ATTACHMENT 4 - VA Lake Baldwin EHRM - Addendum 01 - 8-27-24.pdf

PDF 166 KB Posted

Attached to
Y1DA--675-22-701 EHRM Infrastructure Upgrades Construction Lake Baldwin (Orlando)
Solicitation number
36C77624B0028
Issued by

About this file

This document is an Addendum to the specifications for the VA Lake Baldwin EHRM Infrastructure Upgrades Construction project, Solicitation Number 36C77624B0028. The addendum updates several sections of the general requirements, including the contract working hours, submittal review timelines, and removal of the requirement for 24-hour guards. It also removes specification editor notes from various technical sections. The key updates are:

  • Normal working hours are 7:00 AM to 4:30 PM Monday through Friday, with any work outside those hours requiring approval.
  • Submittal review timelines have been extended from 15 to 21 calendar days, and RFI responses from 10 to 14 calendar days.
  • The requirement for 24-hour guards has been removed.
  • Various technical specification sections have been updated to remove internal specification editor notes.

View the file

Other files

File Type Posted
36C77624B0028 0006.pdf PDF
Building 502 - Plumbing Documentation.zip ZIP file
Technical Questions Speadsheet - Lake Baldwin - Part 2.docx DOCX document
36C77624B0028 0005.pdf PDF
36C77624B0028 0004.pdf PDF
36C77624B0028 0003.pdf PDF
Technical Questions Spreadsheet - Lake Baldwin.docx DOCX document
36C77624B0028 0002.pdf PDF
Site Visit Sign-in Sheet - Lake Baldwin.pdf PDF
36C77624B0028 0001.pdf PDF
ATTACHMENT 5 - Asbestos Report - Part 4.zip ZIP file
ATTACHMENT 2 - Drawings - 1 of 2.pdf PDF
ATTACHMENT 4 - Addendum 01 - 262416.pdf PDF
ATTACHMENT 4 - Addendum 01 - 260923.pdf PDF
36C77624B0028_1.docx DOCX document
ATTACHMENT 4 - Addendum 01 - 312000.pdf PDF
ATTACHMENT 4 - Addendum 01 - 312011.pdf PDF
ATTACHMENT 5 - Asbestos Report - Part 2.zip ZIP file
ATTACHMENT 4 - Addendum 01 - 260573.pdf PDF
ATTACHMENT 4 - Addendum 01 _ 01 91 00.pdf PDF
ATTACHMENT 1 - Specifications.pdf PDF
ATTACHMENT 7 - Pre-Construction Risk Assessment.pdf PDF
ATTACHMENT 4 - Addendum 01 - 265100.pdf PDF
ATTACHMENT 10 - Site Visit Instructions.pdf PDF
ATTACHMENT 8 - Limitations on Subcontracting - Construction.docx DOCX document
ATTACHMENT 4 - Addendum 01 - 010000.pdf PDF
ATTACHMENT 5 - Asbestos Report - Part 3.zip ZIP file
ATTACHMENT 5 - Asbestos Report - Part 6.zip ZIP file
ATTACHMENT 5 - Asbestos Report - Part 1.zip ZIP file
ATTACHMENT 4 - Addendum 01 - 262921.pdf PDF
ATTACHMENT 3 - Drawings - 2 of 2.pdf PDF
ATTACHMENT 6 - Brand Name Justification - Lake Baldwin Redacted.pdf PDF
ATTACHMENT 9 - Construction Wage Rates - Orange - 7-12-24.pdf PDF
ATTACHMENT 5 - Asbestos Report - Part 5.zip ZIP file
ATTACHMENT 4 - Addendum 01 - 013323.pdf PDF
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

This document is for PCAC Internal Use Only.

VA Lake Baldwin - Specification Addendum 01 June 21, 2024:

• Spec Section 01 00 00 General Requirements, updated to reflect the following items:

o TOC updated to remove the referenced missing sections.

o 1.2 General Intention (B): Updated to read “Visits to the site by Bidders may be made in accordance with what is listed in the solicitation and at the discretion of the Contracting Officer.”

o 1.2 General Intention (D): Updated, the spec section 01 45 29 / laboratory services were not provided and will not be required.

o 1.2 Contract Working Hours (F): Updated to reflect working hours:

a. Normal working hours for this contract will be from 7:00AM to 4:30PM (local time) Monday through Friday except for weekends and established Federal Holidays.

b. Performing on-site work outside normal working hours will require approval from the Contracting Officer and the COR. Requests shall be submitted via email at least 72 hours prior to the requested date and at no additional cost to the Government. Approvals are subject to the availability of on-site staff.

o 1.5 Construction Security Requirements, Part C. Guards: There should not be a requirement for 24-hour guards. This section was removed.

• Spec Section 01 33 23 Shop Drawings, Product Data and Samples, updated to reflect the following items:

o 1.6 Submittal Format and transmission (D) & (E): Deleted E and F and replace with the following:

“All documents (submittals) should be sent through FTP File Sharing system. Confirm that the electronic FTP file sharing system can be accessed from the VA computer network. The Contractor is responsible for setting up, providing, and maintaining the electronic FTP file sharing system for the construction contract period of performance.”

o 1.10 VA review and submittals and RFIs: The submittal and RFI response times changed the following: 15 working days for submittals to 21 calendar days and 10 working days for RFIs to 14 calendar days.

This document is for PCAC Internal Use Only.

• Specs updated to remove spec writer Notices:

• 26 05 73 – Updated spec to remove spec editor notes.

• 26 09 23 – Updated spec to remove spec editor notes.

• 26 24 16 – Updated spec to remove spec editor notes.

• 26 29 21 – Updated spec to remove spec editor notes.

• 26 51 00 – Updated spec to remove spec editor notes.

• 31 20 00 – Updated spec to remove spec editor notes.

• 31 20 11 – Updated spec to remove spec editor notes.

• Spec Section 01 91 00 General Requirements, updated to reflect the following items:

o 1.8.C.1 updated language to reflect the following

▪ C. Members Appointed by GC:

1. Commissioning Agent: The designated person, company, or entity that plans, schedules, and coordinates the commissioning team to implement the commissioning process. The GC will engage the CxA under a separate contract.

File details come from the government source that posted it. Updated .