Technical Questions Spreadsheet - Lake Baldwin.docx
DOCX document 3 MB Posted
- Solicitation number
- 36C77624B0028
About this file
This document is a Technical Questions Spreadsheet related to a federal contract opportunity for EHRM Infrastructure Upgrades Construction at the Lake Baldwin VA Medical Center. The solicitation number is 36C77624B0028 and the contract value is estimated to be $10,000,000 to $20,000,000. Key details include:
- The project is not sales tax exempt, and contractors must include all applicable taxes in their bids.
- Award is expected 30-45 days after contract execution. Payment for stored materials is at the Contracting Officer's discretion.
- Requests for an Economic Price Adjustment clause and additional ductbank costs were denied.
- The contractor is responsible for coordinating with the VA on asbestos remediation, testing requirements, and differing site conditions.
- The VA provided site surveys, drawings, and specifications, but additional details on utilities, phasing, and security requirements were requested.
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C77624B0028 EHRM Infrastructure Upgrades Construction – Lake Baldwin VAMC Technical Questions and VA Response Tracking Sheet
ITEM
NO.
| DATE QUESTION RECEIVED |
| DATE QUESTION ANSWERED |
| QUESTION |
| GOVERNMENT RESPONSE |
| 1. |
| 9-5-24 |
| 10-9-24 |
| Is this project sales tax exempt? If the project is sales tax exempt can the government provide a sales tax exemption certificate? |
| Reference Special Notes Regarding FAR 52.229-3, Offerors are hereby notified that all state and local sales or use taxes for construction materials must be included in their bid or proposal price. It is solely the responsibility of the offeror to include all other applicable taxes in their bid or proposal price as well. |
| 1. |
| 9-9-24 |
| 10-9-24 |
| What is the magnitude of this project? |
| The Magnitude of Construction for the project is $10,000,000 to $20,000,000. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| How soon after award is NTP expected to be issued? |
| Approximately 30 to 45 calendar days after Awardee receives the executed contract. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Will pay applications for materials secured on site or in a bonded warehouse be approved for payment? |
| In accordance with contract terms and conditions, Contractors should not bid assuming the Government will approve payment for material and/or equipment procured by the Contractor and stored on the construction site, as space is available, or at a local approved location off the site. Payment of stored materials and/or equipment is at the Contracting Officer’s discretion and will be handled on a case-by-case basis during the contract and under such terms and conditions as the Contracting Officer approves. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Due to the current economic inflation, Will the government reduce the amount of time that contractors must hold their numbers to 60 days? By reducing the inflation risk, the government will avoid escalations costs that general contractors and subcontractors must account for. |
| The Government standard concerning price-hold period is 90 calendar days and will not be altered. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Will the government consider the inclusion of an Economic Price Adjustment Clause in accordance with Federal Acquisition Regulations (FAR), Subpart 16.203 "Fixed-price contracts with economic price adjustment" and the related contract clause language in FAR 52.216-2, 3, 4? We believe such a clause is appropriate for the following reasons: |
· The contract involves an extended period of performance with significant costs to be incurred beyond 1 year after performance begins;
· The contract amount subject to significant fluctuations in price is substantial [may want to list specific examples of highly unstable pricing items within the scope]; and The economic variables for labor and materials are too unstable to permit a reasonable division of risk between the Government and the contractor, without this type of clause."
This procurement will remain as a firm fixed priced award. The government will not consider this request.
| 1. |
| 9-23-24 |
| 10-9-24 |
| If the Contractor is responsible for the additional costs for re-routing the ductbank, how much additional ductbank cost should they carry in their bid (i.e., 10% more, 20% more, etc.)? |
| It is the responsibility of the bidder to determine what percentage to add into their costs. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference SECTION 01 00 00 GENERAL REQUIREMENTS - TABLE OF CONTENTS |
Several para’s have “Error! Bookmark not defined” Are we to assume they deleted and do not form a part of the project specs?
Per ATTACHMENT 4 - VA Lake Baldwin EHRM - Addendum 01 - 8-27-24 and ATTACHMENT 4 - Addendum 01 – 010000, the table of contents has been updated.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference 01 91 00 General Commissioning Requirements, 1.8 |
It states that the Commissioning Agent will be appointed by the VA. Attachment 4 has the GC responsible for the CxA.
