Attachment 1 - Statement of Work (SOW).pdf

PDF 9 MB Posted

Attached to
Repair Water Towers and Ladders B738 & B3475 (GAFB)
Solicitation number
FA303025Q0013
Issued by

About this file

This is a Statement of Work (SOW) for repairing two 400,000-gallon elevated water storage tanks (B738 and B3475) at Goodfellow Air Force Base in Texas. The work must be completed within 90 calendar days and includes exterior repairs, equipment/parts replacement, and interior sediment removal. Key requirements include repairing external ladders, resealing roof plates and anode covers, removing fall protection systems, cleaning interior sediment, installing new gaskets for overflow flappers, and conducting water quality testing.

The SOW specifies that work can only be performed on one tower at a time, with all testing, functionality checks, and certifications completed before starting work on the second tower. Required materials include specific paints (Macropoxy 646 PW and Acrolon Ultra or approved equals) that must meet NSF/ANSI 61 standards for drinking water contact. The contractor must provide safety plans, quality control plans, and construction work plans for approval. The work requires certified journeymen or supervised apprentices, and welding work must be performed by certified licensed welding technicians with documentation submitted for approval. The project is being managed by the 17th Civil Engineer Squadron at Goodfellow AFB.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOW: Page 1 of 17

ABBREVIATED STATEMENT OF WORK

FOR

PROJECT # 1145749

REPAIR WATER TOWERS and LADDERS, B738 and B3475

September 2024

PREPARED BY:

17TH CIVIL ENGINEER SQUADRON (AETC)

460 E. KEARNEY BOULEVARD

GOODFELLOW AFB, TX 76908-4104

SOW: Page 2 of 17

Table of Contents

PART 1.0 – SCOPE OF WORK

PART 2.0 – PRODUCTS

PART 3.0 – EXECUTION

PART 4.0 – UTILITY OUTAGES AND SPECIAL CONDITIONS

PART 5.0 - SITE MAINTENANCE AND CLEANUP

PART 6.0 - ENERGY CONSERVATION

PART 7.0 – RESPONSIBILITY

PART 8.0 – STORAGE AND PARKING

PART 9.0 - COMPLETION OF WORK

Project Package Includes:

1. Statement of Work

2. Goodfellow Environmental Protection Requirements

3. Technical Exhibits

4. AF Form 66

SOW: Page 3 of 17

STATEMENT OF WORK FOR

REPAIR WATER TOWERS and LADDERS, B738 and B3475

PREPARED BY:

17th CIVIL ENGINEER SQUADRON (AETC)

460 E. KEARNEY BOULEVARD

GOODFELLOW AFB, TX 76908-4104

PART 1.0 – SCOPE OF WORK

1.1 GENERAL: The work to be performed under this contract and in accordance with this

Statement of Work shall consist of furnishing all necessary parts, labor, tools, transportation, supplies, supervision, equipment, materials, and incidentals necessary for providing all work shown on the drawings (Technical Exhibits), Statement of Work, and all applicable codes, regulations, standards, and criteria in effect at the date of solicitation. The work outlined below shall consist of, but not be limited to the following:

1.2 PROJECT DESCRIPTION: The work scope consist of the Contractor to perform exterior minor repairs, equipment\parts replacement, and interior sediment removal from both GAFB water towers, B738 and B3475.

1.3 LOCATION: Goodfellow Air Force Base is located in Tom Green County, on the southeast side of San Angelo, TX. and is bounded to the north by Highway #388 (Paint Rock Rd.), to the west by Fort McKavitt Rd and Bell Street/Christoval Road, to the south by Highway #1223

(San Antonio Hwy.) and to the east by the eastern city limits. The location of water tower B738 is on the West side of GAFB near the intersection of Ft. Stockton Ave. and Hornet St. The location of water tower B3475 is on the East side of GAFB within the Fire Training Academy

Complex.

1.3.1 Site Visits: The Contractor shall visit the site to become thoroughly familiar with details of the work and working conditions, verify dimensions in the field, and shall advise the GAFB

Contracting Officer of any discrepancies before starting the work.

1.4 WORK AND MECHANICS: The work for this project shall be executed in the best and most workmanlike manner, by qualified and efficient mechanics/tradesmen, skilled in their respective trades. Only certified journeymen in each respective trade, or apprentices under the direct supervision of certified journeymen, shall be permitted to install and/or supervise installation for this project. Individual trade work for this project shall be performed and quality maintained by the applicable trade, only. All trades shall coordinate their work with that of other trades. The Contractor shall coordinate and perform all operations in a manner that will result in a professional and expeditiously completed project. The work shall be in strict accordance with prevailing industry standards and manufacturer’s instructions. Work and materials shall comply with this Statement of Work and the editions in effect at the time of this solicitation for all applicable criteria, regulations, guidelines and codes, all of which are made a part thereof.

SOW: Page 4 of 17

1.5 PERFORMANCE PERIOD: The Contractor shall have NINETY (90) calendar days to perform all work associated with this project.

1.6 WORKING CONDITIONS: The Contractor should be aware that the work will be performed on two (2) 400k gal elevated water storage tank. Much of the work on both tanks will be on the exterior and the interior of the tank itself. The Contractor shall provide a 72 hour advance written request for the Government to drain the water tower and disable the cathodic protection system for the Contractor to perform all internal and external tank work elements.

Work will be performed on one (1) water tower at a time. No work will be allowed to be performed on the second tower until all work is completed on the first. To include all testing, confirmation of operability/functionality of new equipment, training and the submission of all test reports, checklists, and certifications required by Federal, State, and local governments. At no time will both tanks be allowed to be non-functioning simultaneously. No underwater repairs are to be expected for this project. The interior work area is a darkened area with little to no light. The Contractor shall provide ample lighting for personnel to perform their work.

