This Performance Work Statement (PWS) details a sediment characterization project for the US Army Engineer Research and Development Center (ERDC) at Kings Bay Entrance and Inner Channel along the Florida-Georgia border. The primary objective is to collect 15 in-harbor sediment samples, 1 in-harbor water sample, and 1 offshore sediment sample between November 1, 2024, and February 10, 2024. The contractor will be responsible for providing all labor, equipment, and expertise to conduct comprehensive sampling, including using GPS navigation, specialized sampling devices like vibracores and grab samplers, and following strict decontamination and sample handling protocols. Deliverables include a kick-off meeting, sampling and analysis plans, health and safety plans, daily quality control reports, draft and final logs, data reports, and proper sample preservation and delivery to ERDC Environmental Laboratory for analysis.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT 9
PERFORMANCE WORK STATEMENT (PWS)
SAMPLE CALL
Kings Bay Entrance & Inner Channel Sediment Characterization
Part 1
General Information
1. General: This is a non-personal service(s) contract under which the personnel rendering the service(s) are not subject, either by the contract’s terms or by the manner of its administration, to the supervision and control usually prevailing in relationships between the Government and its employees.
1.1 Description of Services/Introduction: This is a non-personal service(s) contract to collect samples in the Kings Bay
Entrance Channel along the Florida-Georgia border originating between Amelia Island, Florida, and Cumberland Island, Georgia in the Atlantic Ocean.
1.2 Background: The US Army Engineer Research and Development Center (ERDC) Environmental Laboratory (EL) is conducting sediment testing and evaluation to characterize materials native to the system. The samples shall be collected and subsequently characterized at ERDC EL. There is a need to contract tasks to complete this research.
1.3 Scope: The Contractor shall provide non-personal service(s) for R&D tasks that include collecting 15 in-harbor sediment collections; 1 in-harbor water collection; and 1 off-shore sediment collection. The samples will then be shipped to
ERDC EL.
1.4 Objectives: The objective of this contract is to collect samples in the Kings Bay Harbor.
1.5 General Information:
1.5.1 Quality Assurance: The Government will evaluate the Contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). This plan is primarily focused on what the Government must do to ensure that the Contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the acceptable quality levels (performance thresholds).
1.5.2 Recognized Holidays: The following provides information on recognized holidays for the purpose of the PWS. If submittal of any documentation (e.g. deliverables, submittals, etc.) deadlines fall on a holiday, the closest work day prior to the holiday will apply as the deadline for submittal.
1.5.2.1 U.S. Holidays: Work may be performed on U.S. federally recognized holidays occurring during the normal workweek unless otherwise directed by the Contracting Officer. When a U.S. holiday occurs on a Saturday or a Sunday, the holiday is observed on the preceding Friday or following Monday, respectively.
New Year’s Day January 1st M. L. King Memorial Day 3rd Monday in Jan
Presidents Day 3rd Monday in February Memorial Day last Monday in May
Juneteenth June 19th Independence Day July 4th
Labor Day 1st Monday in September Columbus Day 2nd Monday in October
Veteran’s Day November 11th Thanksgiving Day 4th Thursday in November
Christmas Day December 25th
1.5.3 Operating Hours: The Government facility office hours, facility operating hours, and the Contractor support hour requirements often coincide, however, they may differ. Please refer to the following.
1.5.3.1 Government Facility Office Hours: The Government facility office hours are 0700 – 1900 except U.S. Holidays identified in paragraph 1.5.2.1 above or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings.
1.5.3.2 Government Facility Operating Hours: The Government facility operating hours occur between the hours of 0700
– 1900. The Government facility may close due to local or national emergencies, administrative closings, or similar
Government directed facility closings and will be communicated by the Contracting Officer to the Contractor.
1.5.3.3 Contractor Support Hours: The Contractor shall provide support between the hours of 0800 – 1630. The facility my be closed during local or national emergencies, administrative closings, or similar Government directed facility closings.
The Contractor shall maintain an adequate workforce at all times, for the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce is essential.
1.5.4 Place of Performance: The work to be performed under this contract will be at the location specified in the Tasks to be completed.
