ATTACHMENT 6 AE PEREZ AC REPLACEMENT ELECTRICAL_AC DISTRO FINAL REPORT.pdf

PDF 1 MB Posted

Attached to
Request for Proposals No. 72066823R00016 for USAID/South Sudan Residential Compound (RC) and Embassy Compound (EC) AC System Upgradation Project
Solicitation number
720668
Issued by

About this file

This document outlines requirements for upgrading air conditioning systems at the US Agency for International Development's Residential Compound and Embassy Compound in South Sudan. Contractors are requested to propose electrical modifications to distribution systems and installation of new AC units. Proposals are due by March 23, 2023. The contract will require assessment of existing electrical infrastructure to identify necessary upgrades to support three-phase power for outdoor AC units. New distribution panels, circuit breakers, and wiring must be installed as specified. Contractors must also install 225 new AC units matched to buildings and allocate units between the compounds. Work will take approximately five months and quality control plans will ensure standards are met. Pricing should cover all labor, materials, project management costs, and profit. The award date is not specified.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PAGE 1 REPLACEMENT OF AIR CONDITION (AC) UNITS AT THE EMBASSY COMPOUND (EC) AND THE RESIDENCE COMPOUND (RC) – ELECTRICAL

MODIFICATION AND AC INSTALLATION WORKS (ANNEX 2)

Submission Date: 14 March, 2023

IDIQ CONTRACT NO: AID‐OAA‐I‐15‐00051

SOUTH SUDAN ENGINEERING SUPPORT PROGRAM

CONTRACT 72066820F00003

SOUTH SUDAN

ENGINEERING SUPPORT PROGRAM

REPLACEMENT OF AIR CONDITION (AC) UNITS

AT THE EMBASSY COMPOUND (EC) AND THE

RESIDENCE COMPOUND (RC) – ELECTRICAL

MODIFICATION AND AC INSTALLATION

WORKS (ANNEX 2)

PEREZ, A PROFESSIONAL CORPORATION

2525 BURGUNDY STREET, NEW ORLEANS, LOUISIANA 70117

TELEPHONE 504.584.5100 FACSIMILE 504.584.5140 www.e-perez.com

PAGE ii REPLACEMENT OF AIR CONDITION (AC) UNITS AT THE EMBASSY COMPOUND (EC) AND THE RESIDENCE COMPOUND (RC) – ELECTRICAL

PAGE iii REPLACEMENT OF AIR CONDITION (AC) UNITS AT THE EMBASSY COMPOUND (EC) AND THE RESIDENCE COMPOUND (RC) – ELECTRICAL

ARCHITECTURE

ENGINEERING

PLANNING

INTERIORS

LANDSCAPE

CONSTRUCTION

DEVELOPMENT

March 14, 2023

US Agency for International Development ATTN: Bahro Bar, Construction Manager/Alternate Contracting Officer’s Representative (A/COR) USAID/South Sudan

RE: South Sudan Engineering Support Program

Contract 72066820F00003/Job Order #3 Replacement of Air Conditioning (AC) Units at the Residence Compound (RC) and the Embassy Compound (EC) – Report on Electrical Modification and AC Installation Works (Annex 2)

Dear Mr. Bahro Bar:

Perez APC, in conjunction with our sub consultant Liberty Engineering and Construction Ltd, is submitting the attached report on the Electrical Modification and AC Installation Works for the Replacement of AC Units at the RC and the EC for the referenced contract under the Indefinite Delivery Indefinite Quantity (IDIQ) Contract for Global Architecture and Engineering II Infrastructure Services Contract No. AID-OAA-I-15-00051/Contract 72066820f00003.

The report includes sections on electrical site assessment conducted to document the existing midstream and downstream electrical distribution system conditions as it relates to the existing and new AC units; inventory of existing and new AC units; allocation of new AC units; recommendations on the electrical modification works required for the decommission of the existing AC units and installation of the new AC units; and cost estimate for both the electrical modification and AC installation works.

Please review and let us know if you have any questions or require additional information.

Sincerely, Femi Ade, Ph.D., P.Eng

DEPUTY PROGRAM MANAGER

PAGE 1 REPLACEMENT OF AIR CONDITION (AC) UNITS AT THE EMBASSY COMPOUND (EC) AND THE RESIDENCE COMPOUND (RC) – ELECTRICAL

Contents

EXECUTIVE SUMMARY 3

1. INTRODUCTION 4

1.1 PROBLEM STATEMENT 4

2. SITE ASSESSMENT 4

2.1 SITE ASSESSMENT OBJECTIVE 4

2.2 SITE ASSESSMENT TEAM 7

3. SITE ASSESSMENT FINDINGS 9

3.1 ELECTRICAL DISTRIBUTION SYSTEM 9

3.2 REQUIRED ELECTRICAL CHANGES FOR EACH BUILDING 10

4. INVENTORY OF NEW AC UNITS, MATCHING OF AC OUTDOOR UNITS TO AC INDOOR

UNITS AND ALLOCATION OF AC UNITS TO BUILDINGS 17

4.1 INVENTORY OF NEW AC UNITS 17

4.2 MATCHING OF AC OUTDOOR UNITS TO AC INDOOR UNITS AND ALLOCATION OF

AC UNITS TO HOUSES / BUILDINGS 18

5. QUALITY CONTROL 19

5.1 QUALITY CONTROL PLAN 19

5.2 INSPECTION STAGES 19

5.3 TESTING AND RECORDS 20

5.4 AS‐BUILT DOCUMENTATION 20

6. SCHEDULE 20

7. COST ESTIMATE 21

7.1 BASIS OF COST ESTIMATE 21

7.2 DETAILED COST ESTIMATE 21

8. CONCLUSIONS AND RECOMMENDATIONS 22

8.1 CONCLUSIONS 22

8.2 RECOMMENDATIONS 22

APPENDICES 24

Appendix A: Table Detailing Findings on Electrical Distribution System and Required Electrical Solution for the RC 24

Appendix B: Table Detailing Findings on Electrical Distribution System and Required Electrical Solution for the EC 35

PAGE 2 REPLACEMENT OF AIR CONDITION (AC) UNITS AT THE EMBASSY COMPOUND (EC) AND THE RESIDENCE COMPOUND (RC) – ELECTRICAL

Appendix C: Calculation Sheet for Arriving at Circuit Breakers Current Rating 39

Appendix D: Inventory of Existing AC Units & Matching and Allocation of New AC Units for the RC 42

Appendix E: Inventory of Existing AC Units & Matching and Allocation of New AC Units for the EC 47

Appendix F: Detailed Cost Estimate for Electrical Modification Works 50

Appendix G: Detailed Cost Estimate for AC Installation Works 58

List of Tables

TABLE 1 SITE ASSESSMENT TEAM

TABLE 2 SUMMARY OF REQUIRED ELECTRICAL CHANGES IN THE RC

TABLE 3 SUMMARY OF REQUIRED ELECTRICAL CHANGES IN THE EC

TABLE 4 INVENTORY OF NEW AC UNITS

TABLE 5 AC UNITS – PURCHASED, ALLOCATED AND REMAINING QUANTITIES

TABLE 6 SUMMARY COST ESTIMATE

List of Figures

FIGURE 1 RC LAYOUT PLAN

FIGURE 2 EC LAYOUT PLAN

FIGURE 3 SINGLE LINE DRAWING (SLD) OF 150A OUTDOOR DISTRIBUTION PANEL WITH 13

OUTGOING FEEDERS AND METERING

FIGURE 4 SINGLE LINE DRAWING (SLD) OF 400A OUTDOOR DISTRIBUTION PANEL WITH 30

OUTGOING FEEDERS AND METERING

FIGURE 5 SINGLE LINE DRAWING (SLD) OF 100A OUTDOOR DISTRIBUTION PANEL WITH 25

OUTGOING FEEDERS AND METERING

FIGURE 6 SINGLE LINE DRAWING (SLD) OF 100A OUTDOOR DISTRIBUTION PANEL WITH 12

OUTGOING FEEDERS AND METERING

PAGE 3 REPLACEMENT OF AIR CONDITION (AC) UNITS AT THE EMBASSY COMPOUND (EC) AND THE RESIDENCE COMPOUND (RC) – ELECTRICAL

EXECUTIVE SUMMARY

USAID is planning to decommission existing AC units in the Residence Compound (RC) and the Embassy Compound (EC) and replace them with new ones. USAID contracted Perez to conduct a feasibility assessment of the suitability of the present midstream to downstream electrical distribution system to power the new AC units and to recommended solutions where the electrical distribution system was not suitable. This report details the current condition of the sub-distribution panel powering each building and the changes that are required in terms of addition to or replacement of the sub-distribution panel and other electrical materials so that the downstream distribution system supplies the right power phase (3-phase or 1-phase) to the AC units. Additionally, this report details how the new AC units are allocated to the various buildings and the quality control plan expected from the AC contractor to install the AC units. Cost estimates for the electrical modification and AC installation works are presented.

PAGE 4 REPLACEMENT OF AIR CONDITION (AC) UNITS AT THE EMBASSY COMPOUND (EC) AND THE RESIDENCE COMPOUND (RC) – ELECTRICAL

1. INTRODUCTION

1.1 Problem Statement

The USAID compound consists of the Residence Compound (RC) and the Embassy Compound (EC). The RC is the bigger compound with more buildings and it is located about 300 meters east of EC. The layout plans for the RC and the EC are provided in Figure 1 and Figure 2 respectively.

USAID wants to replace the current AC units in 40 buildings in the RC and 10 buildings in the EC with newly purchased units, however USAID needs to know if the current electrical distribution systems at both the RC and the EC are suitable to successfully power the new AC units and if not, provide recommendations on the changes required to make the electrical distribution system suitable to power the new AC units.

At the RC, the current AC system has the indoor unit powered by single phase power from inside each building and the indoor unit in turn powers the outdoor unit with the same single phase power. With the new AC units, the outdoor units will be powered separately by three phase power and the indoor units are powered separately by single phase power. Due to this differing power requirement for the current AC system and the new ones, a problem has arisen which must be solved by a site assessment to verify if the current electrical distribution system for each of the 40 buildings in question is suitable for the new AC units. If unsuitable, actions must be recommended to be carried out to make the electrical distribution system suitable for the new AC units.

The same applies to the 10 buildings in question at EC because the AC units are either powered the same way as the AC units in RC or in the reverse way; that is the outdoor unit is powered by single phase and the outdoor unit in turn powers the indoor unit. Additionally, an assessment must be carried out to confirm if the electrical distribution panel can supply power to the new AC units based on availability of spare circuit breakers in the electrical distribution panels.

2. SITE ASSESSMENT

2.1 Site Assessment Objective

The objective of the site assessment is to provide answers to the problem statement above without causing disruption to the power supply for the use of occupants at both the RC and the EC. The electrical distribution system for each building in the two compounds, with the exception of those buildings that were determined by USAID as not necessary or priority, had to be assessed to determine its suitability to supply power to the new AC units when installed.

PAGE 5 REPLACEMENT OF AIR CONDITION (AC) UNITS AT THE EMBASSY COMPOUND (EC) AND THE RESIDENCE COMPOUND (RC) – ELECTRICAL MODIFICATION AND AC INSTALLATION WORKS (ANNEX 2)

Figure 1 RC Layout Plan

PAGE 6 REPLACEMENT OF AIR CONDITION (AC) UNITS AT THE EMBASSY COMPOUND (EC) AND THE RESIDENCE COMPOUND (RC) – ELECTRICAL MODIFICATION AND AC INSTALLATION WORKS (ANNEX 2)

Figure 2 EC Layout Plan

PAGE 7 REPLACEMENT OF AIR CONDITION (AC) UNITS AT THE EMBASSY COMPOUND (EC) AND THE RESIDENCE COMPOUND (RC) – ELECTRICAL

2.2 Site Assessment Team

The electrical site assessment was carried out on the 26th and 27th of October 2022 at the RC and 4th of November 2022 at the EC. Follow-up site visits were made to both the RC and the EC to collect additional information or confirm collected information. The composition of the site assessment team is shown in Table 1 below with further details.

Table 1 Site Assessment Team

S/No Name Affiliation Job Title Role

1 Femi Ade Liberty Deputy Program Manager

To escort Ogochukwu & Henry within the embassy compound

2 Ogochukwu Okoh Liberty Senior Electrical Engineer

Collection of data

3 Henry Ssemwezi Liberty Senior Electrician Technical support for Ogochukwu

4 Bossi Jibi USAID Senior Electrician To provide historical knowledge

5 Joshua RA Master Electrician To accompany team based on COR’s (Richard Nyarsuk) request

6 William Lyons Perez Program Manager Technical Adviser

2.3 Methodology

The methodology used was to start from downstream by examining the switch gear (isolator or sub – distribution panel or junction box) supplying power to each of the building or houses or townhouses for the presence of three phase power since three phase power supply is needed for the new AC units. Additionally, Perez was required to check for the availability of spare circuit breaker(s) in the sub-distribution panel. In the case where there was no spare circuit breaker(s), Perez had to check if there was enough space in the sub-distribution panel to fit extra circuit breaker(s) (as shown in Picture 1 below) needed to power the new units with 3-phase for the outdoor unit and single phase for the indoor unit. Where three phase power supply was not available at the downstream, we had to investigate the reason by examining the midstream.

PAGE 8 REPLACEMENT OF AIR CONDITION (AC) UNITS AT THE EMBASSY COMPOUND (EC) AND THE RESIDENCE COMPOUND (RC) – ELECTRICAL

PICTURE 1: Showing Availability of Space to Fit Extra Circuit Breakers to Power AC Outdoor 3-Phase Unit in RC.

In the RC, the distribution panel midstream and the sub-distribution panel or junction box downstream had to be opened safely without causing disruption to the power supply and without harm to the assessment team and data collected for townhouse 6 to townhouse 41. The isolators for House 1 to House 4 were also examined and the corresponding data were collected. The same methodology was applied for the 10 buildings in the EC.

For the RC, the existing AC indoor units are single phase and the new AC indoor units are also single phase so there is no issue. The challenge comes with the outdoor unit because the existing outdoor units are single phase powered while the new outdoor units are three phase powered. As a result, some modifications have to be made to the downstream distribution system to make three phase power supply available to the new outdoor units.

Similar challenge exists with all buildings at EC although with a slight variation in the chancery building where the existing AC units are powered such that single phase power flows to the outdoor units and the outdoor units in turn powers the indoor units.

PAGE 9 REPLACEMENT OF AIR CONDITION (AC) UNITS AT THE EMBASSY COMPOUND (EC) AND THE RESIDENCE COMPOUND (RC) – ELECTRICAL

3. SITE ASSESSMENT FINDINGS

3.1 Electrical Distribution System

For the RC, of the 40 building structures, House 1 to House 4 are bungalows that have an isolator as supply into the building and not a distribution panel. For Townhouse 6 to Townhouse 41, it is a case of either a distribution panel or a junction box supplying power to the townhouse.

Additionally, Townhouse 6 to Townhouse 41 are two storied buildings with each floor having its own or shared sub-distribution panel.

For the EC, each of the 10 buildings has its respective sub-distribution panel supplying power.

The cumulative load current flowing into the sub-distribution panels at both downstream and midstream were taken at morning time (between 9:30am and 11:30am) and its was found that the most loaded sub-distribution panel was only using 13% of its total capacity on its most loaded phase. Please take note that Perez APC and Liberty are also working on the Juba Compound Electrical Upgrade (JCEU) project and power analysis done on that project shows that around 11a.m. is when the load tends to peak at both the RC and the EC, which is about the same time current readings were taken during our site assessment. This proves that there is spare capacity of about 83% on the sub-distribution panels at both downstream and midstream. Furthermore, since the Embassy is swapping AC units, we are therefore relieving the power network of the existing AC units and replacing them with more energy efficient AC units. This would lead to less consumption of electrical energy upstream. Additionally, from submittals reviewed on the JCEU project, we see that load allowance for the new AC units has been considered.

All feeder cables are adequately sized to 100% capacity of sub-distribution panel they are feeding, although these feeder cables are only 13% loaded at peak load.

Earthing is a very important part of any electrical work because a good earthing ensures safety of life; as any occurrence of leakage current will be safely carried down to earth. When the sub-distribution panels midstream and downstream were opened, it was noticed that for townhouses 6 to 17 as well as townhouses 18 and 21 there are 4 core armoured cables entering and exiting the midstream sub-distribution panel and entering the downstream sub-distribution panel. Of the 4 cores, 1 core was used for phase 1, 1 core was used for phase 2, 1 core was used for neutral and 1 core was used for earthing; which is in addition to the earthing already achieved by the steel wired armour (SWA) connected to the metal body of the sub-distribution panel using a metallic (brass - an alloy of copper) gland. On discussion with USAID (Mr. Bossi) about achieving three phase supply for the outdoor units, it was agreed that the 1 core used for earthing be withdrawn and used as the phase 3 to complete the three phase power supply for the AC outdoor units while the SWA which is part of the cable, continues to serve as the earth conductor.

PAGE 10 REPLACEMENT OF AIR CONDITION (AC) UNITS AT THE EMBASSY COMPOUND (EC) AND THE RESIDENCE COMPOUND (RC) – ELECTRICAL

3.2 Required Electrical Changes for Each Building

The site assessment findings are tabulated in detail in Appendix A and Appendix B for the RC and the EC respectively. Table 2 and Table 3 below show summaries of required actions to be taken for each building to make the existing electrical distribution system suitable for the new AC units at the two compounds.

Some of the required actions are the addition of 4 quantities of 150A outdoor sub-distribution panel with 13 outgoing feeders and metering, 1 quantity of 400A outdoor sub-distribution panel with 30 outgoing feeders and metering, 2 quantities of 100A outdoor sub-distribution panel with 25 outgoing feeders and metering as well as 15 quantities of 100A outdoor sub-distribution panel with 12 outgoing feeders and metering. The single line drawings (SLDs) for these sub-distribution panels are shown in Figure 3 to Figure 6 below; with Appendix C showing the calculations of how the current rating of the circuit breakers in Figure 3 to Figure 6 were determined.

It is important to state at this point that a required action in this report might overlap with a solution in another contract or report. Whichever contract is executed first will then take the lead for the implementation of the required action or solution while the overlapping solution or required action in the succeeding contract will be removed.

Table 2 Summary of Required Electrical Changes in the RC

S/No. House /Townhouse Unit

Required Actions

1 Houses 1 to 4 Each building will require a new 150A 3-phase outdoor sub-distribution panel with 13 outgoing feeders as well as connecting cables to modify the distribution supply for presence of adequate 3-phase for outdoor units.

2 Townhouses 6 to 17

A new 400A 3-phase outdoor sub-distribution panel with 30 outgoing feeders to replace CH2DP and the introduction of 1 number of 30A 3P MCCB in each sub-distribution panel of townhouse 6 to 17 with connecting cables.

3 Townhouses 18 and 21

Add 4 numbers of 30A 3P MCCB in DP21; 2 numbers each for townhouses 18 and 21 with connecting cables.

4 Townhouses 19, 23, 24, 27, 28, 30, 31, 33, 1 number of new 100A outdoor sub-distribution panel with 12 outgoing feeders to be added for each townhouse with connecting cables.

PAGE 11 REPLACEMENT OF AIR CONDITION (AC) UNITS AT THE EMBASSY COMPOUND (EC) AND THE RESIDENCE COMPOUND (RC) – ELECTRICAL

S/No. House /Townhouse Unit

Required Actions

34B, 35, 36, 39 and 40

5 Townhouses 20 and 22

Add 4 numbers of 30A 3P MCCB in 100A sub-distribution panel 20A with connecting cables.