The lower manholes on both tanks have been welded and are not accessible. Areas not included in the scope of work are expected to maintain operability and functionality throughout the construction process. The Contractor shall be required to submit for approval a Work

Management Plan NLT seven (7) days after signing the Notice to Proceed (NTP) and providing all material submittals 14 days after signing the NTP. The Contractor shall not be allowed to proceed with demolition or construction until all materials submitted are approved, purchased, ready, and available at the work site.

1.7 NORMAL WORK HOURS: The Contractor shall schedule all work to commence between the hours of 7:30 AM and 4:30 PM, Monday through Friday, except on the Federal holidays and days designated as “Family Days” by Air Education and Training Command (AETC) as listed below. Any Holiday falling on a Saturday will be observed the preceding Friday. Any

Holiday falling on a Sunday will be observed the following Monday. Permission to work outside these normal business hours may be granted by the Contracting Officer. Requests to work outside the normal work hours must be submitted in writing to the Contracting Officer at least three (3) working days in advance of the date requested.

Federal Holiday Holiday Family Day Holiday Family Day

New Year’s Day

26 May

01 Jan 02 Jan

Birthday of Martin Luther King, Jr. -- -

Washington’s Birthday -- -

Memorial Day 23 May27 May 24 May

Juneteenth Nat’l Independence Day - 19 Jun -

Independence Day 04 Jul 04 Jul 05 Jul

Labor Day

20 Jun

29 Aug02 Sep 30 Aug

Columbus Day

07 Jul

Veterans Day

1 Sep

Thanksgiving Day 27 Nov 28 NovNov 28 29 Nov

Christmas Day 25 Dec 26 Dec Dec 25 26 Dec

SOW: Page 5 of 17

While AETC Family Days have not been identified past calendar year 2024 it is anticipated that the same number of AETC Family days will be declared each year.

The base could be closed because of security problems, adverse weather, or other events. Unless otherwise notified by the Government, the Contractor should monitor local television stations, radio stations, or Goodfellow’s Facebook page for notification of a possible base closure or late opening. The Contractor may not receive any other form of notification of a base closure from the Government, unless contacted by the Contracting Officer (CO) or the COR. The Contractor is responsible for notifying his/her employees. Contractor(s) do not report when the base is closed due to security problems and/or adverse weather.

1.8 WORK AREA ACCESS: Government escorts are not needed in this area.

1.9 REFERENCES: All publications listed herein shall be the most current editions in effect at the time of solicitation and form a part of this Statement of Work. The publications are referred to in the text by basic designation only and include the following:

GAFB INSTRUCTION

GAFBI 31-102 Installation Security Instruction

AWWA Current Standards

ANSI /AWWA c652-19 - Standard for Disinfection of Water Storage Facilities

AWWA D102-24 Coating Steel Water Storage Tanks

AWWA D100-21 Welded Carbon Steel Tanks for Water Storage

NATIONAL FIRE CODE

NATIONAL ELECTRIC CODE

US ARMY CORPS OF ENGINEERS HEALTH AND SAFETY MANUAL

OCCUPATIONAL HEALTH AND SAFETY ADMINISTRATION (OSHA)

OSHA STD 29 CFR 1910 and 1926

OSHA STD 29 CFR 1926 Subpart M, Fall Protection

OSHA STD 29 CFR 1910.252 Welding, Cutting and Brazing (General Requirements)

30 TEXAS ADMINISTRATIVE CODE (TAC)

§290.43 Water Storage

1.10 SUBMITTALS: The Contractor shall provide submittals in the form of manufacturer’s data, certificates of compliance and samples for all items provided and installed per the attached AF Form 66. The Contractor shall not be permitted to perform any work on site without approved submittals and all materials on-site. The submittals listed on the attached AF

Form 66 shall be required and shall be submitted for Government Approved (GA) or For

Information Only (FIO), as designated. Use AF Form 3000 to process submittals. Submit electronic/digital copies of submittals to Contracting Officer. Execute draft DD Form 1354

SOW: Page 6 of 17

Checklist and submit to Contracting Officer during Pre-Final inspection. Additionally, the

Contractor shall complete and submit via AF Form 3000 the Project Closeout Checklist prior to completion of the project. The Government will only accept the beneficial occupancy date

(BOD) after approval/acceptance of all checklist items, unless otherwise noted as not applicable to the work.

1.11 MANUFACTURER’S CATALOG DATA: Data composed of catalog cuts, brochures, circulars, specifications and product data, and printed information in sufficient detail and scope to verify compliance with requirements of the contract documents.

1.11.1 MANUFACTURERS WARRANTY: The Contractor shall identify all items being installed that are covered by manufacturer’s guarantee or warranty and provide validated copies of such. The identification shall list the name of the company and the expiration date of the guarantee or warranty.

1.11.2 CONTRACTORS WARRANTY: The Contractor shall warrant all equipment, materials, and workmanship for a period of one [1] year after project completion. Any manufacturer and/or specified warranty that is for a period longer than the one [1] year Contractor warranty shall be so warranted. At a date one month prior to termination of the one [1] warranty, the Contractor and the Government shall review all installed equipment, materials and workmanship and the

Contractor shall make repairs and/or replacements of defective warranty items.

1.12 AS BUILT DRAWINGS: The Contractor shall update the attached drawing with notations showing the areas of repairs and/or equipment replacement. To include make/model information of installed equipment.