1.6 Security Requirements: The following information is provided on security related matters.
1.6.1 General Security Requirements and Guidance:
The security requirements described below apply to all contract personnel (including employees of the prime Contractor
(“Contractor”) and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the designated Government representative (e.g., Contracting Officer Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA representative is not appointed)). Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall provide written documentation (e.g., email or memorandum) to the
Government representative. The documentation shall include the names of contract personnel trained and which training they completed; the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contract personnel shall comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as “RAMs”), and Health Protection Condition (HPCON) measures.
The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures --this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clause of this contract, should the FPCON or
HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.
1.6.2 Pre-Screen Candidates using E-Verify Program:
Contractors shall comply with the requirements set forth in FAR clause 52.222-54 Employment Eligibility Verification and
FAR Subpart 22.18 in using the E-Verify Program at (https://www.e-verify.gov/) (website subject to change) to meet the contract employment eligibility requirements. Contractors are encouraged to cooperate with Federal and State agencies responsible for enforcing labor requirements to include eligibility for employment under United States immigration laws in accordance with FAR 22.102-1(i). An initial list of verified/eligible candidates shall be provided to the COR no later than three business days after the initial contract award. When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, and submit it to the Contracting Officer to become part of the official contract file.
1.7 Post Award Conference/Periodic Progress Meetings: The Contractor shall attend any post award conference convened by the contracting activity or contract administration office in accordance with FAR Subpart 42.5. The Contracting
Officer, COR, and other Government personnel, as appropriate, may meet periodically with the Contractor to review the
Contractor's performance. At these meetings the Contracting Officer will apprise the Contractor of how the Government views the Contractor's performance and the Contractor shall apprise the Government of problems, if any, being experienced.
Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the
Government.
1.7.1 The Contractor shall attend, participate in, and furnish input to scheduled and unscheduled meetings, conferences, and briefings that relate to the functions and services herein as required by the Government to provide effective communication and impart necessary information. The Contract Manager or designated representative shall attend meetings as requested by the Government. Meeting attendees shall at times include Contractor managerial, supervisory, and other personnel knowledgeable of the subject matter. Meetings may start or end outside of regular duty hours.
1.8 Contracting Officer’s Representative (COR): As determined by the Contracting Officer, a COR will be appointed and identified by letter of designation, a copy of which will be provided to the Contractor by the Contracting Officer. The designation letter states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates, or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the resulting order. The COR monitors all technical aspects of the contract and assists in contract administration. The COR is not authorized to obligate the Government. If the work is not written in the contract, the COR is not authorized to request new work. The COR is authorized to perform the following functions: assure that the Contractor performs the technical requirements of the contract, perform inspections necessary in connection with contract performance, maintain written and oral communications with the Contractor concerning technical aspects of the contract, issue written interpretations of technical requirements, including Government drawings, designs, specifications, monitor Contractor's performance and notifies both the Contracting Officer and Contractor of any deficiencies, coordinate availability of Government property, and coordinate site entry of Contractor personnel.
1.9 Identification of Contractor Employees: All Contractor personnel attending meetings, answering Government telephones, and working in other situations where their Contractor status is not obvious to third parties must identify themselves, to include proper marking of signature blocks in correspondence, to avoid creating an impression in the minds of members of the public that they are Government officials. The Contractor shall ensure that all documents or reports, produced by Contractors are suitably marked as Contractor products or that Contractor participation is appropriately disclosed.
1.10 Contractor Travel: Contractor personnel may be required to travel withing the Continental United States (CONUS).
The contractor will be reimbursed for travel in accordance with FAR 31.205-46.[CN1]
1.11 Data Rights: Government has unlimited rights to all documents and materials produced under this contract. All documents and materials, to include the source codes of software, produced under this contract shall be Government owned and are the property of the Government with all rights and privileges of ownership and copyright belonging exclusively to the
Government. These documents and materials may not be used or sold by the Contractor without written permission from the
Contracting Officer. All materials supplied to the Government shall be the sole property of the Government and may not be used for any other purpose. This right does not abrogate any other Government rights.
1.12 Non-Disclosure Requirements: Performance under this contract may require the Contractor to access data and information proprietary to a Government agency, another Government Contractor, or of such nature that its dissemination or use other than as specified in this work statement would be adverse to the interests of the Government or others. The
Contractor and Contractor personnel, shall not divulge or release data or information developed, or obtained under performance of this PWS, except to authorized Government personnel or upon written approval of the Contracting Officer.
