Attachment 9 - Contractors Daily Log of Construction.pdf

PDF 165 KB Posted

Attached to
Y1PZ--823-NSP25-003 National Shrine Project at Wood National Cemetery
Solicitation number
36C78626B0015
Issued by

About this file

This is a template for Attachment 9: Contractor's Daily Log of Construction/Inspector Quality Assurance Report (Q.A.R.), used to document daily construction activities on federal projects.

The form captures essential project information including contract number, project title, location, contractor details, and contracting officer identification. It requires daily documentation of weather conditions (temperature, precipitation, visibility, wind speed) and assessment of weather-related delays affecting 50% or more of the critical path. The form tracks workforce composition across multiple trades for contractors and subcontractors, including project managers, site managers, QC managers, field engineers, and miscellaneous laborers. Additional sections document equipment on site, materials delivered, project comments, deficiencies, potential causes for delay, and tests/observations conducted. The form is organized by construction divisions using standard CSI specifications: Division 1 (General Conditions) covering shop drawings and testing laboratory services; Division 2 (Existing Conditions) addressing site surveying; Division 31 (Earthwork); and Division 32 (Exterior Improvements) including flat marker support systems, headstone setting, and turf renovation. The form includes space for visitor information, weekly progress meeting notes, site manager signature, supervisor initials, and project photographs. Project completion percentage is tracked on each report, beginning at 00% for the initial submission.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT 9

CONTRACTOR’S DAILY LOG OF CONSTRUCTION

INSPECTOR QUALITY

ASSURANCE REPORT (Q.A.R.)

DAILY LOG OF CONSTRUCTION

REPORT NUMBER: 01

Project Completion at 00 %

DATE:

CONTRACT NUMBER:

Project Title:

Location:

Contractor:

Name:

Address:

Phone:

Contractor’s Site Manager:

Name:

Address:

Phone:

Contracting Officer:

COR:

Midwest District Project Managers:

WEATHER CONDITIONS:

Temperature:

Max: ° Min: °

Precipitation:

(24hour total)

Visibility:

Miles:

Wind Speed:

mph

WEATHER RELATED DELAYS:

(Affected 50% or more of critical path?)

YES OR NO

OFFICIAL WEATHER DELAY DATES:

WORK FORCE-CONTRACTORS & SUB-CONTRACTORS:

TRADE: # TRADE: # TRADE: #

Project Manager Site Manager QC manager PM assistant Field Admin- Misc. Laborers Field Engineer Construction Mgr.

VISITORS: COMPANY:

EQUIPMENT ON SITE:

1.

2.

3.

4.

5.

6.

MATERIALS DELIVERED TO JOB SITE:

PROJECT COMMENTS:

DEFICIENCIES:

POTENTIAL CAUSES FOR DELAY:

TESTS AND OBSERVATION:

WORK ACCOMPLISHED / PREP. MEETINGS CONDUCTED TODAY:

DIVISION 1: GENERAL CONDITIONS

01 33 23 - Shop Drawings, Product Data, and Samples

01 45 29 - Testing Laboratory Services

DIVISION 2: EXISTING CONDITIONS

02 21 00 – Site Surveying

DIVISION 31: EARTHWORK

31 00 00 - Earthwork

DIVISION 32: EXTERIOR

IMPROVEMENTS

32 39 20 - Flat Marker Support System, Headstone Setting, Alignment, Backfilling, and Headstone Cleaning

32 92 24 – Turf Renovation

WEEKLY PROGRESS MEETINGS:

Site Manager’s Signature: Date Supervisors Initials: Date

PHOTOS: