Attachment 4 - 2026-07-14-Cabot Bus Yard Existing Conditions Narrative and Specs REV1.pdf
PDF 6 MB Posted
- Solicitation number
- BD-27-1206-40000-40000-131688
- Issued by
- Suffolk County, Massachusetts
About this file
This document comprises an Existing Conditions Narrative and two specification sections for the Massachusetts Bay Transportation Authority (MBTA) Outdoor Lighting Improvements project at the Cabot Bus Yard located at 275 Dorchester Avenue in Boston, Massachusetts. The project involves replacing existing outdoor lighting systems and associated duct banks. The memorandum, prepared by VHB and dated July 2, 2026, identifies seven state-listed disposal sites with residual oil and hazardous materials (OHM) contamination within or proximate to the project area, requiring specialized handling procedures. The contractor must submit an Excavated Material Management Plan (EMMP) within 21 days of Notice to Proceed and a Groundwater Management Plan if dewatering is necessary. Excavations are proposed within the disposal site boundary for RTN 3-3096, which is subject to an Activity and Use Limitation (AUL); groundwater is documented at depths of 9 to 20 feet below ground surface and flows in an easterly/southeasterly direction. The contractor must employ an Environmental Consultant including a Licensed Site Professional (LSP) registered with the Massachusetts LSP Board to oversee soil screening, sampling, stockpile management, and documentation throughout the project.
Specification Section 02282 establishes comprehensive requirements for handling, transportation, and disposal of excavated materials, with the MBTA designated as the Generator for all waste streams. The contractor must implement field screening using photoionization detectors (PID) and portable x-ray fluorescence (XRF) for every 20 cubic yards of material excavated, maintain stockpiles segregated by contamination level and covered with nylon-reinforced polyethylene sheeting, and obtain approval before off-site disposal or reuse. Disposal characterization sampling must include analysis for total petroleum hydrocarbons, semivolatile and volatile organic compounds, PCBs, 14 MCP metals, cyanide, sulfide, and TCLP testing where applicable; all laboratories must be certified by the National Environmental Laboratory Accreditation Program. The contractor assumes responsibility for all transportation, manifests, Bills of Lading, and Material Shipping Records, with the MBTA's LSP reviewing and approving all shipping documentation. Specification Section 02283 addresses handling and disposal of contaminated groundwater, requiring a Pre-characterization Sampling Plan within 14 days of a pre-construction workshop and a Groundwater Management Plan within 21 days of pre-characterization testing completion. The contractor must obtain all discharge permits, implement groundwater treatment systems, manage non-aqueous phase liquids and contaminated sediments, and prepare a Health and Safety Plan addressing worker exposure to OHM. All work is included in the Contract Lump Sum Price with no separate payment, and the contractor should assume cost allocation of 50 percent for lined landfill disposal and 50 percent for out-of-state landfill disposal.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Engineers | Scientists | Planners | Designers
260 Arsenal Place #2, Watertown, Massachusetts 02472-4026
P 617.924.1770 F 617.924.2286 www.vhb.com
\\vhb.com\gbl\proj\Wat-TE\16631.02 Outdoor Light Bus
Yards\05_Work\Environmental\SI&R\Design Phase\Existing Conditions Narrative\Cabot Bus Yard
Existing Conditions Narrative_clean.docx
To: Bidders Date: July 2, 2026
Project #: R016631.003
From: Jonathan Harriott, VHB
Matthew Bobkowski, VHB
Re: Existing Conditions Narrative
Outdoor Lighting Improvements - Cabot Bus Yard
Project Overview
The Massachusetts Bay Transportation Authority (MBTA) is proposing to replace the existing outdoor lighting systems and associated duct bank at the Cabot Bus Yard located at 275 Dorchester Avenue in Boston, Massachusetts, hereinafter referred to as the “Project” or the “Project Area.” VHB has prepared this memorandum which summarizes existing environmental conditions at the Cabot Bus Yard, and the prospective Contractor’s Environmental Consultant’s responsibilities pursuant to the Massachusetts Contingency Plan (MCP, 310 CMR 40.0000). This narrative is intended to accompany MBTA Specification Section 02282 – Handling, Transportation, and Disposal of Excavated Materials
(Section 02282), and MBTA Specification Section 02283 – Handling and Disposal of Contaminated Groundwater
(Section 02283). These specifications are included as Appendix A and Appendix B, respectively.
Summary of MassDEP Disposal Site Review
VHB reviewed the Massachusetts Department of Environmental Protection (MassDEP) Bureau of Waste Site Cleanup
(BWSC) online database of Waste Site & Reportable Releases1 to identify known oil and/or hazardous materials (OHM) releases that may potentially impact environmental media within the Project Area. The search was conducted for preliminary screening purposes using only the address/location aid field in the MassDEP database2. The presence of a disposal site indicates that a release of OHM has been reported to MassDEP. VHB has reviewed the disposal site information and provided an opinion as to the likelihood of encountering OHM from these disposal sites during construction of the Project.
Based on VHB’s review, seven state-listed disposal sites associated with residual contamination were identified within the limits of the Project Area. The approximate locations of the disposal sites where residual contamination is present are depicted on Figures 1 and 2. The disposal sites are described by Release Tracking Number (RTN) below. Disposal site maps obtained from MassDEP files are provided in Appendix D.
› Cabot Bus Garage, RTNs 3-3096 & 3-19247, Within the Project Area
In 1991, RTN 3-3096 was assigned due to the identification of light non-aqueous phase liquid (i.e., separate phase petroleum product) that had released from three 12,000-gallon diesel underground storage tanks (USTs) at the
Cabot Bus Garage. In February 2000, free petroleum product was observed at a pumping station at the above-referenced property and secondary RTN 3-19247 was assigned to the release condition. RTN 3-19247 was linked to primary RTN 3-3096 and all response actions were conducted under the primary RTN. Following response actions, in June 2025, a Permanent Solution with Conditions (PSC) Statement was submitted for the disposal site, indicating that an Activity and Use Limitation (AUL) was required in order to maintain a condition of No Significant Risk.
