This document contains a federal contract solicitation and related Request for Information form. The solicitation is for the phased repair and alteration of an airfield apron and other infrastructure improvements at NAS Fort Worth JRB in Fort Worth, Texas. The repairs and alterations must be completed per A&E design specifications and will include temporary fencing, pavement markings, full depth pavement restoration, removal of sun shade structures, storm water improvements, underground utilities, aircraft tie-downs, and environmental protection devices. The solicitation type is firm fixed price, for a magnitude between $5-10 million. The NAICS code is 237310 with a size standard of $39.5 million. A site visit will take place on July 7th and proposals are due by July 12th. Funds are not presently available and prospective contractors must register in SAM. The RFI form provides a template for contractors and the government to communicate questions, responses, impacts to cost and schedule, and reviews during the project.
View the file
Other files for this federal contract opportunity
Show all 30
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR INFORMATION / CLARIFICATION FORM
FOR CONTRACTOR USE ONLY
CONTRACT NO: RFI NUMBER: DATE (MM/DD/YY)
SUBJECT: DRAWING REFERENCE / DETAIL:
ATTACHMENT SENT UNDER SEPARATE
COVER(__)
RESPONSE NEEDED BY:
REQUEST:
PROPOSED SOLUTION (If applicable):
TO(Contracting Officer): 301 CONF/PK FROM (Contractor):
DATE (MM/DD/YY) TYPE OR PRINT NAME AND TITLE SIGNATURE:
REQUEST FOR INFORMATION / CLARIFICATION FORM
FOR GOVERNMENT USE ONLY
FROM CONTRACTING
TO:
For Evaluation and Action
DATE (MM/DD/YY) TYPE OR PRINT NAME AND TITLE SIGNATURE:
RFI RESPONSE / CLARIFICATION (refer to page 2)
RFI RESPONSE / CLARIFICATION:-
Government to complete following sections:
TO:(AF Contracting Office)
DATE (MM/DD/YY) TYPE OR PRINT NAME AND TITLE SIGNATURE:
TO:(Contractor)
DATE (MM/DD/YY) TYPE OR PRINT NAME AND TITLE SIGNATURE:
CONTRACTOR REVIEW
After reviewing the Government response, does the contractor anticipate A change order will be required? YES NO There will be an increase in the cost of the project? YES NO
Reviewer:
DATE (MM/DD/YY) TYPE OR PRINT NAME AND TITLE SIGNATURE:
*Contractor- return reviewed form to Contracting Officer. Should the review results in YES for either of the two questions, if any further action is required by the contractor (i.e. submission of change proporsal), they will be notified by the contracting office.
| TOContractor: |
| Reviewer: |
| Text1: |
| Text2: 001 |
| Date3_af_date: |
| Text4: |
| Text5: |
| Check Box6: Off |
| Date7_af_date: |
| Text9: |
| Text10: |
| Text11: |
| Text12: |
| Date13_af_date: |
| Text14: |
| Text16: |
| Date17_af_date: |
| Text18: |
| Text20: |
| Date21_af_date: |
| Text22: |
| Date24_af_date: |
| Text25: |
| Check Box27: Off |
| Check Box28: Off |
| Check Box29: Off |
| Check Box30: Off |
| Date31_af_date: |
| Text32: |
File details come from the government source that posted it. Updated .