6 Townhouse 25 Add 2 numbers of 30A 3P MCCB in 100A sub-distribution panel 25A with connecting cables.

7 Townhouse 26 Add 2 numbers of 30A 3P MCCB in 100A sub-distribution panel 26 with connecting cables.

8 Townhouse 29 Add 2 numbers of 30A 3P MCCB in 100A sub-distribution panel 29 with connecting cables.

9 Townhouse 32 Add 2 numbers of 30A 3P MCCB in 100A sub-distribution panel 32 with connecting cables.

11 Townhouses 37 and 38

Add 4 numbers of 30A 3P MCB in 250A sub-distribution panel 38;

2 numbers each for townhouses 37 and 38 with connecting cables.

13 Townhouse 41 (Electrical distribution system is sufficient). Add connecting cables.

Table 3 Summary of Required Electrical Changes in the EC

S/No. Building Required Actions

1 Chancery Building (Ground Floor)

Add 1 number of 100A 3P MCCB in 600A sub-distribution panel to feed 1 number of new 100A outdoor sub-distribution panel with 25 outgoing feeders that will also be added.

Add connecting cables.

2 Chancery Building (First Floor)

Add 1 number of 100A 3P MCCB in 600A sub-distribution panel to feed 1 number of new 100A outdoor sub-distribution panel with 25 outgoing feeders that will also be added.

Add connecting cables.

3 New Safe Heaven Add 3 numbers of 30A 3P MCCB in 125A sub-distribution panel SHU12 with connecting cables.

PAGE 12 REPLACEMENT OF AIR CONDITION (AC) UNITS AT THE EMBASSY COMPOUND (EC) AND THE RESIDENCE COMPOUND (RC) – ELECTRICAL

S/No. Building Required Actions

4 Old Safe Heaven (Electrical distribution system is sufficient). Add connecting cables.

5 State Department Add 8 numbers of 30A 3P MCCB in 175A sub-distribution panel P4 with connecting cables.

6 E-CAC Add 3 numbers of 30A 3P MCB in 150A sub-distribution panel Post 2 with connecting cables.

7 Cafeteria Add 2 numbers of 30A 3P MCCB in 125A sub-distribution panel KP1 and 2 numbers of 30A 3P MCCB in 125A sub-distribution panel KP2 with connecting cables.

8 Server Room Add of 1 number of new 100A outdoor sub-distribution panel with 12 outgoing feeders as well as connecting cables.

9 W-CAC Add 2 numbers of 30A 3P MCCB in 100A sub-distribution panel WCU11 with connecting cables.

10 LGF Toilets Add of 1 number of new 100A outdoor sub-distribution panel with 12 outgoing feeders as well as connecting cables.

The required actions will be translated into a BOQ with corresponding specifications for contractor bidding and job execution to make the electrical distribution system suitable for the installation of the new AC units purchased.

PAGE 13 REPLACEMENT OF AIR CONDITION (AC) UNITS AT THE EMBASSY COMPOUND (EC) AND THE RESIDENCE COMPOUND (RC) – ELECTRICAL MODIFICATION AND AC INSTALLATION WORKS (ANNEX 2)

Figure 3 Single Line Drawing (SLD) of 150A Outdoor Distribution Panel With 13 Outgoing Feeders and Metering

PAGE 14 REPLACEMENT OF AIR CONDITION (AC) UNITS AT THE EMBASSY COMPOUND (EC) AND THE RESIDENCE COMPOUND (RC) – ELECTRICAL MODIFICATION AND AC INSTALLATION WORKS (ANNEX 2)

Figure 4 Single Line Drawing (SLD) of 400A Outdoor Distribution Panel With 30 Outgoing Feeders and Metering

PAGE 15 REPLACEMENT OF AIR CONDITION (AC) UNITS AT THE EMBASSY COMPOUND (EC) AND THE RESIDENCE COMPOUND (RC) – ELECTRICAL MODIFICATION AND AC INSTALLATION WORKS (ANNEX 2)

Figure 5 Single Line Drawing (SLD) of 100A Outdoor Distribution Panel With 25 Outgoing Feeders and Metering

PAGE 16 REPLACEMENT OF AIR CONDITION (AC) UNITS AT THE EMBASSY COMPOUND (EC) AND THE RESIDENCE COMPOUND (RC) – ELECTRICAL MODIFICATION AND AC INSTALLATION WORKS (ANNEX 2)

Figure 6 Single Line Drawing (SLD) of 100A Outdoor Distribution Panel With 12 Outgoing Feeders and Metering

PAGE 17 REPLACEMENT OF AIR CONDITION (AC) UNITS AT THE EMBASSY COMPOUND (EC) AND THE RESIDENCE COMPOUND (RC) – ELECTRICAL

4. INVENTORY OF NEW AC UNITS, MATCHING OF AC OUTDOOR UNITS TO AC

INDOOR UNITS AND ALLOCATION OF AC UNITS TO BUILDINGS

4.1 Inventory of New AC Units

A list of already purchased AC 3-phase outdoor units and 1-phase indoor units by USAID is presented in Table 4. The list details the model number, British Thermal Unit (BTU) and quantity of each type of AC unit. The AC manuals are available with USAID, but they are not part of this report appendices.

Table 4 Inventory of New AC Units

Item # Brief Description Qty

OUTDOOR UNITS // VRF SYSTEM

48,000 BTU units

CARRIER OUTDOOR UNIT

38VS006168HCMM

36,000 BTU units

CARRIER OUTDOOR UNIT

38VS005168HCMM

24,000 BTU units

CARRIER OUTDOOR UNIT

38VS004168HCMM

Total 225

INDOOR UNITS // VRF SYSTEM

Cassettes units 36,000 BTU ceiling mounted // CASSETTE

TYPE 40VU036S-4S-TEE

Inside high wall unit 24,000 BTU // 40VK024S-7S-TEE 59 Inside high wall unit 36,000 BTU // 40VC036S-8S-TEE 51 Inside high wall mounted unit

24,000 BTU // 40VK024S-7S-TEE 118

Inside high wall mounted unit

15,000 BTU // 40VK015S-7S-TEE 116

Inside high wall unit 48,000 BTU // 40VC048S-8S-TEE 9 Inside high wall mounted unit

24,000 BTU // 40VK024S-7S-TEE 52

Inside high wall mounted unit

15,000 BTU // 40VK015S-7S-TEE 51

Total 471

PAGE 18 REPLACEMENT OF AIR CONDITION (AC) UNITS AT THE EMBASSY COMPOUND (EC) AND THE RESIDENCE COMPOUND (RC) – ELECTRICAL

4.2 Matching of AC Outdoor Units to AC Indoor Units and Allocation of AC Units to Houses / Buildings

The AC outdoor and indoor units were matched to each other using the criteria below, which were determined in consultation with USAID:

a) Size of building / room: A bigger building or room will require AC outdoor and indoor units with a bigger BTU as compared to a smaller building or room.

b) Availability: USAID have already procured the AC units prior to this feasibility assessment, so the matching is restricted by the existing inventory of new AC units.

