Attachment_5__SOW.docx

DOCX document 20 KB Posted

Attached to
Anadarko Agency- Furniture Move Emergency Sewer
Solicitation number
140A0326Q0008
Issued by

About this file

This is a Draft Scope of Work (SOW) for an emergency furniture relocation and cubicle restoration project at the Anadarko Agency in Anadarko, Oklahoma, in support of sewer line repairs. The contractor must provide all labor, materials, tools, and equipment to temporarily relocate office furniture, equipment, and cubicle systems from the designated sewer line trench path (a 2-foot-wide trench extending across the building) to other designated areas within the building. Work includes disconnecting electrical power to 10 cubicles in the building center, disassembling cubicle walls, work surfaces, and power raceways while labeling components for reinstallation, and clearing all obstructions to allow access for sewer repair work. The inventory affected includes approximately 13 copiers, 7-9 freestanding stations, 32 bookcases/file cabinets/storage units, 15 printers, 51 chairs, 21 monitors, 2 training/conference tables exceeding 7 feet, and 64 metal storage cabinets distributed across multiple rooms (A18-A24, A10-A13, and B4-B7).

Following sewer repair completion, the contractor must reinstall all cubicles in their original configuration, reconnect electrical and data lines, return all furniture and equipment to original locations, and perform final cleaning of dust and debris. All work must be coordinated with the sewer repair contractor and the Anadarko Agency, with relocation completed before demolition and trenching begin. The contractor must comply with federal safety requirements, including OSHA regulations, and ensure all electrical work is performed by qualified technicians. Deliverables include a fully cleared work zone with protected remaining furnishings, documented temporary storage, and restoration of all impacted areas to their original configuration.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Draft Scope of Work (SOW) Project Title: Anadarko Agency Sewer Line Repair – Interior Clearance, Furniture Relocation, and Cubicle Disassembly/Restoration Location: Anadarko Agency, Anadarko, OK

1. Project Overview The Anadarko Agency requires the temporary relocation, protection, and restoration of office furniture, equipment, and cubicle systems to allow for the repair of an existing sewer line. The sewer repair will require cutting a 2‑foot‑wide trench through the flooring along the designated sewer line path extending across the entire building. All items within or adjacent to the work zone must be cleared.

An image depicting the building layout and the proposed sewer line alignment (yellow line) will be included as an attachment to this SOW.

2. Contractor Responsibilities The contractor shall provide all labor, materials, tools, and equipment necessary to complete the following tasks:

2.1 Site Preparation

· Remove all office furniture, equipment, and loose items located within the defined sewer line trench path (Areas in the map colored in GREEN)

· Relocate items to:

• Other designated offices within the building (Areas in the map colored in BLUE)

2.2 Cubicle Disassembly and Electrical Disconnection

· Disconnect electrical power servicing 10 cubicles located in the center of the building.

· Disassemble cubicle walls, work surfaces, and power raceways as needed to completely clear the trench path.

· Label all cubicle components to ensure correct reinstallation.

2.4 Sewer Line Access Facilitation

· Ensure all furniture, and obstructions are cleared to allow the construction contractor to:

• Break through flooring along the 2‑ft trench.

• Access and repair the sewer line.

• Transport debris safely through designated pathways.

2.5 Restoration / Reinstallation

After sewer repairs are completed, the contractor shall:

· Reinstall all cubicles in original layout based on the configuration shown in “Option 1” (attached).

· Reconnect electrical service / data lines to cubicle systems.

· Return all furniture and equipment to their original rooms and functional locations.

· Ensure all areas are cleaned of dust and debris resulting from relocation activities.

3. Deliverables

· Fully cleared work zone matching the sewer trench path.

· Protection of remaining furnishings with plastic sheeting.

· Temporary storage and later full restoration of all impacted rooms and cubicles.

· Final condition where all furniture, cubicles, and equipment are returned to their original configuration.

4. Schedule

· Work must be performed in coordination with the sewer repair contractor and the Anadarko Agency. All relocation must be completed before demolition and trenching begin.

5. Safety Requirements

· Contractor must comply with all federal safety requirements, including OSHA regulations.

· All electrical work must be performed by a qualified technician.

· Maintain protective barriers to shield staff and visitors from active work zones.

6. Approximate Existing Item Count for Movement

Inventory
Room A18-A24
Room A10-A13
Room B4-B7
Copiers
7
3
3
Freestanding Station (L/U/Shape)
5-L

2-L

Bookcase/ File/ Storage/ Cabinet/ Locker
21
3
8
Printers
10
2
3
Metal Storage Cabinets (FULL)
33
17
14
Chairs
39
9
3
Monitors
16

Training/ Conference Tables >7’

Training/ Conference Tables <7’
3
File Boxes/ Full Boxes of Paper Reams
Estimated at 250 Boxes over the whole area.

6. Provided Attachments Based on your filenames and descriptions, the following attachments will be included with the final package:

· Attachment 1, Building Map with Designated Areas Marked

· Attachment 2, Existing cubicle layout

· Attachment 3, IEE Representation Form

· Attachment 4, Wage Determination

· Attachment 5, Scope of Work

· Attachment 6, Photographs of Space