Material Submittals Schedule
| Project Number: | ||
| MAHG111042 | Project Title: | |
| Repair Bryan Hall | Solicitation / Contract Number & Attachment Number: |
FA301023R0001, Attachment 5
| Line Number | (To be completed by Project Engineer) | (To be completed by Contract Administrator) | |||||||||||||||
| Number of Copies Required (if not electronically submitted) | Remarks | ||||||||||||||||
| Item or Description of Item, Contract Reference, Type of Submittal | Certificate of Compliance | Shop Drawings | Samples | Color Selection | Manufacturer's Recommendation | Warranty-Manufacturer and/or Workmanship | Catalog Data | Operating Instructions | Schedules, Listings, Reports, Plans | Technical Data | Test Reports | Field Reports | Required Submission Date |
fergusog: Enter the due date from the Contractor (MM/DD/YY) Date Received in Contracting fergusog: Enter the date received from the Contractor. (MM/DD/YY) Date to Civil Engineering fergusog: Enter the date submittal was given to CE for review. (MM/DD/YY) Return Suspense Date fergusog: Enter the date the submittal is due back from CE
(MM/DD/YY)
Submittal Numbers fergusog: Enter the Submittal Number
| Date Contractor | ||
| Notified | Contractor Resubmittal |
fergusog: Enter Resubmittal Number Final Approval fergusog: Enter the submittal final approval date
(MM/DD/YY)
Approved fergusog: Enter date the Contractor was notified of submittal approval
(MM/DD/YY)
fergusog: Enter Resubmittal Number Disapproved fergusog: Enter date the Contractor was notified of submittal disapproval
(MM/DD/YY)
fergusog: Enter the submittal final approval date
(MM/DD/YY)
| 1 | HazMat Questionnaire | 1 | 5 Days Prior to Start Date | Provide the documents as required per the Environmental packet provided by Keesler AFB. | ||||||||||||
| 2 | HazMat MSDS | 1 | 1 | 5 Days Prior to Start Date | Provide the documents as required per the Environmental packet provided by Keesler AFB. | |||||||||||
| 3 | Hazmat Reporting Entry Form | 1 | 1 | 1 | 5 Days Prior to Start Date | Provide the documents as required per the Environmental packet provided by Keesler AFB. | ||||||||||
| 4 | Recycling and Landfill Report | 1 | 1 | End of Contract | Provide the documents as required per the Environmental packet provided by Keesler AFB. | |||||||||||
| 5 | Warranty (Manufacturer's) | 1 | End of Contract | |||||||||||||
| 6 | 1-Year Warranty (Contractor) | 1 | End of Contract | |||||||||||||
| 7 | 02 41 00 | Existing Conditions, 1.9 | 1 | 1 | 5 Days Prior to Start Date | |||||||||||
| 8 | 02 41 00 | Demolition Plan, 1.2.1 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 9 | 02 41 00 | Notification, 1.7.1 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 10 | 02 82 16.00 20 | Vacuums, 3.1.4 | 1 | 14 days Prior to associated work | ||||||||||||
| 11 | 02 82 16.00 20 | Respirators, 3.1.1.1 | 1 | 14 days Prior to associated work | ||||||||||||
| 12 | 02 82 16.00 20 | Amended Water, 1.2.2 | 1 | 14 days Prior to associated work | ||||||||||||
| 13 | 02 82 16.00 20 | Glove bag | 1 | 14 days Prior to associated work | ||||||||||||
| 14 | 02 82 16.00 20 | MSDS for all materials | 1 | 5 Days Prior to Start Date | ||||||||||||
| 15 | 02 82 16.00 20 | Encapsulants | 1 | 14 days Prior to associated work | ||||||||||||
| 16 | 02 82 16.00 20 | Clearance Sampling | 1 | Once work in section is complete | ||||||||||||
| 17 | 02 82 16.00 20 | Air Sampling | 1 | Once work in section is complete | ||||||||||||
| 18 | 02 82 16.00 20 | Asbestos Abatement Plan, 1.3.8 | 1 | 5 Days Prior to Start Date | ||||||||||||
| 19 | 02 82 16.00 20 | Testing Lab, 1.3.9 | 1 | 14 days Prior to associated work | ||||||||||||
| 20 | 02 82 16.00 20 | Private Qualified Person, 1.5.1 | 1 | approval required prior to abatement plan submittal | ||||||||||||
| 21 | 02 82 16.00 20 | Competent Person, 1.5.2 | 1 | 14 days Prior to associated work | ||||||||||||
| 22 | 02 82 16.00 20 | Contractor's Permits & License | 1 | 14 days Prior to associated work | ||||||||||||
| 23 | 02 82 16.00 20 | Waste Shipment Records, 1.3.10 | 1 | Once work in section is complete | ||||||||||||