Based on availability, the new AC units have been allocated such that the BTU of the new AC units is equal or greater than the BTU of the existing AC units at each building.

c) Maximum ratio of indoor unit BTU to outdoor unit BTU: The matching of AC units should ensure that this ratio is not greater than 0.85. This was achieved for all the houses and townhouses in the RC and also for the Chancery Building, New Safe Heaven, Old Safe Haven, State Department and Server Room in the EC. This ratio was not achieved for the less priority buildings in the EC.

d) Minimum percentage of spare AC units: The matching of AC units should allow for at least 10% spare of each model of purchased AC outdoor and indoor units.

Based on the criteria explained above, we have matched the AC indoor and outdoor units and allocated them to the houses and townhouses in the RC and buildings in the EC as shown in Appendix D and Appendix E respectively.

A summary of purchased, allocated and remaining AC indoor and outdoor units is presented below in Table 5.

Table 5 AC Units – Purchased, Allocated and Remaining Quantities

BTU

Model Number and

Unit Type Purchased

Allocated to the

RC

Allocated to the EC

Total Allocation

Total Remaining

Quantity Percentage

48000

38VS006168HCMM

Outdoor

35 4 27 31 4 11%

36000

38VS005168HCMM

Outdoor

130 102 15 117 13 10%

24000

38VS004168HCMM

Outdoor

60 43 7 50 10 17%

Total for Outdoor Units 225 149 49 198 27 12%

PAGE 19 REPLACEMENT OF AIR CONDITION (AC) UNITS AT THE EMBASSY COMPOUND (EC) AND THE RESIDENCE COMPOUND (RC) – ELECTRICAL

BTU

Model Number and

Unit Type Purchased

Allocated to the

RC

Allocated to the EC

Total Allocation

Total Remaining

Quantity Percentage

48000

40VC048S-8S-TEE

Indoor High Wall

9 0 0 0 9 100%

36000 Indoor Cassettes 15 0 3 3 12 80%

36000

40VC036S-8S-TEE

Indoor High Wall

51 3 8 11 40 78%

24000

40VK024S-7S-TEE

Indoor High Wall

229 60 35 95 134 59%

15000

40VK015S-7S-TEE

Indoor High Wall

167 129 20 149 18 11%

Total for Indoor Units 471 192 66 258 213 45%

5. QUALITY CONTROL

5.1 Quality Control Plan

Perez recommends that the contractor that would execute these works is expected to submit a quality control plan detailing the definition of standard of quality of the works, the methodology to measure / monitor the quality of work against the defined standard and actions to be taken to rectify works that are deviating from the defined standard of quality as well as control measures to put in place to ensure quality of works does not deviate from the defined standard in the first instance.

The quality control plan must include the contractor health, safety and environment (HSE) plan for working on and off site. Off site could be when transporting electrical material from one location to another. The HSE plan must detail how HSE will be monitored on and off site.

Very importantly, the contractor must submit all shop drawings for the distribution panels;

detailing their dimensions for approval prior to manufacturing taking place. This will enable USAID to verify space availability for the distribution panels in the two compounds.

5.2 Inspection Stages

There will usually be three inspection stages explained below.

a) Inspection stage 1: This will take place when electrical materials arrive at site. All electrical materials / product / equipment arriving at site must be inspected that they are in good condition and in good working order. Necessary tests must be carried out

PAGE 20 REPLACEMENT OF AIR CONDITION (AC) UNITS AT THE EMBASSY COMPOUND (EC) AND THE RESIDENCE COMPOUND (RC) – ELECTRICAL in the presence of USAID and Perez / Liberty by the contractor to ascertain the condition and working order of electrical materials / product / equipment.

b) Inspection stage 2: During and after modification of electrical distribution system based on Appendix A and Appendix B to make sub-distribution panel have the right number of phase(s) to power AC outdoor and indoor units as the case might be.

Additionally, to ensure all conducting parts are well isolated from the neutral and body of the sub-distribution panel and that conducting parts are not interfering (short-circuiting) with another conducting part of different phase.

c) Inspection stage 3: During and after installation of the AC units to ensure maximal use, as much as is possible, of the cooling capacity of all units. Additionally, to ensure that there is no leakage of cooling gas or damage to any component of the AC units such as compressor etc.

The contractor quality control plan does not have to be limited to the inspection stages above.

The above only serves to give the contractor some guidance on the inspection stages that should be included when preparing the quality control plan.

5.3 Testing and Records

All tests carried out must be recorded and kept for reference at later times. A list of tests to be carried out should be included in the contractor’s quality control plan. USAID and Perez / Liberty can add more tests, test requirements and conditions to the list of tests if required.

5.4 As‐Built Documentation

All as-built drawings of new and modified sub-distribution panels should be made in triplicate by contractor and handed over to Perez / Liberty for review before onward hand over to USAID.

Same applies for all as-wired drawings, datasheets and other technical as well as non-technical documentation.

6. SCHEDULE

The modification of the electrical distribution system to accommodate the new AC units will take about 3 months because the sub-distribution panels will be manufactured to order. The decommissioning of the existing AC units as well as the installation, testing and commissioning of the new AC units will take about 2 months. However, the contractor is expected to submit a work schedule during tendering and validate the work schedule before commencement of work.

PAGE 21 REPLACEMENT OF AIR CONDITION (AC) UNITS AT THE EMBASSY COMPOUND (EC) AND THE RESIDENCE COMPOUND (RC) – ELECTRICAL

7. COST ESTIMATE

This section presents the cost estimate for the electrical modification and AC installation works based on site assessment findings, design drawings and specifications.

7.1 Basis of Cost Estimate

The cost estimate requires the calculation of the quantities of various work items and the costs likely to be incurred there on. The costs include costs associated with project administration and management activities including project management workforce expenses, transportation, traveling, communications, third party expenses, banking transactions expenses and any other management costs. Some allowance was made for contingency (5%), provided for unforeseen costs that may be incurred due to minor changes in the project scope and design basis during the project execution. The estimation also includes a provision for a small profit margin (about 10%) and excludes duties and taxes on imported materials. This cost estimate is calculated up to accuracy level within +/-20%.

