Attachment A-1 - Specifications - Scope of work for the Kitchen.pdf

PDF 245 KB Posted

Attached to
Kitchen and Bathrooms renovation for apartment B211 in a residence of the U. S Government located in Boulogne-Billancourt, France
Solicitation number
19FR6326Q0073
Issued by

About this file

This is a Scope of Work document for kitchen renovation services at the U.S. Embassy in Paris, France, specifically for apartment B211 in Building 1 at Boulogne.

The contractor must provide all labor, materials, tools, equipment, and supervision to complete the kitchen renovation within 13 weeks, starting 5 calendar days after contract award. Work hours are Monday through Friday, 9:00 AM to 12:00 PM and 1:00 PM to 5:00 PM, with closures during American and French holidays. The property will remain occupied during construction, requiring the contractor to minimize disturbances to occupants. All work must comply with French and European building regulations and the more stringent of either EM-385-1-1 safety requirements or local French occupational safety and health laws. The contractor must use only the service stairwell and clean it daily.

The scope includes removal and storage for reuse of existing cabinets, baseboards, countertops, and hood; disposal of existing floor covering, baseboards, and blue ceramic tiles; wall repairs; and installation of new flooring (Imola ceramic tiles, 60x60 model M2.0 060B with 2mm joints), ceramic baseboards, backsplash (Silestone, 62cm high), sink (Franke SNK8060), faucet (Howdens PA96712), kitchen cabinet doors (Elancon super mat Graphite), handles (copper poignee T), door stops, and thresholds. Additional work includes painting the ceiling, walls, and doors with acrylic white paint; reinstalling the hood; and final cleanup. The contractor must submit all detailed drawings and product data for Contracting Officer Representative approval before commencing work.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCOPE OF WORK

RENOVATION OF KITCHEN

BUILDING 1 AT BOULOGNE – B211

1 | P a g e 2

I – General

The US Embassy, Paris-France (USG) requires kitchen renovation at building 1, Boulogne.

Apartments B211. The works shall be done as per drawings, scope of work, specifications and general contract conditions. This project requires an experienced contractor to execute the works.

The Contractor shall provide all labor, material, tools, equipment, supervision and other related items required to complete the works as per scope of work, specifications and attached drawings. Contractors are advised to visit the site and verify the existing site conditions to develop their proposal.

Prior to any work, the Contractor shall submit for approval all detailed drawings and products data requested by the Contracting Officer Representative (COR).

For all kind of work, shall be provided a “Safety and health protection plan” or PP SPS – Plan particulier de sécurité et de protection de la santé -

The working hours shall be from 9:00 to 12:00 and from 13:00 to 17:00 Monday to Friday.

During American and French holidays the U.S. Government Property shall be closed. The U.S.

Government Property shall be occupied during the works and the contractor shall take all necessary measures to avoid disturbances and nuisances to occupants.

All work shall comply with all applicable French and European building regulations.

All work shall be performed in accordance with:

A. The safety requirements of the EM-385-1-1 http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/ EM_385-1-1.pdf;

B. Local French occupational safety and health requirement laws and regulations;

C. When there is a difference with the minimum requirements the more stringent requirement shall be followed.

The contractor shall use only service stairwell and shall clean after each day work the service stairwell

The contractor shall start the works 5 calendar days after contract awarded.

Starting date Duration : 13 weeks http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf

SCOPE OF WORK

RENOVATION OF KITCHEN

BUILDING 1 AT BOULOGNE – B211

2 | P a g e 2

II – Work

The Contractor shall:

- Install floor protection from

- Remove properly the cabinets, baseboards under kitchen cabinets, countertop and store for reuse

- Remove the existing floor covering /baseboards and dispose debris away from

Property

- Remove the hood, and store properly for reuse

- Remove the blue ceramic tiles on walls and dispose debris away from Property

- Repair the walls

- Furnish and install new floor covering after floor preparation, model M2.0 060B / micron 2.0, 60x60 from Imola or equal Note: the thickness of joint shall be 2mm and color selected by COR

- Furnish and install ceramic baseboards on walls not covered with kitchen cabinets, same model of floor ceramic tiles

- Reinstall kitchen cabinets, baseboard under cabinets and countertop

- Remove doors of kitchen cabinets and dispose debris away from Property

- Install floor protection

- Cut the existing countertop in order to install a new sink

Note : the thickness shall be polished

- Furnish and install a new backsplash model Silestone, 62cm high, marbre gris clair from Howdens or equal Note: the existing outlets shall be recessed in new backlash

- Furnish and install new sink, model Ref. SNK8060 (Franke) from Howdens or equal

- Furnish and install a new faucet Ref. PA96712, chrome from Howdens or equal

Note: the contractor shall furnish and install cut off valves under the sink

- Furnish and install new doors model Elancon super mat Graphite from Howdens or equal

- Furnish and install handles model poignee T, copper from Howdens or equal

- Furnish and install new baseboards under kitchen cabinets model Elancon super mat from Howdens or equal

- Furnish and install a panel with the same color as the kitchen cabinets doors, on the side of cabinet where is located the fridge

- Prepare and paint ceiling with acrylic white paint

- Prepare and paint walls with acrylic white washable paint

- Prepare and paint doors

Note: same color as existing

- Reinstall the hood

- Remove floor protection in kitchen/pantry/storage

- Furnish and install 3 door stops, black rubber and stainless steel

- Furnish and install two thresholds, chrome

- Cut base doors if needed

- Remove floor protection from entrance to kitchen

- clean