ATTACHMENT 5 - Pre-Bid RFI Response Letter.pdf
PDF 71 KB Posted
- Attached to
- SMCISD Mendez Elementary Replacement
- Solicitation number
- CSP-MD-2024-01
- Issued by
- Hays County, Texas
About this file
The Pre-Bid RFI Response Letter is issued by Perkins&Will for the San Marcos Consolidated Independent School District (SMCISD) Mendez Elementary Replacement project. The document details a competitive sealed proposal (CSP) for a complete campus replacement, with bids due on July 16, 2024, through BidNetDirect. The project involves full demolition of the existing campus, with construction expected to begin in Fall 2024 and be completed by March 2026. The project will include abatement of hazardous materials prior to demolition, and some existing campus materials like brick will be salvaged for site pavers.
The total construction budget is $57,056,500, and the district has already procured geotechnical, third-party testing, and structural services during previous board meetings in 2024. The project will utilize rooftop cooling units and standardized security systems. The district does not have a dedicated IT contractor and will be seeking proposals through a competitive sealed proposal process. The project is contingent upon approval from the SMCISD Board of Directors and obtaining a building permit from the City of San Marcos.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
310 Comal Street, Suite 100 Austin, Texas 78702 www.perkinswill.com
Pre-Bid RFI Response Letter
Note: Design team responses are written below in RED.
1. Will there be any abatement on this project?
a. The district can provide the latest asbestos inspection report of the existing building to be demo’d. The owner will hire a third party abatement company to remove hazardous material prior to demolition.
2. Does SMCISD have a dedicated IT company?
a. No, the district does not have a dedicated IT contractor that it works with.
3. Does the entire district have a specific security system (cameras and access control)?
a. Yes, the standardized security systems are noted in the specifications.
4. Does the district have an asbestos report?
a. Yes, the district can provide the 2021 AHERA Three-Year Re-Inspection report.
5. Are you planning on abatement before the demo of the existing campus?
a. Yes, per state and federal requirements abatement is required before demolition if asbestos is present.
6. Are you demoing everything?
a. Yes, the entire existing campus will be demolished as part of this project.
7. Is the cooling all roof top units?
a. Yes. Refer to the drawings and spefications.
8. Are we going to salvage anything?
a. Yes, per the landscape drawings a limited amount of brick is to be salvaged from the existing campus and used for site pavers. Refer to civil drawings for additional salvage notes.
9. Will you be soliciting for a Construction Manager at Risk?
a. No, this project is using a competitive sealed proposal (CSP) contract.
10. Do you know when they are planning to put this out to bid?
a. This project is currently soliciting for bids on https://www.bidnetdirect.com/texas/san-marcos-cisd . Bids are due July 16, 2024.
11. Do you know when they are planning to start construction?
a. Construction is expected to begin in Fall 2024, pending approval of the bid by the SMCISD Board of Directors and the City of San Marcos building permit approval.
12. Do you know when will be the construction completion date?
a. Construction is expected to be completed in March 2026.
13. What is the Estimated cost for the project?
a. Construction budget is $57,056,500.
Date: 7.10.2024
Re: SMCISD Mendez Elementary Replacement https://www.bidnetdirect.com/texas/san-marcos-cisd
Date: 7.10.2024
Re: SMCISD Mendez Elementary Replacement
14. Will you be going out for any other professional services for this project, like structural engineering or geotechnical services?
a. SMCISD has already completed the procurement of Geotechnical, 3rd party testing, and structural during previous board meetings in 2024.