1.13 DD 1354 TRANSFER AND ACCEPTANCE OF DOD REAL PROPERTY: N/A

1.14 SAFETY: All Contractor operations shall be conducted and performed in accordance with

Department of Labor, OSHA requirements found in 29 CFR 1910 (1910.146 and 1910.147) and 29 CFR 1926, and Air Force Occupational Safety & Health (AFOSH) standards including

DAFMAN 91-203 Ch. 23, Air Force Consolidated Occupational Safety Instruction. The

Contractor shall also ensure that all work is performed in accordance with project identified national standards, military manuals, instructions, pamphlets, standards, and handbooks, and with the edition in effect on the date of this solicitation of the Corps of Engineers (COE) Safety

Manual 385-1-1. All job sites are subject to inspections by the Department of Labor. In the event of conflicts between the OSHA standards and these requirements, the most stringent shall apply. Prior to start of work, Contractor shall provide a Health and Safety Plan in accordance with COE Safety Manual 385-1-1 submitted to Contracting Officer via AF Form

3000 for Government Approval. The Contractor shall have a copy of the project safety plan on site for the duration of the project. The Contractor shall submit their most current OSHA safety rating.

1.14.1 FALL PROTECTION: Designed to meet OSHA STD 29 C.F.R. 1926 Subpart

M, Fall Protection, regulations equipped with all necessary plans, training and equipment.

SOW: Page 7 of 17

1.14.2 Resolution of Department of Labor citations for violations of Occupational Safety and

Health Standards is a Contractor responsibility and shall provide for no basis of a claim against the Government.

1.15 CONSTRUCTION WORK PLAN: The Contractor shall submit to Contracting Officer via

AF Form 3000 a Construction Work Plan that fully describes the means to perform all work including but not limited to providing all equipment, tools, materials, supplies, transportation, supervision, management, proposed project schedules, work sequence plans, and associated configurations for all demolition and new work including Architectural, Structural, Mechanical, and Electrical infrastructure as described in this SoW. As part of the work plan, the Contractor shall provide site surveys and other incidentals necessary to provide and test/commission all new systems as described in this SoW. If any departure from the SoW shall be deemed necessary by the Contractor, details of such departures and the reason thereof shall be submitted as soon as possible to the Contracting Officer, or designated representative for

Government Action.

1.16 QUALITY CONTROL PLAN: The Contractor shall prepare and submit for Government

Approval via AF Form 3000, a site-specific Quality Control Plan (QCP) that consists of plans, procedures, and organization necessary to produce a product which complies with the requirements stated in this SoW. The QCP shall cover all definable features of work

(construction operations, both onsite and offsite) and be keyed to the construction sequence.

1.17 PROGRESS SCHEDULE: Prior to start of work the Contractor shall submit an AF Form

3064 Contract Progress Schedule for approval to the Contracting Officer on AF Form 3000.

1.18 BARRIERS AND SIGNAGE: Prior to the start of any work for this project, the Contractor shall provide a “Safety Zone” around the base the water tower by using temporary orange warning fencing with “No Admittance” signage to indicate work site boundaries.

Fencing shall be maintained by the Contractor throughout the life of the contract. Applicable traffic control signage where required by the contract shall remain overnight. The Contractor shall be responsible for providing suitable, approved signs, barricades, roped barriers, etc., to warn personnel of hazardous areas at the job site for the entire duration of the contract.

Contractor shall be responsible for installing appropriate signage regarding worker health safety, wage determination laws, and OSHA requirements as required.

1.19 CONCRETE TRUCKS: N/A

1.20 REFUELING EQUIPMENT: If the project requires equipment that is powered by diesel or unleaded fuel, the Contractor shall designate a refueling area in the perimeter of their work site.

The refueling area shall have a tarp or waterproof liner placed under the refueling area.

Equipment in need of fuel shall be taken to this location to be refueled. Manage and store fuel, lubricants, and oil in accordance with all Federal, State, Regional, and local laws, and regulations. Used lubricants and used oil to be discarded must be stored in marked corrosion-resistant containers and recycled or disposed in accordance with 40 CFR 279, State, and local laws, and regulations. Storage of fuel on the project site is not allowed. Fuel must be brought to

SOW: Page 8 of 17 the project site each day that work is performed. Spills shall be reported to the Contracting

Officer.

1.21 TOBACCO USE IN AETC FACILITIES: Contractors are advised that the Commander has placed restrictions on the smoking of tobacco products in AETC facilities. AFI 40-102, Tobacco Use in the Air Force, outlines the procedures used by the commander to control smoking in our facilities. Contractor employees and visitors are subject to the same restrictions as government personnel. Smoking is permitted only in designated smoking areas. Additional information, to include locations of designated smoking areas, will be provided to the

Contractor upon request.

1.22 BASE ACCESS SECURITY REQUIREMENTS: The Contractor shall comply at all times with base law enforcement and security requirements to include base pass requirements.

Goodfellow Air Force Base is a closed/controlled access base. As an effort to minimize peak traffic flows at the entry gates, the Contractor, his employees, and his subcontractors are highly encouraged to avoid scheduling deliveries through the entry control gates from 7:00 A.M. to

8:00 A.M. Monday through Friday as there could be significant delays. The Government will conduct security/background checks on all construction personnel as required. Security requirements will be briefed at the pre-construction conference and handouts outlining specific requirements will be provided. Screening measures are in place and suitability for employees to access the installation will be determined during the conference. Requirements are subject to change dependent upon current world situations, potential threats, and base exercises. Full cooperation by Contractor work forces is required. Contractor should anticipate certain notification and reporting requirements, preparation of forms, and lists for pass and identification of employees and their vehicles, entry restrictions, key/lock control, and compliance with all base traffic rules and regulations. The Jacobson Gate Visitor Control

Center 325-654-4122 is the Office of Primary Responsibility (OPR) for passes.

