Attachment_6_-_Cost_Proposal.xls

XLS spreadsheet 47 KB Posted

Attached to
HPTC SELECTIVE REPLACEMENT OF PALISADE
Solicitation number
140P2124R0075
Issued by

About this file

This document appears to be a detailed cost proposal for a federal contract opportunity titled "HPTC SELECTIVE REPLACEMENT OF PALISADE". The opportunity is solicited by the Department of the Interior National Park Service under Solicitation Number 140P2124R0075.

The cost proposal provides a breakdown of the estimated construction costs for the FOVA Palisade Wall Replacement project, including material, labor, equipment, and subcontractor costs for items such as pickets, king posts, and walers. It also includes general conditions, overhead, and profit estimates. The total estimated net construction cost is $0. The document also includes a labor breakdown with estimated hourly rates for various roles such as project manager, superintendent, and administrative assistant.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bid Schedule

Project: FOVA Palisade Wall Replacement
Park: FOVA
PMIS: 239761A
MaterialLaborEquipmentSubcontractorTotal
Item No.DescriptionCost/UnitMat'l CostCost/UnitLabor CostCost/UnitEquip. CostCostCost/UnitTOTAL
02230.200-0300Pickets$0$0$0$0.00$0
02230.200-0300King Posts$0$0$0$0.00$0
02230.200-0300Walers$0$0$0$0.00$0
Items 1-3$0$0$0$0
Subtotal$0$0$0$0
General ConditionsAllocated$0
Subtotal$0$0$0$0
OverheadPercent$0$0$0$0
ProfitPercent$0$0$0$0
Subtotal$0$0$0$0
TOTAL Estimated NET Construction Cost$0$0$0$0

&C&11Class A Construction Cost Estimate &LPage &P&C&11&A&RPrinted &D

Labor Breakout

Project: FOVA Palisade Wall ReplacementEstimate By:BDS
Park: FOVADate:03/26/24
PMIS: 239761A
ItemDescriptionQuantityUnitUnit PriceTotal
Project ManagerHrly$0.00
Superintendent (Salary/Per Diem)Hrly$0.00
Admin. Asst.Hrly$0.00
EstimatingHrly$0.00
SchedulingHrly$0.00
Fork lift crewHrly$0.00
Vac truckHrly$0.00
Project SafetyLS$0.00
As-Built DrawingsLS$0.00
Temporary PowerJob$0.00
Bondls$0.00
Toilet FacilitiesMonths$0.00
Total Estimated Cost General Conditions$0.00

&C&11Class A Construction Cost Estimate &LPage &P&C&11&A&RPrinted &D

File details come from the government source that posted it. Updated .