| 24 | 02 83 00 | Competent Person, 1.5.1.1 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 25 | 02 83 00 | Training Certification, 1.5.1.2 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 26 | 02 83 00 | Occupational and Environmental Assessment Data Report, 1.5.2.3 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 27 | 02 83 00 | Medical Examinations, 1.5.2.4 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 28 | 02 83 00 | Lead, Cadmium, Chromium Waste Management Plan, 1.5.2.8 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 29 | 02 83 00 | Licenses, Permits and Notifications, 1.5.4 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 30 | 02 83 00 | Lead, Cadmium, Chromium Compliance Plan, 1.5.2.2, 3.1.1.6 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 31 | 02 83 00 | Written Evidence of TSD Approval | 1 | 14 Days Prior to Start Date | ||||||||||||
| 32 | 02 83 00 | Respirators, 1.6.1 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 33 | 02 83 00 | Vacuum Filters, 1.6.4 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 34 | 02 83 00 | Negative Pressure System, 1.6.7 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 35 | 02 83 00 | Materials & Equipment, 2.1 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 36 | 02 83 00 | Expendable Supplies, 2.1.1 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 37 | 02 83 00 | Local Exhaust System. 3.1.1.5 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 38 | 02 83 00 | Pressure Differential Automatic Recording System, 3.1.1.5 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 39 | 02 83 00 | Pressure Differential Log, 3.1.1.6 | 1 | 1 | 14 Days Prior to Start Date | |||||||||||
| 40 | 02 83 00 | Sampling and Analysis, 1.3.3 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 41 | 02 83 00 | Occupational and Environmental Assessment Data Report, 1.5.2.3 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 42 | 02 83 00 | Sampling Results, 1.5.2.3 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 43 | 02 83 00 | Pressure Differential Recordings For Local Exhaust System, 1.5.3 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 44 | 02 83 00 | Testing Laboratory, 1.5.1.3 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 45 | 02 83 00 | Notification of the Commencement of [LBP] Hazard Abatement | 1 | 14 Days Prior to Start Date | ||||||||||||
| 46 | 02 83 00 | Clearance Certification, 3.5.1.1 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 47 | 02 83 00 | Hazardous Waste Manifest, 3.5.2.1 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 48 | 02 83 00 | Turn-In Documents or Weight Tickets | 1 | 14 Days Prior to Start Date | ||||||||||||
| 49 | 03 30 00 | Reinforcing Steel, 1.6.2.1 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 50 | 03 30 00 | Formwork, 2.4.5 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 51 | 03 30 00 | Curing Materials, 2.3.7 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 52 | 03 30 00 | Joint Sealants, 2.3.10 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 53 | 03 30 00 | Joint Filler, 2.3.9 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 54 | 03 30 00 | Aggregate Materials, 1.7 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 55 | 03 30 00 | Cement, 2.3.1 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 56 | 03 30 00 | Ready-mix concrete, 2.2.2 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 57 | 03 30 00 | Water-vapor barrier subgrade cover, 2.3.6.1 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 58 | 03 30 00 | Bonding Materials, 2.5 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 59 | 03 30 00 | Floor Finish Materials, 2.6 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 60 | 03 30 00 | Liquid Chemical Floor Hardener, 2.6.1 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 61 | 03 30 00 | Mix Design, 2.2.1, 1.6.4.1 | 1 | 1 | 14 Days Prior to Start Date | |||||||||||
| 62 | 03 30 00 | Compressive strength tests, 3.10.2.3 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 63 | 03 30 00 | Unit Weight of Structural Lightweight Concrete, 3.10.2.5 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 64 | 03 30 00 | Air Content, 3.10.2.4 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 65 | 03 30 00 | Slump, 2.7.4 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 66 | 03 30 00 | Air Entrainment, 2.7.1 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 67 | 03 30 00 | Curing concrete element, 1.6.3.1 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 68 | 03 30 00 | Finishing plan, 1.6.3.3 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 69 | 03 30 00 | Fly Ash | 1 | 14 Days Prior to Start Date | ||||||||||||
