IDENTIFIED REMAINING AND DEFICIENT FEATURES OF WORK
1. Mechanical: Identified remaining and deficient mechanical features include but are not limited to the following:
1.1. Plumbing: Coordinate with the Government prior to commencing any plumbing work.
1.1.1. Potable water shall be installed per original contract with the following exception;
Contractor has the option of using PEX tubing for waterlines. All plumbing fixtures shall be installed per original contract.
1.1.2. The contractor shall complete the restrooms (2) located in the office side of EL.
190 and install all fixtures. The water fountains shall be plumbed with fountains installed and powered. The existing water heater (30 gal) located in the Janitor’s
Closet shall be plumbed and installed per original contract. The utility sink shall also be plumbed and installed. The sink in the Break Room shall be plumbed and installed.
All plumbing and fixtures shall be per the contract with the exception of PEX tubing.
1.1.3. The septic system shall be installed per the contract to include the installation of all piping, venting, cleanouts and the septic tank.
1.1.4. No waterlines or hose bibbs have been installed in the station. All waterlines and hose bibbs shall be installed per the contract.
1.1.5. The existing trench drains should be routed through the oil water separator per the contract.
1.2. HVAC:
1.2.1. HVAC shall be completely installed to include all ductwork, insulation, diffusers/grilles, and power to provide a fully functional system. The RTU and exhaust fan are installed on the mezzanine. The system shall be tested and balanced per the contract.
1.2.2. All intake louvers and exhaust fans for the operating floor (EL 190) shall be powered and tested to provide a fully functional system.
1.2.3. Existing exhaust fans located on the mezzanine and roof shall be cleaned of all insects/nests.
1.3. Mechanical:
1.3.1. The rollup service door (EL 190) does not have an emergency stop. Sensors, a photoelectric safety beam and a door bottom sensing edge, should be installed on the door.
1.4. Complete all items of work and correct all identified and discovered deficiencies in accordance with the original plans, specifications, and modifications.
Table 1. Mechanical, Plumbing, HVAC Deficiencies
Elevation Description
Exterior Flow meter chamber sump pump not installed Figure 1
Flow meters have not been installed Figure 2
Dewatering Pit (SW Corner) Figure 3
1. Trash / pipe cutoff at bottom of pit
2. Flap valve missing
Surge tank air/vacuum valve plugs dissimilar metals corroding Figure 4
Clean and apply protective coating system to air/vacuum valves Figure 5
Roof Damaged cooling fins on office roof A/C Unit Figure 6
190.0 Rollup service door Figure 7
1.Electrical is incomplete
2.Door is missing emergency sensors/stops
3. Spacing between frame and block to be fixed
Overhead Crane
Lack warning horn
1. Complete crane to be one color
2. 10T hoist wire rope does not reach El 173.81. New drum and rope assembly required.
3. Footwalk is not checkered steel
4. Lobby RM 101 HVAC incomplete
Figure
Women’s RM 105 Figure 10
1.Interior wall separating plumbing from fixtures not installed (A-103)
2.Plumbing and fixtures not installed
3.Check plumbing for adequacy
Women’s RM 105 one hour fire stop not installed
Women’s RM 105 HVAC incomplete Figure 12
Janitor Closet RM 106 Figure 13
1.Water heater not installed
2.Mop sink and plumbing not installed
Men’s RM 107 plumbing incomplete
Men’s RM 107 one hour fire stop not installed Figure 15
Men’s RM 107 HVAC incomplete Figure 16
Corridor RM 102 drinking fountain and plumbing not installed Figure 17
Break Room RM 108 plumbing, cabinets and kitchenette not installed Figure 18
Break Room RM 108 Figure 19
1.HVAC incomplete
2.One hour fire stop not installed
Network RM 113
1.HVAC incomplete
2.One hour fire stop not installed
HVAC General Note: Supply ductwork not complete throughout rooms/lobby/corridor. Insulation is missing or falling off, diffusers not installed, drop (grid) ceiling not installed. RTU installed on mezzanine. Check power and test and balance the system.
Figure
173.81 Pump plugs (dissimilar metals) Figure 22
South most pump (#2) small leak at flange seal Figure 23
150.81 South 2 most pumps (#2 & #1) leak at access hatch
Rm 402:
Oil / water separator not installed Figure 24
1. Nuts wedged under pump flanges to be removed Figure 25
2. Temporary sump plumbing to be removed Figure 26
3. Rm 404:
Unused compressor tank to be removed Figure 27
1. Nuts wedged under pump flanges to be removed Figure 28
2. Elevator sump pump inoperative Figure 29
Grouting of elevator hydraulic lift cylinder is not complete Figure 29
Figure 1. Flow meter chamber sump pump not installed
Figure 2. Flow meters have not been installed
Figure 3. Dewatering Pit (SW Corner) Flap valve missing; Trash/pipe cutoff at bottom of pit
Figure 4. Surge tank air/vacuum valve plugs dissimilar metals corroding
Figure 5. Clean and apply protective coating system to air/vacuum valves
Figure 6. Damaged cooling fins on office roof A/C Unit
Figure 7. EL 190, Pump Gallery: Overhead Door needs Emergency Stop System; Space Between frame and block fixed; Final wiring
Figure 8. Overhead Crane: Lacks warning horn; Complete crane to be one color; 10T hoist wire rope does not reach El 173.81;
New drum and rope assembly required; Footwalk is not checkered steel
Figure 9. EL. 190, Rm 101: HVAC incomplete
Figure 10. EL 190, Rm 105: Interior wall incomplete; Plumbing and Fixtures incomplete/not installed; Check Plumbing for accuracy
Figure 11. EL 190, Rm 105: One Hour Firestop not installed
Figure 12. EL. 190, RM 105: HVAC Incomplete - Exhaust ductwork not complete. Grilles not installed. Exhaust fan installed on the mezzanine level. Check power and test fan.
Figure 13. EL 190, RM 106: Water heater not plumbed/installed. Utility sink not plumbed/installed. Receptacle should be GFI.
Figure 14. EL 190, RM 107: Plumbing incomplete, fixtures not installed, drop (grid) ceiling not installed, toilet partition not installed.
Figure 15. EL 190, Rm 107: One Hour Fire Rating not installed
Figure 16. EL. 190, Rm 107: HVAC Incomplete - Exhaust ductwork not complete. Grilles not installed. Exhaust fan installed on the mezzanine level. Check power and test fan.
Figure 17. EL 190, RM 102: Drinking fountain not plumbed/installed.
Figure 18. EL 190, RM 108: Plumbing, fixtures, cabinets and kitchenette not installed.
Figure 19. EL 190, RM 108: HVAC Incomplete; One Hour Firestop not installed.
Figure 20. EL. 190, Rm 113: HVAC Incomplete; One Hour Firestop not installed
Figure 21. EL 190. Supply ductwork not complete throughout rooms/lobby/corridor. Insulation is missing or falling off, diffusers not installed, drop (grid) ceiling not installed. RTU installed on mezzanine. Check power and test and balance the system.
Figure 22. Pump plugs (dissimilar metals)
Figure 23. South most pump (#2) small leak at flange seal
Figure 24. EL 150.81, RM 402: Oil/water separator not plumbed/installed.
Figure 25. Rm 402: Nuts wedged under pump flanges to be removed
Figure 26. Rm 402: Temporary sump plumbing to be removed
Figure 27. Unused compressor tank to be removed
Figure 28. Nuts stuck in pump flanges to be removed
Figure 29. Grouting of elevator hydraulic lift cylinder is not complete; Elevator sump pump inoperative
2. Electrical: Identified remaining and deficient electrical features include but are not limited to the following:
2.1. Lighting:
2.1.1. Repair/replace all lighting fixtures (internal, external, emergency, and exit signs) not in good working order or compromised by the environment (bad bulbs, bad ballast, bad batteries, rusting, and similar issues.)
2.1.2. Provide and install all lighting that is missing.
2.1.3. Remove temporary lighting from office/control room level when no longer needed.
2.1.4. Provide and install missing or defective switches and cover plates.
2.2. Power:
2.2.1. Provide and install missing or defective receptacles and cover plates.
2.2.2. Provide power and controls including control wiring to the existing HVAC unit on mezzanine roof. Verify proper operation.