The Contractor shall not use, disclose, or reproduce proprietary data, which bears a restrictive legend, other than as specified in this PWS. All documentation showing individual names or other personal information shall be controlled and protected under the provisions of the Privacy Act of 1974, Public Law 93-579, 5 United States Code (U.S.C.) Section 552a.
1.13 Safety: The following provides information pertaining to Safety and Accident Prevention:
1.14 Safety Laws and Regulations: The Contractor shall comply with FAR 52.236-13, Accident Prevention (November
1991), the references contained therein (e.g. U.S. Army Corps of Engineers Safety and Health Requirements Manual (EM
385-1-1)).
In addition to other requirements for accident prevention specified in this contract, the Contractor shall comply with all
Federal and State requirements governing safety and health protection on construction sites and other applicable occupational safety codes.
PART 2
GOVERNMENT PROPERTY (GP) AND SERVICES
2. Government Property and Services
2.1 No Government furnished property will be provided.
2.2 Services: Contractor shall provide all labor and expertise required to complete research efforts.
2.3 Facilities: The vendor shall provide the boat and all equipment and materials required to complete the tasks.
PART 3
CONTRACTOR FURNISHED ITEMS AND SERVICES
4. Contractor Furnished Property and Services
4.1 General: The Contractor shall furnish the specified labor, equipment, instrumentation, and expertise necessary for the research effort.
4.2 Contractor Qualifications: The contractor must have extensive experience with in-shore and off-shore sampling techniques for the collection of water and sediment.
PART 4
SPECIFIC TASKS
3.1 Basic Services: The Contractor shall provide services for specific tasks associated with this contract.
As detailed below, for this effort the contractor shall conduct sample collection. All sample collection shall include chain-of-custody forms, field data sheets and/or sampling logs.
3.2 Tasks: Tasks consist of the following:
3.2.1 Sample Collection:
Sediment samples will be collected via either a grab sampling device or a vibracore for shoaling depths greater than three feet above the project depth. Grab sampling devices need to be able to obtain sample material from the maximum project depth.
The Contractor shall provide all materials and equipment needed to complete this work as described in the Southeast
Regional Implementation Manual SERIM and the Green Book. The Contractor shall complete this work in general accordance with requirements and guidelines in the SERIM USACE/EPA 2008 and the Green Book https://www.epa.gov/cwa-404/inland-testing-manual-under-cwa-section-404.
Navigation and Sample Site Location: Sub-meter Global Positioning System (GPS) systems will be utilized to mark the vessel position during sample collection. Signal from a beacon GPS antenna (e.g., Raven, Starlink, Trimble, Hemisphere, Lowrance) will be sent to an on-board computer and plotted on a monitor using Hypack navigation software.
Water Collection: Water samples will be collected with an ISCO field portable peristaltic pump. Teflon tubing will be used for the majority of the length for water sampling. A short section of acid cleaned, FDA approved, food grade, tygon tubing will be utilized with the peristaltic pump to allow for collection of water samples without potential contamination from an impeller driven water pump.
Sediment Collection: Bottom sediments will be collected with corers (e.g., Vibracore or Box core) or grab samplers (e.g., Vanveen, Clamshell). Bottom sediment type and surface water conditions at the time of sampling will determine which sampling device is most effective and safe to use. Multiple casts will be made with the selected sampler to collect the required volume of sediment from each sampling site.
All sediment collected will be described prior to being composited. At a minimum, one representative vibracore will be collected within each Dredged Material Management Unit (DMMU) for purposes of logging and material characterization.
The material from these vibracores will remain intact and in the core tube for transportation to the ERDC EL. Each core will be cut into five-foot sections and split longitudinally. Cores will then be logged while still moist. The core logdata will be used to create the gINT logs.
