Attachment 8 - Albany and Cabot Work Hours.pdf

PDF 63 KB Posted

Attached to
RFP 15-26: Albany and Cabot Outdoor Lighting Project
Solicitation number
BD-27-1206-40000-40000-131688
Issued by
Suffolk County, Massachusetts

About this file

This document outlines work-hour requirements for construction activities at two Massachusetts Bay Transportation Authority (MBTA) transit locations: Albany and Cabot. Both sites impose similar restrictions designed to minimize disruption during revenue service hours while accommodating necessary maintenance and construction operations.

For both Albany and Cabot, crane activities, pole demolition and installation, and switchboard work must be completed during non-revenue hours (9:00 PM to 5:00 AM) or weekend hours (9:00 PM Friday through 5:00 AM Monday). Wiring pulling and termination activities are permitted during revenue hours at both locations. Exterior work requires flaggers, whose availability is limited to 5:00 AM to 1:00 AM, with an MBTA Construction Inspector required to be present between 1:00 AM and 5:00 AM. Interior work may be performed during revenue hours without flagger restrictions. The primary distinction between the two sites is minimal; Cabot specifies that switchboard work must occur during weekend nights from 9:00 PM to 5:00 AM, while Albany allows switchboard work during either non-revenue or weekend hours.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Albany Work-Hour Requirements

• Crane activities: All activities involving crane use shall be performed during weekend hours, defined as 9:00 PM Friday through 5:00 AM Monday, or during non-revenue hours (9:00 PM–5:00 AM).

• Pole demolition and installation: Shall be performed during non-revenue hours or weekend hours

• Wiring pulling and termination: All wiring pulling and termination activities can be performed during revenue hours.

• Exterior work: Flaggers are required for all exterior work. Flaggers availability is limited to 5:00 AM–1:00 AM. Between 1 AM to 5 AM MBTA Construction Inspector must always be present.

• Interior work: All interior work may be performed during revenue hours and is not subject to flagger availability.

• Switchboard work: All work within the switchboards shall be performed during non-revenue hours or weekend hours.

Cabot Work-Hour Requirements

• Crane Operations: All activities involving crane use shall be performed during weekend hours, defined as 9:00 PM Friday through 5:00 AM Monday, or during non-revenue hours, (9:00 PM to 5:00 AM).

• Pole Demolition and Installation: Pole demolition and installation shall be performed during non-revenue hours or weekend hours.

• Wiring Pulling and Termination: All wiring pulling and termination activities can be performed during revenue hours.

• Exterior Work / Flaggers: Flaggers are required for all exterior work. Flaggers are available from 5:00 AM to 1:00 AM. Between 1 AM to 5 AM MBTA Construction Inspector must always be present.

• Interior Work: All interior work may be performed during revenue hours and is not subject to flagger availability.

• Switchboard Work: All work within the switchboards shall be performed during weekend nights 9 PM-5 AM.