Assumptions Assume all apply but LDs will be revised
01 22 00.00 10 MEASUREMENT AND PAYMENT
01 30 00.00 11 DESCRIPTION OF NEW WORK
01 32 17.00 20 NETWORK ANALYSIS SCHEDULES (NAS)
01 33 00.00 SUBMITTAL PROCEDURES
01 42 00.00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 02.00 11 QUALITY CONTROL SYSTEM (QCS)
01 45 04.00 11 CONTRACTOR QUALITY CONTROL
01 45 35.00 SPECIAL INSPECTIONS
01 57 20.00 11 ENVIRONMENTAL PROTECTION
01 57 25.00 11 STORM WATER POLLUTION PREVENTION PLAN
01 58 01.00 11 PROJECT SIGN
01 78 02.00 10 CLOSEOUT SUBMITTALS
01 78 23.00 OPERATION AND MAINTENANCE DATA
02 87 00.00 FLOOD SEDIMENT REMOVAL Assume no work but for in progress and final cleaning (3.1.1)
03 11 13.00 10 STRUCTURAL CAST-IN-PLACE CONCRETE FORMING
03 15 00.00 10 CONCRETE ACCESSORIES
03 20 00.00 10 CONCRETE REINFORCING
03 30 00.00 10 CAST-IN-PLACE CONCRETE
03 35 00.00 10 CONCRETE FINISHING
03 39 00.00 10 CONCRETE CURING
03 45 33.00 PRECAST PRESTRESSED STRUCTURAL CONCRETE
04 20 00.00 MASONRY Assume installed correctly but for missing PTA 422
05 12 00.00 STRUCTURAL STEEL
05 21 19.00 OPEN WEB STEEL JOIST FRAMING
05 30 00.00 STEEL DECKS
05 50 13.00 MISCELLANEOUS METAL FABRICATIONS
05 50 14.00 STRUCTURAL METAL FABRICATIONS
05 51 00.00 METAL STAIRS
05 51 33.00 METAL LADDERS
05 52 00.00 METAL RAILINGS
06 10 00.00 ROUGH CARPENTRY
06 61 16.00 SOLID POLYMER (SOLID SURFACING) FABRICATIONS
06 73 01.00 FIBERGLASS REINFORCED PLASTIC (FRP) GRATING
07 14 00.00 FLUID-APPLIED WATERPROOFING
07 21 13.00 BOARD AND BLOCK INSULATION
07 22 00.00 ROOF AND DECK INSULATION
07 51 13.00 BUILT-UP ASPHALT ROOFING
07 60 00.00 FLASHING AND SHEET METAL
07 84 00.00 FIRESTOPPING
07 92 00.00 JOINT SEALANTS
07 95 13.00 EXPANSION JOINT COVERS
08 11 13.00 STEEL DOORS AND DOOR FRAMES
08 14 00.00 WOOD DOORS
08 33 23.00 OVERHEAD COILING DOORS
08 34 73.00 SOUND CONTROL DOOR ASSEMBLIES
08 41 13.00 ALUMINUM-FRAMED ENTRANCES AND
08 51 13.00 ALUMINUM WINDOWS
08 71 00.00 DOOR HARDWARE
08 81 00.00 GLAZING
08 91 00.00 METAL WALL LOUVERS Assume all installed and function properly but for the identified deficiencies
Assume all installed and function properly but for the identified deficiencies:
concrete finish.
DIVISION 04 - MASONRY
DIVISION 05 - METALS
Assume all installed and function properly but for the identified deficiencies
Assume Railings in Pump Gallery at El 190 and the interior stairs going to office roof were installed and function properly
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
No Assumptions
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
Assume all installed and function properly but for the identified deficiencies
Division/Spec Section
No Assumptions - Include all in Bid
DIVISION 02 - EXISTING CONDITIONS
DIVISION 01 - GENERAL REQUIREMENTS
DIVISION 03 - CONCRETE
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
No Assumptions
DIVISION 08 - OPENINGS
No Assumptions
DIVISION 09 - FINISHES
09 06 90.00 COLOR SCHEDULE
09 51 00.00 ACOUSTICAL CEILINGS
09 65 00.00 RESILIENT FLOORING
09 90 00.00 PAINTS AND COATINGS Assume paint in Pump Gallery and Office Areas were applied properly
09 97 02.00 PAINTING: HYDRAULIC STRUCTURES Assume all installed and function properly but for the identified deficiencies
10 21 13.00 TOILET COMPARTMENTS
10 28 13.00 TOILET ACCESSORIES
10 44 16.00 FIRE EXTINGUISHERS Assume Installed Cabinets are done correctly
10 71 13.00 EXTERIOR WEATHER CONTROL DEVICES: METAL CANOPY No Assumptions
11 10 00.00 TRANSPORTATION OF GOVERNMENT-FURNISHED EQUIPMENT Assume Complete
11 20 00.00 INSTALLATION OF GOVERNMENT-FURNISHED EQUIPMENT
Assume small pumps are level; Assume sole plates for the large pumps will need to be leveled;
12 32 00.00 MANUFACTURED WOOD CASEWORK No Assumptions
13 48 00.00 10 SEISMIC PROTECTION FOR MECHANICAL EQUIPMENT
13 48 00.00 SEISMIC PROTECTION FOR MISCELLANEOUS EQUIPMENT