7.2 Detailed Cost Estimate

The detailed cost estimates for the electrical modification and AC installation works are presented in Appendix F and Appendix G respectively. The summary cost estimate is presented below in Table 6.

Table 6 Summary Cost Estimate

S/No Description Amount (USD)

Electrical Modification Works

1 Residence Compound

2 Embassy Compound

3 Miscellaneous Materials (RC and EC) Sub-Total

AC Installation Works

4 Residence Compound

5 Embassy Compound

6 Accessories (RC and EC) Sub-Total

Total

PAGE 22 REPLACEMENT OF AIR CONDITION (AC) UNITS AT THE EMBASSY COMPOUND (EC) AND THE RESIDENCE COMPOUND (RC) – ELECTRICAL

8. CONCLUSIONS AND RECOMMENDATIONS

8.1 Conclusions

The conclusions from this report include the following:

All sub-distribution panels still have enough spare capacity to accommodate the new AC units that will be installed;

Changes that are required in terms of addition to or replacement of the sub-distribution panel and other electrical materials so that the downstream distribution system supplies the right power phase (3-phase or 1-phase) to the AC units were identified for buildings in the two compounds (see Appendix A and Appendix B); and

Plans for matching of AC outdoor units to indoor units and allocation of new AC units to the various buildings in the two compounds were prepared (see Appendix D and Appendix E).

8.2 Recommendations

In addition to all electrical recommendation made in the course of this report, other general recommendation include the contractor familiarizing themselves with their work environment using Figure 1 and Figure 2 above for ease of movement of personnel, materials, tools and equipment.

The single-phase indoor units must be shared as equally as possible between the three phase of the distribution network at both RC and EC in order to ensure that each phase carries a similar amount of load. This will prevent the possibility of a particular phase or phases being overly loaded while other phase or phases have spare capacity that could have relieved the overly loaded phase(s).

RC and EC critical infrastructures should be backed up by UPS so that during the period of power supply isolation, critical infrastructures and data are not lost. UPS back up will also ensure that staffs of EC and RC remain productive during working hours since the UPS will be supplying the electricity to power their computers and other work tool that rely on electricity for its operation.

All circuit breakers in all sub-distribution panels feeding each of the indoor and outdoor AC units must be labelled after installation to help with easy identification and troubleshooting in the future.

It is also important for occupants of both EC and RC to be made aware of AC installation works going on and what time period there will be disruption to their power supply so that they are prepared for such disruption.

Additionally, since the Juba Compound Electrical Upgrade (JCEU) project is expected to commence fully on site soon, work schedule of AC installation contractor can reflect in such a

PAGE 23 REPLACEMENT OF AIR CONDITION (AC) UNITS AT THE EMBASSY COMPOUND (EC) AND THE RESIDENCE COMPOUND (RC) – ELECTRICAL way that power supply isolation will benefit both AC installation contractor and JCEU contractor as against multiple power isolation for each contractor.

PAGE 24 REPLACEMENT OF AIR CONDITION (AC) UNITS AT THE EMBASSY COMPOUND (EC) AND THE RESIDENCE COMPOUND (RC) – ELECTRICAL MODIFICATION AND AC INSTALLATION WORKS (ANNEX 2)

APPENDICES

Appendix A: Table Detailing Findings on Electrical Distribution System and Required Electrical Solution for the RC

S/No Building Number

Phase Present

1P CB for 1-Phase

Indoor Unit

3P CB for 3- Phase

Outdoor Unit

Space Availability in Sub-DP to add 1P CB for Indoor Unit / 3P CB for Outdoor Unit

Required Solution

1 1 3-Phase Yes No No space as only switch-disconnector present Addition of 150A 3-phase sub-DP with connecting cables.

2 1 3-Phase Yes No No space as only switch-disconnector present Solution as above

3 2 3-Phase Yes No No space as only switch-disconnector present Addition of 150A 3-phase sub-DP with connecting cables.

4 2 3-Phase Yes No No space as only switch-disconnector present Solution as above

5 2 3-Phase Yes No No space as only switch-disconnector present Solution as above

6 3 3-Phase Yes No No space as only switch-disconnector present Addition of 150A 3-phase sub-DP with connecting cables.

7 3 3-Phase Yes No No space as only switch-disconnector present Solution as above

8 4 3-Phase Yes No No space as only switch-disconnector present Addition of 150A 3-phase sub-DP with connecting cables.

9 4 3-Phase Yes No No space as only switch-disconnector present Solution as above

10 5 3-Phase Yes No No space as only switch-disconnector present Not applicable

11 6A 2-Phase Yes No Yes, for 2nos. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 6A

400A 3-phase DP to replace CH2DP and addition of 2nos. of 30A 3P MCCB

PAGE 25 REPLACEMENT OF AIR CONDITION (AC) UNITS AT THE EMBASSY COMPOUND (EC) AND THE RESIDENCE COMPOUND (RC) – ELECTRICAL MODIFICATION AND AC INSTALLATION WORKS (ANNEX 2)

S/No Building Number

Phase Present

1P CB for 1-Phase

Indoor Unit

3P CB for 3- Phase

Outdoor Unit

Space Availability in Sub-DP to add 1P CB for Indoor Unit / 3P CB for Outdoor Unit

Required Solution

(Siemens BQD) in 100A sub-DP 6A with connecting cables.

12 6B 2-Phase Yes No Yes, for 2nos. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 6B

400A 3-phase DP to replace CH2DP and addition of 2nos. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 6B with connecting cables.

13 7A 2-Phase Yes No Yes, for 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 7A

400A 3-phase DP to replace CH2DP and addition of 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 7A with connecting cables.

14 7A 2-Phase Yes No Yes, for 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 7A

400A 3-phase DP to replace CH2DP and addition of 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 7A with connecting cables.

15 7B 2-Phase Yes No Yes, for 2nos. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 7B

400A 3-phase DP to replace CH2DP and addition of 2nos. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 7B with connecting cables.

16 8A 2-Phase Yes No Yes, for 2nos. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 8A

400A 3-phase DP to replace CH2DP and addition of 2nos. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 8A with connecting cables.

17 8B 2-Phase Yes No Yes, for 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 8B

400A 3-phase DP to replace CH2DP and addition of 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 8B with connecting cables.

PAGE 26 REPLACEMENT OF AIR CONDITION (AC) UNITS AT THE EMBASSY COMPOUND (EC) AND THE RESIDENCE COMPOUND (RC) – ELECTRICAL MODIFICATION AND AC INSTALLATION WORKS (ANNEX 2)

Number

Phase Present

1P CB for 1-Phase

Indoor Unit

3P CB for 3- Phase

Outdoor Unit

Space Availability in Sub-DP to add 1P CB for Indoor Unit / 3P CB for Outdoor Unit

Required Solution

18 9A 2-Phase Yes No Yes, for 2nos. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 9A

400A 3-phase DP to replace CH2DP and addition of 2nos. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 9A with connecting cables.