2.2.3. Provide power and controls including control wiring to existing bathroom(s) exhaust fan on mezzanine roof. Verify proper operation.
2.2.4. Provide power and control wiring to each of six (6) existing venting exhaust fan units on upper roof. Verify proper operation.
2.3. Main Pumps (6):
2.3.1. Once the pumps and pipes are properly leveled and stable, install motors with both motor and pump shafts aligned and coupled. Verify the installation is plumb, shafts aligned and perform an unpowered rotational check of the installation. If the installation check is good, install power and control wiring along with the lubrication systems and monitoring systems. Test each pump/motor systems with power to verify alignment and operation is good and that the lubrication and monitoring systems are functioning correctly. This testing will be performed with contractor furnished generator power. (See Attachment 10 describing prior contractor’s attempts to achieve the required levelness of the pumps and motors. As shown in the attached documents, no specific defect was identified with Government Furnished Equipment, nor was the actual cause of the unlevelness of the pumps determined. As such, these documents are provided for information only and do not constitute a representation on the part of the Government of any specific actions required or specific site conditions.)
2.4. Support Equipment:
2.4.1. For the flow vault, install any missing equipment in the flow vault. Repair/replace any defective equipment.
2.4.2. Install any missing switchgear heaters, bus duct heaters, and associated wiring currently not installed. Verify all the devices, existing and newly installed, are working properly.
2.4.3. Install power and control wiring, and a pump control panel for pumps P8A and
P8B.
2.4.4. Install missing gate and valve power, control, and instrumentation wiring and verify proper operation.
2.4.5. Install missing heat trace and repair/replace any heat trace not in good working order.
2.4.6. Install any missing fire alarm system components and repair/replace any existing components as necessary. Verify proper operation.
2.4.7. Repair/Replace PLC for overhead crane.
2.5. Control System:
2.5.1. Complete the existing programmable control system, including PLCs, displays, programming, sensors and related items. Repair/replace any existing components, including software/firmware, that are defective or insufficient for the application.
2.5.2. Complete the lightning protection system on the mezzanine level. Correct any deficiencies in the existing lightning protection system.
2.6. Complete all items of work and correct all identified and discovered deficiencies in
Table 2. Electrical Representative Action Items
Exterior Flow meter chamber electrical not installed Figure 30
Various Lighting devices not working or not in good working order Figure 31
Various Rusted Light Fixtures Figure 32
Various Temporary lighting and wiring with permanent wiring and lighting incomplete/missing
Figure 33
Various Wiring device and cover plate missing Figure 34
Office Roof
Restroom exhaust fan needing power connections checked/completed.
Figure 35
173.81 Fan disconnect missing electrical connections and conduit. Figure 36
190 Pump motor sitting on pump but not installed. Figure 37
190 Incomplete wiring Figure 38
173.81 Incomplete wiring (power, control and instrumentation) and temporary wiring.
Figure 39
190 Temporary P8 Pump Panel to be replaced by a permanent panel. Figure 40
190 Control Cabinet to be installed and programmed. Figure 41
190 Gate wiring to be completed Figure 42
190 Sump pit (NW Corner) electrical to be complete Figure 43
Roof Lightning protection to be verified for accuracy and completed Figure 44
Figure 30. Flow meter chamber electrical not installed
Figure 31: Lighting devices not working or not in good working order
Figure 32. Rusted Lights
Figure 33. Temporary lighting and wiring with permanent wiring and lighting incomplete/missing.
Figure 34. Wiring device and cover plate missing; cover plate unsatisfactory
Figure 35. Restroom exhaust fan needing power connections checked/completed.
Figure 36. Fan disconnect missing electrical connections and conduit.
Figure 37. Pump motor sitting on pump but not installed.
Figure 38. Incomplete wiring
Figure 39. Incomplete wiring (power, control and instrumentation) and temporary wiring.
Figure 40. Temporary P8 Pump Panel to be replaced by a permanent panel.
Figure 41. Control Cabinet to be installed and programmed.
