Attachment 8 - Maks Airfield Construction Safety Phasing Plan (CSPP).pdf

PDF 867 KB Posted

Attached to
Fort Johnson Paving and Drainage Federal contract opportunity
Solicitation number
W9124E24B0002
Issued by
Department of the Army Materiel Command Mission and Installation Contracting Command Fort Hood

About this file

This solicitation is for an indefinite delivery indefinite quantity construction contract to provide pavement, infrastructure, and drainage repairs and construction at various locations at Fort Johnson, Louisiana. The contract has an estimated value between $26-100 million and is a 100% set-aside for certified 8(a) small businesses. The work will be performed in accordance with applicable state, local, and federal regulations and codes. A site visit will be held on January 11, 2024 at 1:00 PM for attendance details outlined in the solicitation. Bids must be submitted via the PIEE solicitation module to be considered for this firm fixed price contract awarded by the Mission and Installation Contracting Command at Fort Johnson.

View the file

Other files for this federal contract opportunity

Other files attached to Fort Johnson Paving and Drainage, newest first.
File Type Posted
Conformed Copy Solicitation Amendment 3 W9124E-24-B-0002.pdf PDF
Amendment 3 - W9124E-24-B-0002.pdf PDF
Conformed Copy Solicitation Amendment 2 W9124E-24-B-0002.pdf PDF
Technical Exhibit G Davis Bacon WD LA20240014 dtd 5 Jan 2024.pdf PDF
Technical Exhibit A - Ft. Johnson Statement of Work Rev1, 25Jan24.pdf PDF
Amendment 2 - W9124E-24-B-0002.pdf PDF
Technical Exhibit B Pavement Infrastructure Specs 25Jan24.pdf PDF
Site Visit Attendance Roster W9124E-24-B-0002.pdf PDF
Conformed Copy - Solicitation W9124E-24-B-0002.pdf PDF
Amendment 1 W9124E-24-B-0002.pdf PDF
Technical Exhibit F - Peason Ridge Map 19Oct23.pdf PDF
Attachment 5 Ft. Johnson Bid Schedule Ordering Period 4.xlsx XLSX spreadsheet
Attachment 7 - Submittal Register.pdf PDF
Technical Exhibit C - Ft. Johnson Drawings_Specifications, 19Oct23.pdf PDF
Attachment 1 Ft Johnson Bid Schedule Base Period.xlsx XLSX spreadsheet
W9124E-24-B-0002 Fort Johnson Paving and Drainage Solicitation.pdf PDF
Technical Exhibit B - Pavement Infrastructure Specs 19Oct23.pdf PDF
Technical Exhibit E - Ft. Johnson Range Map, 19Oct23.pdf PDF
Attachment 4 Ft. Johnson Bid Schedule Ordering Period 3.xlsx XLSX spreadsheet
Attachment 6 Ft. Johnson COMBINED Bid Schedule.xlsx XLSX spreadsheet
Technical Exhibit A - Ft. Johnson Statement of Work, 27Dec23.pdf PDF
Technical Exhibit D - Ft. Johnson Vicinity Map, 19Oct23.pdf PDF
Technical Exhibit G - Davis Bacon WD LA20230014 dtd 6Jan23.pdf PDF
Attachment 2 Ft. Johnson Bid Schedule Ordering Period 1.xlsx XLSX spreadsheet
Attachment 3 Ft. Johnson Bid Schedule Ordering Period 2.xlsx XLSX spreadsheet
Show all 25

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CSPP September 2023 i

CONSTRUCTION SAFETY PHASING PLAN

(CSPP)

Maks Army Airfield

Project: xxxxxxx

CSPP September 2023 ii

APPROVALS

By their signature, the undersigned certify that this Construction Safety Plan (CSPP) is approved and will be used at Maks Army Airfield ______________ Construction Project, Fort Johnson, Louisiana.

