existing circuits, conduit layouts, duct bank locations, underground utilities, etc., are based on this information and may or may not reflect ultimate locations of systems. Contractor shall be responsible for verifying, prior to installation, that proposed locations for new systems are feasible. Contractor shall be responsible for all problems that are a result of not determining this feasibility, including but not limited to the installation of new electrical systems and their verification that proposed location(s) is feasible and as a result cannot be used.

2. Where work involving access to utility systems is required, such as modifications to existing service installations, the affected party shall be notified in a timely fashion by the Contractor and fully coordinated.

3. Where existing electrical power and alarm systems including lighting and conduit are in conflict with the proposed work, the Contractor shall request through the Engineer a clarification if the conflict cannot be resolved in the field.

4. Safety:

a. Contractor shall be responsible for initiating, maintaining and supervising all safety precautions and programs in connection with the work. Contractor shall take all necessary precautions for the safety of, and shall provide the necessary protection to prevent damage, injury or loss to:

1) All employees on the work and other persons who may be affected thereby.

2) All the work and all material or equipment to be incorporated there, whether in storage on or off the site.

3) Other property at the site or adjacent thereto, including trees, shrubs, lawns, walks, pavements, roadways, structures and utilities not designated for removal, relocation or replacement in the…