Figure 42. Gate wiring to be completed
Figure 43. Sump pit (NW Corner) electrical to be completed
Figure 44. Lightning protection to be verified for accuracy and completed
3. Structural: Identified remaining and deficient structural features include but are not limited to the following:
3.1. Handrail:
3.1.1. Replace/repair handrails according to construction plans and specifications.
3.1.2. Ensure base plates are properly sized according to contract documents.
3.1.3. Provide adequate post anchorage as shown on the contract documents (4 bolts at each base plate).
3.2. CMU walls:
3.2.1. Install Seismic expansion joints and anchors at all required locations at CMU walls.
3.3. Waterproofing: Repair or apply adequate waterproofing to prevent water from leaking through the walls of the substructure.
3.4. Mounting anchor bolts:
3.4.1. Provide proper bolt lengths that comply with the code to ensure bolts have adequate thread engagement.
3.4.2. Ensure all the bolts in the joint have been tightened sufficiently to prevent removal of the nuts without the use of a wrench.
3.5. Office Roof: Inspect the roof, investigate water intrusion, and repair any leaks.
3.6. Complete all items of work and correct all identified and discovered deficiencies in
Table 3. Structural Deficiencies
Elevation Description
Various Unused penetrations to be filled Figure 45
Various Unused pipe to be cut and filled Figure 46
Various Walls and floors/ceilings below water levels are still leaking fluid water through waterproofing
Figure 47
Various Holes in walls to be grouted Figure 48
Various Stairwell No. 1 and No.2 handrail plates are not proper size, bolts missing, not properly grouted
Figure 49
Various Handrails on stairs are not compliant for height from the construction drawings.
Figure 50
Roof Parapet handrail splices/welds poor quality and rusting multiple locations Figure 51
Poor weld quality and rust on stairs Figure 52
Stair Base Plates at parapet wall not grouted Figure 53
Roof Seam on east parapet wall separating Figure 54
Unused mounting bolts on parapet wall to be removed and grouted Figure 55
Above 190 to Roof
Exterior Stairs: Landing Misaligned with Stringer Figure 56
Exterior Stairs: Landing Mounting Plates not flush with building Figure 57
Bridge Crane Access Landing not level for threshold mounting Figure 58
Bridge Crane Access Landing mounting anchors do not have adequate exposed threads
Figure 59
Bridge Crane Access Landing mounting nuts loose Figure 60
Unused Bridge Crane Access Landing mounting holes to be grouted Figure 61
Bridge Crane Access door frame gap to be filled. Frame to be removed and replaced
Figure 62
Concrete at Office Roof Access too high to mount door threshold Figure 63
190 Class A finish on interior and exterior exposed concrete incomplete Figure 64
Seismic expansion joints and seismic anchors at CMU walls not installed (see PTA 422 fix)
Figure 65
Waste concrete in CMU wall gaps Figure 66
Grate not flush with floor Figure 67
Water intrusion Rm 102 Figure 68
Water intrusion Rm 105 Figure 69
Water intrusion Rm 108 Figure 70
Soldering of water pipes in bathroom to be checked and redone as necessary. Some copper pipes are not connected to feed pipes. Soldering needs to be tested for compliance with Health and safety regulations for
Potable Water.
Bathroom curtain wall to be braced for seismic movements. Possible solution would be to carry the wall all the way to the floor deck above and connect to the floor deck.
Figure 71
Fire caulking is not complete.
173.81 Pipe anchors missing Figure 72
Moisture around anchor bolts for pump shaft through wall connection.