Project Engineer Date

Army Corps of Engineers_________________________ Date

Airfield Safety Program Manager, Brian K Jones Date

Project Manager

Site Superintendent

CSPP September 2023 iii

TABLE OF CONTENTS

APPROVALS ............................................................................................................................ ii

ACRONYMS AND ABBREVIATIONS ................................................................................... v

1.0 EXECUTIVE SUMMARY

1.1 APPROVALS

1.2 REGULATORY DRIVERS

1.3 PENALTIES

2.0 INTRODUCTION

3.0 HEALTH AND SAFETY PERSONNEL

3.1 PROJECT TEAM KEY STAFF ORGANIZATION

3.2 PROJECT MANAGER

3.3 SITE SUPERINTENDENT

3.4 QUALITY CONTROL MANAGER

3.5 QUALITY CONTROL SYSTEMS MANAGER

3.6 SITE HEALTH AND SAFETY OFFICER

3.7 SITE WORKERS

4.0 PROJECT DESCRIPTION AND WORK PLAN

4.1 WORK PHASES

4.1.1 Notification Of Construction Activities to the FAA

4.1.2 Duration of Each Phase

4.1.3 Daily Work Start Time and Finish Time to Include “Night Only” Projects

4.1.4 Aircraft Operational Areas Affected by Construction

4.1.5 NAVAIDS Potentially Affected by Construction

4.2 SPECIAL PRECAUTIONS

4.2.1 Runway and Taxiway Marking and Lighting

4.2.2 Protection of Runway and Taxiway Safety Areas (RSAs and TSAs)

4.2.3 Protection of Obstacle-Free Zones (OFZs), Object-Free Areas (OFAs) and Mandatory Frangibility Zones (MFZs)

4.2.4 Foreign Object Debris (FOD) Control

4.2.5 Wildlife Management

4.2.6 Security Fence Integrity

4.3 CONSTRUCTION PRECAUTIONS

4.3.1 Traffic Control

CSPP September 2023 iv

4.3.2 Area Delineation

4.3.3 Special Construction Limitations – PHASE 1

4.3.4 Stockpile Locations

4.3.5 Hazardous Materials Management (Spill Response)

4.3.6 Trench and Excavation Identification and Cover

4.3.7 Erosion Control

4.3.8 Special Inspection Requirements

4.3.9 Utility Location and Protection

4.3.10 Use of Temporary Visual Aids

5.0 COMMUNICATIONS

5.1 NOTAM ISSUANCE

5.2 ACTIVE AND PASSIVE COMMUNICATIONS

5.3 EMERGENCY NOTIFICATION PROCEDURES

5.4 EMERGENCY PHONE NUMBERS

6.0 TRAINING AND RECORD KEEPING

6.1 INITIAL SAFETY ORIENTATION

6.2 SITE-SPECIFIC TRAINING

6.3 SAFETY BRIEFINGS

6.4 VISUAL COMMUNICATIONS

6.5 EVACUATION

7.0 REFERENCES

TABLE

Table 1 Key Staff

FIGURE

Figure 1 Site Location and Layout

Figure 2 Project Layout Diagram

APPENDIX

Appendix A Field Team Review Roster

CSPP September 2023 v

ACRONYMS AND ABBREVIATIONS

°F Degrees Fahrenheit

UN-NAMED Un-named Construction Services, LLC.

CSPP Construction Safety Phasing Plan

CTAF Common Traffic Advisory Frequency

FAA Federal Aviation Administration

MHz Megahertz

NOTAM Notice to Airmen

PE Project Engineer

PM Project Manager

QC Quality Control

QCM Quality Control Manager

SS On-Site Superintendent

SPCD Safety Plan Compliance Document

SSHP Site Safety and Health Plan

SSHO Site Safety and Health Officer

USACE U.S. Army Corps of Engineers

CSPP March 2014 6

1.0 EXECUTIVE SUMMARY

Construction Services entered into a contract agreement to construct the FYXX Insert Program, Maks Army Airfield (insert type) Project as part of the ID/IQ Contract with the Army Corps of Engineers. This Task Order was awarded by letter dated Insert Date. In accordance with the plans and specifications for this project, FAA Advisory Circular 150/5370-2F will be followed as applicable.

This Construction Safety Phasing Plan (CSPP) has been prepared in conformance with U.S.