19 9B 2-Phase Yes No Yes, for 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 9B

400A 3-phase DP to replace CH2DP and addition of 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 9B with connecting cables.

20 10A 2-Phase Yes No Yes, for 2nos. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 10A

400A 3-phase DP to replace CH2DP and addition of 2nos. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 10A with connecting cables.

21 10B 2-Phase Yes No Yes, for 2nos. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 10B

400A 3-phase DP to replace CH2DP and addition of 2nos. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 10B with connecting cables.

22 11A 2-Phase Yes No Yes, for 2nos. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 11A

400A 3-phase DP to replace CH2DP and addition of 2nos. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 11A with connecting cables.

23 11B 2-Phase Yes No Yes, for 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 11B

400A 3-phase DP to replace CH2DP and addition of 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 11B with connecting cables.

24 12A 2-Phase Yes No Yes, for 2nos. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 12A and addition of 2nos. of 30A 3P MCCB

PAGE 27 REPLACEMENT OF AIR CONDITION (AC) UNITS AT THE EMBASSY COMPOUND (EC) AND THE RESIDENCE COMPOUND (RC) – ELECTRICAL MODIFICATION AND AC INSTALLATION WORKS (ANNEX 2)

Number

Phase Present

1P CB for 1-Phase

Indoor Unit

3P CB for 3- Phase

Outdoor Unit

Space Availability in Sub-DP to add 1P CB for Indoor Unit / 3P CB for Outdoor Unit

Required Solution

(Siemens BQD) in 100A sub-DP 12A with connecting cables.

25 12B 2-Phase Yes No Yes, for 2nos. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 12B

400A 3-phase DP to replace CH2DP and addition of 2nos. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 12B with connecting cables.

26 13A 2-Phase Yes No Yes, for 2nos. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 13A

400A 3-phase DP to replace CH2DP and addition of 2nos. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 13A with connecting cables.

27 13B 2-Phase Yes No Yes, for 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 13B

400A 3-phase DP to replace CH2DP and addition of 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 13B with connecting cables.

28 14A 2-Phase Yes No Yes, for 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 14A

400A 3-phase DP to replace CH2DP and addition of 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 14A with connecting cables.

29 14A 2-Phase Yes No Yes, for 2nos. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 14A

400A 3-phase DP to replace CH2DP and addition of 2nos. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 14A with connecting cables.

30 14B 2-Phase Yes No Yes, for 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 14B

400A 3-phase DP to replace CH2DP and addition of 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 14B

PAGE 28 REPLACEMENT OF AIR CONDITION (AC) UNITS AT THE EMBASSY COMPOUND (EC) AND THE RESIDENCE COMPOUND (RC) – ELECTRICAL MODIFICATION AND AC INSTALLATION WORKS (ANNEX 2)

Number

Phase Present

1P CB for 1-Phase

Indoor Unit

3P CB for 3- Phase

Outdoor Unit

Space Availability in Sub-DP to add 1P CB for Indoor Unit / 3P CB for Outdoor Unit

Required Solution

31 14B 2-Phase Yes No Yes, for 2nos. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 14B

400A 3-phase DP to replace CH2DP and addition of 2nos. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 14B with connecting cables.

32 15A 2-Phase Yes No Yes, for 2nos. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 15A

400A 3-phase DP to replace CH2DP and addition of 2nos. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 15A with connecting cables.

33 15B 2-Phase Yes No Yes, for 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 15B

400A 3-phase DP to replace CH2DP and addition of 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 15B with connecting cables.

34 16A 2-Phase Yes No Yes, for 2nos. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 16A

400A 3-phase DP to replace CH2DP and addition of 2nos. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 16A with connecting cables.

35 16B 2-Phase Yes No Yes, for 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 16B

400A 3-phase DP to replace CH2DP and addition of 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 16B with connecting cables.

36 17A 2-Phase Yes No Yes, for 2nos. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 17A

400A 3-phase DP to replace CH2DP and addition of 2nos. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 17A with connecting cables.

37 17B 2-Phase Yes No Yes, for 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 17B and addition of 1no. of 30A 3P MCCB

PAGE 29 REPLACEMENT OF AIR CONDITION (AC) UNITS AT THE EMBASSY COMPOUND (EC) AND THE RESIDENCE COMPOUND (RC) – ELECTRICAL MODIFICATION AND AC INSTALLATION WORKS (ANNEX 2)

Number

Phase Present

1P CB for 1-Phase

Indoor Unit

3P CB for 3- Phase

Outdoor Unit

Space Availability in Sub-DP to add 1P CB for Indoor Unit / 3P CB for Outdoor Unit

Required Solution

(Siemens BQD) in 100A sub-DP 17B with connecting cables.

38 18A 2-Phase Yes No Yes, for 1no. of 30A 3P MCCB (Siemens NEB3B030) in 225A DP21

Addition of 1no. of 30A 3P MCCB (Siemens NEB3B030) in 225A DP21 with connecting cables.

39 18B 2-Phase Yes No Yes, for 1no. of 30A 3P MCCB (Siemens NEB3B030) in 225A DP21

Addition of 1no. of 30A 3P MCCB (Siemens NEB3B030) in 225A DP21 with connecting cables.

40 19A 3-Phase Yes No No space as only junction box present Addition of 100A 3-phase sub-DP 19 with connecting cables.

41 19B 3-Phase Yes No Same as above Solution as above

42 20A 3-Phase Yes No Yes, for 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 20A

Addition of 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 20A with connecting cables.

43 20B 3-Phase Yes No Yes, for 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 20A

Addition of 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 20A with connecting cables.

44 21A 2-Phase Yes No Yes, for 1no. of 30A 3P MCCB (Siemens NEB3B030) in 225A DP21

Addition of 1no. of 30A 3P MCCB (Siemens NEB3B030) in 225A DP21 with connecting cables.