Just to clarify the GC is to provide the CxA correct?
Per ATTACHMENT 4 - VA Lake Baldwin EHRM - Addendum 01 - 8-27-24 and ATTACHMENT 4 - Addendum 01 – 01 91 00 the GC will engage the CxA under a separate contract.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Is there any second site visit planned for each specialty? |
| A second site visit will not be facilitated. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Please confirm the order of precedence for the contract documents. Does SOW prevail over the specifications and construction drawings? |
| There is no statement of work attached to this requirement. The specifications are the statement of work. |
| 1. |
| 9-12-23 |
| 10-9-24 |
| Is the VA willing to pay for materials stored on and/or offsite such that it meets requisite FAR and VAR clauses for stored materials. There are materials which have a 12+ week lead time which SDVOSB firms cannot procure up front without taking on the financial risk, any schedule impacts could cause irreparable harm financially. Proof of materials possession would include vendor invoices, materials under security systems, insured and bonded, photos of materials, and inspection upon request. |
| In accordance with contract terms and conditions, Contractors should not bid assuming the Government will approve payment for material and/or equipment procured by the Contractor and stored on the construction site, as space is available, or at a local approved location off the site. Payment of stored materials and/or equipment is at the Contracting Officer’s discretion and will be handled on a case-by-case basis during the contract and under such terms and conditions as the Contracting Officer approves. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Will the VA allow deviations to Buy American Act if the noted products are not available? |
| The process of requesting exceptions to the Buy American Act is detailed in the provision at FAR 52.225-12, Notice of Buy American Requirement—Construction Materials Under Trade Agreements, and the clause at FAR 52.225-11 Buy American—Construction Materials under Trade Agreements, in the solicitation. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Due to current potentially significant tariffs being placed on the importation of building materials such as wood or steel by the current Presidential Executive Branch, if a tariff is placed after bid time and before award will the government consider a price escalation on a contract value for products such as steel or wood should the executive branch levee tariffs effecting such materials? Most of these materials would still have been Buy American compliant as the tariffs would increase pricing on all steel or wood materials, regardless of origin. |
| This will be awarded as a Firm Fixed Price (FFP) contract and all escalation should be factored in your FFP. Additionally, FAR 52.216-4 “Economic Price Adjustment – Labor and Material” is not included in the solicitation and will not be added. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Will the VA accept contract modification if the as-built drawings demonstrate conditions that exclude design considerations or impart differing site conditions? |
| All design considerations must be submitted on a RFI and approved both by the AE of record and the COR which will may constitute a modification resulting in an increase of price to the total contract value. Per FAR 52.236-2, allows for differing site conditions that arise during construction, which may come at a cost to the VA. Changes to the contract will follow FAR 52.243-1/4 |
| 1. |
| 9-23-24 |
| 10-9-24 |
| If asbestos and/or mold is found that is not listed in the plans, will this be considered an unforeseen situation? And how would the VA like to handle it. |
| Asbestos/or mold NOT INCLUDED ON THE SURVEY AT ATTACHMENT OF THE SOLICITATION, will be considered an unforeseen CONDITION and constitute a modification, which may come at a cost to the VA |
| 1. |
| 9-23-24 |
| 10-9-24 |
| To promote fairness in bids received, please specify what quantity of hazardous materials we should plan to abate in each TR room. |
| The A/E should have performed a survey and that survey should have been part of the solicitation, so my response would be to direct them to the asbestos survey in the solicitation. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Will the Owner or GC be responsible for purchasing testing and lab services? |
| GC will be responsible for testing |
| 1. |
| 9-23-24 |
| 10-9-24 |
| As a result of the effect of COVID-19 throughout the U.S., and the resulting Federal, State and local governments’ responses / requirements are there any new work requirements or mandates that will be required by VA on this project. |
| No new mandates currently |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Does this project comply with the NEW Biden Administration Executive Order 14005 concerning the Buy American Act? This executive order limits the purchase of materials from previously approved countries to include Canada and Mexico. Can you please confirm whether materials or equipment manufactured in these previously approved Buy American Act countries outside the United States can or cannot be used on this project? |
| See answer to question 13 |
| 1. |
| 9-24-24 |
| 10-9-24 |
| Reference Section 01 00 00, para 1.3 STATEMENT OF BID ITEM(S) |
There are 3 bid items listed in this paragraph. Can the VA clarify these bid items?
