Attachment 9 - Asbestos Report - Bldg. 45.pdf
PDF 5 MB Posted
- Attached to
- Building 45 DPW Repair Renovation
- Solicitation number
- W911QY26RA025
About this file
This is a Final Asbestos Containing Material (ACM) Survey Report for Building 45 at the U.S. Army Soldier Systems Center in Natick, Massachusetts, completed in December 2020. CEI-PARS North Atlantic LLC conducted a limited survey and sampling program under Contract W912WJ-16-D-0006, Task Order W912WJ19F0199, prepared for the U.S. Army Corps of Engineers New England District. The survey reviewed prior asbestos assessments from 2012, identified data gaps, quantified remaining unidentified ACM through non-destructive means, updated material condition assessments, and developed cost estimates for removal of newly identified ACM. Survey activities took place in Spring 2020 with samples analyzed by ProScience Analytical Services using polarized light microscopy (PLM) for ACM analysis. The report identifies one newly discovered asbestos-containing material: red duct sealant (40 linear feet, in good condition) in room L112, containing 3% chrysotile asbestos. Additionally, four previously identified ACM items experienced condition deterioration from good condition to minor damage: basement/stairwell floor tile (100 SF), rooms L100A-D floor tile (4,600 SF), room L112 floor tile (2,300 SF), and room L116 floor tile (400 SF). The total estimated cost for abatement of all identified ACM is $357,874, including approximately $32,534 for contingency, encompassing both newly identified materials and remaining ACM from the 2012 survey. The report notes that destructive surveys should be performed prior to any renovations or demolition activities, as certain inaccessible materials were not sampled.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FINAL
ASBESTOS CONTAINING MATERIAL SURVEY REPORT
BUILDING 45
U.S. ARMY SOLDIER SYSTEMS CENTER
NATICK, MASSACHUSETTS
Prepared for:
US ARMY CORPS OF ENGINEERS
NEW ENGLAND DISTRICT
696 VIRGINIA ROAD
CONCORD, MA 01742
Contract No. – W912WJ-16-D-0006 Task Order No. – W912WJ19F0199
Project No. 803-6
Prepared by:
CEI-PARS North Atlantic, LLC 41 Main Street
Bolton, Massachusetts
December 2020
Natick Army Soldier Systems Center Asbestos Containing Material Survey December 2020 Building 45
Table of Contents
1.0 INTRODUCTION 1
2.0 BUILDING DESCRIPTION 2
3.0 SURVEY METHODOLOGY 3
3.1 Asbestos 3
3.2 Polychlorinated Biphenyls (PCBs) 4
3.3 Health and Safety 4
4.0 SUMMARY OF SAMPLING RESULTS 5
4.1 Asbestos 5
4.2 PCBs 5
4.3 Data Validation 5
5.0 FINDINGS 6
5.1 Asbestos 6
5.2 PCBs 7
6.0 ASBESTOS SURVEY CONCLUSIONS 8
7.0 LIMITATIONS 10
Acknowledgement
Figures Figure 1. Site Locus – Building 45
Tables Table 1. Summary of Building 45 Asbestos Sample Results Table 2. Summary of Newly Identified Asbestos – Building 45 Table 3. Summary of Previously Identified Asbestos with a Change in Condition – Building 45 Table 4. Building 45 ACM Abatement Cost Estimate
Appendices Appendix A. Asbestos Sample Locations Appendix B. Survey Photographs Appendix C. Asbestos Laboratory Analysis Reports Appendix D. Data Validation Reports Appendix E. Historic Asbestos Survey and Abatement Plans
December 2020 Building 45
1.0 INTRODUCTION
CEI-PARS North Atlantic LLC (CEI-PARS), under contract with the U.S. Army Corps of Engineers (USACE), New England District (CENAE), has completed a limited survey and sampling for suspect asbestos containing material (ACM) and polychlorinated biphenyl (PCB) in building materials for select buildings at the U.S. Army Soldier Systems Center in Natick, Massachusetts (NSSC). This report was completed in accordance with the Performance Work Statement (PWS) defined under Contract Number W912WJ-16-D-0006 and Task Order
W912WJ19F0199.
The scope of the survey report includes:
• Review of prior asbestos survey(s) prepared in 2012 and the subsequent ACM abatement actions completed by NSSC.
• Perform a physical ACM survey utilizing a Massachusetts Certified Asbestos Inspector to identify data gaps and quantify the remaining unidentified ACM (accessible through non-destructive means).
• Update the condition of both newly and previously identified ACM.
• Collect select PCB samples if an ACM sample has also been collected under the current contract.
• Update existing CAD drawings with new sampling data.
• Develop cost estimates for the removal of newly identified ACM, as applicable.
Building survey and sampling activities took place in the Spring 2020 by a Massachusetts Certified Asbestos Inspector. Collected suspect ACM and select PCB samples were sent to a certified analytical laboratory for analysis by polarized light microscopy (PLM) for ACM samples and EPA Method SW-846 3540C for PCB samples.
The following report outlines this survey and sampling methodology, results, estimated quantities and costs estimates.
December 2020 Building 45
2.0 BUILDING DESCRIPTION
The following building description is based on available information provided by the NSSC.
A Site Locus for Building 45 is included as Figure 1.
Building # Square Footage Floors Estimated Date of Construction Building Name
45 61,799 2 1970 Barnes Building
Minor renovations appear to have been completed in Building 45 since the 2012 survey. Floor tile and transite wallboards have been removed from room L111. The wall separating rooms L113 and L115 was removed to create a large filing room. Additionally, the parachute shop in the basement has been renovated which included the abatement of floor tiles.
December 2020 Building 45
3.0 SURVEY METHODOLOGY
3.1 Asbestos
The asbestos survey goal is to identify and sample suspect ACM not previously tested so that an accurate cost estimate for ACM abatement can be prepared. The following is an overview of the CEI-PARS asbestos survey activities.
Asbestos Survey & Sampling
CEI-PARS reviewed the prior asbestos survey report(s) completed in 2012 and any available asbestos abatement documentation provided by NSSC. All readily accessible areas of the building were visually inspected. Any inaccessible areas are noted in this report with limitations outlined in Section 6.0.
The survey consisted of the following methodology in each accessible space:
1. Abatement Activities – All ACM previously sampled during the 2012 survey was located if possible. Material no longer present was noted as an indication of ACM abatement. This information was cross-referenced with abatement records; however, lack of abatement records was not used as proof that the material had not been abated. It was noted prior to the start of the survey that not all abatement activities were recorded since the 2012 survey.
Ultimately, CEI-PARS relied on the presence or absence of the material based on the 2012 material description and current material condition to determine if abatement actions may have taken place. Abatement activities were noted and quantified if possible.
2. Material Condition – The condition of ACM identified in the 2012 survey was assessed as either in good condition, minor damage, or damaged. This is noted in Table 3 with present and historic conditions identified and highlighted if a change in condition was identified.
3. Sample Collection – Any additional suspect ACM identified during the CEI-PARS visual inspection was sampled for laboratory analysis. Readily accessible areas were inspected with asbestos sampling only taking place if the suspect material had not been previously sampled. Sampling activities did not include destructive sampling.
Samples were collected by a Massachusetts Licensed Asbestos Inspector using appropriate safety measures and hand tools, including a utility knife, pliers, screwdriver, and chisel, all utilized as needed. The sampling surface and surrounding area was wet prior to sample collected with an amended water solution as needed to eliminate airborne fibers. Sample containers were marked with a CEI-PARS sample ID. In most cases, sample IDs start with the NSSC Building # (see Figure 1) followed by a number beginning with 101 (so as not to be confused with the 2012 sample IDs). Subsequent letters indicate additional samples of the same material.
Data collected during asbestos sample collection included:
− material description
− location on plan
− material condition
− approximate extent of the material and quantity
− photographs
December 2020 Building 45
Since this survey is part of a broader NSSC asbestos survey that includes multiple buildings across the NSSC site, a limited number of samples were initially collected to ensure at least one sample was collected of each material type suspected to contain asbestos that had not already been previously sampled. Additional samples may have been collected later in the survey timeline based on available samples. This additional sampling was based on the quantity of suspect material with greater material quantities resulting in additional samples to help ensure homogeneity of material.
ACM samples were held under proper chain of custody until delivery to ProScience Analytical Services, Inc. (ProScience) in Woburn, MA.
A plan of all ACM sampling locations is included in Appendix A.
Asbestos Laboratory Analysis
The collected asbestos bulk samples were analyzed by ProScience using the Polarized Light Microscopy (PLM) analysis, EPA Method 600. ProScience is accredited by the American Industrial Hygiene Association (AIHA) and the Massachusetts Department of Labor Standards and participates in the National Voluntary Laboratory Accreditation Program (NVLAP Lab Code 200090-0). It should be noted that ProScience also analyzed the ACM samples collected during the 2012 survey.
3.2 Polychlorinated Biphenyls (PCBs)
Polychlorinated biphenyls (PCBs) building material samples were collected concurrent with the asbestos sampling to help determine material disposal options if/when ACM abatement takes place. Select PCB sampling was determined to be unnecessary in Building 45 based on the materials collected for ACM analysis. A comprehensive PCB survey was not conducted as part of this Task Order.
3.3 Health and Safety
CEI-PARS is committed to providing its employees with a safe and healthful workplace both in the office and on project sites. CEI-PARS developed a project specific Accident Prevention Plan (APP) dated January 2020. Approved by USACE, the APP was followed throughout the course of this project.
A group health and safety meeting took place with all project field staff prior to the start of the field effort. This training included review of the approved APP and specific training related to asbestos and PCB hazard awareness training. Additionally, a daily on-site health and safety briefing took place with all field staff prior to the start of field activities.
No health and safety issues were reported.
December 2020 Building 45
4.0 SUMMARY OF SAMPLING RESULTS
4.1 Asbestos
A summary of ACM laboratory results is included in Table 1 with samples testing positive for asbestos highlighted in bold both in the table and on the plan(s) located in Appendix A. The plans also include the location and results from the 2012 survey. Photographs of newly identified ACM are provided in Appendix B with laboratory analysis reports provided in Appendix C.
Table 1. Summary of Building 45 Asbestos Sample Results
Sample # Floor Sample Location Material Description Result 45-101A 1 116 12"x12" White w/ Tan Fleck Floor Tile NAD
45-102A 1 116 12"x12" White w/ Tan Fleck Floor Tile
Mastic
NAD
45-103A 1 L105 Black Sink Undercoating NAD 45-103B 1 L105 Black Sink Undercoating NAD 45-104A 1 Janitor's Closet Plaster Ceiling NAD 45-105A B E001 Door Assembly Caulking NAD 45-106A B E001 Residual Joint Compound NAD 45-107A 1 L105 Column Skim Coating NAD 45-107B 1 L105 Column Skim Coating NAD 45-108A 1 L107 4” Beige Cove Base NAD 45-108B 1 L107 4” Beige Cove Base NAD 45-109A 1 L107 4” Beige Cove Base Glue NAD 45-109B 1 L107 4” Beige Cove Base Glue NAD 45-110A 1 L112 Red Duct Sealant 3% CHR
NAD = No Asbestos Detected
4.2 PCBs
PCB sampling was not required for Building 45 based on the materials sampled for asbestos as part of this Task Order. A comprehensive PCB survey was not conducted.
4.3 Data Validation
Data validation was performed internally by CEI-PARS under Tier 1 data validation guidelines.
Appendix D includes relevant data validation reports. No data was qualified and all data is considered acceptable for use.
December 2020 Building 45
5.0 FINDINGS
5.1 Asbestos
A total of 127 representative bulk asbestos samples of 47 types of homogeneous materials were collected as part of the 2012 survey. Results and photographs from the 2012 survey report are provided in Appendix E.
CEI-PARS personnel identified and sampled 10 additional suspect ACM material types that were analyzed by ProScience. All asbestos sample results are provided in Table 1 with survey photographs provided in Appendix B.
A summary of newly identified ACM as part of the current survey along with location and material condition are presented in Table 2. Table 3 includes a summary of ACM identified during the 2012 survey where the condition of the material has changed based on 2020 observations.
Table 2. Summary of Newly Identified Asbestos – Building 45
Location/Room Material Description Estimated Quantity Condition Amount Units L112 Red Duct Sealant 40 LF Good
Appendix A includes updated floor plans with both the current and 2012 sample results. These plans have been updated to show the 2012 and CEI-PARS sample locations as well as the location of ACM remaining. Positive ACM sample locations are colored red with CEI-PARS positive samples in bold red; samples collected in 2012 that were not positive are colored blue while samples collected by CEI-PARS that were not positive are colored green.
ACM Abatement Notes
CEI-PARS confirmed material abatement noted in the 2012 ACM survey final report, unless otherwise stated. Additionally, positive ACM identified in 2012 was investigated for additional abatement that may have occurred after the investigation. During the 2012 survey, hard fitting insulation throughout the building was sampled, all of which came back negative. CEI-PARS believes the fittings are all on one interconnected system and, therefore all fittings are assumed to be negative.
Table 3. Summary of Previously Identified Asbestos with a Change in Condition – Building 45
Location/Room Material Description Estimate Quantity Condition Amount Units 2012 2020
Basement/Stairwell 9”x9” Beige Floor Tile and
Mastic 100 SF Good
Minor Damage
L100A, B, C, D 9”x9” Beige Floor Tile and
Mastic 4,600 SF Good
Minor Damage
L112 12”x12” Brown Fleck Floor Tile 2,300 SF Good Minor
Damage
L116 9”x9” Beige Floor Tile and
Mastic 400 SF Good
Minor Damage
December 2020 Building 45
Most 12”x12” White with Yellow Fleck floor tiles were abated in the basement of Building 45 with the exception of the Conference Room in which carpeting was placed directly on top of the ACM floor tiles. Transite wallboard and 9”x9” Beige floor tiles have been abated from rooms L111 and L111B since the 2012 survey. Additionally, ductwork in room L115 was replaced and the previous HVAC Vibration Cloth was abated.
5.2 PCBs
No PCB samples were collected for Building 45 based on the materials collected for ACM sampling as part of this Task Order. A comprehensive PCB survey was not performed.
December 2020 Building 45
6.0 ASBESTOS SURVEY CONCLUSIONS
Site survey work was performed by a Massachusetts Licensed Asbestos Inspectors who collected suspect ACM samples that were submitted to an accredited laboratory for asbestos analysis by PLM. As applied to demolition and renovations operations, there are two main categories of regulated asbestos-containing material, friable and non-friable. Friable is a NESHAP term defined in 40 CFR 61, Subpart M and EPA 340/1-90/018 meaning any material containing more than one percent asbestos that, when dry, can be crumbled, pulverized or reduced to powder by hand pressure. Whereas, non-friable means any material containing more than one percent asbestos that, when dry, cannot be crumbled, pulverized, or reduced to powder by hand pressure. The classification of friable and nonfriable material can impact disposal options within Massachusetts where Asbestos Containing Waste Material (ACWM) as defined by the Air Pollution Control Regulations (310 CMR 7.15):
Asbestos Containing Waste Material (ACWM) means any ACM removed during a demolition or renovation project and anything contaminated with asbestos in the course of a demolition or renovation project including, but not limited to, asbestos waste from control devices, bags or containers that previously contained asbestos, contaminated clothing, materials used to enclose the work area during the demolition or renovation operation, and demolition or renovation debris.
Table 4 includes a summary of ACM estimated quantities and cost estimates for both the 2020 survey and 2012 survey. Estimated quantities for previously identified ACM are based on the 2012 survey and take into consideration any identified abatement that has taken place. Some window glazing was previously identified to contain asbestos, however, replacement windows were not positive for asbestos during the 2012 survey. Based on the apparent age of the various windows throughout the building, CEI-PARS estimated the number of windows which are likely to contain asbestos at the time of the 2020 survey.
The quantity costs do not include inaccessible areas and are based on current industry rates intended to be inclusive of all abatement contractor costs. They do not include costs for relocating building occupants, reinstallation of materials, design, monitoring, sampling, or other consultant fees.
December 2020 Building 45
1These estimates do not include abatement for asbestos in inaccessible areas.
2 Includes abatement of entire window.
Note that the EPA, Occupational Safety and Health Administration (OSHA), and the Commonwealth of Massachusetts Division of Occupational Safety (DOS) defines any material that contains greater than one percent (1%) asbestos as being an ACM. The Massachusetts Department of Environmental Protection (MassDEP) defines any material that contains equal to or greater than one percent (≥1%) asbestos as being ACM. Per MassDEP, CEI-PARS identified any material ≥1% asbestos as being ACM.
Prior to initiating plans for maintenance, renovation or demolition activities, survey results should be reviewed to determine whether any of the materials identified as ACM will be disturbed by proposed work activities. Any suspect material encountered during renovation/demolition that is not identified in this report as being non-ACM should be assumed to be ACM unless laboratory analytical data for bulk samples prove otherwise. Suspect ACM that was not accessible or required destructive testing to collect a sample and that accordingly was not inspected, should be assumed to contain asbestos if discovered until otherwise verified, as previously described. If ACM is disturbed, the ACM must be removed by a Massachusetts Licensed Asbestos Abatement Contractor and be performed in accordance with applicable regulations. If proposed work activities will not disturb intact ACM, continuous monitoring of ACM should be conducted throughout work activities to ensure the ACM remains in an intact condition. Additionally, prior to commencing work activities, personnel involved with the work activities should be made aware of the location of ACM within the building in which they will be working.
Table 4. Building 45 ACM Abatement Cost Estimate
Material Description Friable or Nonfriable
Estimated Quantity Abatement Cost
Estimate Per Unit1
Total Cost Estimate Total
Amount Units
2020 SURVEY
Red Duct Sealant Nonfriable 40 LF $20 $800
2012 SURVEY
ACM Flooring Nonfriable 10,730 SF $8 $85,840 Transite Wallboard (PACM) Nonfriable 8,620 SF $25 $215,500 HVAC Vibration Cloth (PACM) Nonfriable 240 SF $20 $4,800 Large and Small Tank Insulation Friable 350 SF $25 $8,750 Heat Exchanger and Fitting Insulation Friable 50 SF $20 $1,000 Steam Condensate Fitting Insulation Friable 10 EA $20 $200 Pre-Molded Pipe Insulation Friable 10 LF $20 $200 Window Glazing Nonfriable 30 Window2 $275 $8,250
(~10% Contingency) $32,534 Total $357,874
December 2020 Building 45
7.0 LIMITATIONS
CEI-PARS completed a comprehensive and thorough ACM survey but does not claim to have identified all of the ACM that could be present since only areas that were accessible during the investigation were inspected and no destructive sampling took place. Inaccessible areas include but are not limited to materials hidden by: floor, wall, ceiling finishes or materials in tunnels, shafts, vaults, pipe, or flue chases. Prior to any renovations, maintenance, or demolition, destructive ACM surveys should be performed.
Suspect ACM that was identified by CEI-PARS, but would require destructive sampling, include (but is not limited to):
• Green decorative floor tiles in entrance
• Toe kicks throughout building
• Hidden caulking behind exterior doors and windows
• Pump casings and gaskets in mechanical rooms
• Insulation in wooden and metal fire doors
• Bathroom mirror glue
• Interior expansion joint
• Ceramic tiles around water fountain
• Duct pin tabs
The project has been completed within generally accepted industry standards and with reasonable care. This survey was performed with limitation inherent to visual inspection. There are no assurances this may not change in the future and consequently affect the results of this report.
PCB samples were not collected from Building 45 based on this Task Order.
ACKNOWLEDGMENT
This Asbestos Containing Materials (ACM) Survey Report was prepared for the Department of the Army New England District Corps of Engineers and the U.S. Army Soldier Systems Center, Natick, Massachusetts, in accordance with an established scope of work as defined in Contract Number W912WJ- 16-D-0006, Task Order Number W912WJ19F0199. This information presented herein is based on the facts and information conveyed to or received by CEI-PARS North Atlantic LLC (CEI-PARS) during the preparation of this report. Physical inspection was limited and generally did not include destructive sampling techniques. Activities, including but not limited to demolition and renovation, that result in the discovery of suspect ACM and/or PCB materials, should stop immediately. The affected area should be isolated and the material tested.
If any of the information provided to CEI-PARS that was used in preparing this report is incorrect, incomplete, or subject to change, CEI-PARS would wish to alter its opinion(s) accordingly. In addition, the professional opinions and information contained in the report are based solely on the requirements of the applicable regulations and technical data as known to CEI-PARS as of the date of inspection and considered applicable to this report.
This report was prepared, reviewed, and approved by the following CEI-PARS team members:
Edwin Morgan Asbestos Materials Specialist Massachusetts Asbestos Inspector Al51838 Massachusetts Asbestos Management Planner AP51839 Massachusetts Asbestos Project Monitor AM51114 Massachusetts Asbestos Project Designer AD00008
Richard Cote, P.E., LSP Project Manager
Lake Cochituate
N
S
EW
Figure 1 Site Locus Building 45
Natick Soldier Systems Center Asbestos Survey - 2020
U.S. Army Corps of Engineers New England District
Contract No. W912WJ-16-D-0006
AutoCAD SHX Text
BUILDING 45
Appendix A
Asbestos Sample Locations
Appendix B
Survey Photographs
Photographs
Red Duct Sealant Sample 45-110A
Appendix C
Asbestos Laboratory Analysis Reports
Appendix D
Data Validation Reports
CEI-PARS NORTH ATLANTIC LLC
A COMPREHENSIVE ENVIRONMENTAL INC. AND PARS ENVIRONMENTAL INC. JOINT-VENTURE
March 17 2020 PROJECT: Natick Soldier Systems Center Asbestos Survey
CEI-PARS PROJECT: #803-6
CEI-PARS PROJECT MANAGER: Stephanie Hanson CEI-PARS DATA VALIDATOR: Sara Nelson
SDG: B120580
ANALYSIS METHODS: Asbestos - PLM LABORATORY: ProScience Analytical Services, Inc. 22 Cummings Park, Woburn, MA 01801
This data validation was performed under Tier 1 validation guidelines. The analyses were validated using the following documents and variances, as applicable to each method.
• U.S. Department of Defense General Data Validation Guidelines, Environmental Data Quality Workgroup, February 9, 2018.
• USEPA, National Functional Guidelines for Inorganic Superfund Methods Data Review, January 2017
Bolton, MA 01740
508.281.5160
3/17/2020
SDG#B120580
CEI-PARS NORTH ATLANTIC LLC
A COMPREHENSIVE ENVIRONMENTAL INC. AND PARS ENVIRONMENTAL INC. JOINT-VENTURE
DATA VALIDATION REPORT
Project/Site Name: Natick Soldier Systems Center – Building 45 CEI-PARS Report Date: March 17, 2020 Parameters: Asbestos (EPA/600/R-93/116) Validation Level: Tier 1 Laboratory: ProScience Analytical Services, Inc.
Sample Delivery Group (SDG): B120580
PROJECT SAMPLE
IDENTIFICATION
LABORATORY SAMPLE
IDENTIFICATION MATRIX COLLECTION
DATE
45-101A 45-101A Solid 2/26/2020 45-102A 45-102A Solid 2/26/2020 45-103A 45-103A Solid 2/26/2020 45-104A 45-104A Solid 2/26/2020
SDG#B120580
CEI-PARS NORTH ATLANTIC LLC
A COMPREHENSIVE ENVIRONMENTAL INC. AND PARS ENVIRONMENTAL INC. JOINT-VENTURE
INTRODUCTION
This Data Validation Report (DVR) presents data validation findings and results for the associated samples listed on the cover page. Data validation was performed in accordance with the U.S. Department of Defense General Data Validation Guidelines, Environmental Data Quality Workgroup, February 9, 2018 and a modified outline of the USEPA National Functional Guidelines for Inorganic Superfund Methods Data Review (January 2017). Where specific guidance was not available, the data has been evaluated in a conservative manner consistent with industry standards using professional experience.
The analyses were performed using the following methods:
Asbestos by EPA 600/R-93/116
All sample results were subjected to Tier 1 data validation, which comprises an evaluation of quality control (QC) summary results.
SDG#B120580
CEI-PARS NORTH ATLANTIC LLC
A COMPREHENSIVE ENVIRONMENTAL INC. AND PARS ENVIRONMENTAL INC. JOINT-VENTURE
The following are definitions of the data qualifiers utilized during data validation:
J (Estimated): The compound or analyte was analyzed for and positively identified by the laboratory;
however the reported concentration is estimated due to nonconformances discovered during data validation.
U (Non-detected): The compound or analyte was analyzed for and positively identified by the laboratory;
however, the compound or analyte should be considered non-detected at the reported concentration due to the presence of contaminants detected in the associated blank(s).
UJ (Non-detected estimated): The compound or analyte was reported as not detected by the laboratory;
however the reported quantitation/detection limit is estimated due to non-conformances discovered during data validation.
R (Rejected): The sample results were rejected due to gross non-conformances discovered during data validation. Data qualified as rejected is not usable.
NA (Not Applicable): The non-conformance discovered during data validation demonstrates a high bias, while the affected compound or analyte in the associated sample(s) was reported as not detected by the laboratory and did not warrant the qualification of the data.
A qualification summary table is provided at the end of this report if data has been qualified. Flags are classified as P (protocol) or A (advisory) to indicate whether the flag is due to a laboratory deviation from a specified protocol or is of technical advisory nature.
SDG#B120580
CEI-PARS NORTH ATLANTIC LLC
A COMPREHENSIVE ENVIRONMENTAL INC. AND PARS ENVIRONMENTAL INC. JOINT-VENTURE
I. Sample Receipt and Technical Holding Times
All samples were received in good condition.
All technical holding time requirements were met.
II. Initial Calibration
Initial calibration data were not reviewed for Tier 1 validation.
Ill. Continuing Calibration
Continuing calibration data were not reviewed for Tier 1 validation.
IV. Laboratory Blanks
Laboratory blanks were not required by the methods.
V. Field Blanks
No field blanks were identified in this SDG.
VI. Matrix Spike/Matrix Spike Duplicates
Matrix spike (MS) and matrix spike duplicates (MSD) analyses were not required by the methods.
VII. Duplicate Sample Analysis
Duplicate (DUP) sample analysis was not required by the methods.
VIII. Laboratory Control Samples
Laboratory control samples (LCS) and laboratory control samples duplicates (LCSD) were not required by the methods.
IX. Field Duplicates
No field duplicates were identified in this SDG.
X. Sample Result Verification
Raw data were not reviewed for Tier 1 validation.
XI. Overall Assessment of Data
The analysis was conducted within all specifications of the methods. No results were rejected in this SDG.
The quality control criteria reviewed were met and are considered acceptable. Based upon the data validation all results are considered valid and usable for all purposes.
SDG#B120580
CEI-PARS NORTH ATLANTIC LLC
A COMPREHENSIVE ENVIRONMENTAL INC. AND PARS ENVIRONMENTAL INC. JOINT-VENTURE
DATA QUALIFICATION SUMMARY
Project: Natick Soldier Systems Center
SDG: B120580
Sample Analysis: Asbestos – PLM
NO SAMPLE QUALIFIED IN THIS SDG
SDG#B120580
CEI-PARS NORTH ATLANTIC LLC
A COMPREHENSIVE ENVIRONMENTAL INC. AND PARS ENVIRONMENTAL INC. JOINT-VENTURE
VALIDATION COMPLETENESS WORKSHEET
Project/Site Name: Natick Soldier Systems Center – Building 45 CEI Report Date: March 17, 2020 Parameters: Asbestos (EPA/600/R-93/116) Validation Level: Tier 1 Laboratory: ProScience Analytical Services, Inc Sample Delivery Group (SDG): B120580
The samples listed in the validation report were reviewed for each of the following validation areas.
VALIDATION AREA NOTE COMMENTS
I. Sample receipt/Technical holding times A/A
II. Initial calibration N
III. Calibration verification N
IV. Laboratory blanks N Not required
V. Field blanks N
VI. Matrix spike/Matrix spike duplicate N Not required
VII. Duplicate sample analysis N Not required
VIII. Laboratory control samples N Not required
IX. Field duplicates N
X. Sample result verification N
XI. Overall assessment of data A
Note: A = Acceptable ND = No compounds detected D = Duplicate
N = Not provided/applicable R = Rinsate TB = Trip blank SW = See worksheet
TB = Trip blank FB = Field blank SB = Source blank EB = Equipment blank
Other:
March 17, 2020
CEI-PARS PROJECT: #803-6
CEI-PARS PROJECT MANAGER: Stephanie Hanson CEI-PARS DATA VALIDATOR: Sara Nelson
SDG: B120717
ANALYSIS METHODS: Asbestos - PLM
SDG#B120717
CEI-PARS NORTH ATLANTIC LLC
A COMPREHENSIVE ENVIRONMENTAL INC. AND PARS ENVIRONMENTAL INC. JOINT-VENTURE
DATA VALIDATION REPORT
Project/Site Name: Natick Soldier Systems Center – Building 45 CEI-PARS Report Date: March 17, 2020 Parameters: Asbestos (EPA/600/R-93/116) Validation Level: Tier 1
Sample Delivery Group (SDG): B120717
LABORATORY SAMPLE
IDENTIFICATION MATRIX COLLECTION
DATE
45-105A 45-105A Solid 3/4/2020 45-106A 45-106A Solid 3/4/2020
SDG#B120717
CEI-PARS NORTH ATLANTIC LLC
A COMPREHENSIVE ENVIRONMENTAL INC. AND PARS ENVIRONMENTAL INC. JOINT-VENTURE
INTRODUCTION
This Data Validation Report (DVR) presents data validation findings and results for the associated samples listed on the cover page. Data validation was performed in accordance with the U.S. Department of Defense General Data Validation Guidelines, Environmental Data Quality Workgroup, February 9, 2018 and a modified outline of the USEPA National Functional Guidelines for Inorganic Superfund Methods Data Review (January 2017). Where specific guidance was not available, the data has been evaluated in a conservative manner consistent with industry standards using professional experience.
The analyses were performed using the following methods:
Asbestos by EPA 600/R-93/116
All sample results were subjected to Tier 1 data validation, which comprises an evaluation of quality
SDG#B120717
CEI-PARS NORTH ATLANTIC LLC
A COMPREHENSIVE ENVIRONMENTAL INC. AND PARS ENVIRONMENTAL INC. JOINT-VENTURE
The following are definitions of the data qualifiers utilized during data validation:
J (Estimated): The compound or analyte was analyzed for and positively identified by the laboratory;
however the reported concentration is estimated due to nonconformances discovered during data validation.
U (Non-detected): The compound or analyte was analyzed for and positively identified by the laboratory;
however, the compound or analyte should be considered non-detected at the reported concentration due to the presence of contaminants detected in the associated blank(s).
UJ (Non-detected estimated): The compound or analyte was reported as not detected by the laboratory;
however the reported quantitation/detection limit is estimated due to non-conformances discovered during data validation.
R (Rejected): The sample results were rejected due to gross non-conformances discovered during data validation. Data qualified as rejected is not usable.
NA (Not Applicable): The non-conformance discovered during data validation demonstrates a high bias, while the affected compound or analyte in the associated sample(s) was reported as not detected by the laboratory and did not warrant the qualification of the data.
A qualification summary table is provided at the end of this report if data has been qualified. Flags are classified as P (protocol) or A (advisory) to indicate whether the flag is due to a laboratory deviation from
SDG#B120717
CEI-PARS NORTH ATLANTIC LLC
A COMPREHENSIVE ENVIRONMENTAL INC. AND PARS ENVIRONMENTAL INC. JOINT-VENTURE
I. Sample Receipt and Technical Holding Times
All samples were received in good condition.
All technical holding time requirements were met.
II. Initial Calibration
Initial calibration data were not reviewed for Tier 1 validation.
Ill. Continuing Calibration
Continuing calibration data were not reviewed for Tier 1 validation.
IV. Laboratory Blanks
Laboratory blanks were not required by the methods.
V. Field Blanks
No field blanks were identified in this SDG.
VI. Matrix Spike/Matrix Spike Duplicates
Matrix spike (MS) and matrix spike duplicates (MSD) analyses were not required by the methods.
VII. Duplicate Sample Analysis
Duplicate (DUP) sample analysis was not required by the methods.
VIII. Laboratory Control Samples
Laboratory control samples (LCS) and laboratory control samples duplicates (LCSD) were not required by the methods.
IX. Field Duplicates
No field duplicates were identified in this SDG.
X. Sample Result Verification
Raw data were not reviewed for Tier 1 validation.
XI. Overall Assessment of Data
The analysis was conducted within all specifications of the methods. No results were rejected in this SDG.
SDG#B120717
CEI-PARS NORTH ATLANTIC LLC
A COMPREHENSIVE ENVIRONMENTAL INC. AND PARS ENVIRONMENTAL INC. JOINT-VENTURE
DATA QUALIFICATION SUMMARY
Project: Natick Soldier Systems Center
SDG: B120717
SDG#B120717
CEI-PARS NORTH ATLANTIC LLC
A COMPREHENSIVE ENVIRONMENTAL INC. AND PARS ENVIRONMENTAL INC. JOINT-VENTURE
VALIDATION COMPLETENESS WORKSHEET
Project/Site Name: Natick Soldier Systems Center – Building 45 CEI Report Date: March 17, 2020 Parameters: Asbestos (EPA/600/R-93/116) Validation Level: Tier 1
Sample Delivery Group (SDG): B120717
The samples listed in the validation report were reviewed for each of the following validation areas.
II. Initial calibration N
III. Calibration verification N
IV. Laboratory blanks N Not required
V. Field blanks N
VI. Matrix spike/Matrix spike duplicate N Not required
VII. Duplicate sample analysis N Not required
VIII. Laboratory control samples N Not required
IX. Field duplicates N
X. Sample result verification N
XI. Overall assessment of data A
Note: A = Acceptable ND = No compounds detected D = Duplicate
N = Not provided/applicable R = Rinsate TB = Trip blank SW = See worksheet
March 30, 2020
CEI-PARS PROJECT: #803-6
CEI-PARS PROJECT MANAGER: Stephanie Hanson CEI-PARS DATA VALIDATOR: Sara Nelson
SDG: B120902
ANALYSIS METHODS: Asbestos - PLM
3/30/2020
SDG#B120902
CEI-PARS NORTH ATLANTIC LLC
A COMPREHENSIVE ENVIRONMENTAL INC. AND PARS ENVIRONMENTAL INC. JOINT-VENTURE
DATA VALIDATION REPORT
Project/Site Name: Natick Soldier Systems Center – Building 45 CEI-PARS Report Date: March 30, 2020 Parameters: Asbestos (EPA/600/R-93/116) Validation Level: Tier 1
Sample Delivery Group (SDG): B120902
LABORATORY SAMPLE
IDENTIFICATION MATRIX COLLECTION
DATE
45-103B 45-103B Solid 3/18/2020 45-107A 45-107A Solid 3/18/2020 45-107B 45-107B Solid 3/18/2020 45-108A 45-108A Solid 3/18/2020 45-108B 45-108B Solid 3/18/2020 45-109A 45-109A Solid 3/18/2020 45-109B 45-109B Solid 3/18/2020 45-110A 45-110A Solid 3/18/2020
SDG#B120902
CEI-PARS NORTH ATLANTIC LLC
A COMPREHENSIVE ENVIRONMENTAL INC. AND PARS ENVIRONMENTAL INC. JOINT-VENTURE
INTRODUCTION
This Data Validation Report (DVR) presents data validation findings and results for the associated samples listed on the cover page. Data validation was performed in accordance with the U.S. Department of Defense General Data Validation Guidelines, Environmental Data Quality Workgroup, February 9, 2018 and a modified outline of the USEPA National Functional Guidelines for Inorganic Superfund Methods Data Review (January 2017). Where specific guidance was not available, the data has been evaluated in a conservative manner consistent with industry standards using professional experience.
The analyses were performed using the following methods:
Asbestos by EPA 600/R-93/116
All sample results were subjected to Tier 1 data validation, which comprises an evaluation of quality
SDG#B120902
CEI-PARS NORTH ATLANTIC LLC
A COMPREHENSIVE ENVIRONMENTAL INC. AND PARS ENVIRONMENTAL INC. JOINT-VENTURE
The following are definitions of the data qualifiers utilized during data validation:
J (Estimated): The compound or analyte was analyzed for and positively identified by the laboratory;
however the reported concentration is estimated due to nonconformances discovered during data validation.
U (Non-detected): The compound or analyte was analyzed for and positively identified by the laboratory;
however, the compound or analyte should be considered non-detected at the reported concentration due to the presence of contaminants detected in the associated blank(s).
UJ (Non-detected estimated): The compound or analyte was reported as not detected by the laboratory;
however the reported quantitation/detection limit is estimated due to non-conformances discovered during data validation.
R (Rejected): The sample results were rejected due to gross non-conformances discovered during data validation. Data qualified as rejected is not usable.
NA (Not Applicable): The non-conformance discovered during data validation demonstrates a high bias, while the affected compound or analyte in the associated sample(s) was reported as not detected by the laboratory and did not warrant the qualification of the data.
A qualification summary table is provided at the end of this report if data has been qualified. Flags are classified as P (protocol) or A (advisory) to indicate whether the flag is due to a laboratory deviation from
SDG#B120902
CEI-PARS NORTH ATLANTIC LLC
A COMPREHENSIVE ENVIRONMENTAL INC. AND PARS ENVIRONMENTAL INC. JOINT-VENTURE
I. Sample Receipt and Technical Holding Times
All samples were received in good condition.
All technical holding time requirements were met.
II. Initial Calibration
Initial calibration data were not reviewed for Tier 1 validation.
Ill. Continuing Calibration
Continuing calibration data were not reviewed for Tier 1 validation.
IV. Laboratory Blanks
Laboratory blanks were not required by the methods.
V. Field Blanks
No field blanks were identified in this SDG.
VI. Matrix Spike/Matrix Spike Duplicates
Matrix spike (MS) and matrix spike duplicates (MSD) analyses were not required by the methods.
VII. Duplicate Sample Analysis
Duplicate (DUP) sample analysis was not required by the methods.
VIII. Laboratory Control Samples
Laboratory control samples (LCS) and laboratory control samples duplicates (LCSD) were not required by the methods.
IX. Field Duplicates
No field duplicates were identified in this SDG.
X. Sample Result Verification
Raw data were not reviewed for Tier 1 validation.
XI. Overall Assessment of Data
The analysis was conducted within all specifications of the methods. No results were rejected in this SDG.
SDG#B120902
CEI-PARS NORTH ATLANTIC LLC
A COMPREHENSIVE ENVIRONMENTAL INC. AND PARS ENVIRONMENTAL INC. JOINT-VENTURE
DATA QUALIFICATION SUMMARY
Project: Natick Soldier Systems Center
SDG: B120902
SDG#B120902
CEI-PARS NORTH ATLANTIC LLC
A COMPREHENSIVE ENVIRONMENTAL INC. AND PARS ENVIRONMENTAL INC. JOINT-VENTURE
VALIDATION COMPLETENESS WORKSHEET
Project/Site Name: Natick Soldier Systems Center – Building 45 CEI Report Date: March 30, 2020 Parameters: Asbestos (EPA/600/R-93/116) Validation Level: Tier 1
Sample Delivery Group (SDG): B120902
The samples listed in the validation report were reviewed for each of the following validation areas.
II. Initial calibration N
III. Calibration verification N
IV. Laboratory blanks N Not required
V. Field blanks N
VI. Matrix spike/Matrix spike duplicate N Not required
VII. Duplicate sample analysis N Not required
VIII. Laboratory control samples N Not required
IX. Field duplicates N
X. Sample result verification N
XI. Overall assessment of data A
Note: A = Acceptable ND = No compounds detected D = Duplicate
N = Not provided/applicable R = Rinsate TB = Trip blank SW = See worksheet
Appendix E
Historic Asbestos Survey &
Abatement Plans
U.S. Army Soldier Systems Center – Building 45 March 2012 ©2012, Mabbett & Associates, Inc. Page 1 of 3 Appendix A, Table 3 - Survey Report Natick Building 45 Final.doc
Table 3 - Summary of ACM Building Survey Results U.S. Army Soldier Systems Center, Natick, MA, Building 45
Sample No.
Floor Sample Location Description of Material Percent and
Type of Asbestos
1A 1 Corridor 12"x12" Black Floor Tile NAD 1B 1 Corridor 12"x12" Black Floor Tile NAD 1C 1 Corridor 12"x12" Black Floor Tile NAD 2A 1 Corridor 12"x12" Black Floor Tile Mastic NAD 2B 1 Corridor 12"x12" Black Floor Tile Mastic NAD 2C 1 Corridor 12"x12" Black Floor Tile Mastic NAD 3A 1 Corridor 12"x12" White w/ Black Dot Floor Tile NAD 3B 1 Corridor 12"x12" White w/ Black Dot Floor Tile NAD 3C 1 Corridor 12"x12" White w/ Black Dot Floor Tile NAD 4A 1 Corridor 12"x12" White w/ Black Dot Floor Tile Mastic NAD 4B 1 Corridor 12"x12" White w/ Black Dot Floor Tile Mastic NAD 4C 1 Corridor 12"x12" White w/ Black Dot Floor Tile Mastic NAD 5A 1 L112 12"x12" Gray Marble Floor Tile NAD 5B 1 L112 12"x12" Gray Marble Floor Tile NAD 6A 1 L112 12"x12" Gray Marble Floor Tile Mastic NAD 6B 1 L112 12"x12" Gray Marble Floor Tile Mastic NAD 7A 1 L105 9"x9" Beige Floor Tile 3% Chrysotile 7B 1 L105 9"x9" Beige Floor Tile NA/PS 7C 1 L111 9"x9" Beige Floor Tile NA/PS 8A 1 L105 9"x9" Beige Floor Tile Mastic 2% Chrysotile 8B 1 L105 9"x9" Beige Floor Tile Mastic NA/PS 8C 1 L111 9"x9" Beige Floor Tile Mastic NA/PS 9A 1 L114 12"x12" Beige Marble Floor Tile NAD 9B 1 L111B 12"x12" Beige Marble Floor Tile NAD 9C 1 L116 12"x12" Beige Marble Floor Tile NAD 10A 1 L114 12"x12" Beige Marble Floor Tile Mastic NAD 10B 1 L111B 12"x12" Beige Marble Floor Tile Mastic NAD 10C 1 L116 12"x12" Beige Marble Floor Tile Mastic NAD 11A 1 L116 12"x12" Brown Fleck Floor Tile 2% Chrysotile 11B 1 L116 12"x12" Brown Fleck Floor Tile NA/PS 11C 1 L116 12"x12" Brown Fleck Floor Tile NA/PS 11D 1 L116 12"x12" Brown Fleck Floor Tile NA/PS 12A 1 L116 12"x12" Brown Fleck Floor Tile Mastic NAD 12B 1 L116 12"x12" Brown Fleck Floor Tile Mastic NAD 12C 1 L116 12"x12" Brown Fleck Floor Tile Mastic NAD 12D 1 L116 12"x12" Brown Fleck Floor Tile Mastic NAD 13A 1 L112 9"x9" Olive Floor Tile 5% Chrysotile 13B 1 L112 9"x9" Olive Floor Tile NA/PS 14A 1 L112 9"x9" Olive Floor Tile Mastic 2% Chrysotile 14B 1 L112 9"x9" Olive Floor Tile Mastic NA/PS 15A 1 L112 9"x9" Brown Floor Tile 5% Chrysotile 15B 1 L112 9"x9" Brown Floor Tile NA/PS 16A 1 L112 9"x9" Brown Floor Tile Mastic 2% Chrysotile 16B 1 L112 9"x9" Brown Floor Tile Mastic NA/PS
©2012, Mabbett & Associates, Inc. Page 2 of 3 Appendix A, Table 3 - Survey Report Natick Building 45 Final.doc
Table 3 - Summary of ACM Building Survey Results U.S. Army Soldier Systems Center, Natick, MA, Building 45
Sample No.
Floor Sample Location Description of Material Percent and
Type of Asbestos
17A Basement 112 12"x12" White w/Blue Fleck Floor Tile NAD 17B Basement 112 12"x12" White w/Blue Fleck Floor Tile NAD 17C Basement 112 12"x12" White w/Blue Fleck Floor Tile NAD 18A Basement 112 12"x12" White w/Blue Fleck Floor Tile Mastic NAD 18B Basement 112 12"x12" White w/Blue Fleck Floor Tile Mastic NAD 18C Basement 112 12"x12" White w/Blue Fleck Floor Tile Mastic NAD 19A Basement Parachute Shop 12"x12" White w/ Yellow Fleck Floor Tile 5% Chrysotile 19B Basement Parachute Shop 12"x12" White w/ Yellow Fleck Floor Tile NA/PS 19C Basement Parachute Shop 12"x12" White w/ Yellow Fleck Floor Tile NA/PS 20A Basement Parachute Shop 12"x12" White w/ Yellow Fleck Floor Tile Mastic NAD 20B Basement Parachute Shop 12"x12" White w/ Yellow Fleck Floor Tile Mastic NAD 20C Basement Parachute Shop 12"x12" White w/ Yellow Fleck Floor Tile Mastic NAD 21A 1 Breezeway Drywall NAD 21B 1 L117 Drywall NAD 21C 1 L103 Drywall NAD 21D Basement Parachute Shop Drywall NAD 21E Basement Corridor Drywall NAD 21F Basement Corridor Drywall NAD 22A 1 L111 Carpet Mastic NAD 22B 1 L114 Carpet Mastic NAD 22C 1 PAO Carpet Mastic NAD 23A 1 Corridor @ CL-2 2'x2' Textured Ceiling Tile NAD 23B 1 Corridor @ Entrance 2'x2' Textured Ceiling Tile NAD 23C 1 L117 2'x2' Textured Ceiling Tile NAD 24A 1 Corridor @ Entrance Hard Pipe Fitting NAD 24B 1 Corridor @ Entrance Hard Pipe Fitting NAD 24C 1 Corridor @ L110 Hard Pipe Fitting NAD 25A 1 L107 12"x12" Light Gray Marble Floor Tile NAD 25B 1 L107 12"x12" Light Gray Marble Floor Tile NAD 26A 1 L107 12"x12" Light Gray Marble Floor Tile Mastic NAD 26B 1 L107 12"x12" Light Gray Marble Floor Tile Mastic NAD 27A 1 L117 4" Cove Base NAD 27B 1 Corridor 4" Cove Base NAD 27C 1 Hall @ L100A 4" Cove Base NAD 28A 1 L117 4" Cove Base Mastic NAD 28B 1 Corridor 4" Cove Base Mastic NAD 28C 1 Hall @ L100A 4" Cove Base Mastic NAD 29A 1 L117 Joint Compound NAD 29B 1 L117 Joint Compound NAD 29C 1 L103 Joint Compound NAD 29D Basement Parachute Shop Joint Compound NAD 29E Basement Corridor Joint Compound NA 29F Basement Corridor Joint Compound NAD
30A 1 DPW Technical
Services 2'x2' Gray Textured Ceiling Tile
NAD
30B 1 DPW Technical 2'x2' Gray Textured Ceiling Tile NAD
©2012, Mabbett & Associates, Inc. Page 3 of 3 Appendix A, Table 3 - Survey Report Natick Building 45 Final.doc
Table 3 - Summary of ACM Building Survey Results U.S. Army Soldier Systems Center, Natick, MA, Building 45
Sample No.
