ATTACHMENT 9
PHASE-OUT TASKS/TIMELINE
Task Description Employee Group NLTD before Contract End
Train new Contractor on base pass paperwork PM/CM 72
Start Cross-flow with incoming Contractor PM/CM PM/CM 45
DFAC Orientation (PM/CM) PM/CM 45
Monthly Inventory of Reimbursable with inbound PM/CM 30
Equipment orientation Maintenance, Food Prep, Pots and Pans, Clipper 30
Recyclable Program Overview PM/CM 30
Housekeeping Services Overview PM/CM 29
Equipment MX Overview PM/CM 29
Fire Prevention Training PM/CM PM/CM 28
Sanitation Requirements PM/CM 28
Grounds Maintenance Overview PM/CM 27
Provide Update to KO/COR on timeline concerns/issues PM/CM 24
Food Handler training (Time/Date, Food Code, etc) Servers, PM/CM, Food Prep 21
Aloha POS cashier training Cashier 15 Proper serving techniques (proper temps, cross-panning trng, etc) Servers 15
DFAC Orientation (workers) All others 15
Table Bussing Cleaning team, PM/CM 15
Fire Prevention Training All others All others 15
Customer Eligibility Cashiers, PM/CM 15
Menu Board training Shift Leaders 15
Proper portion control Servers 14 Customer Service (Timeliness of service, courtesy of employees) Servers/Cashiers, PM/CM 14
Flight Kitchen Meal Prep expectations Servers 14
Manual cash register procedures Cashiers, PM/CM 14 Replenish Supplies/Clean facility, maintain safe/sanitary environment Cleaning team, PM/CM 10
Maintain interior/exterior expectations PM/CM 7 Repair request process PM/CM 7
Final Joint Inventory of GT Equipment PM/CM 3
Final Joint Inventory of Pac House Equipment PM/CM 2
Final Joint Inventory of Reimbursable (Changeover) PM/CM 1
Final Joint Inventory of Back of the Hangar Equipment PM/CM 1
PM/CM turn in all Contractor base passes PM/CM 0