Attachment 5 Liquidated Damages_FY26_2478_11B 10116 6P_Kitchenette.pdf
PDF 362 KB Posted
- Attached to
- Amendment 3 Install Kitchenette Fort Bliss
- Solicitation number
- W911RX-26-B-A001
About this file
This document is a Determination for Inclusion of Liquidated Damages for a roof repair contract at Fort Bliss, Texas. The Directorate of Public Works established liquidated damages at $1,717.24 per calendar day of delay in contract completion. The Directorate of Contracting evaluated this amount and determined it to be justifiable and not constituting a penalty to the contractor.
The liquidated damages calculation encompasses costs from three organizational branches. The Design Branch includes five positions (Civil Engineer, Mechanical Engineer, Electrical Engineer, Architect, and Supervisor) at 2.00 man hours each with varying hourly rates, totaling $515.38 per day. The Construction Branch includes a Project Engineer (8.00 man hours at $50.00/hour), Inspector (8.00 man hours at $33.24/hour), and Supervisor (4.00 man hours at $57.69/hour), totaling $896.68 per day. The Contracting Office includes three positions (Contracting Officer, Contract Specialist, and Staff Judge Advocate) at 2.00 man hours each, contributing $305.18 per day. These three categories combine to establish the total daily liquidated damages rate of $1,717.24 per calendar day of delay.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .