This is a Technical Requirements Worksheet for a Request for Proposals issued by the New Hampshire Department of Public Health (DPH) for Perinatal Mental Health Support. The document establishes mandatory (M), preferred (P), optional (O), and not applicable (N/A) technical and operational requirements that vendors must address in their proposals. The requirements span multiple functional areas including general specifications, application security, testing, hosting and cloud infrastructure, disaster recovery, service level agreements, support and maintenance, project management, and website and social media management. Vendors are required to submit detailed responses explaining how their proposed solutions will meet each requirement, with particular emphasis on mandatory requirements that are essential for proposal acceptance.

The technical requirements mandate that the proposed solution utilize open standards and web-based compatibility with W3C standards (HTML5, CSS 2.1, XML 1.1). Security requirements are extensive and mandatory, including multi-factor authentication, encryption using Advanced Encryption Standard (AES), role-based access controls, comprehensive audit logging for one year (or six years if protected health information is involved), and compliance with state password policies. The hosting environment must meet ANSI/TIA-942 Tier 3 Data Center standards with 99.982% availability, 24/7 operation, and support for remote access via VPN. Disaster recovery and backup requirements include daily differential backups and weekly complete backups with off-site storage. The vendor must provide Class A deficiency responses within two hours and Class B/C deficiency responses within four hours, maintain quarterly status reports, and assign a full-time Project Manager to the engagement, with virtual meeting participation permitted.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Instructions

Vendor Instructions for Technical (TR) Requirements
Criticality Column:

(M) Indicates a requirement that is "Mandatory". The State considers it to be of such great importance that is must be met in order for the porposal to be accepted. If the proposer believes that there is something about their proposal that either obviates the need for this requirement or makes it of less importance this must be explained within the comments. The State retains the right to accept a proposal if the need of the requirement is reduced or eliminated by another feature of the proposal.

(P) Indicates a requirement whic is "Preferred". This requirement is considered by the State to be of great usefulness but the lack of this feature is not considered serious enough to disqualify the proposal.

(O) Indicates a requirement which is "Optional". This requirement is considered by the State to be one which useful or potentially useful but not a central feature of the Project.

(N/A) Indicates a requirement that is "Not Applicable". This requirement is will not be required by the State for this project.

Vendors Response Column:

Vendor must provide a brief explanation of how the requirement will be met. Free form text can be entered into this column.

Technical Requirements

APPLICATION REQUIREMENTS
State Requirements
Req #Requirement DescriptionCriticalityVendor ResponseExample Response
GENERAL SPECIFICATIONS
A1.1Ability to access data using open standards access protocol.
MThe solution being proposed will use a commercial off the shelf (COTS) software that utilizes XML, HTML and SQL all of which leverage open standards to allow for interoperability and continued quality.
A1.2Data is available in commonly used format over which no entity has exclusive control, with the exception of National or International standards. Data is not subject to any copyright, patent, trademark or other trade secret regulation.MAs represented in A1.1 by utilizing open standards our solution is compliant with this requirement.
A1.3Web-based compatible and in conformance with the following W3C standards: HTML5, CSS 2.1, XML 1.1MThe web based component of this solution conforms to w3c standards in our case specifically leveraging HTML5, XML and SOAP
APPLICATION SECURITY
A2.1Verify the identity or authenticate all of the system client applications before allowing use of the system to prevent access to inappropriate or confidential data or services.
MUtilizing our COTS solution will require the user to validate their identify through a user name and password provided after information is obtained to create the users account.
A2.2Verify the identity and authenticate all of the system’s human users before allowing them to use its capabilities to prevent access to inappropriate or confidential data or services.MBased on the role based access controls within the COTS solution we will ensure the users have access only to the data that the State authorizes.
A2.3Enforce unique user names.MThe COTS solution combined with our logical access procedure to create user accounts ensures the unique user name.
A2.4Comply with the Department's Password Standard and DoIT’s statewide User Account and Password Policy when developing, establishing, and enforcing system Administrative (privileged) and End User (non-privileged) accounts. Should a requirement conflict reside between the two documents the more restrictive requirement must be followed.MThe COTS solution will comply with the requirements as listed in the Department's Password Standard and NH DoIT's Password Policy.
A2.8Provide the ability to limit the number of people that can grant or change authorizations.
MBased on State approval the system will allow for up to 3 administrators to support granting or changing permissions.
A2.10The application shall not store authentication credentials or sensitive data in its code.MAll authentication credentials are encrypted utilizing the Advanced Encryption Standard (AES)
A2.11Log all attempted accesses that fail identification, authentication and authorization requirements.MThe system in compliance with failed attempt policy automatically logs all failed attempts to result in a lockout. See A2.4
A2.13All logs must be kept for one (1) year, unless protected health information is entered into/stored in the system or product, then all audit logs must be kept for six (6) years for HIPPA compliance.MThe COTS solution will maintain logs for 1 years
A2.14The application must allow a human user to explicitly terminate a session. No remnants of the prior session should then remain.MThe COTS solution allows for the termination of the user account which will result in the termination of access.
A2.15Do not use Software and System Services for anything other than they are designed for.
MThe solution will be implemented at the direction of the department to meet the requirements of the contract.
A2.16The application Data shall be protected from unauthorized use when at rest.
MThe COTS solution will encrypt data in transit and at rest coupled with role based access permissions the application data will be protected at rest
A2.17The application shall keep any sensitive Data or communications private from unauthorized individuals and programs.MSee A2.16
A2.18Subsequent application enhancements or upgrades shall not remove or degrade security requirements.
MThe COTS solution and subsequent upgrades will maintain or enhance security requirements in partnership and communication with the State.
A2.19Utilize change management documentation and procedures.
MThe COTS solution will follow industry best practices for change management and the configuration administrators will document all changes made to production after final user acceptance of the changes.
A2.21Logs must be configured using "fail-safe" configuration. Audit logs must contain the following minimum information:

1. User lDs (of all users who have access to the system)

2. Date and time stamps

3. Changes made to system configurations

4. Addition of new users

5. New users level of access

6. Files accessed (including users)

7. Access to systems, applications and data

8. Access trail to systems and applications (successful and unsuccessful attempts)

9. Security events M The COTS solution will be able to maintain the following information either in a log or separate documentation:

1. User lDs (of all users who have access to the system)

2. Date and time stamps

3. Changes made to system configurations

4. Addition of new users

5. New users level of access

6. Files accessed (including users)

7. Access to systems, applications and data

8. Access trail to systems and applications (successful and unsuccessful attempts)

9. Security events

TESTING REQUIREMENTS
State Requirements
Req #Requirement DescriptionCriticalityResponseExample Response
APPLICATION SECURITY TESTING
T1.1All components of the Software shall be reviewed and tested to ensure they protect the Department and State’s web site and its related Data assets.
MAs this is a COTS solution the components of the software that will be reviewed and tested will focus on the configuration of the system to meet the business and technical requirements of the solution.
T1.2The Vendor shall be responsible for providing documentation of security testing, as appropriate. Tests shall focus on the technical, administrative and physical security controls that have been designed into the System architecture in order to provide the necessary confidentiality, integrity and availability.
MThe COTS solution has published documentation to address the technical, administrative and physical security controls available upon request.
T1.3Provide evidence that supports the fact that Identification and Authentication testing has been recently accomplished; supports obtaining information about those parties attempting to log onto a system or application for security purposes and the validation of users.
MThis is addressed via logs associated with login attempts
T1.4Test for Access Control; supports the management of permissions for logging onto a computer or network.
MSee A2.4
T1.5Test for encryption; supports the encoding of data for security purposes, and for the ability to access the data in a decrypted format from required tools.
MSee A2.4 and A2.16
T1.6Test the Intrusion Detection; supports the detection of illegal entrance into a computer system.
MSee T1.2
T1.8Test the User Management feature; supports the administration of computer, application and network accounts within an organization.
MSee A2.4, this process is tested each time an account is activated or de-activated
T1.9Test Role/Privilege Management; supports the granting of abilities to users or groups of users of a computer, application or network.
MThis will be accomplished after final configuration and account creation has been completed and validated by the department
T1.10Test Audit Trail Capture and Analysis; supports the identification and monitoring of activities within an application or system.
MThe COTS solution has an internal testing plan for ensuring the audit trail logs are in place.
T1.11Test Input Validation; ensures the application is protected from buffer overflow, cross-site scripting, SQL injection, and unauthorized access of files and/or directories on the server.
MThe COTS solution has an internal testing plan and is covered contractually to protect against the items listed
T.1.12For web applications, ensure the application has been tested and hardened to prevent critical application security flaws. ( At a minimum, the application shall be tested against all flaws outlined in the Open Web Application Security Project (OWASP) Top Ten (http://www.owasp.org/index.php/OWASP_Top_Ten_Project).
MThe COTS solution has an internal testing plan for ensuring the audit trail logs are in place.
T1.13Provide the State with validation of 3rd party security reviews performed on the application and system environment. The review may include a combination of vulnerability scanning, penetration testing, static analysis of the source code, and expert code review (please specify proposed methodology in the comments field).
MThe 3rd party scans can be provided upon request. These reports are a sub-contract component with the COTS solution being employed on this solution.
HOSTING-CLOUD REQUIREMENTS
State Requirements
Req #Requirement DescriptionCriticalityResponseExample Response
OPERATIONS
H1.1Vendor shall provide an ANSI/TIA-942 Tier 3 Data Center or equivalent. A tier 3 data center requires 1) Multiple independent distribution paths serving the IT equipment, 2) All IT equipment must be dual-powered and fully compatible with the topology of a site's architecture and 3)Concurrently maintainable site infrastructure with expected availability of 99.982%.
MSee T1.14
H1.2Vendor shall maintain a secure hosting environment providing all necessary hardware, software, and Internet bandwidth to manage the application and support users with permission based logins.MSee T1.14
H1.3The Data Center must be physically secured – restricted access to the site to personnel with controls such as biometric, badge, and others security solutions. Policies for granting access must be in place and followed. Access shall only be granted to those with a need to perform tasks in the Data Center.
MSee T1.14
H1.4Vendor shall install and update all server patches, updates, and other utilities within 60 days of release from the manufacturer.
MSee T1.14
H1.5Vendor shall monitor System, security, and application logs.
MSee T1.14
H1.6Vendor shall manage the sharing of data resources.
MSee T1.14
H1.7Vendor shall manage daily backups, off-site data storage, and restore operations.
MDaily backups will be performed nightly per sub-contract with COTS solution
H1.8The Vendor shall monitor physical hardware.
MSee T1.14
H1.9Remote access shall be customized to the State’s business application. In instances where the State requires access to the application or server resources not in the DMZ, the Vendor shall provide remote desktop connection to the server through secure protocols such as a Virtual Private Network (VPN).
MThe COTS solution will be a cloud based solution accessible based on the role based access permissions configured as part of the project based on the State's requirements.
DISASTER RECOVERY
H2.1Vendor shall have documented disaster recovery plans that address the recovery of lost State data as well as their own. Systems shall be architected to meet the defined recovery needs.
MSee T1.14
H2.2The disaster recovery plan shall identify appropriate methods for procuring additional hardware in the event of a component failure. In most instances, systems shall offer a level of redundancy so the loss of a drive or power supply will not be sufficient to terminate services however, these failed components will have to be replaced.
MSee T1.14
H2.3Vendor shall adhere to a defined and documented back-up schedule and procedure.
MSee H1.7
H2.4Back-up copies of data are made for the purpose of facilitating a restore of the data in the event of data loss or System failure.
MSee H1.7
H2.5Scheduled backups of all servers must be completed regularly. The minimum acceptable frequency is differential backup daily, and complete backup weekly.
MSee H1.7
H2.6Tapes or other back-up media must be securely transferred from the site to another secure location to avoid complete data loss with the loss of a facility.
MSee H1.7
H2.7Data recovery – In the event that recovery back to the last backup is not sufficient to recover State Data, the Vendor shall employ the use of database logs in addition to backup media in the restoration of the database(s) to afford a much closer to real-time recovery. To do this, logs must be moved off the volume containing the database with a frequency to match the business needs.MAll data recovery is managed via the backup and restore process
HOSTING SECURITY
H3.2If State data is hosted on multiple servers, data exchanges between and among servers must be encrypted.
MAll data is encrypted and at rest regardless of number of servers.
H3.4All components of the infrastructure shall be reviewed and tested to ensure they protect the State’s hardware, software, and its related data assets. Tests shall focus on the technical, administrative and physical security controls that have been designed into the System architecture in order to provide confidentiality, integrity and availability.
MAll security controls are tested and addressed via the item T1.14
H3.7All servers and devices must have event logging enabled. Logs must be protected with access limited to only authorized administrators. Logs shall include System, Application, Web and Database logs.
MAll security controls are tested and addressed via the item T1.14
H3.8Operating Systems (OS) and Databases (DB) shall be built and hardened in accordance with guidelines set forth by CIS, NIST or NSA.
MAll security controls are tested and addressed via the item T1.14
SERVICE LEVEL AGREEMENT
H4.1The Vendor’s System support and maintenance shall commence upon the Effective Date and extend through the end of the Contract term, and any extensions thereof.
MThe COTS solution will be maintained, operated and supported per the contract terms.
H4.2The vendor shall maintain the hardware and Software in accordance with the specifications, terms, and requirements of the Contract, including providing, upgrades and fixes as required.MThe COTS configuration may be changed as needed to meet the State's requirements.
H4.3The vendor shall repair or replace the hardware or software, or any portion thereof, so that the System operates in accordance with the Specifications, terms, and requirements of the Contract.
MSince the solution is dependent upon the COTS solution proposed any replacement of the software would require a change order and amendment to the contract.
H4.4All hardware and software components of the Vendor hosting infrastructure shall be fully supported by their respective manufacturers at all times. All critical patches for operating systems, databases, web services, etc., shall be applied within sixty (60) days of release by their respective manufacturers.
MThis will follow the COTS solutions roadmaps for patches in alignment with item T1.14
H4.6The Vendor shall conform to the specific deficiency class as described: o Class A Deficiency - Software - Critical, does not allow System to operate, no work around, demands immediate action; Written Documentation - missing significant portions of information or unintelligible to State; Non Software - Services were inadequate and require re-performance of the Service.

o Class B Deficiency - Software - important, does not stop operation and/or there is a work around and user can perform tasks; Written Documentation - portions of information are missing but not enough to make the document unintelligible; Non Software - Services were deficient, require reworking, but do not require re-performance of the Service.

o Class C Deficiency - Software - minimal, cosmetic in nature, minimal effect on System, low priority and/or user can use System; Written Documentation - minimal changes required and of minor editing nature; Non Software - Services require only minor reworking and do not require re-performance of the Service.

M The proposed solution will be a COTS solution and thus the solution will be able to comply with the following:

Class A Deficiency - system is not available or is not performing the function agreed upon during production go live

Class B Deficiency - COTS configuration issue with a workaround not impacting system utilization, but requires attention to resolve manual workaround.

Class C Deficiency - COTS configuration that has minimum impact on the function. Would be de prioritized to complete remediation on Class B and Class A deficiencies.

H4.7 As part of the maintenance agreement, ongoing support issues shall be responded to according to the following:

a. Class A Deficiencies - The Vendor shall have available to the State on-call telephone assistance, with issue tracking available to the State, eight (8) hours per day and five (5) days a week with an email / telephone response within two (2) hours of request; or the Vendor shall provide support on-site or with remote diagnostic Services, within four (4) business hours of a request;

b. Class B & C Deficiencies –The State shall notify the Vendor of such Deficiencies during regular business hours and the Vendor shall respond back within four (4) hours of notification of planned corrective action; The Vendor shall repair or replace Software, and provide maintenance of the Software in accordance with the Specifications, Terms and Requirements of the Contract.

MThe proposed solution will be able to provide response times as described herein.
H4.8The hosting server for the State shall be available twenty-four (24) hours a day, 7 days a week except for during scheduled maintenance.
MThe COTS solution will be available 24 hours a day and 7 days a week; however support will be available as described in H4.5
H4.9A regularly scheduled maintenance window shall be identified (such as weekly, monthly, or quarterly) at which time all relevant server patches and application upgrades shall be applied.
MThe COTS solution has full failover functionality allowing for maintenance to occur without impact to the business functionality.
H4.10If The Vendor is unable to meet the uptime requirement, The Vendor shall credit State’s account in an amount based upon the following formula: (Total Contract Item Price/365) x Number of Days Contract Item Not Provided. The State must request this credit in writing.
MAgreed for any uptime requirement not met for the COTS solution included in the proposal.
H4.13The Vendor shall maintain a record of the activities related to repair or maintenance activities performed for the State and shall report quarterly on the following: Server up-time; All change requests implemented, including operating system patches; All critical outages reported including actual issue and resolution; Number of deficiencies reported by class with initial response time as well as time to close.
MThe COTS solution will not be able to provide the details identified herein. The proposed solution will be able upon request to provide documentation surrounding configurations changes that were completed in production through the change management process, see A2.19.
H4.14The Vendor will give two-business days prior notification to the State Project Manager of all changes/updates and provide the State with training due to the upgrades and changes.
MFollowing the change management process see item A2.19 notification will be provided prior to implementation in production and training shall be performed either via in-person, video computer based training, and/or in documentation.
SUPPORT & MAINTENANCE REQUIREMENTS
State Requirements
Req #Requirement DescriptionCriticalityResponseExample Response
SUPPORT & MAINTENANCE REQUIREMENTS
S1.1The Vendor’s System support and maintenance shall commence upon the Effective Date and extend through the end of the Contract term, and any extensions thereof.
N/AAgreed
S1.3Repair Software, or any portion thereof, so that the System operates in accordance with the Specifications, terms, and requirements of the Contract.
N/ABased on assigned deficiencies the support team will resolve the issue and obtain acceptance following standard change management practices.
S1.6The Vendor shall make available to the State the latest program updates, general maintenance releases, selected functionality releases, patches, and Documentation that are generally offered to its customers, at no additional cost.
N/AThese documents will be provided based on their availability from the third-party COTS solution.
S1.7For all maintenance Services calls, The Vendor shall ensure the following information will be collected and maintained: 1) nature of the Deficiency; 2) current status of the Deficiency; 3) action plans, dates, and times; 4) expected and actual completion time; 5) Deficiency resolution information, 6) Resolved by, 7) Identifying number i.e. work order number, 8) Issue identified by;N/AAgreed
S1.8The Vendor must work with the State to identify and troubleshoot potentially large-scale System failures or Deficiencies by collecting the following information: 1) mean time between reported Deficiencies with the Software; 2) diagnosis of the root cause of the problem; and 3) identification of repeat calls or repeat Software problems.
N/AThe proposed solution and support will be able to diagnose root cause as needed as well as problem management to address repeat calls or configuration issues.
S1.15The Vendor shall utilize the NH secure FTP site provided by the State for uploading and downloading files if applicable.
MAgreed
S1.16The hosting server for the State shall be available twenty-four (24) hours a day, 7 days a week except for during scheduled maintenance.MSee H4.8
PROJECT MANAGEMENT
State Requirements
Req #Requirement DescriptionCriticalityResponseExample Response
PROJECT MANAGEMENT
P1.1Vendor shall participate in an initial kick-off meeting to initiate the Project.
MAgreed
P1.2Vendor shall provide Project Staff as specified in the RFP.
MAgreed
P1.3Vendor shall submit a finalized Work Plan within thirty (30) days after Contract award and approval by Governor and Council. The Work Plan shall include, without limitation, a detailed description of the Schedule, tasks, Deliverables, milestones/critical events, task dependencies, vendors and state resources required and payment Schedule.MAgreed
P1.4Vendor shall provide detailed quarterly status reports on the progress of the Project, which will include expenses incurred year to date.
MThis proposal includes a weekly update for status reports that will include risks, actions, decisions. A monthly financial expense report will be provided.
P1.5All user, technical, and System Documentation as well as Project Schedules, plans, status reports, and correspondence must be maintained as project documentation.
MThis proposal includes standard project management principles and deliverables to include schedules, plans, reports, risks, actions, issues, decisions and financials and we can support utilizing the State project management solution or provide our own at the State's direction.
P1.6Vendor shall provide a full time Project Manager assigned to the project.MAgreed
P1.7The Vendor Project Manager, and relevant key staff, shall every three (3) months, beginning in the first month of the Contract, travel to Concord, NH to meet with project representatives from DHHS to review past quarter performance and upcoming quarter Plan of Operations. Virtual meetings may be permitted if approved by DHHS.MAll staff will be work remotely for the duration of this contract
P1.8The Vendor's project manager is also expected to host other important meetings, assign contractor staff to those meetings as appropriate and provide an agenda for each meeting.MAgreed
P1.9Meeting minutes will be documented and maintained electronically by the contractor and distributed within 24 hours after the meeting. Key decisions along with Closed, Active and Pending issues will be included in this document as well.MAgreed
WEBSITE AND SOCIAL MEDIA MANAGEMENT
State RequirementsVendor
Req #Requirement DescriptionCricitcalityResponseExample Response
PROJECT MANAGEMENT
W.1.1The Vendor shall work with the Department’s Communications Bureau to ensure that any social media or website designed, created, or managed on behalf of the Department meets all of the Department’s and NH Department of Information Technology’s website and social media requirements and policies.M

Exhibit L: IT Requirements Workbook