Redundant field instrumentation required for the above data collection will be on hand during field operations in the event of instrument malfunction.
a) Decontamination: All sampling equipment contacting sediment or water samples will be cleaned and decontaminated in accordance with procedures described in Methods for Collection, Storage and Manipulation of Sediments for Chemical and
Toxicological Analyses: Technical Manual (EPA 2001). Sampling devices, handling equipment, and vessel work area will be decontaminated after the entire substation is collected. If a substation is collected at different times the sampler, handling equipment, and vessel work area will be decontaminated between sampling events.
b) Pertinent Boring Information: Bottom sediments will be collected with coring devices (e.g., Vibracore or Box core) or grab samplers (e.g., Vanveen, Clamshell). Depth of sediment to be collected to represent the dredging prism and as indicated in the Sample Analysis Plan (SAP) will determine which sampling device is most effective and safe to use. Multiple casts will be made with the selected sampler to collect the required volume of sediment from each sampling site.
https://www.epa.gov/cwa-404/inland-testing-manual-under-cwa-section-404
Redundant field instrumentation required for the above data collection will be on hand during field operations in the event of instrument malfunction.
For estimating purposes, the Contractor may assume that a vibracore and surficial sample will both be collected at each of the
10 sample locations. Any vibracores and surficial samples not collected will be deducted at the end of the period of performance.
Vibracore depth collection must be determined during SAP development, using the most recent project bathymetry (to be provided), in order to represent the existing dredging prism. The SAP must contain a table of estimated cubic yards of material, including current depth and allowable overdredge depth material. Cores will be advanced below ground surface by using galvanized pipe and core sleeves/liners. Each vibracore must recover at least 80% of the subsurface material unless refusal is encountered. Penetration graphs should be generated and incorporated into the final Data Report.
Sample coordinates will be entered into a GPS receiver capable of less than 20-meter accuracy, as well as a back-up unit.
Sampling sites will be located onsite using the first unit and will be confirmed with the second unit. The depth at all stations will be recorded. At each site, water depth will be corrected to MLLW using a tide staff or the predicted tides from the
National Oceanic and Atmospheric Administration (NOAA). The most recent bathymetric surveys will be used as a reference in the field to confirm depths.
A licensed Professional Engineer (PE) or Professional Geologist (PG) is not required to be present on the vessel during vibracore collection operations. An engineer-in-training (EIT), geologist-in-training (GIT)), or Technician, experienced in and familiar with collection of vibracore and sediment samples according to the requirements of the SERIM and GreenBook, is sufficient to oversee the vibracore collection effort.
c) Composite Samples: Samples (3 sub-samples) belonging to each sampling zone or DMMU, shall be homogenized and tested as a single sample composite for analysis. Note, only material above the authorized dredge depth shall be included in the composite sample. The composited samples shall be stored in decontaminated 55-gallon drums with liners. Multiple casts will be made with the selected sampler to collect the required volume of sediment from each sampling site.
d) Sample Homogenization (Preparation of the Samples): Sample homogenization procedures should be clearly detailed in the SAP in accordance with guidance documents. Field collected sediments will be transported to the laboratory for further processing. Discrete sediment sub-samples will be thoroughly homogenized to consistent texture for a minimum of five minutes using an appropriately sized overhead power mixer with a SS blade (e.g., Lightnin mixer model ND-1A, Rochester, NY, or similar). This will be done either within the HDPE buckets they were delivered in or by transferring to stainless steel
(SS) pails.
e) Sample Compositing and Homogenization: The homogenized discrete sediments from each zone will be composited into high-density polyethylene (HDPE) drums to form the test material, or DMMU composite. To create each DMMU composite material, equal volumes of the individual discrete sediment collected within each zone will be combined and composited in a larger container and homogenized as described above. The approximate volumes from each site will be calculated by the contractor and provided within the SAP. Composited materials will be returned to a pre-cleaned HDPE container for cold storage.
Prior to the sampling trip, the volume of sediment needed will be re-calculated and enough sample volume will be collected to ensure sufficient volume for all analyses and archiving. Project specific field data sheets for each sub-sample location will be produced and on hand in the field. Field data sheets will include site conditions (e.g., prevailing weather, wind, air temperature), sample location (GPS coordinates), date, time, and field personnel. Once the sediment subsample is collected the sediment character (e.g., color, odor, texture, debris) will be noted in the field data sheet. The sample device(s) utilized, and the duration of deployment will be recorded. The number of containers and the date & time placed in refrigeration will also be recorded.
f) Sample Storage and Transport: Upon collection, samples will be placed in a refrigerated truck, trailer or kept in coolers on wet ice and brought down to and maintained at a temperature of approximately 4°C until delivered to the National
Environmental Laboratories Accreditation Conference (NELAC) certified laboratory for analysis. Daily temperature logs and loading schedule will be recorded in the Daily Quality Control Reports (DQCR).