Verify if the stain is oil. Seal against moisture permeation as required
Figure 73
Electrical Bus opening not covered Figure 74
Stairwell 1, Right descending handrail: Wall busted and handrail loose Figure 75
Stairwell 2: No Wrap Around Figure 76
Stairwell 2: Post Offset Figure 77
150.81 Rm 402 & Rm 404: Platform safety chain missing Figure 78
Rm 402: Handrail base plates not grouted Figure 79
Rm 403: Stair Handrails currently not installed; previous installed handrails had base plates in incorrect locations, baseplates were incorrect size, and ends were not finished
Figure 80
Rm 404: Handrail joints not welded Figure 81
Rm 404: Pump inspection platform mounting bolts missing Figure 82
Rm 404: Temporary anchors in wall to be removed and grouted Figure 83
Rusted nails from formwork on lower level roof to be sealed Figure 84
Exterior Items
Flow meter chamber ladder does not have required safety rail Figure 85
Flow meter chamber unused exposed bolts to be grouted Figure 86
Flow meter chamber honeycomb in bottom of slab Figure 87
Platform to be removed in dewatering pit and mounting bolts grouted (SW Corner)
Figure 88
Sump Pit sump pump brace and mounting bolts in poor condition (NW Corner)
Figure 89
Handicap parking slab cracking Figure 90
Wall drain manholes lacking required handrail - 2 locations Figure 91
Trash racks not installed Figure 92
Stoplogs to be stored on top of pad Figure 93
Motor Chatter in vertical lift gate #3
Check oil at stem nuts of vertical lift gates
Mud Valves – Loose and Rusty Handles; hard to turn. Figure 94
Dissimilar metals on two of mud valve handles. Stainless steel handles welded to carbon steel yoke. Mounted on stainless steel stem.
Figure 95
Missing ½ inch bolt at column to beam connection on Exterior Bus Duct Figure 96
Roller Gate Operator Base – Anchor bolt cut off too short Figure 97
Bus Duct incomplete
Figure 45. Unused floor penetrations to be filled
Figure 46. Unused pipes to be cut and filled
Figure 47. Walls and floors/ceilings below water levels are still leaking fluid water through waterproofing
Figure 48. Holes in walls to be grouted
Figure 49. Stairwell No. 1 and No.2 handrail plates are not proper size, bolts missing, not properly grouted
Figure 50. Handrail height not compliant
Figure 51. Parapet handrail splices/welds poor quality and rusting multiple locations
Figure 52. Poor weld quality and rust on stairs
Figure 53. Stair Base Plates at parapet wall need grout
Figure 54. Roof Seam on east parapet wall separating
Figure 55. Unused mounting bolts on parapet wall to be removed and grouted
Figure 56. Landing Misaligned with Stringer
Figure 57. Landing Mounting Plates not Flush with Building
Figure 58. Bridge Crane Access Landing not level for threshold mounting
Figure 59. Bridge Crane Access Landing mounting anchors do not have adequate exposed threads
Figure 60. Bridge Crane Access Landing mounting nuts loose
Figure 61. Unused Bridge Crane Access Landing mounting holes to be grouted
Figure 62. Bridge Crane Access door frame gap to be filled. Frome to be removed and replaced.
Figure 63. Concrete at Office Roof Access too high to mount door threshold
Figure 64. Class A finish incomplete
Figure 65. Seismic expansion joints and seismic anchors at CMU walls not installed. See PTA 422 fix.
Figure 66. Waste concrete in CMU wall gaps
Figure 67. Grate not flush with floor
Figure 68. Water intrusion Rm 102
Figure 69. Water intrusion Rm 105
Figure 70. Water intrusion Rm 108
Figure 71. Bathroom curtain wall to be braced for seismic movements.
Figure 72. Pipe anchors missing
Figure 73. Moisture around anchor bolts for pump shaft through wall connection. Verify if the stain is oil. Seal against moisture permeation as required
Figure 74. Electrical Bus opening not covered
Figure 75. El 173.81, Stairwell 1: Right descending handrail: Wall busted and handrail loose
Figure 76. El 173.81, Stairwell 2: No wrap around
Figure 77. Post offset
Figure 78. Platform safety chain missing
Figure 79. Rm 402: Handrail base plates not grouted
Figure 80. Rm 403: Stair Handrails currently not installed; previous installed handrails had base plates in incorrect locations, baseplates were incorrect size, and ends were not finished
Figure 81. Rm 404: Handrail joints not welded
Figure 82. Rm 404: Pump inspection platform mounting bolts missing
Figure 83. Rm 404: Temporary anchors in wall to be removed and grouted
Figure 84. Rusted nails from formwork on lower level roof to be sealed
Figure 85. Flow meter chamber ladder does not have required safety rail
Figure 86. Flow meter chamber unused exposed bolts to be grouted
Figure 87. Flow meter chamber honeycomb in bottom of slab
Figure 88. Platform to be removed in dewatering pit and mounting bolts grouted (SW Corner)
Figure 89. Sump Pit sump pump brace and mounting bolts in poor condition (NW Corner)
Figure 90. Handicap parking slab cracking
Figure 91. Wall drain manholes lacking required handrail - 2 locations
Figure 92. Trash racks not installed
Figure 93. Stoplogs to be stored on top of pad
Figure 94. Mud Valves – Loose and Rusty Handles; hard to turn.