Department of Transportation Federal Aviation Administration (FAA) Advisory Circular 150/5370-2F, “Operational Safety on Airports During Construction”. It addresses airport operational activities during construction, specifically at the Maks Army Airfield.

In order to facilitate the work, this Plan will be developed and approved in Phases. In addition, if circumstances change after approval of the Plan, the CSPP will be changed and approved accordingly.

Compliance with this CSPP is required for all UN-NAMED personnel, third parties, and subcontractors that participate in construction activities. UN-NAMED will exercise the responsibility for implementing this CSPP through the Project Manger; the Site Superintendent;

and the Project Engineer via the Safety Plan Compliance Document (SPCD) provided by UN- NAMED. To that end UN-NAMED will:

1. Submit a SPCD as required.

2. Maintain an approved copy of the CSPP and SPCD in the Site Job Office at all times.

3. Comply with all aspects of the CSPP and SPCD.

4. Designate a Point of Contact who will be available to coordinate immediate response to correct any construction-related safety issues.

5. Provide workers who are familiar with the CSPP and SPCD; and supervisors who will continually monitor construction activity.

6. Restrict movement of construction vehicles by appropriate flags and barricades.

7. Provide escorts as required by regulations.

8. Ensure that no construction personnel enter any Air Operational Areas.

1.1 APPROVALS

The signatures on the approval page at the front of this document, certifies that the PE, PM, and SS have approved the plan for use during construction activities. Addenda or changes will require written approval by the PM and concurrence of The Army Corps of Engineers.

CSPP March 2014 7

1.2 REGULATORY DRIVERS

Key parties for this contract include the US Army Corps of Engineers, FAA, and UN-NAMED.

If a contract modification includes an activity not already addressed in this CSPP, the CSPP will be re-evaluated and revised if necessary to ensure health and safety compliance related to that activity. This will be accomplished before the start of the changed activity.

1.3 PENALTIES

Penalties for non-compliance with airport rules, regulations and this CSPP may result in rescission of driving privileges or access to the AOA. Examples include: entering a movement area without permission or communications with air traffic control; failure to yield the right of way to an aircraft; driving to close to a parked aircraft; taking pictures of the airfield, personnel or equipment.

2.0 INTRODUCTION

The UN-NAMED ID/IQ Contract # 12345 provides a vehicle for the Army to accomplish multiple small-scope construction projects using a single contractor. The contract Task Order that necessitates this CSPP is 34568 with a scope to (Describe work) at the Maks Army Airfield. The Task Order has an anticipated time duration of ? months from DEC 1 to FEB 1.

3.0 HEALTH AND SAFETY PERSONNEL

UN-NAMED shall provide the site health and safety staff for this project in the following table and describe their functions in the following paragraphs.

3.1 PROJECT TEAM KEY STAFF ORGANIZATION

Table 1 identifies key personnel and the key staff positions:

Table 1 Key UN-NAMED Staff

TITLE NAME PHONE COMPANY

Sr. PM Tom 337-531-1234 UN-NAMED

PM Bob UN-NAMED

CQCSM Jane UN-NAMED

SHSO Jones UN-NAMED

SS Smith UN-NAMED

QCM UN-NAMED

Notes:

CSPP March 2014 8

PM = Project Manager

CQCSM =

Contractor Quality Control System Manager

QCM = Quality Control Manager

SS = On-site Superintendent

SHSO = Site Health and Safety Officer

3.2 PROJECT MANAGER

Un-named will be the PM for this project. He has the overall project management responsibility.

Un-named has the responsibility to ensure that the CSPP and SPCD meets or exceeds FAA Advisory Circular 150/5370-2F. He will ensure that adequate resources are provided to the construction staff to carry out their responsibilities as outlined in this CSPP and SPCD. He will also ensure that adequate personnel and equipment resources are available to complete the project safely.

3.3 SITE SUPERINTENDENT

Un-named will be the Site Superintendent for this work. He will ensure that all site work is performed in accordance with contract requirements and in full compliance with the specifications and with this CSPP. The SS is responsible for implementing this CSPP and initiating changes to the SPCD with the concurrence of the PM and Project Engineer (PE). The SS has the authority to stop work if the CSPP or SPCD is compromised. The SS will also serve as the site emergency coordinator. The SS will conduct a daily walk-through of the site to ensure CSPP and SPCD compliance. Any discrepancies noted and corrective actions taken will be documented in a Daily Quality Control (QC) Report, which will be found in the approved Quality Control Plan. He has authority to stop work when it is determined that existing work conditions are unsafe.