g) Storage and Disposal of Samples: The contractor or toxicology and chemistry laboratories will retain all remaining unused sample volume (4 ± 1 ºC, dark) until the data generated from the samples goes through Quality Assurance/Quality
Control (QA/QC) and are approved as acceptable. Samples will be disposed of properly according to federal, state, and local laws.
h) Water Grab Sampling: Water samples will be collected consistent with the SERIM. All instruments should be calibrated by either the manufacturer suggested procedure or an approved standard operating procedure (SOP) in the SAP. Site water will be collected at Naval Station Mayport at a location determined by USACE.
Water samples will be collected with an ISCO field portable peristaltic pump one (1) meter from the sediment surface. A short section of acid cleaned, FDA approved, food grade, Tygon tubing will be utilized with the peristaltic pump to allow for collection of water samples without potential contamination from an impeller driven water pump. Teflon tubing will be used for the majority of the length for water sampling. The two sections of tubing will connect with a stainless-steel hose barb. When collecting the inshore site water sample, in-situ measurements for water temperature, pH, dissolved oxygen, salinity, and conductivity will be measured 1 meter from the sediment surface.
In-situ Water Conditions: In-situ measurements of temperature, salinity, conductivity, pH, dissolved oxygen (DO), and depth will be collected at each sampling location. Water quality probe(s) (e.g., Aqua TROLL 600, YSI 63, YSI 600XLM, YSI
600OMS, YSI 6820, Oxi 330 meter (WTW; Weilheim, Germany) for DO will be calibrated according to manufacturer specifications prior to use. The probe will be placed in the water column and lowered to a depth 1m above the bottom.
Salinity, temperature, conductivity, and pH will be measured in this manner. Water depth at each sampling station will be recorded with an Odom CV-100 or similar fathometer.
i) Repositioning Borings. The Government may reposition some borings based on future shoaling within the channel, as identified by surveys collected closer to the field effort. The number of sampling locations will not change.
In the event the Contractor is not able to access a boring location, or if a boring needs to be repositioned by more than 10 feet, the COR and Temporary Point of Compliance (TPOC) shall be immediately contacted to relocate any boring locations that cannot be accessed by the Contractor and the drilling vessel.
Task 1 Deliverable:
a) Kick-off Meeting
Within 10 days after the award, the Contractor shall lead a teleconference/Webex meeting with the COR and TPOC to informally discuss proposed methods of sampling. The purpose of this meeting is to ensure the Contractor’s plan is appropriate to maintain sample integrity prior testing. Meeting minutes shall be provided electronically to the COR and
TPOC within 3 days after the proposed meeting to document attendees, general discussion points, and resolution/outcome.
b) Draft Sampling and Analysis Plan/Draft Quality Assurance Project Plan (SAP/ Quality Assurance Project Plan
[QAPP])
The SAP/QAPP shall be submitted electronically to the TPOC and COR for review and comment. USACE will submit to
EPA for final approval.
c) Health and Safety Plan (HASP)
A site-specific HASP is required for this task order. The HASP shall be submitted electronically to the TPOC and COR for approval.
d) Final Sampling and Analysis Plan/draft Quality Assurance Project Plan (SAP/QAPP)
The Contractor shall update the SAP/QAPP accordingly based on comments. This document must be submitted electronically to EPA for final approval prior to sampling. USACE will submit to EPA for final approval.
e) Draft logs shall be electronically delivered, via email, to the COR and TPOC
Draft logs shall be electronically delivered within 21 days after boring completion. The Contractor may provide the draft logs in smaller batches for Government review, provided that all draft logs are received 21 days after boring completion. Boring logs, laboratory data reports, photographs, and vibracore penetration graphs shall be provided as electronic pdf files. The final gINT file containing all xyz, log, and laboratory data shall be submitted via a password protected zipped folder.
i) Daily Quality Control Reports (DQCR)
A DQCR will be prepared by the Field Team Leader or Project Manager for each day sampling is conducted. This report will contain a description of the work performed, samples collected, general conditions, corrective actions taken, departures from the sampling plans, and any other notes or comments needed that will document the day’s activities. This report will be an appendix to the Final Sediment Testing Report.