Depth to groundwater reportedly ranges from approximately 9 to 20 feet below ground surface at the disposal site
1 MassDEP, Search for Waste Site & Reportable Releases, Accessed at: https://eeaonline.eea.state.ma.us/portal/dep/wastesite/ 2 Disposal site location information was determined using the MassDEP database and online mapping services, which may not always be accurate http://www.vhb.com/
Ref: R016631.003
July 2, 2026 and has been documented to flow in an easterly/southeasterly direction. Based on MassDEP documentation reviewed, residual separate phase product and elevated concentrations of petroleum-related constituents remain in soil and groundwater at the disposal site. Petroleum impacts to soil have generally been encountered just above the groundwater interface, between 9 and 22 feet below ground surface. Based on the most recent gauging data presented in the PSC Statement, separate phase product was detected at thicknesses ranging between 0.01 and
0.03 feet in the final round of gauging in January 2020.
Based on the Project design plans as of June 14, 2026, subsurface excavations associated with the installation of light pole, connecting duct bank, and the removal of an adjacent existing light pole are planned within the disposal site boundary. Additionally, the LP3 installation is located within the AUL area. The AUL limits with approximate overlays of the design demolition and layout plans are depicted on Figures 3 and 4. A copy of the AUL is included as Appendix C, which details obligations and restrictions for conducting work within the AUL area.
Based on groundwater gauging data presented in the July 2025 PSC Statement, groundwater is present at approximately 9 to 14 feet below ground surface in the vicinity of the LP1 and LP2 excavation, and between 16 and
18 feet below grade near the LP3 installation. Therefore, depending on planned Project excavation depths, petroleum-impacted groundwater may be encountered.
› Cabot Yard MBTA, 275 Dorchester Avenue, RTN 3-34247, Approximately 100 Feet from the Project Area
In May 2017, elevated concentrations of lead and 2-methylnaphthalene were detected in soil at the disposal site during the replacement of a fuel dispenser within the Cabot Bus Garage and RTN 3-34247 was assigned to the disposal site. The concentrations of contaminants in soil were attributed to the presence of historical fill, and no response actions were performed. In May 2018, a Permanent Solution with Conditions was submitted for the disposal site indicating that a Condition of No Significant Risk was achieved without the implementation of an AUL
(i.e., deed restriction) due to the presence of contaminants in soil attributed to the presence of historical fill.
Groundwater was reportedly not impacted. The PSC requires the maintenance of a 12-inch cover of clean material or asphalt over historical fill soils, and the use of clean, imported soils for backfilling new utility excavations.
Due to the location of the disposal site in relation to the Project Area, this disposal site has likely impacted environmental conditions within the Project Area.
› Cabot RTL, 275 Dorchester Avenue, RTN 3-34777, Approximately 100 Feet from the Project Area
RTN 3-34777 was assigned in February 2018 following the identification of elevated concentrations of polychlorinated biphenyls (PCBs) in soils at the Cabot Bus Yard. The source of PCBs was attributed to PCB-containing caulk used in the construction of the Cabot Maintenance Facility located in the railyard portion of the property. The release has not achieved regulatory closure as response actions are ongoing in accordance with the
Toxic Substances Control Act (TSCA). While the current disposal site boundary does not encroach upon the Project
Area, due to the proximity of the disposal site relative to the Project Area, and its active regulatory status, there is the potential for this release to have affected environmental conditions within the Project Area.
› MBTA Cabot Yard, 275 Dorchester Avenue, RTN 3-35842, Approximately 100 Feet from the Project Area
During subsurface investigations, elevated levels of metals, polycyclic aromatic hydrocarbons (PAHs), pesticides, and petroleum-related constituents were encountered in soil, and RTN 3-35842 was assigned to the release in
September 2019. Response actions conducted to date at the disposal site have included the removal and off-site disposal of approximately 4,500 tons of impacted soil to facilitate construction. Based on the latest MCP reports, impacts to soil have been identified at depths between approximately 0 and 12 feet below ground surface.
Response actions are ongoing.
Due to the proximity of the disposal site to the Project Area, and documented historical filling across the Cabot Bus
Yard property, there is the potential for similar urban fill impacts to be encountered within the Project Area.
› MBTA Cabot Yard, 275 Dorchester Avenue, RTN 3-36678, Approximately 50 Feet from the Project Area
During subsurface investigations in support of the installation of a utility corridor, elevated levels of metals, PAHs, and petroleum hydrocarbons were encountered in soil. RTN 3-36678 was assigned to the disposal site in December
2020. Elevated concentrations of petroleum hydrocarbons and PAHs were detected in groundwater in excess of the applicable MCP Method 1 GW-2 standards. Response actions conducted to date at the disposal site have included the removal and off-site disposal of impacted soil and the dewatering, treatment, and discharge of groundwater under an industrial wastewater discharge permit to facilitate construction. Based on the latest MCP reports, historical fill has been observed from ground surface to depths ranging between 10 and 18 feet below ground surface. Response actions are ongoing.
Due to the proximity of the disposal site to the Project Area, and documented historical filling across the Cabot Bus
Yard property, there is the potential for similar urban fill impacts to be encountered within the Project Area.
› MBTA Cabot Yard, 275 Dorchester Avenue, RTN 3-22679, Approximately 50 Feet from the Project Area
In October 2002, during the sampling of soil generated in support of construction at the Cabot Bus Yard, PAHs and lead were detected in soil in excess of the applicable MCP Reportable Concentrations. RTN 3-22679 was assigned to the disposal site in March 2003. Additional subsurface investigations at the disposal site identified cinders, asphalt, ash, brick and glass in the soil from within the area of generation. Concentrations of PAHs and lead in soil were attributed to historical urban filling. In November 2003, a Class A-2 Response Action Outcome (RAO)
Statement was submitted for the disposal site indicating a condition of No Significant Risk was achieved, yet concentrations were not reduced to background.
Due to the proximity of the disposal site to the Project Area, and documented historical filling across the Cabot Bus
Yard property, there is the potential for similar urban fill impacts to be encountered within the Project Area.
Findings and Additional Considerations for Construction
In summary, the preliminary screening of the MassDEP database indicated that seven state-listed disposal sites are present within or in close proximity to the Project Area, all of which have resulted in residual impacts to soil and in some cases, groundwater.
Based on the above-noted findings and nature of the Project, VHB provides the following considerations for the
Contractor and their Environmental Consultant:
› Excavations associated with the removal and installation of light pole foundations and duct bank are proposed within the disposal site boundary for RTN 3-3096. Additionally, the excavation areas are located within the vicinity of several MassDEP disposal sites associated with RTNs 3-34247, 3-35842, 3-22679 and 3-36678. Constituents of concern associated with these disposal sites include metals, PAHs, petroleum hydrocarbons, and pesticides. Across the disposal sites, urban fill was encountered from ground surface to 18 feet below existing grade, which is likely to be encountered during Project excavations.
› VHB understands the Contractor will provide an Excavated Material Management Plan (EMMP) as required under
Specification Section 02282. If dewatering is deemed necessary by the Contractor to facilitate the Project, the
Contractor shall also submit a Groundwater Management Plan in accordance with Project Specification Item
Section 02283.
› Excavations associated with the removal and installation of light pole foundations and duct bank are proposed within the disposal site boundary for RTN 3-3096, with some work proposed within the portion of the disposal site subject to an AUL. A copy of the AUL, detailing the obligations for utility construction within the AUL, is included as
Appendix C. Remediation Waste in excess of 20 cubic yards and Remedial Wastewater generated from within the disposal site boundaries shall be managed under a Release Abatement Measure (RAM) Plan or Utility-related
Abatement Measure (URAM) under the supervision of a Licensed Site Professional (LSP). Furthermore, if the
Contractor determines that excavations will extend beyond nine (9) feet below grade within the AUL area, the preparation of a Soil/LNAPL Management Plan is required in addition to the Project EMMP.
› Due to the presence of RTN 3-3096 and RTN 3-34247 within the Project Area, Remediation Waste in excess of 20 cubic yards and Remedial Wastewater generated from within the disposal site boundaries shall be managed under a RAM Plan or URAM under the supervision of a LSP.
› This memorandum summarizes preliminary information pertaining to OHM concerns associated with the Project and is not intended to serve as a comprehensive assessment. The selected Contractor and their Environmental
Consultant may need to conduct supplemental assessments to facilitate the development of soil and/or groundwater management and disposal procedures.
Attachments: Figure 1 – AUL Location Plan – Demolition Plan Overlay
Figure 2 - AUL Location Plan – Layout Plan Overlay
Figure 3 – Site Plan – Demolition Plan Overlay
Figure 4 - Site Plan – Layout Plan Overlay
Appendix A – Section 02282: Handling, Transportation and Disposal of Excavated Materials
Appendix B – Section 02283: Handling and Disposal of Contaminated Groundwater
Appendix C – Notice of AUL for RTN 3-3096
Appendix D – MassDEP Disposal Site Figures
CABOT HANDLING, TRANSPORTATION AND DISPOSAL 100% SUBMITTAL
2026 OF EXCAVATED MATERIALS REV 05/15; DESIGNER REV 07/02/2026
02282 - 1
SECTION 02282
HANDLING, TRANSPORTATION AND DISPOSAL OF EXCAVATED MATERIALS
PART 1 - GENERAL
1.1 DESCRIPTION OF WORK
A. Work Included: This Section specifies the procedures used for field screening; soil sampling, stockpile management, reuse, transportation and disposal of excavated materials.
B. This section includes furnishing all plant, labor, equipment, appliances and materials, and performing all operations in connection with the handling, testing, treating, stockpiling, transporting and disposal and/or re-use of soil (defined hereinafter as including sediments for the purposes of this Section) and associated fill and waste material resulting from the construction operations as specified.
C. Related Work: The following items are not included in this Section and will be performed under but may not be limited to the following designated Sections:
1. Section 02283 – HANDLING AND DISPOSAL OF CONTAMINATED GROUNDWATER
D. For the purpose of this section the Authority will be the Generator and will sign all disposal facility waste profiles, Hazardous Waste Manifests (manifest), Material Shipping Records (MSR) and
Massachusetts Contingency Plan (MCP) Bills of Lading (BOLs) as the Generator. The Contractor’s
Licensed Site Professional (LSP) will sign all BOL as the LSP and MSRs as the Environmental
Professional, following review and approval by the Authority’s LSP. Except for soil that requires transport under a manifest, all soil shall be transported under BOL or MSR whichever is applicable, based on the results of the laboratory chemical analysis of soils. All paperwork required for work under this Section shall be prepared by the Contractor.
E. Furnish all labor, materials, equipment, and incidentals necessary to properly, sample, segregate, handle/manage, load, transport and dispose of excavated materials located from within the Limit of
Work. Work covered by this Section shall include furnishing, operating, and maintaining soil stockpile/staging areas and equipment decontamination stations for the duration of excavation activities and dismantling, disposing of decontamination stations and stockpile/staging areas at project completion. Decontamination stations shall be capable of eliminating the dispersion of dust and mud caused by vehicles exiting the site.