3.4 QUALITY CONTROL MANAGER

Un-named will be the Quality Control Manager. He will be responsible for quality control during the project.

3.5 QUALITY CONTROL SYSTEMS MANAGER

Un-named will be the Quality Control Systems Manager for this project. He shall be responsible for overall management of CQC and have the authority to act in all CQC matters for the contractor.

3.6 SITE HEALTH AND SAFETY OFFICER

Un-named will be the designated Health and Safety Officer for the project. He will be responsible to monitor all activities to ensure that all work is accomplished in accordance with the Corps of Engineers Safety Manual.

CSPP March 2014 9

3.7 SITE WORKERS

All site workers must be familiar with and comply with the terms and conditions of this CSPP, SPCD as well as all Airport and Base Safety and Security Regulations. All site workers shall receive site-specific safety training from the airfield safety program manager and sign the CSPP and SPCD Field Team Review Roster before beginning work. All site workers have the responsibility to immediately report any unsafe or potentially hazardous condition to the SS, stop work if an accident or injury is foreseen, and/or correct any work or safety hazard.

In addition, all drivers who will operate vehicles or construction equipment on Maks Army Airfield must pass a Flightline Driving Test prior to being able to operate a vehicle on the Airfield proper.

UN-NAMED will ensure all potential drivers take this test and that records of passing the test are maintained with the airfield operations officer who will issue temporary flightline licenses which shall be maintained on their person while operating on the airfield.

4.0 PROJECT DESCRIPTION AND WORK PLAN

This is a taxiway and parking painting project. Figure 1 shows the location of the work. The Airport will NOT be closed/restricted during construction activity; however, UN-NAMED will have exclusive access to a Work Area designated in Figure 2. To further ensure safety, a portion of Taxiway A will be closed to all Aircraft and Base vehicles for the duration of this work.

Figure 2 also delineates the parts of Taxiway A that will be closed. Airfield operations will issue a NOTAM to announce this closure before construction begins.

The Airport Construction Project will:

1. Install improved.

2. Construct.

3. Repair and reinstall.

Accident prevention activities occur throughout every phase of this project and include inspections and employee training. Anticipated field activities for this project are listed below:

4.1 WORK PHASES

UN-NAMED shall list each phase of work in the SPCD Task Order Work for the Project:

(Examples listed)

Phase I (Covered in SPCD)

Mobilization and setup project office.

Preliminary Safety meetings and orientations.

Pre-construction activities and approval of the SPCD.

CSPP March 2014 10

Notification to FAA

Contractor Geotechnical Soils Testing.

Contractor Environmental Soils Testing

Contractor Utility Identification and Protection Measures

Construction surveying and staking in the project area.

Phase II (Covered in SPCD)

Install Site Control and Delineation Barriers separating Taxiways and Fire Lane.

Establish staging areas, storage, safety, decontamination, and sanitary facilities.

Establish approved stockpile areas.

Establishing material haul routes.

Perform Erosion and pollution control

Erect silt fencing and sediment control features along the runway side of the project, Install Site access and control and spill response features, and

Establish environmental protection features of site work.

Stage spill response and other previously unstaged equipment.

Transportation, receipt, and storage of equipment and supplies.

Begin FOD Control Measures

Clear and grub.

Remove Electrical Taxiway Lighting as required.

Install Storm Drainage

Phase III (Covered in SPCD)

Site Drainage System and Underground Collection Facilities.

Haul, place, and compact subgrade fill materials.

Install Aircraft Anchor Points.

Install Paving, Restripe Existing Taxiway Transitions

Install Striping

Phase IV (Covered in SPCD)

Storm drainage wet vault and infiltration tanks.

Demobilization

Dispose of project wastes, CSPP March 2014 11

Perform post-site activities clean up, and

Transport project equipment offsite.