| 70 | 03 30 00 | Ground Granulated Blast-furnace slag | 1 | 14 Days Prior to Start Date | ||||||||||||
| 71 | 03 30 00 | Steel bar | 1 | 14 Days Prior to Start Date | ||||||||||||
| 72 | 05 12 00 | Erection Plan, 1.4.2.1 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 73 | 05 12 00 | Fabrication Drawings, 1.4.1 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 74 | 05 12 00 | Shop primer, 2.4 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 75 | 05 12 00 | Welding electrodes and rods, 2.3.1 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 76 | 05 12 00 | Load indicator bolts and washers | 1 | 14 Days Prior to Start Date | ||||||||||||
| 77 | 05 12 00 | Non-shrink grout, 2.3.2 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 78 | 05 12 00 | Class B Coating, 2.4 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 79 | 05 12 00 | Bolts, Nuts, and Washers, 2.2 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 80 | 05 12 00 | Galvanizing, 2.5 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 81 | 05 12 00 | Welding procedures and qualifications, 1.4.2.2 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 82 | 05 40 00 | Framing components | 1 | 14 Days Prior to Start Date | ||||||||||||
| 83 | 05 40 00 | Metal Framing Calculations, 1.6.2 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 84 | 05 50 13 | Roof hatch, 3.10 | 1 | 1 | 14 Days Prior to Start Date | |||||||||||
| 85 | 05 50 13 | Access Doors and Panels, 2.3 | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||||||||
| 86 | 05 50 13 | Expansion Joint Covers, 2.4 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | |||||||||
| 87 | 05 50 13 | Floor Gratings, 2.6 | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||||||||
| 88 | 05 52 00 | Fabrication Drawings, 1.2.1 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 89 | 05 52 00 | Aluminum Railings and Handrails, 2.2.2 | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||||||||
| 90 | 05 52 00 | Anchorage and Fastening Systems, 1.2.1 | 1 | 1 | 14 Days Prior to Start Date | |||||||||||
| 91 | 05 52 00 | Welding Procedures, 1.4.1 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 92 | 05 52 00 | Welder Qualifications,1.4.2 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 93 | 06 10 00 | Self-adhering Membrane | 1 | 14 Days Prior to Start Date | ||||||||||||
| 94 | 06 10 00 | Liquid Applied Membrane Adhesives | 1 | 14 Days Prior to Start Date | ||||||||||||
| 95 | 06 20 00 | Detail Drawings, 1.3 | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||||||||
| 96 | 06 61 16 | Solid Polymer Material, 2.1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | |||||||||
| 97 | 06 61 16 | Fabrications, 2.3 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 98 | 07 21 16 | Blanket Insulation, 2.1 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 99 | 07 22 00 | Insulation Board Layout, 1.3 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 100 | 07 22 00 | Verification of Existing Conditions, 1.3 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 101 | 07 22 00 | Insulation, 2.1 | 1 | 1 | 14 Days Prior to Start Date | |||||||||||
| 102 | 07 22 00 | Cover Board, 1.47 | 1 | 1 | 14 Days Prior to Start Date | |||||||||||
| 103 | 07 22 00 | Fasteners, 2.5 | 1 | 1 | 14 Days Prior to Start Date | |||||||||||
| 104 | 07 22 00 | Installer Qualifications, 1.6 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 105 | 07 22 00 | Felt Materials, 1.6 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 104 | 07 22 00 | Warranty | 1 | 14 Days Prior to Start Date | ||||||||||||
| 106 | 07 24 00 | EIFS Shop Drawings, 3.3 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 107 | 07 24 00 | Sheathing Board, 2.12 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 108 | 07 24 00 | Thermal Insulation, 2.5 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 109 | 07 24 00 | Adhesive, 2.3 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 110 | 07 24 00 | Accessories, 2.11 | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||||||||