F. The objective of the soil management practices is to handle all soil and fill excavated during this contract in accordance with applicable state, federal and local regulations and bylaws and to implement off-site soil management in a cost-effective manner.
To the extent possible, the Contractor shall reuse geotechnically suitable excavated material prior to using imported backfill to reduce the volume of material to be disposed.
1.2 RESPONSIBILITIES
A. The Contractor shall employ the services of an Environmental Consultant to assist in the activities listed below. Contractor’s Responsibilities:
02282 - 2
1. The Contractor shall employ the services of an Environmental Consultant to perform the soil screening, soil sampling, dust control measures, management coordination and support compliance efforts associated with all references listed in this Section. The Environmental
Consultant shall include at least one professional experienced in soil sampling and dust control measures and a Licensed Site Professional (LSP) registered with the Massachusetts LSP Board.
Proof of current licensure and professional experience on projects of similar nature and complexity shall be provided to the Engineer with the Excavated Materials Management Plan
(EMMP) and/or MCP deliverable, whichever is appropriate.
2. The Contractor and/or the Contractor’s Environmental Consultant shall develop a field-screening program, as detailed in Section 3.2, to include the following:
a. Screening of excavated material for the presence of volatile organic compounds (VOCs) with a photo ionization detector (PID). As directed by the Engineer, samples representative of each 20 cubic yards of material excavated shall be screened.
b. The Contractor shall, as deemed appropriate by the Contractor’s LSP and the Engineer, utilize portable x-ray fluorescence (XRF) for initial soil screening and segregation purposes.
3. The Contractor and/or the Contractor’s Environmental Consultant shall be responsible for submitting to the Engineer the daily logs summarizing field screening and excavating activities.
4. The Contractor shall identify and propose locations for construction staging of both on or offsite temporary soil stockpiles and miscellaneous materials, soil/waste treatment technologies and treatment areas (on-site or offsite), disposal, recycling and treatment facilities, facilities for the beneficial re-use of excavated materials including but not limited to soil, debris, or other miscellaneous materials, temporary storage facilities, landfills, soil recycling and hazardous waste treatment, storage and disposal facilities for all excavated material.
5. The Contractor shall be responsible for transporting excavated material to the approved construction storage location/stockpile area and, disposal, recycling, treatment facilities and facilities for beneficial re-use.
6. The Contractor shall furnish, operate and maintain equipment decontamination stations for the duration of excavation and soil disposal work.
7. The Contractor shall develop and implement site-specific emergency response and health and safety protocols and procedures.
8. For each shipment of material transported to a disposal facility, the Contractor shall demonstrate to the Engineer that the least costly means of disposal has been selected. This demonstration shall be made prior to shipment.
9. The Contractor and/or the Contractor’s Environmental Consultant shall prepare the necessary documents to transport and dispose of excavated material. These documents include, but are not limited to waste profiles, Bills of Lading, MSR and manifests. The Contractor and the
Contractor’s LSP shall be responsible for submitting these completed documents to the
Engineer within two weeks of shipment to a storage or disposal/recycling facility. The
Contractor and the Contractor’s LSP are responsible for up-loading these BOLs onto the
MassDEP electronic filing system (eDEP). The Contractor’s LSP will sign and stamp BOLs.
The receiving facility shall provide electronic attestation of receipt of soils within 5 days of receiving notification from the LSP of the availability of the BOL for that purpose on eDEP.
10. In addition to the submittals detailed above, the Contractor and/or the Contractor’s
Environmental Consultant shall prepare, sign, and submit all construction-related MCP deliverables.
02282 - 3
11. The Contractor shall advise the Engineer at least three working days in advance of the schedule for off-site disposal of excavated material. No off-site shipments or on-site re-use will occur without the approval of the Engineer.
12. The Contractor and/or the Contractor’s Environmental Consultant shall advise the Engineer at least three working days in advance of the collection of soil samples and any other environmental sampling. The Contractor and/or the Contractor’s Environmental Consultant shall collect, analyze and characterize samples of excavated material prior to off-site recycling and/or disposal.
13. The Contractor shall submit the executed transportation and disposal documents to the appropriate local, state and federal agencies as well as the Engineer.
14. The Contractor shall provide an environmental field technician to oversee the loading of excavated material into transport vehicles for off-site disposal/recycling.
15. The Contractor shall develop an excavated soil tracking/management system and keep records, including daily logs and photographs, of all waste streams, stockpiles, and excavated materials for the purposes of tracking points of origin and final disposition.
16. The Contractor shall develop and implement dust control measures in conjunction with a health and safety plan which addresses oil and/or hazardous materials (OHM), if present in soil and/or groundwater.
B. Authority's Responsibilities:
1. The Authority will review and approve the proposed facilities selection of off-site recycling, reuse or disposal facilities.
2. The Authority will be the designated Generator for excavated material identified for off-site reuse, recycling and/or disposal.
3. The Authority will review and approve all paperwork, manifests, and Bills of Lading prior to soil disposal.
4. The Authority’s LSP will review and approve all shipping documentation and MCP deliverables prior to submittal by the Contractor and/or the Contractor’s Environmental Consultant.
1.3 QUALITY ASSURANCE QUALITY CONTROL
A. The Contractor and/or the Contractor’s Environmental Consultant shall be responsible for the collection and analysis of soil samples from all areas of the site. Sampling frequency and selection of laboratory analytical methods shall be conducted as to meet the requirements of the disposal facility.
The analysis and analytical documentation shall meet the MassDEP Compendium of Analytical
Methods requirements. The Contractor and/or the Contractor’s Environmental Consultant shall include the result of all soil testing in the Excavated Materials Management Plan and/or MCP deliverable in accordance with Section 1.4 Submittals.