The GC shall provide a bid based on the drawings and specs.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Has the VA validated the equipment schedules for MEP can comply with Buy American Act? |
| Contractor is responsible to meet Buy America Act, any deviations will have to be approved by CO |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Please clarify if WHEN hours are required for all work. |
| When hours are required for all work, any day work can be approved if necessary |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Can this work be performed during not regular hours (afterhours, nighttime, or weekends) to expedite the remediation process, and minimize the impact to patient and staff care. |
| WHEN hours required |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Is there any ICRA requirement for this project? If yes, could you please confirm what are the areas that require them? |
| All buildings will require ICRA |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Is there any Project Phasing and the estimated duration of each phase? |
| Schedule and phasing need to be submitted by contractor |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Is the VA’s (PSRDM) Physical Security and Resiliency Design Manual Revised January 1, 2024, applicable to this project? |
| The most current version of the PSRDM and associated appendices is always applicable. The most current revision is dated 05-01-2024. In addition, please see the OVAHCS Physical Security Systems Technical Specifications document. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS, para 1.7 SYSTEMS TO BE COMMISSIONED |
Can the VA confirm that the list of systems provided is all that is required for 01 91 00?
Contractor responsible to confirm they meet all requirements.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Section 01 91 00, para 1.7 SYSTEMS TO BE COMMISSIONED |
The drawings do not appear to have anything related to a new boiler fuel system or generator fuel system as noted in the list. Can the VA confirm that a boiler fuel system or generator fuel system is not within the scope of this project?
Per the drawings, a boiler fuel system or generator fuel system is not within the scope.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Section 01 91 00, para 1.7 SYSTEMS TO BE COMMISSIONED |
The list of systems to be commissioned seems to be missing many of the systems included under the drawing packages HVAC IT, & fire protection. Are we to include commissioning of these systems or just what is on the list?
Contractor responsible to confirm they meet all requirements.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Can the required SSHO positions be fulfilled by the qualified superintendent? |
| Determined by contractor |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Will the Government provide comprehensive written badging requirements for the project if badging is required? |
| Will be provided by Post Award Team. Background forms will be sent Post award to contractor. Anyone working at VA will be required to be badged. We will provide badges to competent personnel in the project (ie Superintendent, and team leads). |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Where will the designated parking area be for workers accessing the construction site? |
| Laydown area and worker parking to be designated |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Will the Owner accept the use of the industry leading Procore Project Management software as the primary submittal and data tracking tool for this project? |
| Acceptable |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Does the Government have a fire alarm servicer that they currently work with? What is the name and contact information of the person or persons that will need to be coordinated with for security and fire alarm and suppression systems work and/or disruptions? |
| Yes. Innovative Life Safety Solutions / Dynafire |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Is AISC (American Iron and Steel Certification) required for the structural steel fabrication and/or erection for this project? |
| Yes, it is required per the VA specs. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Electrical Panel Schedules |
Can the VA confirm that circuits not identified as “SPACE” on any given schedule vs. having “SPARE”, that “SPARE” means new breakers are required to be installed in all panels that are existing?
No new spare breakers in existing panel are expected to be provided
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference EXISTING PANEL: PL-1 (BLDG 3133), ckt#16 |
Can the VA provide the amperage & pole for the circuit?
For every Telecommunication Enclosure ( TE ) in the project, it needs (2) two 30 amps 1 pole and (1) one 20 amps 1 pole breakers.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference EXISTING PANEL: PL-1 (BLDG 3133), ckt#14 |
Can the VA provide the amperage & pole for the circuit?
See above
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference EXISTING PANEL: PL-1 (BLDG 3133), ckt#7 |
Can the VA verify the amperage of 30A for the circuit?
