Attachment 5 - Phasing Schedule.pdf
PDF 152 KB Posted
- Solicitation number
- FA303025Q0013
About this file
This is a phasing schedule for repairs to water towers and ladders at Buildings B738 and B3475 at Goodfellow Air Force Base, Texas, under CLIN 0001. The total performance period is 90 calendar days for all phases, which run concurrently.
The work is divided into four phases for each building. For B738, Phase 1 involves repairing/replacing components of the upper ladder portion, Phase 2 covers draining, sediment removal and internal inspection, Phase 3 includes external/internal work and protective coating application, and Phase 4 involves testing, training, certification and inspection. Building B3475 follows the same four-phase structure but focuses on the lower portion of the ladder for Phase 1 repairs. Each phase must be performed according to the statement of work and inspection report requirements, with all phases running concurrently within the 90-day performance period.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CLIN SCHEDULE
REPAIR WATER TOWERS and LADDERS, B738 & B3475
FOR
GOODFELLOW AIR FORCE BASE, TEXAS
Phasing Schedule
Provide all labor, equipment, materials, and incidentals necessary to accomplish CLIN 0001, and it’s 8 phases in accordance with the project Statement of Work and subject to the terms and conditions of the complete contract. Refer to the Phase Schedule below for Performance period. Total performance period for CLIN 0001, is NINETY (90) calendar days.
–B738 Phase 1 Repairs: Work includes but not limited to, repairing\replacing with new components to the upper portion of the existing ladder by welding\securing to the existing structure. Perform all work as described in the statement of work and inspection report. Total performance period shall be NINETY (90) calendar days, including subsequent phases.
– B738 Phase 2 Drain\Sediment\Inspection: Work includes but not limited to, request draining of tank, interior sediment removal, haul-off, and internal inspection. Perform all work as described in the statement of work and inspection report. Total performance period shall be NINETY (90) calendar days, concurrent with the previous phase.
– B738 Phase 3 External\Internal Work: Work includes but limited to, all external and internal work as outlined on “Water Tower B738”, Phase 3 in the SOW. Also included shall be applying a protective coating to the newly installed raw metal and exposed raw materials. Perform all work as described in the statement of work and inspection report. Total performance period shall be NINETY (90) calendar days, concurrent with previous phases.
– B738 Phase 4 Testing, Training, Certification, Inspection: Work includes the complete all testing, training, certification, and inspection. Perform all work as described in the statement of work. Total performance period shall be NINETY (90) calendar days, concurrent with previous phases.
CLIN SCHEDULE
REPAIR WATER TOWERS and LADDERS, B738 & B3475
FOR
GOODFELLOW AIR FORCE BASE, TEXAS
– B3475 Phase 1 Repairs: Work includes but not limited to, repairing\replacing with new components to the lower portion of the existing ladder by welding and making usable. Perform all work as described in the statement of work and inspection report. Total performance period shall be NINETY (90) calendar days, concurrent with previous phases.
– B3475 Phase 2 Drain\Sediment\Inspection: Work includes but not limited to, request draining of tank, interior sediment removal, haul-off, and internal inspection. Perform all work as described in the statement of work and inspection report. Total performance period shall be NINETY (90) calendar days, concurrent with previous phases.
– B3475 Phase 3 External\Internal Work: Work includes the complete but not limited to, all external and internal work as outlined on “Water Tower B3475”, Phase 3 in the SOW. Also included shall be applying a protective coating to the newly installed raw metal and exposed raw materials. Perform all work as described in the statement of work and inspection report. Total performance period shall be NINETY (90) calendar days, concurrent with previous phases.
– B3475 Phase 4 Testing, Training, Certification, Inspection: Work includes but not limited to, the complete all testing, training, certification, and inspection. Perform all work as described in the statement of work. Total performance period shall be NINETY (90) calendar days, concurrent with previous phases.
| ` |