Figure 95. Dissimilar metals on two of mud valve handles. Stainless steel handles welded to carbon steel yoke. Mounted on stainless steel stem.
Figure 96. Missing ½ inch bolt at column to beam connection at exterior bus duct
Figure 97. Roller Gate Operator Base – Anchor bolt cut off too short
4. Architectural: Identified remaining and deficient architectural features include but are not limited to the following:
4.1. Complete all items of work and correct all identified and discovered deficiencies in
Table 4. Identified remaining and deficient architectural features
All Doors and Door Frames to be replaced Figure 98
190 Exterior
Down Spouts Missing East Side of Building Figure 99
190 Lobby RM 101 Figure 100
1. Suspension acoustical panels not completed
2. Acoustical panels not installed
3. Replace exterior door frame. Install new exterior door assembly. Replace cracked glass.
4. Vinyl composite tile not installed
5. Vinyl base board not installed
6. Light fixture not installed
7. Window sills missing Figure 101
Corridor RM 102 Figure 102
1. Suspension acoustical panels not completed
2. Acoustical panels not installed
3. Vinyl composite tile not installed
4. Vinyl base board not installed
5. Light fixture not installed
6. Window sills missing Figure 101
Stair RM 104
1. Vinyl composite tile not installed
2. Vinyl base board not installed
3. Light fixture not installed
4. Walls not painted
Women’s RM 105 Figure 103
1. Suspension acoustical panels not completed
2. Acoustical panels not installed
3. Vinyl composite tile not installed
4. Vinyl base board not installed
5. Light fixture not installed
6. Plumbing fixtures (toilet and sink) not installed
7. Partitions and accessories not installed
8. Mirror not installed
9. Grab bar not installed
10. Soap dispenser and paper towel dispenser not installed
11. 1 hour fire stop not installed
12. Floor drain cover not installed
13. Door to restroom not installed
Janitor closet RM 106 Figure 104
1. Suspension acoustical panels not completed `
2. Acoustical panels not installed
3. Floor not sealed
4. Vinyl base board not installed
5. Light fixture not installed
6. Mop sink and faucet not installed
7. Water heater not installed
8. Floor drain cover not installed
9. Mop/Broom holder installed
Men’s RM 107 Figure 105
1. Suspension acoustical panels not completed
2. Acoustical panels not installed
3. Vinyl composite tile not installed
4. Vinyl base board not installed
5. Light fixture not installed
6. Plumbing fixtures (toilet, sink, faucets) not installed
7. Partitions and accessories not installed
8. Mirror not installed
9. Grab bar not installed
10. Soap dispenser and paper towel dispenser not installed
11. 1 hour fire stop not installed Figure 106
12. Floor drain cover not installed
Break Room RM 108 Figure 107
1. Suspension acoustical panels not completed
2. Acoustical panels not installed
3. Vinyl composite tile not installed
4. Vinyl base board not installed
5. Light fixture not installed
6. Plumbing fixtures (kitchen sink and faucet) not installed
7. Lower and upper cabinets
8. Closet door frame and assembly
9. 2 Man doors (D12 & D11) to break room not installed
10. Expansion material
11. 1 hour fire stop not installed
Control Center RM 109 Figure 108
1. Suspension acoustical panels not completed
2. Acoustical panels not installed
3. Vinyl composite tile not installed
4. Vinyl base board not installed
5. Light fixture not installed
6. Expansion material
7. 1 hour fire stop not installed
Corridor RM 110
1. Suspension acoustical panels not completed
2. Acoustical panels not installed
3. Vinyl composite tile not installed
4. Vinyl base board not installed
5. Light fixture not installed
