Attachment 9 - MAHG231035 Repair Well 10_Generator Scope Details Rev.2.pdf

PDF 150 KB Posted

Attached to
Repair Well #10 Federal contract opportunity
Solicitation number
FA301025R0026
Issued by
Department of the Air Force Air Education and Training Command

About this file

This is a technical attachment document (Attachment 9) for federal contract FA301025R0026, specifically detailing generator scope requirements for the MAHG23-1035 Repair Well #10 project at Building 7301, dated May 2, 2025, Revision 2.

The contractor must provide and install a complete generator system including a 150 KW standby generator with 480 VAC WYE output at 60 hertz, an Automatic Transfer Switch (ATS) with NEMA 3R rating mounted outside Building 7301, and diesel tank components north of the generator. The work involves connecting the new generator to an existing 500-gallon diesel fuel tank, wiring the generator to the ATS and existing electrical systems, and performing mechanical/electrical demolition and installation per SOW drawings and specifications. Special requirements include extensive redundancy with dual components for critical systems: two fuel pumps with separate injection locations and fuel lines, oil sensors at separate locations, spark plugs at separate locations, fuel gauges and pressure indicators at separate locations, parallel fuel filters and valves, dual oil level sensors, engine block heaters, blowby stacks, voltage regulators that automatically switch between each other, air filters, anti-condensation heaters, vibration measurement sensors near bearings, and generator windings reporting from two separate locations. All sensors must report to two separate controllers, and the contractor must conduct a test run with manufacturer's representative as witness, maintain dust control throughout Building 7301, provide daily cleaning, and assume responsibility for any construction-related damage.

View the file

Other files for this federal contract opportunity

Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 9

FA301025R0026

MAHG23-1035 Repair Well #10 Generator Scope Details Rev. 2

MAHG 231035 Repair Well #10 Casing, Drop Pipe, Instrumentation and Controls

02 May 2025

1. SCOPE: Provide Generator & ATS for Bldg. 7301.

1.1. Notes:

1.1.1. Provide and maintain filters, temporary dust barriers, etc. to prevent construction dust and debris from spreading throughout Bldg. 7301, adjacent areas, Fire System Devices, and IT equipment, and other spaces.

1.1.2. Provide constant daily cleaning of the work area.

1.1.3. The contractor is responsible for the repair/replacement of items damaged during construction at their own cost.

1.2. CONTRACTOR TO REMOVE & INSTALL:

1.2.1. Bldg. 7301 surrounding area

1.2.1.1. Install ATS outside Bldg. 7301

1.2.1.2. Wire Generator to ATS and from existing electrical source, at Bldg 7301.

1.2.1.3. Wire ATS to existing electrical system.

1.2.1.4. Plumb Diesel Tank to generator.

1.2.1.5. Test run generator following manufacturer’s instructions, with manufacturer’s representative as a witness.

1.2.1.6. Mechanical / Electrical Demolition work shall be accomplished per drawings and specifications given in the SOW.

1.3. CONTRACTOR TO MODIFY EXISTING:

1.3.1. Mechanical / Electrical work to modify existing building components shall be accomplished per drawings and specifications as outlined within the SOW.

1.4. CONTRACTOR TO PROVIDE AND INSTALL NEW:

1.4.1. Building 7301

1.4.1.1. Generator

1.4.1.2. ATS, outside bldg. 7301.

1.4.1.3. Diesel tank components immediately north of the generator

1.4.1.4. Mechanical / Electrical Installation work shall be accomplished per drawings and specifications as outlined within the SOW.

2. SPECIAL GENERATOR CONSIDERATIONS:

2.1. 150 KW Standby; 480 VAC WYE output, 60 hertz. Plumb the existing 500-Gallon diesel fuel tank into the new generator.

2.2. Two of each of the following sub equipment: fuel pumps with different injection locations; each pump with its own fuel line; oil sensors at separate locations; spark plugs at separate locations; fuel gauges at separate locations; fuel pressure indication at separate but near equal locations; fuel filters at separate locations in parallel fuel lines;

fuel valves for all fuel lines in parallel; oil level sensors at separate locations; engine block heaters at separate locations; blowby stacks at separate locations; voltage regulators at separate locations automatically switched between each other as needed; air filters at separate locations; anti condensation heaters at separate locations; vibration

Attachment 9

FA301025R0026

MAHG23-1035 Repair Well #10 measurement near bearings at separate locations; diodes condition reporting; generator windings reporting from two separate locations including current, resistance, and voltage. sensors for all the above to report to two separate controllers.

2.3. Automatic Transfer Switch (ATS) 480 VAC WYE mounted outside; NEMA 3R; wired for power transfer