1.23 INSTALLATION ACCESS PASS: Before arrival, a government identification card-holding person from the sponsoring agency, Base Contracting office/administrator or applicable local project manager will submit a request for base access using the 17 Training

Wing’s Base Access List (BAL) memorandum as a form of registration for each credential applicant. The base sponsor/sponsoring agency/Contracting Officer and the contracted management team should establish an accountability process to account for each applicant, to oversee the BAL process, and to retrieve installation passes when access is no longer required. Base sponsors/sponsoring agencies or contract officers will ensure the BAL is accurate, it is signed and forwarded to the 17 SFS Pass & Registration section for completion of the vetting and fitness determination processes. The BAL should be delivered to Pass &

Registration, located at the Visitor Control Center (VCC). When delivery is not possible, the

BAL may be forwarded to Pass & Registration via a “.mil” email account located on

Goodfellow AFB. The BAL will include pertinent visitor information, reason for entry, frequency of entry, destination, times each day requiring entry, and duration of request.

1.23.1 ACCESS DENIAL. If it is determined a Contractor requesting access has been convicted of a felony or pled guilty to a felony charge within the past 10 years, or is considered not fit to obtain authorized access based on the information obtained during the identity

SOW: Page 9 of 17 vetting, or criminal history indicates the individual may present a threat to the good order, discipline and morale of the installation, Security Forces personnel will deny entry. The

Contractor will be informed of the access denial, will be issued an Access Denial Letter, and will be informed on how they may appeal this order.

1.23.2 DENIAL APPEAL PROCESS. When denied access, contract visitors will be informed to report back their manager. If the contract worker and management are considering an appeal, it will be submitted by letter to the 17 SFS Commander, within 30 days of access denial. The contract manager should first contact the military contract officer/administrator or on-base sponsor for additional guidance and clarification. The appeal may be delivered to the installation Visitor Control Section or mailed to Security Forces, addressed to 17 SFS/CC, 361

Apache Trail, Goodfellow AFB, 76908. The Contractor's appeal should discuss all facts and reasons to support rescinding access denial. The 17 TRW/CC will approve/disapprove all appeals for entry.

1.23.3 ABNORMAL WORK SCHEDULE: For access on non-duty hours or down days:

Identify which workers need access on weekends, federal holidays/family days, and down days. Ensure only workers that are already vetted are on the Extended-Hours request (no new personnel). New personnel require a new BAL and formal vetting. Complete the “After Hours”

BAL for workers requiring down day access to the installation. Identify the vehicle requirements. If operations cannot support the search procedures for large vehicles/special purpose equipment, the request may be declined unless arrangements are made to deliver the vehicle/equipment prior, during normal duty hours.

1.23.4 PASS HANDLING: All BALs are accomplished each time employees or personnel change, not to exceed 180 days. Oversight for BAL updates and establishment of procedures to ensure Physical Access Control System (PACS) credentials and locally created access credentials from individuals who no longer require installation access is the responsibility of the contracting officer/contract administrator. When an employee (regardless of position) is no longer employed by the Contractor or Sub-Contractor all DBIDS passes are to be returned to the Contract Officer/Administrator or to the Visitor Control Center. If a local issued access credential/pass is not returned, the contract officer may withhold funds, or the Installation

Commander may consider permanent debarment to the installation. Immediate access denial may be initiated by Pass & Registration updating the DBIDS database until disposition of the

DBIDS pass is resolved.

PART 2.0 – PRODUCTS

2.1 REFERENCES TO MATERIALS, MANUFACTURERS AND PRODUCTS: Materials shall be the standard product of manufacturer’s regularly engaged in the manufacture of such products. The products furnished shall meet the quality and specifications indicated herein.

2.1.1 Technical exhibits provided by Government are for informational use only and may not constitute an accurate representation of site conditions. The Contractor is highly encouraged to visit the premises to become thoroughly familiar with the details of the work and working conditions. The Contractor shall field verify all dimensions, equipment, and conditions prior to

SOW: Page 10 of 17 the start of construction and advise the Contracting Officer of any discrepancies prior to commencing the work.

2.1.2 All materials to be used on this project shall be submitted via an AF Form 3000 by the

Contractor and approved by the Contracting Officer prior to installation.

2.1.2.2 PAINTS: Paint shall be:

Prime Coat – Macropoxy 646 PW or approved equal

Intermediate Coat – Macropoxy 646 PW or approved equal

Top Coat – Acrolon Ultra or approved equal

Contractor shall submit samples to match existing colors for the topcoat. Contractor shall submit SDS information on all surface cleaning and paint products to be used for the water towers.

NOTE: All paints must meet NSF/ANSI 61 Standard. NSF/ANSI 61 is intended to cover specific materials or products that come into contact with drinking water, drinking water treatment chemicals or both.

2.2 GOVERNMENT FURNISHED EQUIPMENT (GFE): There is no GFE for this project.

2.3 CONTRACTOR PROVIDED MATERIALS (CPM): The Contractors shall provide all materials and shall comply with Goodfellow Air Force Base Standards and the project specific criteria herein.

PART 3.0 – EXECUTION

3.1 GENERAL: All work shall be performed as shown and in accordance with the manufacturer’s diagrams and instructions, unless otherwise specified. All locations are expected to remain operational until a formal written request for an outage, shutdown, and/or disconnect by the Contractor has been submitted and approved by the Contracting officer. The

Contractor shall field verify all dimensions and site conditions. Price increase adjustments to the original contract price will not be issued because the Contractor was not aware of existing conditions. The Contractor shall provide all labor, materials, tools, and equipment required to perform all dismantling, repairs and installation as listed in this statement of work.