1.4 SUBMITTALS
A. The Contractor and/or the Contractor’s Environmental Consultant shall prepare the necessary documentation, which may include an EMMP or appropriate MCP deliverable (e.g., Release
Abatement Measure Plan) that describes the work to be performed under this Specification. The
EMMP and/or MCP deliverable shall be submitted to the Authority within 21 days after the issuance of the Notice to Proceed. The EMMP and/or MCP deliverable shall be accepted by the Authority
02282 - 4 before excavated soil is disposed of off-site or re-used. At a minimum, the EMMP and/or MCP deliverable shall address the following:
1. The Plan shall include the current licensure of the Contractor’s LSP and proof of relevant experience of the field personnel.
2. A schedule detailing the proposed sequence of work.
3. A soil reuse strategy detailing the Contractor’s plan to maximize reuse of existing soils within the Project Limits (i.e. timing/sequencing of soil movement, approximate volumes, transportation methods, etc.).
4. Procedures that shall be used for field screening of the excavated soils, in accordance with
Section 3.2 Field Screening of Excavated Material.
5. Procedures for the collection of soil samples for laboratory chemical analysis. The plan shall list the proposed laboratory analytical parameters, in accordance with Section 3.3 Disposal
Characterization Sampling.
6. A detailed site plan (in accordance with Section 3.4 Temporary Stockpiling of Excavated
Materials) indicating the construction staging/stockpile area as it relates to the active construction area. The detailed site plan shall show the potential layout of the staging area as it relates to the stockpile soil, debris and/or miscellaneous materials and construction materials.
For off -site staging areas, the plan shall include the location name, address and any other pertinent information.
7. In addition to the EMMP and/or MCP deliverable, a material management system plan to track the excavated materials from generation through final disposition is also required. Plan shall include at a minimum the following:
a. Provisions for the tracking of the excavated materials from the “point of excavation” to the location of the stockpile material in the storage/staging area to the final disposition of the stockpiled material including all proposed daily log sheets.
b. A description of the tracking methodology that shall be implemented to identify the source excavation area(s) and the final disposition of the excavated soil from each area of excavation which.
c. A description of the location (i.e. station, offset) depth, date of excavation, stockpile location and stockpile identification system.
d. Drawings of the area of excavation and shall document the origins of each soil stockpile and its location within temporary storage area.
e. The plan shall be maintained to show the location of all excavated material that has been stockpiled on a daily basis.
f. Furnish a duplicate copy of the stockpile plan to be located in the field office and updated on a weekly basis or as needed.
g. Provide to the Engineer at a minimum on a weekly basis or as needed copies of field records documenting the location of the stockpiled material in the system and stockpile identification data.
h. The plan shall include an Equipment Vehicle decontamination Plan.
8. The means and methods for decontaminating all equipment and personnel, including provisions for installing equipment decontamination pad within the work zone and a plan for decontamination waste disposal.
9. The means and method for on-site treatment of excavated soil determined through toxicity characteristic leaching procedure (TCLP) analysis to be characteristically hazardous pursuant to the Massachusetts Hazardous Waste Regulations (310 CMR 30.00) and RCRA (40 CFR 260 et.
seq.). Treatment may be conducted pursuant to the MassDEP Technical Update –
02282 - 5
Considerations for Managing Contaminated Soil: RCRA Land Disposal Restrictions and
Contained-In Determinations. If required, the Contractor and/or the Contractor’s
Environmental Consultant shall prepare appropriate MCP deliverables to facilitate on-site treatment, pursuant to 310 CMR 40.0046(3).
10. All pertinent information relating to the transport of excavated material. The information, at a minimum, shall include:
a. Name and address of all transporters.
b. Transporter identification number (USEPA or Massachusetts Department of
Transportation Transporter) and expiration date.
c. Proof of permit, license, or authorization to transport excavated material in all affected states.
d. Details of methods, vehicle and containers (as applicable) to be used for transporting excavated material. Refer to Part 2 of this Section.
e. Dust control measures
f. On-site pre-treatment of excavated soil unsuitable for re-use.
11. The Contractor shall identify each waste stream and propose an appropriate disposal facility that will accept the excavated material as classified. The Contractor shall submit approvals or letters of intent and facility information for each facility proposed. For each facility, the
Contractor shall submit the following information:
a. General Information
1) Facility Name
2) Facility Address
3) Name of Contract Person
4) Title of Contact Person
5) Telephone Number of Contact Person
6) Permit Number
b. The facility shall specify the volume of material that can be accepted from the site on a weekly and a total basis.
c. The facility shall provide written confirmation that they are permitted to accept and will accept the classified material of the general quality and quantity described by these
Specifications.
d. The facility shall provide a listing of all current and valid permits, licenses, letters of approval, and other authorizations to operate that they hold, pertaining to the receipt and management of the soils or materials specified in this contract.
e. The Contractor shall submit a complete list of the disposal facility’s permitted allowable contaminant levels and physical characteristic requirements for excavated material, and list any required regulatory approvals for individual waste streams.
12. The documents shall be amended as necessary.
B. Laboratory results for all samples collected and/or analyzed by the Contractor and the Contractor’s
Environmental Consultant shall be tabulated and compared to applicable MCP standards by the
Contractor’s Environmental Consultant and subsequently submitted to the Engineer within two days of receipt. The results shall include all Chain-of-Custody forms and all documentation provided by the laboratory.
C. The Contractor and/or the Contractor’s Environmental Consultant shall submit soil disposal documentation, as detailed herein.
1. Pre-disposal documentation shall be prepared and submitted prior to disposal. Each documentation submittal shall be assigned a unique identification referenced to the stockpile or sample name.