4.1.1 Notification Of Construction Activities to the FAA

UN-NAMED shall file FAA Form 7460-1 with the FAA per 14 CFR part 77.

4.1.2 Duration of Each Phase

UN-NAMED shall provide the anticipated durations of each phase in the SPCD.

4.1.3 Daily Work Start Time and Finish Time to Include “Night Only” Projects

UN-NAMED shall provide the anticipated daily start and finish work times in the SPCD. Night only projects would still require this entry.

4.1.4 Aircraft Operational Areas Affected by Construction

Taxiway A between the Fire Station and Hanger 4295 will be closed to all base vehicle and aircraft traffic for the duration of the work. An existing 25 foot wide Fire Lane will be delineated and maintained clear during all phases of work.

Existing (Abandoned) Helicopter Landing Pads adjacent to the North side of the project will be closed to air operations for the duration of the project.

4.1.5 NAVAIDS Potentially Affected by Construction

There are no NAVAIDS affected by this work.

4.2 SPECIAL PRECAUTIONS

4.2.1 Runway and Taxiway Marking and Lighting

This is project is outside the Runway Safety Area and will not impact the existing runway or aircraft takeoff or landings.

Taxiway Lighting for Taxiway A, within the Project Site, will be out of service for the duration of work. These lights will be removed and reinstalled at the completion of work.

4.2.2 Protection of Runway and Taxiway Safety Areas (RSAs and TSAs)

UN-NAMED will protect the integrity of all appropriate RSAs and TSAs by means of barricades and Orange Construction Silt Fencing.

UN-NAMED will isolate the Work Site from existing Taxiways using Multi Barrier, Model AR- 10, HDPE Impact-Resistant, Water-Filled, UV Resistant Safety Barricades. These barricades

CSPP March 2014 12 meet the requirements of FAA Circular 150/5370-2F and will be equipped with Red Caution lights. These barriers are shown in Appendix B.

4.2.3 Protection of Obstacle-Free Zones (OFZs), Object-Free Areas (OFAs) and Mandatory Frangibility Zones (MFZs)

This Project will have no impact on Obstacle-Free Zones, Object-Free Areas or Mandatory Frangibility Zones.

4.2.4 Foreign Object Debris (FOD) Control

UN-NAMED will not contribute to FOD contamination of the taxiways. FOD Control will be included in the general training given to all employees on site. Haul Routes within the site, and shown in Figure 2, will be developed to minimize FOD and to keep vehicles and materials as far as possible from existing Taxiways.

The SS and Foremen will continually inspect the work during operations and each Foreman will walk the site each day before ceasing operations.

UN-NAMED shall list within the SPCD equipment on site for control of FOD i.e. tarps for dumpsters, tractor with brush, and scheduled usage.

4.2.5 Wildlife Management

UN-NAMED must carefully control and continuously remove waste or loose materials that might attract wildlife. Contractor personnel must be aware of and avoid construction activities that can create wildlife hazards on airports, such as:

a. Trash. Food scraps must be collected from construction personnel activity.

b. Standing Water.

c. Tall Grass and Seeds. Requirements for turf establishment can be at odds with requirements for wildlife control. Grass seed is attractive to birds. Lower quality seed mixtures can contain seeds of plants (such as clover) that attract larger wildlife. Seeding should comply with the guidance in AC 150/5370-10, Standards for Specifying Construction of Airports, Item T-901, Seeding.

4.2.6 Security Fence Integrity

UN-NAMED shall notify airfield management if the integrity of the security fence will be violated and if so what measures will be taken to maintain security.

4.3 CONSTRUCTION PRECAUTIONS

4.3.1 Traffic Control

This CSPP constitutes the approved Traffic Control Plan for the Task Order. All traffic on the construction site, including construction equipment and support vehicles will be strictly

CSPP March 2014 13 controlled at all times. At no time will any vehicle be allowed to enter any Restricted Area, including the Work Site, without approval, proper two-way communication, and escort.

All UN-NAMED and subcontractor vehicles will be prominently marked to ensure identification.

All Construction vehicles will be inspected daily to ensure all safety features are operational. All vehicles will utilize hazard/warning lights as required by Regulations.