3.2 FIRST WORK: Prior to any on site activities are to begin at either location, the Contractor shall be responsible for reviewing the existing site conditions to ensure a safe and accessible working space for all Government, Contractor and sub-contractor personnel. Also, the

Contractor shall provide a “Safety Zone” at a minimum of 25’, if feasible, around the base the water tower by using temporary orange warning fencing with “No Admittance” signage to indicate work site boundaries.

NOTE: The Contractor should be aware that the adjacent buildings next to the west water tower, B738, are used daily. Therefore, the Government and the Contractor shall coordinate with the building personnel that overhead work will be conducted.

SOW: Page 11 of 17

3.2.1 EXTERIOR LADDER WORK: The Contractor shall make all necessary repairs to the external ladders and ensure that the ladders are secure and safe for personnel to use. No unauthorized personnel will be allowed to ascend the ladders until the ladders have been repaired, inspected, and approved to be safe and accessible.

3.3 DEMOLITION: The Contractor shall remove all items indicated in this SoW and on the provided inspection report. The Contractor shall recycle or divert construction wastes from landfill disposal to the maximum extent practicable. Rubbish and debris resulting from the demolition or construction activities shall be disposed of or placed in a refuse container daily.

All other salvage, unless requested specifically by the Government, shall belong to the

Contractor. The Contractor shall track recycling and waste disposal and submit the report on the provided Construction Waste Management Form for Government Approval at the end of the project, and prior to final acceptance of the work. The Contractor shall take all necessary precautions to prevent damage to property to remain in place.

3.2 CONSTRUCTION: The Contractor shall perform all work as outlined in this SoW and per the provided inspection report. The Contractor shall ensure that work for this project is performed in accordance with the criteria herein and that all equipment and systems shall be fully operational at the completion of work for this project.

Water Tower B738 – (To be performed first)

Phase 1 External Work -

1. The Contractor shall repair, secure, and make usable the external upper ladder.

2. The Contractor shall repair slider fall protection on the external upper ladder.

Phase 2 Drain Tank\Sediment Removal\Internal Inspection -

3. The Contractor shall request that the elevated tank be drained prior to any internal work is to be performed. A 72 hour written notice is required.

4. The Contractor shall remove all sediment from the interior of the tank.

5. The Contractor shall perform an internal inspection, after the sediment has been removed from the tank, and immediately notify the Government, by either photographic or video evidence, of any additional findings to the interior of the tank in need of repair or replacement that are not listed in the items below. To include the condition of the interior coating of the tank.

6. The Contractor shall haul off and dispose of all sediment from GAFB.

Phase 3 External\Internal Work –

7. The Contractor shall provide and install a new gasket to the overflow flapper seal.

8. The Contractor shall request that cathodic protection system be disabled prior to any external work is to be performed.

9. The Contractor shall repair external upper roof plates.

10. The Contractor shall reseal anode covers on the external roof plates.

11. The Contractor shall reseal the holes on the roof ventilation.

12. The Contractor shall remove fall protection system from internal access ladder.

13. The Contractor shall reseal holes in the internal roof plates.

SOW: Page 12 of 17

14. The Contractor shall remove internal heavy staining with an internal pressure washer.

15. The Contractor shall disinfect the interior of the tank after all interior work has been performed and completed.

16. The Contractor shall apply a protective coating to all bare metal surfaces created due to repairs and\or replaced items. Refer to the NSF/ANSI 61 for guidance

17. The Contractor shall install a Government provided pad lock to secure the access hatches.

18. The Contractor shall haul off and dispose of all generated refuse from GAFB.

19. The Contractor shall provide photographic and video evidence that all work mentioned above has been performed prior to the refilling of the tank and BOD inspection/acceptance.

Phase 4 Testing\Training\Certification\Inspection -

20. The Contractor shall perform all testing necessary to ensure that all equipment is operating\functioning as intended. To include any water quality sample testing.

21. The Contractor shall provide any training necessary to GAFB maintenance personnel.

22. The Contractor shall submit via an AF form 3000 all test reports, checklists, and certifications required by Federal, State, and local governments.

23. At the completion of the project, the Contractor shall perform a complete annual inspection of all elements of the water storage tank and provide the inspection report to the Government.

Reference TE “Water Storage Tank Inspection Log Sheet”

Water Tower B3475 –

Phase 1 External Work -

1. The Contractor shall repair and make usable the external lower ladder.

Phase 2 Drain Tank\Sediment Removal\Internal Inspection -

2. The Contractor shall request that the elevated tank be drained prior to any internal work is to be performed. A 72 hour written notice is required.

3. The Contractor shall remove all sediment from the interior of the tank.

4. The Contractor shall perform an internal inspection, after the sediment has been removed from the tank, and immediately notify the Government, by either photographic or video evidence, of any additional findings to the interior of the tank in need of repair or replacement that are not listed in the items below. To include the condition of the interior coating of the tank.

5. The Contractor shall haul off and dispose of all sediment from GAFB.

Phase 3 – External\Internal Work -

6. The Contractor shall provide and install a new gasket to the overflow flapper seal.

7. The Contractor shall repair the cathodic protection conduit and apply a protective coating over the repaired/replaced conduit.

8. The Contractor shall provide and install a new internal manual visual water level indicator system.

9. The Contractor shall haul and dispose of, off base, all generated refuse and sediment.

10. The Contractor shall remove internal heavy staining with an internal pressure washer.

11. The Contractor shall sanitize the interior of the tank after all interior work had been performed and completed.

SOW: Page 13 of 17

12. The Contractor shall apply a protective coating to all bare metal surfaces created due to repairs and /or replaced items. Refer to the NSF\ANSI 61 for guidance

13. The Contractor shall install a Government provided pad lock to the access hatches.

14. The Contractor shall provide photographic and video evidence that all work mentioned above has been performed prior to the refilling of the tank and BOD inspection/acceptance.