02282 - 6
a. Completed MSR, BOL, or manifest signed by the Authority and the Contractor’s LSP as required, following review and approval by the Authority’s LSP.
b. Completed and signed profiles as required by the receiving facility
c. Analytical data report provided by the analytical laboratory
d. Sketch plan showing sampling location
e. Summary of soil source location; site history; sampling methods and data comparison to facility criteria and MCP reporting criteria
f. LSP narrative and opinion regarding the representativeness of the sampling method, usability of the analytical data, certification regarding the presence or absence of RCRA listed or characteristic waste and suitability for onsite reuse or off-site reuse at the intended facility.
g. Receiving facility –required checklist or requirements
2. Post disposal documentation shall be prepared and submitted following disposal and referenced to the pre-disposal documentation by name
a. Load sheets completed and signed by the hauler and the receiving facility
b. Certified weight slips from the receiving facility
c. For BOLs only, the facility and Authority attestations of shipment and receipt.
3. All soil disposal documentation shall be compiled and re-submitted at the completion of the disposal activities. The submittal shall consist of one or more PDF-Searchable electronic files contained on a CD. The final submittal shall be organized by the uniquely identified MSR, BOL, or manifest.
D. In addition to the submittals detailed above, the Contractor and/or the Contractor’s Environmental
Consultant shall prepare, sign, and submit all construction-related MCP deliverables, following review and approval by the Authority’s LSP.
E. All elements of the submittals detailed above shall submitted as a final close-out document within 4 weeks after of the completion of all excavation and disposal activities. The final submittal shall consist of one or more PDF-searchable electronic files on a CD. Previous submittals of one or more of the elements described herein or previous eDEP filings shall not modify the requirements of the final submittal. The final submittal shall contain the supporting documentation identified in 1.4 (A) through (C).
F. The Contractor shall submit their air quality monitoring program for review prior to commencement of site activities in conjunction with a health and safety plan which addresses OHM, if present in soil and/or groundwater.
1.5 REFERENCES
A. All regulations cited and those of other governing agencies in their most recent version are applicable.
This Section refers to many requirements found in these references, but in no way is intended to cite or reiterate all provisions therein or elsewhere. It is the Contractor's responsibility to know, understand, and abide by all such regulations and common practices. The Contractor shall be responsible for adhering to regulations, specifications, and recognized standard practices related to soil management and disposal during excavation activities. The Authority will not be responsible at any time for the Contractor’s violation of pertinent state or federal regulations or endangerment of laborers and others. Other provisions contained in these references may from time to time during the execution of this Contract be enforced by the Engineer. In the event of a conflict, the most stringent regulations shall govern. The following documents and/or publications are made part of this Section by reference herein:
1. Massachusetts Contingency Plan (MCP), 310 CMR 40.0000.
02282 - 7
2. Massachusetts Hazardous Waste Regulations, 310 CMR 30.000.
3. Massachusetts Solid Waste Management Facility Regulations, 310 CMR 19.000.
4. Massachusetts Site Assignment Regulation for Solid Waste Facilities, 310 CMR 16.00.
5. Interim Remediation Waste Management Policy for Petroleum Contaminated Soils, MassDEP
WSC-94-400.
6. “Hazardous Waste Operations and Emergency Response”, Federal Occupational Safety and
Health Act (OSHA), 29 CFR 1910.120.
7. “General Regulations for Hazardous Waste Management”, EPA, 40 CFR 260.
8. “Regulations for Identifying Hazardous Waste, Hazardous Waste Generators and Hazardous
Waste Transporters”, EPA, 40 CFR 261, 262 and 263.
9. “Standards for Management of Specific Hazardous Wastes and Facilities”, EPA, 40 CFR 266.
10. “Construction of Buildings in Contaminated Areas,” MassDEP #WSC-00-425.
11. Reuse and Disposal of Contaminated Soil at Massachusetts Landfills, MassDEP Policy
#COMM-97-001.
12. Local regulations governing dust control, soil handling, and health & safety.
13. Compendium of Quality Assurance and Quality Control Requirements and Performance
Standards (CAM), MassDEP WSC #02-320.
14. MassDEP Technical Update Background Levels of Polycyclic Aromatic Hydrocarbons and metals in soils.
15. MassDEP Technical Update Considerations for Managing Contaminated Soil: RCRA Land
Disposal Restrictions and Contained-In Determinations.
16. Similar Soils Provision Guidance, MassDEP WSC#13-500.
17. MassDEP Draft Technical Update Historic Fill/Anthropogenic Background.
18. MassDEP Policy # COMM-15-01 - Interim Policy on the Re-Use of Soil for Large Reclamation
Projects.
19. Interim Remediation Waste management Policy for Petroleum Contaminated Soils Attachment
II, Jar headspace analytical Screening Procedure. MassDEP Policy no. WSC-94-900.
20. MassDEP Policy WSC#-13-500, “Similar Soils Provision Guidance,” dated September 4, 2014.
21. All other applicable Federal, State, or local requirements.
1.6 DEFINITIONS
A. Area of Excavation: For the purpose of reusing soil/fill on site the limit of excavation is considered to be the approximate area in which the soil/fill was removed provided that area is consistent in soil strata, color, texture, geotechnical properties and has substantially similar visual and olfactory characteristic as accepted by the Authority’s Engineer. Soil/fill returned to the limit of excavation shall be placed approximately in the same location from which it originated.
B. Background: Any soil or fill material which meets the regulatory definition of “background” as defined in 310 CMR 40.0006 and meets the requirements of applicable regulatory guidance such as
Similar Soils Provision Guidance, MassDEP WSC#13-500 may be reused as common fill/ordinary borrow provided it also meets the physical requirements as specified herein and as specified in Section
02210 – Earth Excavation, Backfill and Grading or the environmental requirements as specified in
02282 - 8
Section 3.6. Excess soil that meets the definition of background shall be transported under an MSR or
BOL.