| 111 | 07 24 00 | Base Coat, 2.6 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 112 | 07 24 00 | Portland Cement, 2.7 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 113 | 07 24 00 | Reinforcing Fabric, 2.8 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 114 | 07 24 00 | Finish Coat, 2.9 | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||||||||
| 115 | 07 24 00 | Joint Sealants, 2.12 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 116 | 07 24 00 | Sealant Primer, 2.10 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 117 | 07 24 00 | Bond Breaker, 2.13 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 118 | 07 24 00 | Backer Rod, 2.14 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 119 | 07 24 00 | Insulation Board, 1.4.5, 2.5.2 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 120 | 07 24 00 | Warranty, 1.7 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 121 | 07 24 00 | Sample Boards & Mock up, 1.2.1.3, 1.2.3.7 | 1 | 1 | 14 Days Prior to Start Date | |||||||||||
| 122 | 7 24 00 | Wind load | 1 | 14 Days Prior to Start Date | ||||||||||||
| 123 | 7 24 00 | Moisture Analysis | 1 | 14 Days Prior to Start Date | ||||||||||||
| 124 | 7 24 00 | Abrasion Resistance1.2.3.1 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 125 | 7 24 00 | Accelerated Weathering | 1 | 14 Days Prior to Start Date | ||||||||||||
| 126 | 7 24 00 | Impact Resistance | 1 | 14 Days Prior to Start Date | ||||||||||||
| 127 | 7 24 00 | Mildew Resistance | 1 | 14 Days Prior to Start Date | ||||||||||||
| 128 | 7 24 00 | Salt Spray Resistance | 1 | 14 Days Prior to Start Date | ||||||||||||
| 129 | 7 24 00 | Vapor Transmission | 1 | 14 Days Prior to Start Date | ||||||||||||
| 130 | 7 24 00 | Absorption-Freeze-Thaw | 1 | 14 Days Prior to Start Date | ||||||||||||
| 131 | 7 24 00 | Wall Fire Test | 1 | 14 Days Prior to Start Date | ||||||||||||
| 132 | 7 24 00 | Water Penetration | 1 | 14 Days Prior to Start Date | ||||||||||||
| 133 | 7 24 00 | Water Resistance | 1 | 14 Days Prior to Start Date | ||||||||||||
| 134 | 7 24 00 | Surface Burning Characteristics | 1 | 14 Days Prior to Start Date | ||||||||||||
| 135 | 7 24 00 | Radiant Heat | 1 | 14 Days Prior to Start Date | ||||||||||||
| 136 | 7 24 00 | Substrate | 1 | 14 Days Prior to Start Date | ||||||||||||
| 137 | 7 24 00 | Wind Load | 1 | 14 Days Prior to Start Date | ||||||||||||
| 138 | 7 24 00 | Qualifications of EIFS Manufacturer, 1.4.1 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 139 | 7 24 00 | Qualifications of EIFS Installer, 1.4.2 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 140 | 7 24 00 | Qualifications of Sealant Applicator, 1.4.3 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 141 | 7 24 00 | Qualifications of third-party inspector, 1.4.4 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 142 | 7 24 00 | Inspection Checklist, 3.5.2 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 143 | 7 24 00 | Installation, 3.3 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 144 | 7 24 00 | EIFS, 1.7 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 145 | 07 60 00 | Gutters, 3.1.7 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||||
| 146 | 07 60 00 | Downspouts, 3.1.8 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||||
| 147 | 07 60 00 | Expansion Joints, 3.1.10 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||||
| 148 | 07 60 00 | Flashings at Roof Penetrations, 3.1.11 | 1 | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | |||||||
| 149 | 07 60 00 | Copings, 3.1.13 | 1 | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | |||||||
| 150 | 07 84 00 | Firestopping Materials, 2.1 | 1 | 1 | 14 Days Prior to Start Date | |||||||||||
| 151 | 07 84 00 | Inspections, 3.3 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 152 | 08 11 13 | Doors, 2.1 | 1 | 1 | 14 Days Prior to Start Date | |||||||||||
| 153 | 08 11 13 | Frames, 2.1 | 1 | 1 | 14 Days Prior to Start Date | |||||||||||
| 154 | 08 11 13 | Accessories, 2.7 | 1 | 1 | 14 Days Prior to Start Date | |||||||||||
