Attachment 2. Schedule.docx
DOCX document 20 KB Posted
- Solicitation number
- 127EAW23R0011
- Issued by
-
Department of Agriculture Forest Service
About this file
This document contains an attachment schedule for a construction contract solicitation. The solicitation is for the GAOA Sierra Vista Scenic Byway, Sky Ranch Road 2 project located on the Sierra National Forest. The schedule lists estimated quantities and unit prices for various construction items including mobilization, testing, base rock placement and compaction, asphalt paving, chip sealing, crack sealing, pavement markings, traffic control, and drainage work totaling between $1,000,000 and $5,000,000. The opportunity is a total small business set aside issued by the Forest Service. Offerors must submit all proposals and any requests for information by April 14, 2023. A pre-proposal conference will also be held.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PART I—THE SCHEDULE
SECTION B-- SCHEDULE OF ITEMS
B.1 SCHEDULE OF ITEMS
| Item |
| Construction Items |
| Qty |
| UOI |
| Unit Price |
| Total Price |
| 151 |
| Mobilization |
| 1 |
| LS |
| 154 |
| Contractor Testing |
| 1 |
| LS |
| 301 |
| Import and place Caltrans 3/4" class 2 base rock, compaction method D. |
(2" layer MP 6.72 - 7.46)
| 1455 |
| Cubic |
Yard
| 403 |
| 3/4" Hot Mix Asphalt. Caltrants Type A, |
Grading: PG 64-16. (MP 6.72-7.46)
| 1795 |
| Ton |
| 406 |
| Fog Seal (MP 5.69 - 6.72) |
| 1.03 |
| Mile |
| 407 |
| Double course chip seal, type 2C |
(MP 0-5.69)
| 5.69 |
| Mile |
| 414 |
| Asphalt pavement crack sealing and filling |
(MP 0-5.69)
| 5.69 |
| Mile |
| 416(b) |
| Road Mix Surfacing Laid, type SC-250 |
Road Oil (MP 7.46 -9.98)
| 2.52 |
| Mile |
| 634 |
| Permanent Pavement Markings, double |
yellow centerline type B. (Mile post 0- 7.46)
| 7.46 |
| Mile |
| 635 |
| Temporary traffic control |
| 1 |
| LS |
| 814 |
| Pothole repairs |
| 230 |
| Ton |
| 834 |
| Drainage structures maintenance |
| 9.98 |
| Mile |
| 842 |
| Cutting roadway vegetation (0-5.69) |
| 5.69 |
| Mile |
| TOTAL: |
| ___________ |
B.2 SCHEDULE NOTES
* QUANITIES ARE ESTIMATED, CONTRACTOR SHALL FIELD VERIFY TO SATISFY ALL REQUIREMENTS OF THE DRAWINGS, STATEMENT OF WORK, AND SPECIFICATIONS.
NOTE: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price.
| Company Name: |
| POC & Title: |
| Email: |
| Phone Number: |
| Unique Entity Identifier (UEI) Number: |
| Tax ID: |
Solicitation No: 127EAW23R0011 Project Name: GAOA Sierra Vista Scenic Byway, Sky Ranch Road