C. Contaminated Material/Soil: Any excavated material found to contain oil or hazardous material
(OHM) at concentrations in excess of applicable MCP Reportable Concentrations as specified at 310
CMR 40.0361 or regulated background levels (as defined in the MassDEP Technical Update
Background Levels of Polycyclic Aromatic Hydrocarbons and Metals in Soil, the Draft MassDEP
Historic Fill/Anthropogenic Background Technical Update, and 310 CMR 40.0006) or other applicable State or Federal Regulations.
D. Excavated Material: All soil, sediment and/or debris excavated from within the Limit of Excavation.
E. Generator: The Authority will be the generator, with the exception of materials contaminated by releases from the Contractor’s vehicles, equipment or supplies.
F. Hazardous Material/Waste: A waste/material or combination of waste/material, that because of its quantity, concentration, physical chemical or infectious characteristics may cause or significantly contribute to an increase in a serious irreversible or incapacitating reversible illness, or pose a substantial present or potential hazard to human health or the environment when improperly treated, stored, transported, disposed of or otherwise managed. This definition also includes but is not limited to materials regulated under the Toxic Substances Control Act (TSCA, 40 CFR 700-766), M.G.L. Chapter 21E, the Massachusetts Hazardous Waste Regulations (310 CMR 30.00), and the
MCP (310 CMR 40.0000) and any additional applicable state or federal regulations. Where applicable, consideration shall be given to MSDS in determining if a material could be potentially hazardous.
G. Historic Fill: As specified at 310 CMR 40.0006, historic fill was emplaced prior to January 1983 and may contain construction and demolition debris, reworked or dredged soils, coal and wood ash, or other solid waste. The fill may have been contaminated with metals, petroleum, and/or polycyclic aromatic hydrocarbons (PAHs) prior to its emplacement. This definition does not include soil or fill that contains oil or hazardous materials originating from operations at the location of emplacement.
Soil or fill containing chemical production waste, manufacturing waste, or waste material disposed in a municipal solid dump is excluded from this definition.
H. Natural soils: Unconsolidated sand gravel silt clay and organic material that originated at the location at which it was generated and was not previously disturbed.
I. Non-RCRA Waste: Any solid waste that is determined not to be hazardous waste and that exist in such quantities or in such chemical or physical state or any combination thereof so that a particular management controls are required to prevent an adverse impact from the collection, transport, transfer storage processing, treatment or disposal of the solid waste.
J. Stockpiled Materials: Any excavated soil/fill and/or debris (which include Asphalt Pavement, Brick, and Concrete [ABC] material or other construction/demolition waste) which are stored prior to re-use, disposal, recycling or treatment.
1.7 PERMIT REQUIREMENTS
A. The Contractor shall obtain all Federal, State, and local permits required for the transport and disposal of excavated material. The Contractor shall adhere to all permit requirements.
02282 - 9
B. The Contractor shall verify that the disposal facilities, recycling/treatment facilities proposed have all certifications and permits as required by Federal, State, and local regulatory agencies to receive and dispose of the excavated material.
C. The Contractor shall submit and/or amend all documentation of the permit requirements as stated in this subsection in accordance to the requirements of the EMMP and/or MCP deliverable (Section 1.4).
PART 2 - PRODUCTS
2.1 GENERAL
A. All Contractor personnel shall wear personal protective equipment and protective clothing consistent with the levels of protection for this Work.
B. The containers must be approved by and labeled in accordance with the US Department of
Transportation (DOT). The containers shall have a secure cover which will prevent a release of material from truck during transportation.
2.2 STORAGE LABELS
A. Provide signage to label all stockpiles. Labels shall be of 6-inch by 12-inch weatherproof material, such as plastic, affixed to 1" x 3" wood straps, 3 feet long. The labels shall be clearly marked with indelible ink marker. Markings shall be as agreed upon between Authority and Contractor.
2.3 STOCKPILE SHEETING
A. Stockpile Sheeting: Provide nylon-reinforced polyethylene (NRPE) sheeting as follows:
1. The membrane shall be manufactured of new, first quality product designed and manufactured specifically for the intended use.
2. The material shall be 10-mil polyethylene reinforced with a non-woven grid of high strength nylon cord.
3. The material shall be ultra-violet resistant and cold crack resistant to -40 degrees F.
4. The materials shall be manufactured in a minimum 12 foot seamless width. Labels on the roll shall identify the thickness, length width and manufacturer’s mark number.
2.4 AIR MONITORING EQUIPMENT
A. The Contractor and/or the Contractor’s Environmental Consultant shall conduct air monitoring and supply the appropriate air monitoring equipment. Procedures and equipment are to be outlined in the health and safety plan, EMMP, and/or appropriate MCP deliverable(s) and shall be dependent upon contaminants of concern and the associated concentrations, if present in soil and/or groundwater. Air monitoring is discussed further in Section 3.8.
02282 - 10
2.5 EQUIPMENTAND VEHICLE DECONTAMINATION PAD
A. A decontamination pad shall be constructed of reinforced concrete or bituminous concrete to withstand an H-20 loading. The decontamination pad shall be of minimum length to accommodate one 18-wheel dump truck, and a minimum area to accommodate the largest piece of equipment to be used in the excavation. The pad shall have a six inch containment berm and provisions for collection, storage and disposal of decontamination waste. Decontamination shall be performed by properly trained and certified staff provided by the Contractor. The Contractor shall construct and demolish the decontamination pad as part of the lump sum price.
PART 3 - EXECUTION
3.1 GENERAL
A. The Contractor shall handle and convey all materials to perform site work described in these Contract documents.
B. The Contractor shall perform any additional disposal characterization sampling and analytical testing of the excavated material as required by the permitted disposal facility at no additional cost to the
Authority.
C. Based upon all analytical results, the Contractor shall transport and dispose of the excavated material as specified herein.