UN-NAMED will control access to and egress from the Construction Zone by means of controlling the entry gate so that no vehicle can enter the site without permission.

As noted in Section 3.6, all drivers operating any type of vehicle in the Work Area will be required to pass a Flightline Driving Test.

4.3.2 Area Delineation

The Construction site will be marked and separated from the remaining airport areas by means of approved (lighted) barricades as noted in Section 4.2.2.

UN-NAMED will inspect the Site Perimeter on a daily basis and maintain positive control of all perimeter barriers.

4.3.3 Special Construction Limitations – PHASE 1

Phase 1 of the Work defines the Site Investigation. The construction barrier system will not be in place during this Phase of work. In Phase 1, three specific work scopes will be accomplished:

1. Geotechnical Crews will excavate Test Pits and Drill Bore Holes for geotechnical evaluation. Drill rigs, which may reach 100 feet into the air, will be on site for 1 Day.

The Testing contractor will use a backhoe to excavate Test Pits. Test Pit work will take two (2) days.

2. Environmental Testing Crews will sample soils. This work will take two (2) days and will require a pick-up truck.

3. Survey Crew will perform a survey of the work area. This work will take three (3) days and will require a pick-up truck.

In order to manage this work, UN-NAMED will do the following:

Ensure Orientation training is conducted prior to accessing the airfield.

Delineate the boundaries and corners of the Work Area using construction cones.

Provide full-time on-site supervision while any aspect of this work is ongoing.

Ensure all vehicle drivers have passed the Maks Airfield Flightline Driving Test.

Ensure that all vehicles and personnel are kept under constant visual control.

Ensure that no one will be allowed to leave the Work Area without escort.

There are no special limitations of construction in Phases 2, 3, or 4 of this contract and the terms of this CSP will govern operations.

CSPP March 2014 14

4.3.4 Stockpile Locations

UN-NAMED shall include approved stockpile locations are designated on attached Figure 2. To avoid dust and FOD, all stockpiles will be covered with plastic at all times when not in continual use.

4.3.5 Hazardous Materials Management (Spill Response)

UN-NAMED shall notify airfield safety of the presence of hazardous materials on the airfield and insure proper procedures are used and applicable documents (SDS) are present at the job site.

Spill response shall be address in UN-NAMEDs SPCD.

4.3.6 Trench and Excavation Identification and Cover

No Trenches are anticipated in any areas other than the Work Site. All trenches on the site will be promptly backfilled and covered, and identified by construction tape if they present a depression of more than 4 inches.

All trenches and excavations in any traffic areas (Work Site Haul Routes) will be covered at the end of each work shift.

4.3.7 Erosion Control

Soil erosion must be controlled to maintain RSA standards, that is, the RSA must be cleared and graded and have no potentially hazardous ruts, humps, depressions, or other surface variations, and capable, under dry conditions, of supporting aircraft rescue and firefighting equipment, and the occasional passage of aircraft without causing structural damage to the aircraft.

4.3.8 Special Inspection Requirements

The Site Superintendent will inspect the work site at the beginning and end of each work shift to ensure compliance with the CSPP and SPCD. UN-NAMED will develop and use a Checklist to facilitate these inspections and this Checklist will be included in the Daily Reports and maintained as part of the contract record.

4.3.9 Utility Location and Protection

The utilities potentially impacted by these operations are electricity for Taxiway A lights on the south side of the project, and an underground electrical power line on the far north side of the project. The Army has performed a Utility-Locate prior to the start work.

All electrical runs will be prominently marked on the surface. Where the location of any utility is unclear, hand-excavations will be performed if there is any danger the excavation will impact the utility.

CSPP March 2014 15

UN-NAMED will note the location of all utility runs on As-Built Drawings.

In the event of an unplanned utility outage, UN-NAMED will immediately contact the Airfield Flight Operations Office and Project Manager, and will begin repair actions as instructed.

4.3.10 Use of Temporary Visual Aids

No Temporary closed runway markers will be required for this project.

