This document appears to be a detailed cost proposal for a federal contract opportunity titled "HPTC SELECTIVE REPLACEMENT OF PALISADE". The opportunity is solicited by the Department of the Interior National Park Service under Solicitation Number 140P2124R0075.
The cost proposal provides a breakdown of the estimated construction costs for the FOVA Palisade Wall Replacement project, including material, labor, equipment, and subcontractor costs for items such as pickets, king posts, and walers. It also includes general conditions, overhead, and profit estimates. The total estimated net construction cost is $0. The document also includes a labor breakdown with estimated hourly rates for various roles such as project manager, superintendent, and administrative assistant.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid Schedule
| Project: FOVA Palisade Wall Replacement | ||||||||||||
| Park: FOVA | ||||||||||||
| PMIS: 239761A | ||||||||||||
| Material | Labor | Equipment | Subcontractor | Total | ||||||||
| Item No. | Description | Cost/Unit | Mat'l Cost | Cost/Unit | Labor Cost | Cost/Unit | Equip. Cost | Cost | Cost/Unit | TOTAL | ||
| 02230.200-0300 | Pickets | $0 | $0 | $0 | $0.00 | $0 | ||||||
| 02230.200-0300 | King Posts | $0 | $0 | $0 | $0.00 | $0 | ||||||
| 02230.200-0300 | Walers | $0 | $0 | $0 | $0.00 | $0 | ||||||
| Items 1-3 | $0 | $0 | $0 | $0 | ||||||||
| Subtotal | $0 | $0 | $0 | $0 | ||||||||
| General Conditions | Allocated | $0 | ||||||||||
| Subtotal | $0 | $0 | $0 | $0 | ||||||||
| Overhead | Percent | $0 | $0 | $0 | $0 | |||||||
| Profit | Percent | $0 | $0 | $0 | $0 | |||||||
| Subtotal | $0 | $0 | $0 | $0 | ||||||||
| TOTAL Estimated NET Construction Cost | $0 | $0 | $0 | $0 |
&C&11Class A Construction Cost Estimate &LPage &P&C&11&A&RPrinted &D
Labor Breakout
| Project: FOVA Palisade Wall Replacement | Estimate By: | BDS | |||
| Park: FOVA | Date: | 03/26/24 | |||
| PMIS: 239761A | |||||
| Item | Description | Quantity | Unit | Unit Price | Total |
| Project Manager | Hrly | $0.00 | |||
| Superintendent (Salary/Per Diem) | Hrly | $0.00 | |||
| Admin. Asst. | Hrly | $0.00 | |||
| Estimating | Hrly | $0.00 | |||
| Scheduling | Hrly | $0.00 | |||
| Fork lift crew | Hrly | $0.00 | |||
| Vac truck | Hrly | $0.00 | |||
| Project Safety | LS | $0.00 | |||
| As-Built Drawings | LS | $0.00 | |||
| Temporary Power | Job | $0.00 | |||
| Bond | ls | $0.00 | |||
| Toilet Facilities | Months | $0.00 | |||
| Total Estimated Cost General Conditions | $0.00 |
&C&11Class A Construction Cost Estimate &LPage &P&C&11&A&RPrinted &D