Attachment 5 - Site Details and Drawings.pdf
PDF 2 MB Posted
- Solicitation number
- 1240LT25R0026
About this file
The document is a project map series for the Aquatic Nuisance Species (ANS) Round 2 Project, detailing planned improvements at five different boat launch locations: Green Ridge, Highland Marina, Stillwater, Sunset, and Willow Creek Reservoir. These maps are part of a federal contract opportunity for gate replacements and site improvements in the Arapaho & Roosevelt National Forests and Pawnee National Grassland.
The project maps highlight improvements completed in 2018-19 and planned for 2020-21, including installing gates, traffic spikes, boulder barriers, parking definitions, and inspector area improvements. Specific site-specific enhancements include a second gate at Green Ridge, parking definition at Highland Marina, a large boat launch ramp gate and asphalt repairs at Stillwater, and ANS information boards at multiple locations. The maps use color-coded legends to indicate completed and planned improvements, providing a visual guide for the gate replacement and site enhancement project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 1 - Q and A.pdf | ||
| 1240LT25R0026 A00001.pdf | ||
| Attachment 2- Statement of Work.pdf | ||
| Attachment 3 - Maps.pdf | ||
| Attachment 1- SOI.pdf | ||
| Attachment 6- Wage Determination.pdf | ||
| Attachment 4 - Gate Drawings.pdf | ||
| 1240LT25R0026.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Green Ridge – ANS Round 2 Project Map
Legend Improvements Completed 2018-19
Traffic Spikes/Gate with Numerous Signs
Improvements Planned 2020-21
Gate
Inspector Area Improvement
ANS Info Board
Second gate to be installed at other end of roadway
Attachment B
Highland Marina – ANS Round 2 Project Map
Improvements Planned 2020-21
Gate Parking Definition Area
Rock Barriers
Stillwater – ANS Round 2 Project Map
Improvements Completed 2018-19
Traffic Spikes/Gate with Numerous Signs
Boulder Barriers
Improvements Planned 2020-21
Large Boat Launch Ramp Gate Boulder Barriers
Inspector Area Improvement ANS Info Board
Asphalt Repairs Develop Water Hydrant Use for Inspectors
Sunset – ANS Round 2 Project Map
Improvements Completed 2018-19
Traffic Spikes/Gate with Numerous Signs
Boulder Barriers
Gate
ANS Info Board
Willow Creek Reservoir – ANS Round 2 Project Map
Boulder Barriers
File details come from the government source that posted it. Updated .