Attachment 9 - IA C713 Progress Report.pdf
PDF 125 KB Posted
- Attached to
- BIA Great Plain Region MATOC Federal contract opportunity
- Solicitation number
- 140A1621R0003
About this file
This document contains a progress report template for Indian Affairs contracts. The form requires contractors to provide the contract address, report number, period covered, project and contract numbers, and completion date. Contractors must indicate the percentage of total work and percentage completed for the current and cumulative periods for each work element. Space is included for remarks. The contractor and a reviewing contracting officer must sign and date certifying satisfactory completion according to contract specifications. A question is also included regarding submission of payrolls for the period.
The related federal contract opportunity is a solicitation for the Bureau of Indian Affairs Great Plain Region for an indefinite delivery/indefinite quantity multiple award task order contract for construction services. The solicitation number is provided. The agency is listed as the Department of the Interior Bureau of Indian Affairs Central Office.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 3 R1 - Past Performance Questionaire (PPQ)_0002.doc | DOC document | |
| Sol_140A1621R0003_Amd_0002.pdf | ||
| Sol_140A1621R0003_Amd_0001.pdf | ||
| Attachment 4 - Health and Safety Codes.pdf | ||
| Attachment 8 - IA C113 Progress Schedule.pdf | ||
| Attachment 3 - Past Performance Questionaire (PPQ).doc | DOC document | |
| Attachment 2 - Construction and Design Experience Project Data Sheet.docx | DOCX document | |
| Attachment 11 - Final Inspection and Certificate of Occupancy Guidelines.pdf | ||
| Attachment 10 - BIA Design Handbook.pdf | ||
| Attachment 6 - SF25 Performance Bond.pdf | ||
| Sol_140A1621R0003.pdf | ||
| Attachment 12 - Guiding Principles for Sustainable Federal Buildings.pdf | ||
| Attachment 1 - Statement of Work.pdf | ||
| Attachment 7 - SF25a Payment Bond.pdf | ||
| Attachment 5 - RFI Form.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Department of the Interior, Indian Affairs
CONTRACT PROGRESS REPORT
CONTRACTOR ADDRESS
REPORT NO. PERIOD COVERED
FROM: TO:
PROJECT NO. CONTRACT NO. COMPLETION DATE
LINE
NO.
WORK ELEMENT % OF
TOTAL
% COMPLETED
THIS PERIOD
% COMPLETED
CUMULATIVE
TOTAL
REMARKS
At the Contracting Officer's discretion and according to the payments clause of the contract, the information provided on this form may be used for computing progress payments.
PROGRESS OR COMPLETION CERTIFICATE
I hereby certify that the contractor has satisfactorily completed the indicated percentage of the contract per contract specifications.
SUBMITTED BY: _________________________
TYPE OR PRINT NAME AND TITLE SIGNATURE DATE
REVIEWED BY OR FOR CONTRACTING OFFICER
TYPE OR PRINT NAME AND TITLE SIGNATURE DATE
FORM IA-C713
Have payrolls been submitted for this time period? YES / NO