6. Fire Extinguisher
7. Door not installed
8. Fire Extinguisher not installed
Closet RM 111
1. Painted gypsum board on ceiling not installed.
2. Vinyl composite tile not installed
3. Vinyl base board not installed
4. Light fixture not installed
5. Doors
Projection RM 112 Figure 111
1. Suspension acoustical panels not completed
2. Acoustical panels not installed
3. Vinyl composite tile not installed
4. Vinyl base board not installed
5. Light fixture not installed
6. 1 Hour Firestop not installed
Network RM 113 Figure 112
1. Suspension acoustical panels not completed
2. Acoustical panels not installed
3. Vinyl composite tile not installed
4. Vinyl base board not installed
5. Light fixture not installed
6. Expansion material
7. Towel dispenser/Waste receptacle not installed
8. 1 Hour Firestop not installed
Stair No. 2 RM 114 Figure 113
1. Painted gypsum board on ceiling not installed.
2. Vinyl composite tile not installed
3. Vinyl base board not installed
4. Light fixture not installed
5. Joints need backer rod and caulk Figure 114
6. Wall damage from through bolts Figure 114
Closet RM 115 Figure 115
1. Painted gypsum board on ceiling not installed.
2. Vinyl composite tile not installed
3. Vinyl base board not installed
4. Light fixture not installed
5. Doors
UPS Rm 116 Figure 116
1. Suspension acoustical panels not completed
2. Acoustical panels not installed
3. Vinyl composite tile not installed
4. Vinyl base board not installed
5. Light fixture not installed
6. 1 Hour Firestop not installed
Pump Gallery RM117 Figure 117
1. Reveals need second coat of paint
2. Sealed concrete floor not completed
3. Expansion material
Elevator Equipment Room RM 118 Figure 118
1. Concrete Floor not sealed
173.81 Electrical Room RM 201 Figure 119
1. Concrete Floor not sealed
Upper North Pump Bay RM 202 Figure 120
1. Concrete Floor not sealed
Upper Center Pump Bay RM 203 Figure 121
1. Concrete Floor not sealed
Upper South Pump Bay RM 204 Figure 122
1. Concrete Floor not sealed
Stair No. 1 - 205 Figure 123
1. Concrete Floor not sealed
2. Hand rails and guard rails not painted
3. Door not installed (D26)
Stair No. 2 - 206 Figure 124
1. Concrete Floor not sealed
2. Hand rails and guard rails not painted
3. 1 Hour fire rated wall missing Figure 125
162.31 Maintenance Room RM 301 Figure 126
1. Concrete Floor not sealed
Stair No. 1 - 302 Figure 127
1. Concrete Floor not sealed
2. Hand rails and guard rails not painted
3. Door not installed (D27)
Stair No. 2 - 303 Figure 128
1. Concrete Floor not sealed
2. Hand rails and guard rails not painted
3. Door not installed (D30)
150.81 Mechanical Room RM 401 Figure 129
1. Concrete Floor not sealed
Lower North Pump Bay RM 402 Figure 130
1. Concrete Floor not sealed
2. Mud covering anchor bolts to be cleaned and painted
Lower Center Pump Bay RM 403 Figure 132
1. Concrete Floor not sealed
Lower South Pump Bay RM 404 Figure 133
1. Concrete Floor not sealed
2. Mud covering anchor bolts to be cleaned and painted
Stair No. 1 - 405 Figure 134
1. Concrete Floor not sealed
2. Hand rails and guard rails not painted
3. Door not installed (D28)
Stair No. 2 - 406 Figure 135
1. Concrete Floor not sealed
2. Hand rails and guard rails not painted
3. Door not installed (D31)
Figure 98. All doors and door frames to be replaced
Figure 99. Down Spouts Missing East Side (4)
Figure 100. El 190, Rm 101
Figure 101. El. 190, Rm 101 & Rm 102: Widow Sills Missing
Figure 102. El. 190, Rm 102
Figure 103. El. 190, Rm 105
Figure 104. El. 190, Rm 106
Figure 105. El 190, Rm 107
Figure 106. El. 190 Rm 107: 1 Hour Firestop not installed
Figure 107. El. 190, Rm 108
Figure 108. El. 190, Rm 109
Figure 109. El 190, Rm 110