Phase 4 Testing\Training\Certification\Inspection -

15. The Contractor shall perform all testing necessary to ensure that all equipment is operating\functioning as intended. To include any water quality sample testing.

16. The Contractor shall provide any training necessary to GAFB maintenance personnel.

17. The Contractor shall submit via an AF form 300 all test reports, checklists, and certifications required by Federal, State, and local governments.

18. At the completion of the project, the Contractor shall perform a complete annual inspection of all elements of the water storage tank and provide the inspection report to the Government.

Reference TE “Water Storage Tank Inspection Log Sheet”

3.4 UTILITIES: Always protect all utilities. The Contractor shall immediately notify the

Contracting representative of any disruptions to utilities within the project SoW and provided inspection report. Any damage to the aforementioned items to remain in place shall be repaired or replaced by the Contractor at no additional cost to the Government.

3.5 COMPLETION: The Contractor shall ensure that all equipment and systems are fully operational and functioning as intended. The Contractor shall also be responsible for returning the work site in a clean, clear, and free of debris, trash, or refuse area.

3.6 FINAL INSPECTION: The Contractor shall advise the Contracting Officer (CO) in writing of the Contractor’s desired final inspection date seven (7) calendar days in advance of that desired date to permit proper coordination. The date selected shall provide adequate time for

Contractor to perform corrections of final inspection deficiencies within the contract performance period. The Contracting Officer will be the final authority for determining whether or not the Contractor’s performance is sufficiently advanced to warrant a final inspection. The final inspection shall include all required testing\sampling and operational functionality report of replaced\repaired equipment submit via AF Form 3000 for Government approval.

PART 4.0 – UTILITY OUTAGES AND SPECIAL CONDITIONS

4.1 BASE CIVIL ENGINEERING WORK CLEARANCE REQUEST: The Contractor shall obtain and process AF Form 103 for approval prior to commencement of work for this project.

The Contractor shall have this approved form on the job site at all times.

4.1.1 Due to the requirement for multiple agencies to coordinate on these requests, expect 7 –

10 days for paperwork processing. Contractor requests should be submitted at the earliest possible date to preclude delays.

4.2 UTILITIES: Upon a written request by the Contractor, the Government will provide all

SOW: Page 14 of 17 available information in its possession concerning utilities in the contract work area.

4.2.1 UTILITY OUTAGES: When a utility outage is necessary to perform the contract work, regardless of whether the work area is occupied, the outage shall be performed by the

Contractor during non-duty hours at no additional cost to the Government, unless otherwise approved by the Contracting Officer. The Contractor shall notify the Contract Inspector of outage requirements to include buildings affected, length of outage, and reasons for outage.

The Contractor must allow affected occupants a minimum of two (2) weeks’ notice prior to the outage. The Contractor is also required to provide the Contracting Office a written notification of the requested outage. In the event of accidental disruption of any utility, the Contractor shall immediately notify the Contracting Officer of the unplanned outage. After reporting it to the

Contracting Officer, call Civil Engineering (325-654-3436) to inform them of an outage with what type of utility you may have encountered. The Contractor shall immediately take every reasonable step to repair the damage in a manner acceptable to the Government and shall restore the utility to full use as soon as practicable.

4.2.2 ACCIDENTAL UTILITY DISRUPTIONS: In the event of accidental disruption of any utility, the Contractor shall immediately notify the Contracting officer of the unplanned outage.

After reporting it to the Contracting Officer, call Civil Engineering (325-654-3436) to inform them of an outage with what type of utility you may have encountered.

4.3 BASE FIRE REGULATIONS: The Contractor shall comply with Base Fire Regulations as set forth by the GAFB Fire Department during the project pre-construction meeting. The

Contractor shall use no explosives or fire in performing the work. All work shall be in strict compliance with all National Fire Codes.

4.4 WELDING, CUTTING, AND BRAZING: Fire Protection shall complete inspection of all welding, cutting and brazing operations prior to any operation. The Contractor shall provide the appropriate operable fire extinguisher. Contractor shall comply be with OSHA STD29

CFR 1910.252 Welding, Cutting and Brazing (General Requirements) and AFOSH 91-5

Welding, Cutting and Brazing. Air Force Form 592 USAF Welding, Cutting and Brazing permit will be issued prior to any operation and shall be kept on site until completion of operation or permit expires. Contact Fire Protection at (325) 654-3532/33/34 for issuance of permit. Only certified licensed welding technicians experienced with this type of work will be allowed to perform work on the water tanks. The Contractor shall provide and submit to the

Contracting officer, the welding technicians credentials via an AF form 3000 to the

Government prior to work being performed.

4.5 FIRE HYDRANT USE REQUIREMENTS: N/A

4.6 CONFINED SPACE: Prior to start of work and in accordance with Air Force Occupational

Safety, Fire, and Health Standards, DAFMAN 91-203 Ch. 23. The Contractor shall coordinate with the Government to ensure the following criteria has been met when entering a confined space:

a) Verify if the space is classified as “Confined Space” and if permit or non-permit is required.

b) Verify of the existing contents of the space.

SOW: Page 15 of 17

c) Verify of known hazards within the space.

d) Provide a “Confined Space” plan outlining what precautions and procedures will be implemented by the organization to protect all personnel entering the space.

e) Coordinate operations and procedures and agree on permit system to be used if both AF and

Contractor personnel will enter the space at the same time.

The Fire Department will provide a written notification in the contract if they are supplying a rescue team.

