Attachment 5-BID FORMS for CSC-19731.xlsx

XLSX spreadsheet 17 KB Posted

Attached to
Project: CSC-19731 M&R Sanitary Lines SIte Wide
Solicitation number
SP4702-20-R-0026
Issued by

About this file

This document contains bid forms and specifications for a federal contract opportunity to provide maintenance and repair services for sanitary sewer lines at the Defense Supply Center Columbus site in Ohio. The work includes cleaning and television inspection of the sanitary sewer system, as well as rehabilitating sewer pipelines through cured-in-place pipe lining. Bids are due on August 10, 2020 at 1:00pm EST. The solicitation was issued by the Defense Logistics Agency for Project CSC-19731 and includes requirements for furnishing all labor, equipment, materials, testing and supervision to perform cleaning and inspection of the sanitary sewer system, as well as pipeline rehabilitation using cured-in-place pipe lining methods.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

BID FORM (FOUO)
PROJECTCSC-19731SHEET1OF3
Project Title: M & R to Sanitary Lines Site WideDATE PREPARED
LOCATIONCLIN-0001ESTIMATOR
Building and/or Description: Cleaning & TV InspectionsCHECKED BY
NARRATIVE / DATA SOURCE[EDIT AS NEEDED] Estimate was developed using RSMeans Online. Detailed cost breakdowns for labor, material, and equipment are available upon request.
BID ITEMSUB CONTRACT COSTPRIME CONTRACT COSTTOTAL DIRECT COST
No. / Div.DescriptionQTY.Unit
1General Requirements1LS
2Existing Conditions1LS
3Concrete1LS
4Masonry1LS
5Metals1LS
6Wood, Plastics, and Composites1LS
7Thermal and Moisture Protection1LS
8Openings1LS
9Finishes1LS
10Specialties1LS
11Equipment1LS
12Furnishings1LS
13Special Construction1LS
14Conveying Equipment1LS
21Fire Suppression1LS
22Plumbing1LS
23Heating, Ventilating, and Air Conditioning1LS
26Electrical1LS
27Communications1LS
28Electronic Safety and Security1LS
31Earthwork1LS
32Exterior Improvements1LS
33Utilities1LS
34Transportation1LS
SUB-TOTAL DIRECT COST
OVERHEAD
PROFIT
BOND
TOTAL COST FOR CLIN 0001
BID FORM (FOUO)
PROJECTCSC-19731SHEET2OF3
Project Title: M & R to Sanitary Lines Site WideDATE PREPARED
LOCATIONCLIN-0002ESTIMATOR
Building and/or Description: Relining Sewer LinesCHECKED BY
NARRATIVE / DATA SOURCE[EDIT AS NEEDED] Estimate was developed using RSMeans Online. Detailed cost breakdowns for labor, material, and equipment are available upon request.
BID ITEMSUB CONTRACT COSTPRIME CONTRACT COSTTOTAL DIRECT COST
No. / Div.DescriptionQTY.Unit
1General Requirements1LS
2Existing Conditions1LS
3Concrete1LS
4Masonry1LS
5Metals1LS
6Wood, Plastics, and Composites1LS
7Thermal and Moisture Protection1LS
8Openings1LS
9Finishes1LS
10Specialties1LS
11Equipment1LS
12Furnishings1LS
13Special Construction1LS
14Conveying Equipment1LS
21Fire Suppression1LS
22Plumbing1LS
23Heating, Ventilating, and Air Conditioning1LS
26Electrical1LS
27Communications1LS
28Electronic Safety and Security1LS
31Earthwork1LS
32Exterior Improvements1LS
33Utilities1LS
34Transportation1LS
SUB-TOTAL DIRECT COST
OVERHEAD
PROFIT
BOND
TOTAL COST FOR CLIN 0002
BID FORM (FOUO)
PROJECTCSC-19731SHEET3OF3
Project Title: M & R to Sanitary Lines Site WideDATE PREPARED
LOCATIONESTIMATOR
CHECKED BY
COST SUMMARYCHECKED BY
NARRATIVE / DATA SOURCE[EDIT AS NEEDED] Estimate was developed using RSMeans Online. Detailed cost breakdowns for labor, material, and equipment are available upon request.
BID ITEMSUB CONTRACT COSTPRIME CONTRACT COSTTOTAL COST
CLIN NODescriptionQTY.Unit
1Cleaning & TV Inspections1LS
2Relining Sewer Lines1LS

TOTAL COST FOR THIS PROJECT

File details come from the government source that posted it. Updated .