Attachment 6 - GNV EHRM - Phasing Plan - 260618.pdf
PDF 101 KB Posted
- Attached to
- Y1DA--573-21-106 EHRM Infrastructure Upgrades and Data Center Construction - Gainesville VAMC
- Solicitation number
- 36C77626B0026
About this file
This is a construction phasing plan for the GNV EHRM (Gainesville Electronic Health Records Management) project dated 6/18/26, detailing the sequencing and timing of various construction activities across multiple buildings and floors.
The plan outlines work initiation requirements for several construction categories: Data Center work can begin at any time following Notice to Proceed; Sitework and ductbank construction can commence following Notice to Proceed with coordination required to mitigate impacts on ongoing facility operations; shell construction for technical rooms (TRs) designated as Phase 0 can start immediately after Notice to Proceed; and Phases 1-8 shell construction must proceed sequentially upon Notice to Proceed for Phase 1, with subsequent phases requiring completion or Contracting Officer Representative (COR) approval before advancement. Data Cable Replacement work will begin in sequence mirroring the TR shell construction upon Data Center activation and affected TR completion. The document provides a comprehensive matrix identifying 75+ specific building areas (designated by codes such as C263A-1, G161-1, H133-1, and others) mapped to their respective construction phases (0 through 8), buildings, and floor locations. The phasing approach ensures coordinated progression through the facility while maintaining operational continuity and allowing for COR oversight at critical completion milestones.
View the file
Other files
Show all 33
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Construction Phase Area Building Floor
N/A Data Center T11 1 Data Center Work on the Data Center construction can be statted at any time following Notice to Proceed
N/A Sitework N/A N/A
Sitework Sitework and ductbank construction can be started at any time following Notice to Proceed. Impact to on-going facility operations will need to be coordinated and mitigated.
0 C263A-1 1 1 Phase 0 Shell construction for these TRs can be started at any time following Notice to Proceed.
G161-1 1 1
Phase 1 - 8 Shell construction can be started on upon Notice to Proceed on Phase 1 and then following completion or approval from COR, work can proceed to next phase, one by one.
H133-1 1 1 Data Cable
Replacement Data Cable Replacement can begin in a sequencing mirroring the TR shell construction sequence upon activation of the Data Center and the effected TRs
0 110-12 12 1 0 A241-1 1 2 0 E261-1 1 2 0 A341-1 1 3 0 E357A-1 1 3 0 A441-1 1 4 0 E449-1 1 4 0 A543-1 1 5 0 E561A-1 1 5 0 J527-1 1 5 1 A132-1 1 1 1 C259-1 1 1 1 D304-1 1 1 1 E154-1 1 1 1 E154-1 1 1 1 E154-1 1 1 2 F122-1 1 1 2 F122-1 1 1 2 J138-1 1 1 2 J138-1 1 1 2 122-14 14 1 2 A210-1 1 2 3 110-12 12 1 3 247-12 12 2 3 E303-1 1 3 3 347-12 12 3 3 J427-1 1 4 4 202-28 28 2 4 A502-1 1 5 4 E503-1 1 5 4 E503-1 1 5 4 H519-1 1 5 5 B050C-1 1 B 5 C085A-1 1 B
5 EB51A-1 1 B
5 FB28L-1 1 B
6 H235-1 1 2 6 H235-1 1 2 6 J227-1 1 2 6 A305-1 1 3 6 A305-1 1 3
6 FB23B-1 1 B
7 H335-1 1 3 7 J327-1 1 3 7 A402-1 1 4 7 H435-1 1 4 8 117-11 11 1 8 117-11 11 1 8 A030A-1 1 B
Phasing Key
GNV EHRM Phasing Plan - 6/18/26
Sheet1