14 24 00.00 ELEVATOR: LOW RISE TRACTION Deleted from Contract. See Modification
22 00 00.00 PLUMBING, GENERAL PURPOSE
22 14 29.00 40 SUMP PUMPS
23 00 00.00 AIR SUPPLY, DISTRIBUTION, VENT., & EXHAUST SYSTEMS
23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS
23 07 00.00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS
26 05 9.00 METAL-ENCLOSED BUSWAY
26 05 13.00 40 MEDIUM-VOLTAGE CABLES
26 05 19.00 10 INSULATED WIRE AND CABLE
26 05 48.00 10 SEISMIC PROTECTION FOR ELECTRICAL EQUIPMENT
26 18 23.00 40 MEDIUM-VOLTAGE SURGE ARRESTERS
26 19 36.00 MEDIUM-VOLTAGE MOTOR STARTERS
26 20 00.00 INTERIOR DISTRIBUTION SYSTEM
26 24 16.00 40 PANELBOARDS
26 24 19.00 40 MOTOR CONTROL CENTERS
26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION
26 28 21.00 40 AUTOMATIC TRANSFER SWITCHES
26 32 15.00 10
DIESEL-GENERATOR SET STATIONARY 100-
2500 KW, WITH AUXILIARIES
Assume Equipment will work. No commissioning or testing has occurred
26 41 00.00 40 LIGHTNING PROTECTION SYSTEM No Assumptions
26 42 15.00 10
CATHODIC PROTECTION SYSTEM FOR STEEL
PRESSURE PIPE
Assume Installed and Functions properly
26 51 00.00 40 INTERIOR LIGHTING
26 56 00.00 EXTERIOR LIGHTING
28 31 64.00 10 FIRE DETECTION AND ALARM SYSTEM, ADDRESSABLE No Assumptions
31 05 19.03 12 GEOTEXTILE SEPARATOR UNDER ROADS
31 23 16.16 11 EXCAVATION, FILL, BACKFILL & EMBANKMENT FOR STRUCTURES
31 23 19.00 11 DEWATERING
32 15 00.00 11 AGGREGATE SURFACE COURSE
32 17 24.00 10 PAVEMENT MARKINGS
32 31 13.00 CHAIN LINK FENCES AND GATES
32 92 19.00 11 SEEDING AND FERTILIZING
33 71 02.00 20 UNDERGROUND ELECTRICAL DISTRIBUTION No Assumptions
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
Earthwork deleted from Contract but for language in Modification.
DIVISION 32 - EXTERIOR IMPROVEMENTS
DIVISION 31 - EARTHWORK
DIVISION 22 - PLUMBING
DIVISION 10 - SPECIALTIES
No Assumptions; some material on site
No Assumptions; some stored material
No Assumptions; some material on site
DIVISION 11 - EQUIPMENT
DIVISION 12 - FURNISHINGS
DIVISION 13 - SPECIAL CONSTRUCTION
No Assumptions
DIVISION 14 - CONVEYING EQUIPMENT
No Assumptions
DIV 23 - HEATING, VENTILATING, & AIR CONDITIONING
Assume the Roof Vents are installed and will function properly. Assume A/C unit on office roof was installed and will function properly, but for identified deficiencies
No Assumptions; some material on site
DIVISION 26 - ELECTRICAL
Exterior Improvements deleted from Contract. See Modification.
DIVISION 33 - UTILITIES
35 20 14.00 STOPLOGS AND TRASHRACKS
35 20 16.53 VERTICAL LIFT GATES
35 20 23.13 11 INLET CHANNEL EXCAVATION
35 31 19.00 11 STONE PROTECTION
40 05 13.96 WELDING PROCESS PIPING
40 05 13.00 PIPELINES, LIQUID PROCESS PIPING
40 95 00.00 PROCESS CONTROL No Assumptions
41 22 13.13 BRIDGE CRANES No Assumptions
1001 MOBILIZATION AND DEMOBILIZATION No Assumptions
1002 ENVIRONMENTAL PROTECTION
1003 STORMWATER POLLUTION PREVENTION
1003AA SILT FENCES / EROSION CONTROL
1003AB CHECK DAMS
1004 CATHODIC PROTECTION Assume Installed and Functions properly
1005 DISCHARGE PIPE AND ACCESSORIES Assume Correct but for deficencies noted
1006 FIBER OPTIC SYSTEM No Assumptions
1007 FENCING Assume Correct but for deficencies noted
1008 THRUST BLOCKS W/PILING Assume Installed and Functions properly
1009 SURGE TANKS AND ACCESSORIES Assume Correct but for deficencies noted
1010 CLEARING AND GRUBBING
1011 EXCAVATION
1012 COMPACTED EMBANKMENT
1013 PIPE BEDDING
1014 AGGREGATE SURFACE COURSE
1015 GEOTEXTILE
1016 TURFING Assume Installed and Functions properly
DIVISION 41-MATERIAL PROCESSING & HANDLING EQUIP.
Assume No Requirements
Assume Installed and Functions properly
Deleted from Contract. See Modification
Assume function properly. Address any deficencies noted.
Deleted from Contract. See Modification
DIVISION 40 - PROCESS INTEGRATION
Assume all installed and function properly but for the identified deficiencies
OPTIONS