Copies of all field paperwork, including:
• Sediment collection data sheets for grabs and cores specifying the sample location, date and time of sample collection, sampling conditions, a brief sample description, and in-situ measurements
• Water quality field sheets
• Daily temperature logs
• Chain of custody forms
• Calibration logs
j) Data Report
A short data report summarizing the field activities and lab testing will be required for this assignment. The report shall include, at a minimum, the following: photographs and description of equipment used, general description of the materials encountered, boring location table and maps(s), summary tables of lab testing results, boring logs, grainsize analysis graphs, test result data sheets, penetration reports, and photographs of the vibracores. The report shall be submitted in electronic format (pdf).
k) Archiving of Samples
Prior to the sampling trip, the volume of sediment needed will be re-calculated; enough sample volume will be collected to ensure sufficient volume for all analyses and archiving. Set aside 0.5 (up to 2 gallons if bioassays are considered) of discrete sediment for potential discrete sample testing (using two 1-gallon clean HDPE or glass containers) for archiving. Sediment volumes collected from the field are based on laboratory calculated volume requirements to conduct all analyses (30 gallons composite sediment required), with additional volume (6 gallons composite sediment) to archive in the case additional analysis is required. To achieve this composite volume, approximately 9 to 12 gallons of sediment was collected from each location. This volume will be calculated and described within the SAP/QAPP.
l) Final Reports
Final reports will be provided as electronic files. Editable Microsoft Word documents will be provided during the review periods. The final report, including appendices, will be provided as an Adobe Acrobat PDF. Dissemination will be via
SharePoint, or via the Department of Defense Safe FTP Site (DoD Safe). In addition, raw data will be disseminated via
Microsoft Excel spreadsheets if requested.
m) Communication
a) At least one (1) status call/email shall be held between the Contractor, COR and TPOC prior to each mobilization in order to ensure a smooth execution and to address any issues.
b) Notify the COR and TPOC via call/email at least ten (10) calendar days prior to initiating fieldwork thus providing the
Corps of Engineers an opportunity to schedule a representative to be onsite during sample collection activities. Any boring relocations due to shoaling within the channel shall be identified at this time.
Performance Period
The samples shall be collected between 01 November 2024 to 10 February 2024 in order to allow additional shoaling prior to the next dredging event. The contractor shall coordinate with the COR and TPOC the availability of Government (i.e., USACE Geosystems Branch and Planning Division) Representatives at least ten (10) calendar days prior to performing this task. The draft site investigation report, the electronic copy of the gINT file of logs with surveyed data, photographs, and penetration reports of each sampling location shall be submitted to the COR and TPOC no later than the date shown in the tables below.
Travel (Please see comment above about travel and add in travel details.
PART 5
ATTACHMENT AND TECHNICAL EXHIBIT LISTING
6. Attachment and Technical Exhibit List
6.1 Technical Exhibit A – Performance Requirements Summary
TECHNICAL EXHIBIT A
Performance Requirements Summary (PRS)
PERFORMANCE
OBJECTIVE
STANDARD PERFORMANCE
THRESHOLD
ACCEPTABLE QUALITY
LEVELS (AQLs)
METHOD OF
SURVEILLANCE
Task 1 – Kings Bay
Entrance & Inner Channel
Sediment Characterization
The contractor shall collect samples
Deliverables:
kickoff meeting; draft sampling and analyses plan;
health & safety plan; final sampling & analyses plan;
draft logs; data reports; field sampling reports; daily quality control reports; daily status reports and/or teleconferences; final reports
& delivery of properly preserved samples to ERDC.
Deliverables include kickoff meeting; draft sampling and analyses plan; health & safety plan; final sampling & analyses plan; draft logs; data reports; field sampling reports; daily quality control reports;
daily status reports and/or teleconferences;
final reports & delivery of properly preserved samples to ERDC.
Delays should be reported as soon as possible. A delay of 5 days is acceptable.
Protocols, results and discussion shall pass peer review scrutiny.
Exceptional – 100%
Complete and correct
Very Good –
95% Complete and correct
Satisfactory –
90% Complete and correct
Marginal –
70% Complete and correct
Unsatisfactory –
50% Complete and correct