| 155 | 08 11 16 | Door and Frame Assembly, 1.5.1, 1.5.2, | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||||||
| 156 | 08 11 16 | Calculations, 1.2.2 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 157 | 08 11 16 | Air Infiltration, 1.2.3 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 158 | 08 11 16 | Water Penetration, 1.2.4 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 159 | 08 11 16 | NFRC Project Label Certificates, 1.2.5 | 1 | 1 | 14 Days Prior to Start Date | |||||||||||
| 160 | 08 11 16 | Adjustments, Cleaning, and Maintenance, 1.5.4 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 161 | 08 14 00 | Doors, 2.1 | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||||||||
| 162 | 08 14 00 | Accessories, 2.2 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 163 | 08 14 00 | Water Resistant Sealer, 2.3.6 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 164 | 08 14 00 | Warranty, 1.4 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 165 | 08 14 00 | Fire resistance rating, 2.1.2 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 166 | 08 71 00 | Hardware schedule, 1.3 | 1 | 1 | 14 Days Prior to Start Date | |||||||||||
| 167 | 08 71 00 | Keying system, 2.3.7 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 168 | 08 71 00 | Hardware items, 2.3 | 1 | 1 | 14 Days Prior to Start Date | |||||||||||
| 169 | 08 71 00 | Hardware Schedule, 1.3 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 170 | 08 81 00 | Insulating Glass, 1.6.1 | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||||||
| 171 | 08 81 00 | Glazing Accessories. 1.3 | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||||||||
| 172 | 08 91 00 | Wall Louvers, 1.4, 1.5, 2.2 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | |||||||||
| 173 | 09 22 00 | Metal Support systems, 2.1 | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||||||||
| 174 | 09 29 00 | Sheathing, 2.1.3, 2.1.4 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 175 | 09 29 00 | Accessories, 2.1.8 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 176 | 09 30 00 | Tile, 2.1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | |||||||||
| 177 | 09 30 00 | Mortar, Grout, and Adhesives, 2.4 | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||||||
| 178 | 09 51 00 | Acoustical Ceiling, 1.2, 2.1, 2.1.1 | 1 | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | |||||||
| 179 | 09 65 00 | Resilient Flooring and accessories | 1 | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | |||||||
| 180 | 09 65 00 | Rubber Tile | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||||||
| 181 | 09 65 00 | Wall Base | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||||||
| 182 | 09 65 36 | Static- Resistive Flooring, 2.2.1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||||
| 183 | 09 65 36 | Adhesives, 2.3 | 1 | 1 | 14 Days Prior to Start Date | |||||||||||
| 184 | 09 68 00 | Carpet and adhesives,1.3, 2.1, 3.1, 3.4 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||||
| 185 | 09 68 00 | Moisture and Alkalinity tests, 3.2 | 1 | 1 | 14 Days Prior to Start Date | |||||||||||
| 186 | 09 69 13 | Rigid grid Access Flooring, 1.2, 1.2.7, 1.4, | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||
| 187 | 09 90 00 | Painting and accessories, 2.1 | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||||||
| 188 | 10 10 00 | Visual Display Boards | 1 | 1 | 14 Days Prior to Start Date | |||||||||||
| 189 | 10 14 02 | Interior Signage | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | |||||||||
| 190 | 10 21 13 | Toilet Compartments and accessories | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||
| 191 | 10 26 13 | Corner Guards | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||||||
| 192 | 10 28 13 | Toilet Accessories | 1 | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | |||||||
| 193 | 10 44 16 | Fire Extinguishers, cabinets and accessories | 1 | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | |||||||
| 194 | 14 24 00 | Passenger Elevator | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | |||||
| 195 | 21 13 13 | Sprinkler - QFPE, Designer, Installer | 1 | 14 Days Prior to Start Date | ||||||||||||
| 196 | 21 13 13 | System and Accessories | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | ||