5.0 COMMUNICATIONS

5.1 NOTAM ISSUANCE

Only flight operations personnel will issue NOTAMs. UN-NAMED shall keep airfield operations manager updated on the progress of the project to ensure proper notification is given to airfield users through the NOTAM system.

5.2 ACTIVE AND PASSIVE COMMUNICATIONS

UN-NAMED shall provide company communication specifics in the SPCD.

All vehicles and each crew foreman will be equipped with 2-way radio communications, tuned to the approved frequency. The SS will continually monitor the Airport Operational and Emergency Frequencies.

The SS will be monitoring the designated radio frequencies for aircraft at all times during construction activities.

5.3 EMERGENCY NOTIFICATION PROCEDURES

In the event of a Medical Emergency on site, UN-NAMED will exercise the appropriate requirements of the Health and Safety Plan (HASP).

In the event of a non-Medical Emergency, UN-NAMED will stop all work and call a general evacuation of the site. Simultaneously, the SS or PM will notify the Project Engineer, Airfield Safety Office and Control Tower relating the nature of the emergency and the ongoing response.

5.4 EMERGENCY PHONE NUMBERS

UN-NAMED shall use the below table to list applicable emergency phone numbers.

Organization/Personnel Phone Number

Fire/Rescue 911 or 337-531-COPS/2677

CSPP March 2014 16

Airfield Safety Program Manager 337-531-6782

6.0 TRAINING AND RECORD KEEPING

Safety training for this project includes an initial project safety meeting, site-specific safety training, and Daily Safety Tailgate Briefings. The SS or designee will provide and document all training.

6.1 INITIAL SAFETY ORIENTATION

Before beginning field work, employees, subcontractors, and visitors will read the CSPP and SPCD and sign a Team Review Roster. Individuals refusing to sign the agreement may be prohibited from working at the site.

6.2 SITE-SPECIFIC TRAINING

No drivers can operate a vehicle without first passing the Maks Army Airfield Vehicle test as noted in Section 3.3 of this CSPP.

No site workers will be allowed to begin work onsite until the site-specific training is completed and documented by the SS on the CSPP and SPCD Field Team Review Roster, provided as Appendix A. This training will address this CSPP and all health and safety issues and procedures pertinent to site operations. As part of the site-specific training, the following topics will be covered:

Radio Communications

Scope of Work

Vehicle Identification

6.3 SAFETY BRIEFINGS

UN-NAMED shall provide company requirements for safety briefings within the SPCD.

6.4 VISUAL COMMUNICATIONS

Construction equipment will be fitted with an amber strobe and will have two-way radio communication capabilities.

6.5 EVACUATION

UN-NAMED shall provide, in the SPCD, their procedures in the event of an emergency situation where evacuation is required:

CSPP March 2014 17

Sound three blasts with an air horn;

Solicit the aid of the SS, or the nearest employee. Have that individual call for help. Notify the SS, if onsite, and give the exact location of the evacuated area. Direct all personnel in the affected area to evacuate and assemble upwind in a designated safe area;

Establish the safety of all personnel and direct the administration of first aid as appropriate;

Shut down all combustion equipment;

Provide emergency equipment as appropriate; and

Notify SS, or on-site representative.

7.0 REFERENCES

United Facilities Criteria, Airfield and Heliport Planning and Design.

UFC 3-260-01, 17 November 2008, Section 14

Advisory Circular, U.S. Department of Transportation, Federal Aviation Administration.

AC No: 150/5370/2F. Construction Safety Planning.

Airfield Construction Safety Phasing Plan Maks Army Airfield Project Contract No. UN-NAMED Project No.

FIGURE 1

Site Location and Layout

FIGURE 2

Project Location and Layout

APPENDIX A

UN-NAMED Field Team Review Roster

APPENDIX B

Airfield Warning Barrier System

Contract No. UN-NAMED Project No.

CSPP AND SPCD FIELD TEAM REVIEW ROSTER

Each Field Team Member shall sign this section after site-specific training is completed and before being permitted to work on site.

I have read and reviewed the Construction Safety Phasing Plan and the Safety Plan Compliance Document for Maks Army Airfield Parking Apron Construction Project and I understand the information presented. I will comply with the provisions contained therein.

NAME DATE