Figure 110. El 190, Rm 111
Figure 111. El 190, Rm 112
Figure 112. El. 190, Rm 113
Figure 113. El 190, Rm 114
Figure 114. El. 190, Rm 114: Joints need backer rod and caulk; wall damaged from through bolts
Figure 115. El 190, Rm 115
Figure 116. El 190 Rm 116
Figure 117. El. 190, Rm 117
Figure 118. El. 190, Rm 118
Figure 119. El 173.81, Rm 201
Figure 120. El. 173.81, Rm 202
Figure 121. El 173.81, Rm 203
Figure 122. El 173.81, Rm 204
Figure 123. El 173.81 Rm 205
Figure 124. El 173.81, Rm 206
Figure 125. El 173.81, Stair No. 2: 1 Hour Fire Wall missing
Figure 126. El 162.31, Rm 301
Figure 127. El 162.31, Rm 302
Figure 128. El 162.31, Rm 303
Figure 129. El 150.81, Rm 401
Figure 130. El 150.81, RM 402
Figure 131. El 150.81, RM 402: Mud covering anchor bolts - to be cleaned and painted to match pump housing
Figure 132. El 150.81, Rm 403
Figure 133. El 150.81, Rm 404
Figure 134. El 150.81, Rm 405
Figure 135. El 150.81, Rm 406
5. Civil: Identified remaining and deficient civil features include but are not limited to the following:
5.1. Drainage
5.1.1. Ensure positive drainage away from all structures at the site and ensure a smooth transition from all constructed slopes to tie-in with existing slopes at the site. Do not block existing drainage during construction.
5.2. Disposal of Materials
5.2.1. The disposal of all items and material at the site shall be in accordance with all federal, state, and local regulations.
5.3. Handicap Parking Slab
5.3.1. Ensure all construction requirements, with the exception of the striping work, as shown in the plans and specifications are completed for the handicap parking slab.
5.4. Fencing
5.4.1. Ensure all fence construction work is in accordance with the plans and specifications.
5.5. Maintenance of Existing Access Road
5.5.1. Contractor shall maintain the existing access road according to the plans and specifications for the duration of the project.
5.6. Complete all items of work and correct all identified and discovered deficiencies in
Table 5. Identified remaining and deficient civil features
Exterior Wheel stop and signage not complete at Handicap parking slab Figure 136
Positive drainage away from completed structures to be established Figure 137
Mounds of dirt and debris to be removed Figure 138
Settling of unauthorized burn pit to be fixed to accommodate positive drainage
Figure 139
Waste concrete, debris, abandoned erosion control measures, and trash to be removed from site (multiple locations)
Figure 140
Post near air/vacuum valves to be removed Figure 141
Sludge and trash in abandoned fueling station to be disposed of per regulations
Figure 142
Contaminated soil from hydraulic oil to be disposed of per regulations (multiple locations)
Figure 143
Cross bracing on surge tank fencing unacceptable Figure 144
Maintenance of existing access road required for duration of project Figure 145
Figure 136. Wheel stop and signage not complete at handicap parking slab
Figure 137. Positive drainage away from completed structures to be established
Figure 138. Mounds of dirt and debris to be removed
Figure 139. Settling of unauthorized burn pit to be fixed to accommodate positive drainage
Figure 140. Waste concrete, debris, abandoned erosion control measures, and trash to be removed from site (multiple locations)
Figure 141. Post near air/vacuum valves to be removed
Figure 142. Sludge and trash in abandoned fueling station to be disposed of per regulations
Figure 143. Contaminated soil from hydraulic oil to be disposed of per regulations (multiple locations)
Figure 144. Cross bracing on surge tank fencing unacceptable
Figure 145. Maintenance of existing access road required for duration of project