Floor Sample Location Description of Material Percent and
Type of Asbestos
Services
30C 1 Corridor @ L100A 2'x2' Gray Textured Ceiling Tile NAD 31A 1 L102 2'x2' Dot Fissure Ceiling Tile NAD 31B 1 L118 2'x2' Dot Fissure Ceiling Tile NAD 31C 1 L111 2'x2' Dot Fissure Ceiling Tile NAD 32A Basement Crawl Space Soil Debris NAD 32B Basement Crawl Space Soil Debris NAD 32C Basement Crawl Space Soil Debris NAD 33A 1 L116B 2'x4' Dot Fissure Ceiling Tile NAD 33B 1 Basement 2'x4' Dot Fissure Ceiling Tile NAD 33C 1 Basement 2'x4' Dot Fissure Ceiling Tile NAD 34A Exterior Exterior Door Caulk NAD 34B Exterior Exterior Door Caulk NAD 34C Exterior Exterior Door Caulk NAD 35A Exterior Exterior Window Caulk NAD 35B Exterior Exterior Window Caulk NAD 35C Exterior Exterior Window Caulk NAD 36A Exterior Exterior Window Glazing NAD 36B Exterior Exterior Window Glazing 2% Chrysotile 36C Exterior Exterior Window Glazing NA/PS 37 Basement Corridor Basement Pipe Fitting Insulation NAD 38 1 L116 Large Diameter Pipe Fitting Insulation NAD
39A 1 M100 Large Tank Insulation 5% Chrysotile 39B 1 M100 Large Tank Insulation NA/PS 39C 1 M100 Large Tank Insulation NAD 40A 1 M100 Small Tank Insulation 30% Chrysotile 40B 1 M100 Small Tank Insulation NA/PS 40C 1 M100 Small Tank Insulation NA/PS 41A 1 M100 Heat Exchanger Insulation 60% Chrysotile 41B 1 M100 Heat Exchanger Insulation NA/PS 41C 1 M100 Heat Exchanger Insulation NA/PS 42A 1 M100 Heat Exchanger Fitting Insulation 70% Chrysotile 42B 1 M100 Heat Exchanger Fitting Insulation NA/PS 43A 1 M100 Lo Pressure Steam Fitting Insulation NAD 43B 1 M100 Lo Pressure Steam Fitting Insulation NAD 44A 1 M100 Steam Condensate Fitting Insulation 40% Chrysotile 44B 1 M100 Steam Condensate Fitting Insulation NA/PS 45A 1 M100 Pre Molded Pipe Insulation 70% Amosite 45B 1 M100 Pre Molded Pipe Insulation NA/PS
Footnotes:
NAD - No Asbestos Detected (PLM) NA - Not Analzed NA/PS - Not Analyzed, Positive Stop
5 Alfred Circle Bedford, Massachusetts 01730-2318 Tel: (781) 275-6050 Fax: (781) 275-5651 info@mabbett.com www.mabbett.com
01730-2318 Tel: (781) 275-6050 Fax: (781) 275-5651
01730-2318 Tel: (781) 275-6050 Fax: (781) 275-5651
01730-2318 Tel: (781) 275-6050 Fax: (781) 275-5651
01730-2318 Tel: (781) 275-6050 Fax: (781) 275-5651
01730-2318 Tel: (781) 275-6050 Fax: (781) 275-5651
©2012, Mabbett & Associates, Inc. Page 1 of 6 Appendix B, Survey Report Natick Building 45 Final.doc
9”x9” Beige Floor Tile and Mastic Samples 7 A, B & C and 8 A, B & C
12”x12” Brown Fleck Floor Tile Samples 11 A, B, C & D and 12 A, B, C & D
©2012, Mabbett & Associates, Inc. Page 2 of 6 Appendix B, Survey Report Natick Building 45 Final.doc
9”x9” Olive Floor Tile and Mastic Samples 13 A & B, 14 A & B, 15 A & B and 16 A & B
12”x12” White with Yellow Fleck Floor Tile Samples 19 A, B & C
©2012, Mabbett & Associates, Inc. Page 3 of 6 Appendix B, Survey Report Natick Building 45 Final.doc
Window Glazing Samples 36 B & C
Large Tank Insulation Samples 39 A, B & C
©2012, Mabbett & Associates, Inc. Page 4 of 6 Appendix B, Survey Report Natick Building 45 Final.doc
Small Tank Insulation Samples 40 A, B & C
Heat Exchanger Insulation Samples 41 A, B & C
©2012, Mabbett & Associates, Inc. Page 5 of 6 Appendix B, Survey Report Natick Building 45 Final.doc
Heat Exchanger Fitting Insulation Samples 42 A, B & C
Steam Condensate Fitting Insulation Samples 44 A & B
©2012, Mabbett & Associates, Inc. Page 6 of 6 Appendix B, Survey Report Natick Building 45 Final.doc
Pre Molded Pipe Insulation Samples 45 A & B
File details come from the government source that posted it. Updated .