Split between 21A and

21B

2-Phase Yes No Yes, for 1no. of 30A 3P MCCB (Siemens NEB3B030) in 225A DP21

Addition of 1no. of 30A 3P MCCB (Siemens NEB3B030) in 225A DP21

PAGE 30 REPLACEMENT OF AIR CONDITION (AC) UNITS AT THE EMBASSY COMPOUND (EC) AND THE RESIDENCE COMPOUND (RC) – ELECTRICAL MODIFICATION AND AC INSTALLATION WORKS (ANNEX 2)

Number

Phase Present

1P CB for 1-Phase

Indoor Unit

3P CB for 3- Phase

Outdoor Unit

Space Availability in Sub-DP to add 1P CB for Indoor Unit / 3P CB for Outdoor Unit

Required Solution

46 21B 2-Phase Yes No Yes, for 1no. of 30A 3P MCCB (Siemens NEB3B030) in 225A DP21

Addition of 1no. of 30A 3P MCCB (Siemens NEB3B030) in 225A DP21 with connecting cables.

47 22A 3-Phase Yes No Yes, for 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 20A

Addition of 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 20A with connecting cables.

Split between 22A and

22B

3-Phase Yes No Yes, for 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 20A

Addition of 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 20A with connecting cables.

49 22B 3-Phase Yes No Yes, for 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 20A

Addition of 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 20A with connecting cables.

50 23A 3-Phase Yes No No space as only junction box present Addition of 100A 3-phase sub-DP 23 with connecting cables.

51 23B 3-Phase Yes No Same as above Solution as above

52 24A 3-Phase Yes No No space as only junction box present Addition of 100A 3-phase sub-DP 24 with connecting cables.

53 24B 3-Phase Yes No Same as above Solution as above

54 25A 3-Phase Yes No Yes, for 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 25A

Addition of 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 25A with connecting cables.

55 25B 3-Phase Yes No Yes, for 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 25A

Addition of 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 25A

PAGE 31 REPLACEMENT OF AIR CONDITION (AC) UNITS AT THE EMBASSY COMPOUND (EC) AND THE RESIDENCE COMPOUND (RC) – ELECTRICAL MODIFICATION AND AC INSTALLATION WORKS (ANNEX 2)

Number

Phase Present

1P CB for 1-Phase

Indoor Unit

3P CB for 3- Phase

Outdoor Unit

Space Availability in Sub-DP to add 1P CB for Indoor Unit / 3P CB for Outdoor Unit

Required Solution

56 26A 3-Phase Yes No Yes, for 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 26

Addition of 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 26 with connecting cables.

57 26B 3-Phase Yes No Yes, for 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 26

Addition of 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 26 with connecting cables.

58 27A 3-Phase Yes No No space as only junction box present Addition of 100A 3-phase sub-DP 27 with connecting cables.

59 27B 3-Phase Yes No Same as above Solution as above

60 28A 3-Phase Yes No No space as only junction box present Addition of 100A 3-phase sub-DP 28 with connecting cables.

61 28B 3-Phase Yes No Same as above Solution as above

62 29A 3-Phase Yes No Yes, for 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 29

Addition of 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 29 with connecting cables.

63 29B 3-Phase Yes No Yes, for 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 29

Addition of 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 29 with connecting cables.

64 30A 3-Phase Yes No No space as only junction box present Addition of 100A 3-phase sub-DP 30 with connecting cables.

65 30B 3-Phase Yes No Same as above Solution as above

66 31A 3-Phase Yes No No space as only junction box present Addition of 100A 3-phase sub-DP 31

67 31B 3-Phase Yes No Same as above Solution as above

PAGE 32 REPLACEMENT OF AIR CONDITION (AC) UNITS AT THE EMBASSY COMPOUND (EC) AND THE RESIDENCE COMPOUND (RC) – ELECTRICAL MODIFICATION AND AC INSTALLATION WORKS (ANNEX 2)

Number

Phase Present

1P CB for 1-Phase

Indoor Unit

3P CB for 3- Phase

Outdoor Unit

Space Availability in Sub-DP to add 1P CB for Indoor Unit / 3P CB for Outdoor Unit

Required Solution

68 32A 3-Phase Yes No Yes, for 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 32

Addition of 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 32 with connecting cables.

69 32B 3-Phase Yes No Yes, for 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 32

Addition of 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 32 with connecting cables.

70 32B 3-Phase Yes No Yes, for 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 32

Addition of 1no. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 32 with connecting cables.

71 33A 3-Phase Yes No No, not enough space for 6nos. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 32

Addition of 100A 3-phase sub-DP 33 with connecting cables.

72 33B 3-Phase Yes No Same as above Solution as above

73 34A 3-Phase Yes No No, not enough space for 12nos. of 30A 3P MCCB (Siemens BQD) in 100A sub-DP 34

Addition of 100A 3-phase sub-DP 34B with connecting cables.

74 34B 3-Phase Yes No Same as above Solution as above

75 35A 3-Phase Yes No Same as above Addition of 100A 3-phase sub-DP 35 with connecting cables.

76 35A 3-Phase Yes No Same as above Solution as above

77 35B 3-Phase Yes No Same as above Solution as above

78 36A 3-Phase Yes No No space as only MCCB in enclosure present Addition of 100A 3-phase sub-DP 36

79 36B 3-Phase Yes No Same as above Solution as above

PAGE 33 REPLACEMENT OF AIR CONDITION (AC) UNITS AT THE EMBASSY COMPOUND (EC) AND THE RESIDENCE COMPOUND (RC) – ELECTRICAL MODIFICATION AND AC INSTALLATION WORKS (ANNEX 2)

Number

Phase Present

1P CB for 1-Phase

Indoor Unit

3P CB for 3- Phase

Outdoor Unit

Space Availability in Sub-DP to add 1P CB for Indoor Unit / 3P CB for Outdoor Unit

Required Solution

80 37A 3-Phase Yes No Yes, for 1no. of 30A 3P MCB (Schneider Electric or ABB) in 250A sub-DP 38

Addition of 1no. of 30A 3P MCB (Schneider Electric or ABB) in 250A sub-DP 38 with connecting cables.

81 37B 3-Phase Yes No Yes, for 1no. of 30A 3P MCB (Schneider Electric or ABB) in 250A sub-DP 38

Addition of 1no. of 30A 3P MCB (Schneider Electric or ABB) in 250A sub-DP 38 with connecting cables.

82 38A 3-Phase Yes No Yes, for 1no. of 30A 3P MCB (Schneider Electric or ABB) in 250A sub-DP 38

Addition of 1no. of 30A 3P MCB (Schneider Electric or ABB) in 250A sub-DP 38 with connecting cables.

83 38B 3-Phase Yes No Yes, for 1no. of 30A 3P MCB (Schneider Electric or ABB) in 250A sub-DP 38

Addition of 1no. of 30A 3P MCB (Schneider Electric or ABB) in 250A sub-DP 38 with connecting cables.

84 39A 3-Phase Yes No No space as only junction box present Addition of 100A 3-phase sub-DP 39 with connecting cables.

85 39B 3-Phase…

This is the start of the file's text. The full file is on GovTribe.