Attachment 5. Drawings GAOA Sky Ranch Road.pdf

PDF 4 MB Posted

Attached to
127EAW23R0011 - GAOA Sierra Vista Scenic Byway, Sky Ranch Road
Solicitation number
127EAW23R0011
Issued by

About this file

This document package includes drawings and specifications for a road repair project on Sky Ranch Road in the Sierra National Forest in California. The project involves brushing, double chip sealing, fog sealing, asphalt reconstruction, and bridge repairs along 5.69 miles of the road. Work includes grinding up to 6 inches of existing material, installing geotextile, placing and compacting hot mix asphalt and base rock. The related federal contract opportunity is solicitation number 127EAW23R0011 for repair of the GAOA Sierra Vista Scenic Byway on Sky Ranch Road with an estimated value between $1 million and $5 million, set aside for total small business. The solicitation requires any requests for information to be submitted by April 14, 2023. A pre-proposal conference will also be held. The Forest Service is the contracting agency.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT LOCATION

VICINITY MAP

TRAVEL DIRECTIONS:

SHEET OF001

INDEX OF SHEETS

SHEET SHEET TITLE DATE

1 COVER SHEET 1/5/2023

2 MAP 1/5/2023

3 CLEARING NOTES 1/5/2023

4 TYPICAL CROSS SECTIONS 1/5/2023

5 GENERAL DETAILS 1/5/2023

From Oakhurst, CA head Northeast on Highway 41, travel approximately 4.0 miles and turn right on Road 632, continue for 1.4 miles until reach the beginning of the NFSR 6S10 (Sky Ranch Road).

RECOMMENDED BY:

APPROVED:

FOREST ENGINEER

DISTRICT RANGER DATE

DATE

DIRECTOR OF ENGINEERING

DATE

FOREST SUPERVISOR DATE

United States Department of Agriculture

Forest Service

GAOA - SCENIC BYWAY

SKY RANCH ROAD REPAIRS

CALIFORNIA

MADERA COUNTY

SIERRA NATIONAL FOREST

(R05) PACIFC SOUTHWEST REGION

Map provided on separate document.

DRAWING TITLE

DRAWN

DESIGNER

CHECKED

PROJECT NO.

OFSHEET

PROJECT NAME

DATE

ARCHIVE NO.

DWG SHEET NO.

(R05)

PACIFIC SOUTHWEST REGION

GAOA - SCENIC BYWAY

SKY RANCH ROAD

REPAIRS

SIERRA NATIONAL

FOREST

BASS LAKE RANGER

DISTRICT

MAP

01/05/2023

PABLO GONZALEZ

ANTONIO CABRERA

G-02

Vicinity Map

Grinding 4" and 2" layer of base rock w/oil

MP 7.46 - 9.98 (2.52 miles)

Brushing, double chipseal

MP 0.0 - 5.69

(5.69 miles)

FogSeal

MP 5.69 - 6.72

(1.03 Miles)

Asphalt Reconstruction

MP 6.72 - 7.46

(0.74 Miles)

Soquel Ditch Bridge

DRAWING TITLE

DRAWN

DESIGNER

CHECKED

PROJECT NO.

OFSHEET

PROJECT NAME

DATE

ARCHIVE NO.

DWG SHEET NO.

(R05)

PACIFIC SOUTHWEST REGION

GAOA - SCENIC BYWAY

SKY RANCH ROAD

REPAIRS

SIERRA NATIONAL

FOREST

BASS LAKE

RANGER DISTRICT

CLEARING DETALS

01/05/2023

PABLO GONZALEZ

ANTONIO CABRERA

G-03

CLEARING DETAILS (BRUSHING)

1.5 : 1 Backslope

2 : 1 Ditch

TYPICAL GRADING DETAIL - OUTSLOPE

Existing Ground

TYPICAL GRADING DETAIL - CROWNED

TYPICAL GRADING DETAIL - INSLOPE

NOT TO SCALE

NOT TO SCALE

NOT TO SCALE

Exist ing Ground

Varies 14' to 24'

2%

2:1Fill SlopeExisting Ground

Exist ing Ground

Varies 14' to 24'

2%

2:1Fill Slope

DEPTH AS STATED

IN WORK LIST

2%

Existing Ground

Exist ing Ground

2:1Fill Slope

DEPTH AS STATED

IN WORK LIST

1.5 : 1 Backslope

2 : 1 Ditch

2%

TYPICAL GRADING DETAIL - INSLOPE W/DITCH

NOT TO SCALE

Exist ing Ground

2:1Fill Slope

1.5 : 1 Backslope

2 : 1 Ditch

Existing Ground

Varies 14' to 24'

2%Varies 14' to 24'

NOTE: Shoulder and travel way width varies.

Note: Road width varies and for calculations purposes consider a continuous road width of 19 feet.

PROFILE VIEW

CROSS SECTION

Undisturbed native material

Grind and compact a 4" layer.

Place 4" layer of Hot Mix Asphalt

PG 64-16.

Match existing slope

Match existing slope

Pavement Geotextile

(Tenscate Mirafi MPG 100 or equivalent)

**This is an optional item.

DRAWING TITLE

DRAWN

DESIGNER

CHECKED

PROJECT NO.

OFSHEET

PROJECT NAME

DATE

ARCHIVE NO.

DWG SHEET NO.

(R05)

PACIFIC SOUTHWEST REGION

GAOA - SCENIC BYWAY

SKY RANCH ROAD

REPAIRS

SIERRA NATIONAL

FOREST

BASS LAKE

RANGER DISTRICT

TYPICAL CROSS

SECTIONS

01/05/2023

PABLO GONZALEZ

ANTONIO CABRERA

G-04

TYPICAL CROSS SECTIONS

ASPHALT RECONSTRUCTION

PROFILE VIEW

CROSS SECTION

Undisturbed native material

Grind 2" of existing asphalt

Install Tencate MPG 100 or equivalent.

Grind a 4" layer.

Install Tencate Mirafi RS580i or equivalent.(Optional item)

Mix, place and compact the grindings including a 2" layer of base rock for a total of 6". Then apply bituminous material per the specifications.

Place 4" layer HMA (See schedule of items for details)

Black

Yellow

DRAWING TITLE

DRAWN

DESIGNER

CHECKED

PROJECT NO.

OFSHEET

PROJECT NAME

DATE

ARCHIVE NO.

DWG SHEET NO.

(R05)

PACIFIC SOUTHWEST REGION

SCENIC BYWAY

CREEK FIRE ROAD

REPAIRS

SIERRA NATIONAL

FOREST

BASS LAKE RANGER

DISTRICT

GENERAL DETAILS

01/05/2023

PABLO GONZALEZ

ANTONIO CABRERA

G-05

ASPHALT GRINDING

TYPICAL CENTERLINE02

THIS SECTION INTENTIONALLY

LEFT BLANK