PART 5.0 - SITE MAINTENANCE AND CLEANUP

5.1 PROTECTION OF GOVERNMENT PROPERTY: The Contractor shall use reasonable care to avoid damaging existing interior and exterior conditions of buildings or equipment on the

Government installation. If the Contractor fails to use reasonable care and causes damage to any of this property, the Contractor shall replace or repair the damage at no expense to the

Government as recommended by Civil Engineering and approved by the Contracting Officer.

5.2 SITE MAINTENANCE: The Contractor shall use reasonable care to protect existing interior and exterior elements of the building, adjacent property, and equipment outside the scope of work. Work areas shall be maintained in a neat, clean, safe condition and shall, at a minimum, be cleaned at the end of each shift. All streets and roadways in/or adjacent to the site shall remain free of project generated trash and debris at all times.

5.3 DAILY CLEANUP: All trash, debris, refuse, garbage, etc., that is generated shall be immediately removed, at a minimum on a daily basis and as required, at the Contractor’s expense in accordance with all local, state, and federal environmental laws and regulations.

The aforementioned materials shall be hauled from the site by appropriate means, unless otherwise approved by the Contracting Officer (CO). The Contractor shall collect any and all trash, debris, refuse, garbage, etc., that is generate and place it in appropriate containers with lids or approved covers on a daily basis or as directed by the Contracting Officer’s representative. All areas shall be cleaned at a minimum daily and as required to maintain a professional appearance at all times. All existing building interiors affected by construction shall be maintained and fully protected by the Contractor until completion of work for this project.

5.4 FINAL CLEANUP: Upon completion of the work, the Contractor shall leave the work site and storage area(s) in a clean, neat, and organized condition to the satisfaction of the

Contracting Officer. The Contractor shall remove debris or loose material remaining on the site and dispose in accordance with this SoW. The Contractor is prohibited from using installation dumpsters and other trash receptacles. The aforementioned materials shall be hauled from the site by appropriate means on a daily basis, unless otherwise approved by the Contracting

Officer’s Representative. Disposal shall be outside the limits of Government property. Disposal shall be by sanitary landfill, or recycled and shall conform to all local, city, state, and federal guidelines, EPA criteria, and regulations. The Contractor shall ensure that work for this project is performed in accordance with the criteria herein and that all equipment and systems shall be

SOW: Page 16 of 17

PART 6.0 - ENERGY CONSERVATION

6.1 UTILITIES CONSERVATION: The Contractor shall instruct employees in utilities conservation practices. For this contract, utilities, such as water and electricity, will be furnished by the government at no cost to the Contractor. Long distance and Defense Switched

Network (DSN) telephone services will not be provided. The Contractor shall not adjust mechanical equipment controls for heating, ventilation, and air conditioning systems. Water faucets or valves shall be turned off after the required usage has been accomplished. The

Contractor shall use good judgment in the conservation of Government utilities. Prevailing energy conservation practices shall be adhered to and enforced by the Contractor.

PART 7.0 – RESPONSIBILITY

7.1 CONTRACTOR RESPONSIBILITY: The above Parts 1 through 6 do not in any way limit the responsibility of the Contractor to perform all work and furnish all plant, labor, and materials required by this Statement of Work.

PART 8.0 – STORAGE AND PARKING

8.1 CONTRACTOR STORAGE: Goodfellow AFB does not provide on base storage for

Contractor use. The Contractor shall request in the form of an RFI a materials and equipment laydown area. All project storage areas shall be kept free of debris, leaks, stains, or splashes and kept in a neat, clean, and safe condition. Due to high winds that may occur, the Contractor shall be responsible for strapping down any loose material and storing in accordance with manufacturer recommendations. Any contamination of the storage area by a hazardous substance shall be immediately remediated by the Contractor, in accordance with the contract above at no additional expense to the Government. All hazardous materials shall be secured when not in use.

The Contractor shall not work or store materials in a manner that would hinder or otherwise block pedestrian circulation. If additional storage space is needed, the Contractor shall submit a request along with a single line diagram describing additional needed space. In all instances, the

Contractor shall be responsible for the security, storing and preparing of materials in the manner specified herein, or by the manufacturer’s instructions, so that materials are properly suited for installation.

PART 9.0 - COMPLETION OF WORK

9.1 OPERATIONAL SYSTEMS: The Contractor shall ensure that work for this project is performed in accordance with the criteria herein and that all equipment and systems shall be

END OF STATEMENT OF WORK

SOW: Page 17 of 17

SEE ATTACHMENT

ATTACHMENT 1: ENVIRONMENTAL PROTECTION

TECHNICAL EXHIBITS (TE)

• FIO - Inspection Report with Recommended Repairs w/ Photos and Notes

• Section 01540 Green Purchasing

• Example - Water Storage Tank Inspection Log Sheet

• Water Tower Drawing

February 17, 2023 Section 01400 – Page 1 of 14

ATTACHMENT 1

DIVISION 1 - GENERAL REQUIREMENTS

SECTION 01400 - ENVIRONMENTAL PROTECTION

1. APPLICABLE ENVIRONMENTAL REGULATIONS, LAWS, AND PUBLICATIONS:

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only. All publications shall be the latest version / edition / revision of the documents listed below, in effect on the date of this solicitation, except where a date is given.

1.1. Code of Federal Regulations (CFR):

29 CFR, Part 1910 Hazardous Waste Operation and Emergency Response

40 CFR 61, Subpart M National Emissions Standard for Hazardous Air Pollutants

40 CFR, Part 82 Protection of Stratospheric Ozone - N\A

40 CFR, Part 117 Determination of Reportable Quantities for Hazardous

Substances

40 CFR, Part 122 National Pollutant Discharge Elimination System

(NPDES) Regulations – N\A

40 CFR, Parts 260 - 282 Solid Waste Regulations

40 CFR, Part 302 Designation, Reportable Quantities, and Notification

49 CFR, Parts 171-176 Hazardous Materials Regulations, Department of

Transportation, (DOT) Rules

1.2. Environmental Protection Agency Publication (EPA):

EPA Publication No. SW-846 Test Methods for Evaluating Solid Waste

1.3. Environmental Laws:

Archaeological and Historic Preservation Act (AHPA) – N\A

Archaeological Resources Protection Act (ARPA) – N\A

Clean Air Act (CAA) and all amendments

February 17, 2023 Section 01400 – Page 2 of 14

Clean Water Act (CWA) as amended

Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) – N\A

Endangered Species Act (ESA) – N\A

Emergency Planning and Community Right-To-Know Act (EPCRA)

Federal Insecticide, Fungicide, and Rodenticide Act (FIFRA) as amended – N\A

Federal Water Pollution Control Act (FWPCA)

National Oil and Hazardous Substances Contingency Plan (NCP) – N\A

Occupational Health and Safety Act (OSHA)

Oil Pollution Act (OPA) – N\A

Pollution Prevention Act (PPA)

Resources Conservation and Recovery Act (RCRA)

Safe Drinking Water Act (SDWA), as amended

1.4. State Regulations (Texas Administrative Code):

25 TAC§295 Occupational Health

30 TAC§205 General Permit to Discharge Waste

30 TAC§290 Public Drinking Water

30 TAC§335 Industrial Solid Waste and Municipal Hazardous Waste

1.5. Air Force Instruction (AFI): 32-7001 Environmental Management

1.6. Air Force Manual (AFMAN): 32-7002 Environmental Compliance and Pollution

Prevention

1.7. Energy Independence and Security Act (EISA) Section 438 – N\A

2. ENVIRONMENTAL ISSUES

2.1. Activities which are implemented, in whole or in part with approved funding, must comply with applicable legislation and regulations established to protect the human or physical environment. The

Contractor will remain in compliance with Federal statutes during the performance of the contract, including but not limited to the Clean Air Act (CAA), Clean Water Act (CWA), Resource Conservation and Recovery Act (RCRA), and other applicable laws, regulations, and requirements.

February 17, 2023 Section 01400 – Page 3 of 14

2.2. In order to comply with all Environmental Laws and Regulations as set forth by Federal, State, Department of Defense, Air Force and any other mandated requirements for Federal installations, Goodfellow AFB (GAFB) must comply with and are required to identify, manage and track all chemicals (hazardous materials), air emissions, stormwater, and construction and debris (C&D) that are transported, managed, used, and disposed of from any part of this installation. This requirement is for all installation organizations, workplaces, work centers, shops, and for all Contractors doing any work on the installation. Contractors shall investigate, comprehend, and comply with all environmental rules and regulations applicable to their chosen method of accomplishment of the work under this contract.

2.3. The Contractor will be responsible for and will indemnify and hold the Government harmless for any and all spills, releases, emissions, and discharges of any toxic or hazardous substance, any pollutant, or any waste, whether sudden or gradual, caused by or arising under the performance of this contract or any substance, material, equipment, or facility utilized therefore for the purposes of any environmental statute or regulation. The Contractor will be considered the "operator" for any facility utilized in the performance of the contract and will indemnify and hold the Government harmless for the failure to adhere to any applicable law or regulation established to protect the human or physical environment.

The Contractor will be responsible in the same manner as above regardless of whether activities leading to or causing a spill, release, emission, or discharge is performed by the contractor, its agent or designee, an offender, visitor, or any third party.

3. PROTECTION OF RESOURCES

3.1. Construction activities are NOT exempt from air emission, stormwater, hazardous waste, and other environmental compliance rules and regulations. Contractor shall investigate, comprehend, and comply with all environmental rules and regulations applicable to his/her chosen method of accomplishment of the work under this contract.

3.2. Protection of Land Resources: The Contractor shall confine his/her construction activities to areas defined by the plans and specifications and/or as approved in his/her Storage Area submittal (refer to paragraph 7). Except in areas to be cleared, the Contractor shall not remove, cut, deface, injure or destroy trees or shrubs without written permission from the Natural Resource Officer/Manager and

Contracting Officer. Do not fasten or attach ropes, cables, or guys to existing or nearby trees for anchorage unless authorized by the Natural Resource Officer/Manager and the Contracting Officer.

Where such use of ropes, cables, or guys is authorized, the Contractor shall be responsible for any resultant damage.

3.3. N\A

3.4. N\A

3.4.1. N\A

3.5. Protection of Water Resources: The Contractor shall not pollute streams, lakes, or reservoirs with fuels, oils, bitumens, calcium chloride, acids, construction wastes, siltation from stormwater runoff, or other harmful materials identified in 40 CFR Parts 117 and 302. It is the responsibility of the

Contractor to investigate, comprehend, and comply with all applicable Federal, State, County, and

Municipal regulations and ordinances concerning pollution of rivers and streams. All work under this

February 17, 2023 Section 01400 – Page 4 of 14 contract shall be performed in such a manner that objectionable or nuisance conditions will not be created in lakes, reservoirs, or streams through or adjacent to the project areas.

3.5.1. N\A

3.5.2. Regardless of the amount of soil disturbed, all non-storm water discharges shall conform with the base’s Storm Water Management Program regulated by TPDES General Permit TXR040000 for

Small Municipal Separate Storm Sewer Systems (MS4).

3.5.3. N\A

3.5.4. N\A

3.5.5. N\A

3.5.6. Post-Construction Cleanup or Obliteration: The Contractor shall obliterate all evidence of…