The Contractor’s Environmental Contractor shall provide an LSP Opinion for all material shipped using a BOL or for off-site re-use of excavated materials.
D. Materials generated during construction must be managed and disposed in accordance with the
EMMP and/or MCP deliverable or other similar regulatory documents pursuant to 310 CMR 40.0000, to be provided to the Contractor by the Authority. Procedures to be included in these documents may be provided or developed by the Contractor.
E. The Engineer shall have final approval over all disposal options.
F. Immediately notify the Engineer of visible stains or unnatural odor of any excavated material, or if potentially contaminated and/or hazardous material including asbestos piping is encountered. Work shall not be allowed to continue in this area until approved by the Engineer.
3.2 FIELD SCREENING EXCAVATED MATERIAL
A. The Contractor and/or the Contractor’s Environmental Consultant shall screen excavated materials for the presence of oil and hazardous materials as excavation proceeds using visual, olfactory and jar headspace analysis in accordance with the EMMP and/or MCP deliverable
B. The Contractor and/or the Contractor’s Environmental Consultant shall perform jar headspace field screening evaluation in accordance with MassDEP Policy No. WSC-94-900, "Interim Remediation
Waste Management Policy for Petroleum Contaminated Soils, Attachment II, Jar Headspace
Analytical Screening Procedure."
02282 - 11
C. The Contractor and/or the Contractor’s Environmental Consultant shall perform field screening of soils for metals by XRF as appropriate on a site-specific basis or as directed by the Engineer.
D. The Contractor and/or the Contractor’s Environmental Consultant shall identify additional methods of field screening in the EMMP and/or MCP deliverable if other screening is deemed necessary based upon site conditions.
E. The Contractor and/or the Contractor’s Environmental Consultant shall provide services of one or more individuals to field screen excavated materials in accordance with MassDEP WSC- 94-400 and the EMMP and/or MCP deliverable The individual(s) shall have been adequately trained in the use of the PID and the XRF. XRF and jar headspace results shall be recorded on the Contractor’s daily excavation log.
F. Field screening equipment shall be provided by the Contractor and/or the Contractor’s Environmental
Consultant and maintained and calibrated according to the manufacturer’s recommendations.
G. Maintenance and calibration data shall be recorded on the Contractor’s daily excavation log and submitted to the Engineer.
H. The Contractor and/or the Contractor’s Environmental Consultant shall perform field screening of excavated material at a frequency no less than every 20 cubic yards of material or fraction thereof.
I. The Contractor shall use the following field screening classification system in order to segregate excavated material:
FIELD SCREENING CLASSIFICATION SYSTEM
MEDIA
VISUAL/ODOR
JAR HEADSPACE
ANALYSIS
SCREENING
CLASSIFICATION
Material
Light or No Staining
<10 ppm
Presumed Reusable/ within project limits
Material
Staining/Odor or
Unnatural Colors >10 ppm
Presumed not suitable for project re-use unless supported by laboratory analysis and LSP approval
3.3 DISPOSAL CHARACTERIZATION SAMPLING
A. The Contractor and/or the Contractor’s Environmental Consultant shall be responsible for sampling and characterizing the excavated material to determine appropriate off-site disposal and/or re-use opportunities. The Contractor and/or the Contractor’s Environmental Consultant is responsible for final waste characterization and shall determine if any additional waste characterization is required at no additional cost to the Authority. The Contractor shall provide the Engineer with a minimum of 2 days notice prior to sampling and shall not sample unless the Engineer’s approval is received.
B. Stockpiled soils: Soil stockpiles shall be limited in size to a maximum of 500 cubic yards. For every
500 yards of material, a minimum of one grab sample (for VOC analysis) and a composite sample
(generated by collection of at least six (6) random grab samples from across the stockpile) shall be collected from each stockpile. The sample will be collected at a minimum depth of one foot from the
02282 - 12 stockpile surface. Higher-frequency sampling may be required for facility approval dependent upon the facility requirements and contaminants and concentrations present.
C. For in-situ soils: Soil samples shall be collected at a frequency of a minimum of one six-point composite sample (except for VOCs) per 500 cubic yards of material. Higher-frequency sampling may be required for facility approval dependent upon the facility requirements and contaminants and concentrations present.
D. Test pit sampling: Test pit samples shall be collected from the excavation pit or from soil within the excavator bucket, as dictated by site conditions and health and safety considerations. Samples shall be composited from the excavation bottom and the sidewalls so as to form a sample representative of the test pit soils. If samples are collected from the excavator bucket or from a stockpile generated from the test pit excavation, the collection method described in Section 3.3(B) shall apply.
E. Should the Disposal Facility require additional samples, the Contractor and/or the Contractor’s
Environmental Consultant shall collect a sufficient number of samples that will satisfy the requirements of the disposal facility.
F. Samples shall be collected in such a manner as not to result in cross-contamination. All sampling equipment shall be decontaminated between uses. Disposable sampling equipment shall not be used for collection of more than one sample.
G. The collected samples shall be submitted, at a minimum, for the following chemical analyses: total petroleum hydrocarbons (TPH) using modified EPA method 8100, semivolatile organic compounds
(SVOCs) using EPA method 8270, VOCs using EPA method 8260, PCBs using EPA Method 8082, MCP 14 metals using Method 6010/7471, reactive cyanide and sulfide using EPA method sw-846, ignitability using modified EPA method 1010, corrosivity using EPA Method 9045, pH, and conductivity using EPA method 120.1. Any sample found to contain contaminant concentration equal to or greater than “20 times” their hazardous waste toxicity threshold (i.e. the 20-times rule) shall be analyzed for TCLP. Based on site conditions and/or facility requirements, additional analyses and/or analytes such as pesticides/herbicides, toxaphene, and pyridine may be required.
H. All analyses shall be…