Attachment 7. MAHG211140 Controls Phase II_Rev2 - MSS.xlsx
XLSX spreadsheet 27 KB Posted
- Attached to
- MAHG 21-1140 Controls Phase 2 Federal contract opportunity
- Solicitation number
- FA301024R0007
About this file
This document is a Material Submittals Schedule for the MAHG 21-1140 Controls Phase II federal contract opportunity. The solicitation number is FA301024R0007, and the project title is "ICS Controls Phase II".
The key details are:
- The contract will be a Total Small Business Set-Aside with an estimated contract value between $1,000,000 and $5,000,000.
- Required submittals include HazMat documentation, project schedule, control system documentation, testing reports, O&M manuals, and as-built drawings. Submittal due dates range from 10 days after Notice to Proceed to the end of the contract period.
- The contract is being issued by the Department of the Air Force Air Education and Training Command.
- An organized site visit for offerors is scheduled for July 25, 2024.
- Funds are not presently available for this effort, and the government reserves the right to cancel the solicitation.
View the file
Other files for this federal contract opportunity
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Material Submittals Schedule
| Project Number: | |||
| MAHG211140 | Project Title: | ||
| ICS Controls Phase II | Solicitation / Contract Number: |
FA301024R0007
| Line Number | (To be completed by Project Engineer) | (To be completed by Contract Administrator) | ||||||||||||||
| Number of Copies Required (if not electronically submitted) | Remarks | |||||||||||||||
| Item or Description of Item, Contract Reference, Type of Submittal | Certificate of Compliance | Shop Drawings | Samples | Color Selection | Manufacturer's Recommendation | Warranty-Manufacturer and/or Workmanship | Catalog Data | Operating Instructions | Schedules, Listings, Reports, Plans | Technical Data | Test Reports | Field Reports | Required Submission Date |
fergusog: Enter the due date from the Contractor (MM/DD/YY) Date Received in Contracting fergusog: Enter the date received from the Contractor. (MM/DD/YY) Date to Civil Engineering fergusog: Enter the date submittal was given to CE for review. (MM/DD/YY) Return Suspense Date fergusog: Enter the date the submittal is due back from CE
(MM/DD/YY)
Submittal Numbers fergusog: Enter the Submittal Number
| Date Contractor | ||
| Notified | Contractor Resubmittal |
fergusog: Enter Resubmittal Number Final Approval fergusog: Enter the submittal final approval date
(MM/DD/YY)
Approved fergusog: Enter date the Contractor was notified of submittal approval
(MM/DD/YY)
fergusog: Enter Resubmittal Number Disapproved fergusog: Enter date the Contractor was notified of submittal disapproval
(MM/DD/YY)
fergusog: Enter the submittal final approval date
(MM/DD/YY)
| 1 | HazMat Questionnaire | 3 | 3 | 5 Days Prior to Start Date | |||||
| 2 | HazMat MSDS | 3 | 3 | 5 Days Prior to Start Date | Must be filled out if Contractor answers YES to to the HazMat questinnaire | ||||
| 3 | HazMat Reporting Entry Form | 3 | 3 | 5 Days Prior to Start Date | Submot Final Quantities | ||||
| 6 | AF3065 Project Schedule | ||||||||
| (11 BLDGS TOTAL) | 3 | 3 | 3 | Within 7 days of NTP, updated weekly | Identify NTP, Work Start & End Dates, and End of Contract | ||||
| 9 | Control / BAS |
(Each of 11 BLDGS)
| Network Diagrams, Flow Diagrams, Points Lists, Material Lists, SOO, Devices. | 1 | 1 | 1 | 1 | 1 | 10 Days Following NTP | Provide 1 hard copy and 2 electronic copies on DVD | |||||
| 10 | ELEC wiring & conduit | 1 | 1 | 1 | 1 | 1 | 10 Days Following NTP | |||||
| 11 | Piping Insulation | 1 | 1 | 1 | 1 | 10 Days Following NTP | ||||||
| 12 | Ductwork Insulation | 1 | 1 | 1 | 1 | 10 Days Following NTP | ||||||
| 13 | Suspended Ceiling Systems |
and Ceiling Panels
| 1 | 1 | 1 | 1 | 1 | 1 | 10 Days Following NTP | ||
| 14 | OP TESTING REPORTS |
Control Points Check at EMCS (Each of 11 BLDGS) 3 3 3 5 Days Following TEST Idenfity EMCS (CMD, STATUS, ALARM, MONITORING, etc) connectivity, Identify any EQPT, Instrumentation, Sensor issues via RFI.
15 HVAC T&B
(Each of 11 BLDGS)
| (All interlocked SYSTEMS in EACH BLDG) | 3 | 3 | 3 | 5 Days Following TEST | Identify any EQPT, Instrumentation, Sensor issues via RFI. | ||
| 16 | CHW system T&B |
(Each of 11 BLDGS)
| 3 | 3 | 3 | 5 Days Following TEST | Identify any EQPT, Instrumentation, Sensor issues via RFI. | ||
| 17 | HW system T&B |
(Each of 11 BLDGS)
| 3 | 3 | 3 | 5 Days Following TEST | Identify any EQPT, Instrumentation, Sensor issues via RFI. | ||||||||
| 18 | Application Software Listing | 3 | 3 | 3 | End of Contract | Identify revision level, functionality, specifications | ||||||
| 19 | BACNet PICS | 3 | 3 | 3 | End of Contract | Identify for all DDCs, Software, and other … using BACNet on BAS installed. | ||||||
| 20 | BAS Training | |||||||||||
| (Each of 11 BLDGS) | 1 | 1 | 1 | 1 | 1 | End of Contract | ||||||
| 21 | O & M Manuals |
Electric Control Devices
| and NAE panels | 2 | 2 | 2 | 2 | 2 | 2 | End of Contract | Provide 2 hard copies in loose leaf binders and 2 electronic copies on DVD | ||
| 22 | As-Built Drawings |
(Each of 11 BLDGS)
| Network Diagrams, Flow Diagrams, Points Lists, Material Lists, SOO, Devices. | 1 | 1 | 1 | 1 | End of Contract | Provide 1 hard copy and 2 electronic copies on DVD | ||
| 4 | HazMat Reporting entry Form | 3 | 3 | End of Contract | ||||
| 5 | Recycling and Landfill Report | 3 | 3 | End of Contract | ||||
| 7 | Warranty (Manufacturer's) | 3 | 3 | End of Contract | ||||
| 8 | 1-Year Warranty (Contractor's) | 3 | 3 | End of Contract |
&"Verdana,Bold"&12Schedule of Material Submittals &12Print on Legal size paper ( 8 x 14 ). Attachment 7
FA301024R0007
&P of &N