| 197 | 22 00 00 | Plumbing Systems | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||||
| 198 | 22 00 00 | Tests, Flushing and Disinfection | 1 | 14 Days Prior to Start Date | ||||||||||||
| 199 | 23 05 15 | Common Piping of HVAC | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||
| 200 | 23 05 15 | Coordination Drawings, 1.2 | 1 | 14 Days Prior to Start Date | ||||||||||||
| 201 | 23 05 48.19 | Bracing for HVAC | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||||||
| 202 | 23 05 93 | TAB for HVAC | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | |||||||||
| 203 | 23 07 00 | HVAC insulation | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | |||||||||
| 204 | 23 08 00.00 20 | Commissioning of HVAC & Plumbing Systems | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | |||||||||
| 205 | 23 09 00 | Instrumentation and control for HVAC | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||||||||
| 206 | 23 09 23 .02 | BACNET DDC | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | |||||||||
| 207 | 23 11 20 | Facility Gas Piping | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||||||
| 208 | 23 21 13.00 20 | LTW Heating System | 1 | 1 | 14 Days Prior to Start Date | |||||||||||
| 209 | 23 30 00 | HVAC Air Distribution | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | ||
| 210 | 23 64 10 | Piping System | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||||
| 211 | 23 64 26 | Chilled, Chilled-Hot, and Condenser Water Piping System | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||
| 212 | 23 73 13.00 40 | Modular Indoor AHU | 1 | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | |||||||
| 213 | 23 80 20 .00 10 | Terminal Heating Units | 1 | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | |||||||
| 214 | 25 05 11 | Cybersecurity | 1 | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | |||||||
| 215 | 26 05 48.00 10 | Lighting Systems | 1 | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | |||||||
| 216 | 26 20 00 | Interior Distribution System | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||||
| 217 | 26 24 13 | Switchboards | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||||||
| 218 | 26 28 01.00 10 | Coordinated Power System Protection | 1 | 1 | 14 Days Prior to Start Date | |||||||||||
| 219 | 26 29 23 | ASD Systems | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | |||||||||
| 220 | 26 32 15.00 | Generator | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | |||||
| 221 | 26 36 23 | ATS and By-Pass/Isolation Switch | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||||||
| 222 | 26 41 00 | Lightning Protection System | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||||||
| 223 | 26 51 00 | Interior Lighting | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | |||||
| 224 | 26 56 00 | Exterior Lighting | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | |||||
| 225 | 27 05 13 .43 | Television Distribution System | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | |||||
| 226 | 27 10 00 | Telecommunications Cabling | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||||
| 227 | 28 31 76 | Fire Alarm & Mass Notification | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | |||
| 228 | 31 00 0 0 | Earthwork | 1 | 1 | 14 Days Prior to Start Date | |||||||||||
| 229 | 32 16 13 | Concrete curbs, gutters and walks | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||||||||
| 230 | 32 17 24.00 10 | Pavement Markings | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||||||||
| 231 | 32 93 23 | Sodding | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | |||||||||
| 232 | 33 11 00 | Water Utility Distribution | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||||
| 233 | 33 71 02 | Underground Electrical | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||||||
| 234 | 33 82 00 | Telecommunications OSP | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 14 Days Prior to Start Date | ||||
| 235 | ||||||||||||||||
| 236 | ||||||||||||||||
| 237 | ||||||||||||||||
| 238 | ||||||||||||||||
| 239 | ||||||||||||||||
| 240 |
&"Verdana,Bold"&12Schedule of Material Submittals &12Print on Legal size paper ( 8 x 14 ).
&P of &N