See above
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference EXISTING PANEL: MAIN |
The panel schedule does not indicate which bldg the panel is in, however bottom of sheet E808 it appears to be bldg 3128. Can the VA confirm this panel is located in BUILDING 3128 Located in Building 3128
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet E607, PRELIMINARY GROUNDING RISER DIAGRAM |
The diagram provided is not readable. Can the VA provide this sheet that can be read?
See source document
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet E705, Pictures |
The pictures provided are not readable. Can the VA provide this sheet so that the pictures can be read?
See source imagery
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet E606, LIGHTING SCHEDULE NOTES: #2 |
Can the VA clarify the intent of the following note: “OTHER FIXTURES MAY BE SUBMITTED FOR APPROVAL UP TO 10 WORKING DAYS PRIOR TO BID DATE, TO ALLOW FOR PROPER EVALUATION. SUBMISSIONS WITHIN 10 WORKING DAYS PRIOR TO BID DATE WILL NOT BE EVALUATED. EQUIPMENT IS APPROVED THROUGH ADDENDUM ONLY.”
It is intended for lighting vendor coordination
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet E603 |
Can the VA provide this sheet that can be read?
Unclear on question. Text is found legible in full size printed drawings. Refer to Infrastructure Standard for Telecommunications Spaces Version 3.1, OIT Design Guide Template for details.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference EXISTING PANEL: A bldg 508, CKT#12 |
Can the VA clarify the missing “Pole” for this CKT?
It is a 3-pole breaker, as noted on sheet ET500
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference EXISTING PANEL: PL-1 (BLDG 3133), CKT’s#14 & 16 |
Can the VA clarify the missing breaker information for these CKT’s?
See above
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference EXISTING PANEL: C2P2 (BUILDING 500 2ND LEVEL) |
Can the VA clarify if CKT’s #23 & 27 that new breakers are not required however require new conduit/cabling?
Existing breaker and wiring to remain
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference EXISTING PANEL: C4P1 (BUILDING 500 4TH LEVEL) |
Can the VA clarify if CKT #30 require new conduit/cabling?
Existing breaker and wiring to remain
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference EXISTING PANEL: N1P16 (BUILDING 500 1ST LEVEL) |
Can the VA clarify what “OFF” for CKT’S #22 & 41 stands for?
In Off position
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference EXISTING PANEL: EXISTING PANEL: MDP |
Can the VA confirm that this panel does not require a new GROUND BUS & NEUTRAL BUS and TYPE WRITTEN DIRECTORY?
Provide as noted on drawings
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference ALL NEW PANELS Drawing Sheet E805 |
Can the VA confirm that these panels do not require a new GROUND BUS & NEUTRAL BUS and TYPE WRITTEN DIRECTORY, if so can the VA please specify?
Provide as noted on drawings
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference ALL EXISTING PANELS Drawing Sheet E803 |
Can the VA confirm that these panels do not require a new GROUND BUS & NEUTRAL BUS and TYPE WRITTEN DIRECTORY, if so can the VA please specify?
Provide as noted on drawings
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference NEW XFMR-PANEL COMB-Z1 |
Panel note states “FOR SPACE 2,4 - PROVIDE 30A-2P BREAKER FOR NEW AH.”
Whereas the schedule reflects NEW CU-500-1713D. Can the VA clarify which is correct?
Breaker is still intended for HVAC. Refer to mechanical drawings for additional details.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference MINI SPLIT SCHEDULE |
The HVAC schedule reflects all units as 1P/60amp, the EC panel schedule appears to reflect something different. Can the VA clarify which is correct, the HVAC schedule or the electrical panel schedules for each of these units?
The MINI SPLIT SCHEDULE indicates that the equipment is single phase 60 Hz. The amps are listed in the MCA column.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet E604, Section Details 5 & 6 |
Both of these sections appear to be the same “3 BY 6 TYPE C DUCTBANK”
Can the VA clarify if the intent is for these to be the same?
No. The center conduits show detail 6 with more utilized conduits.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet E604, CONDUIT FILL DETAIL 7 |
Going by this detail for the SPARE INTERDUCT, are we to provide 2 each CORRUGATED HPDE INTERDUCT within the 4" SCHEDULE 40 PVC CONDUIT for all “Spares” shown for the various Duct Bank Section configurations on this sheet or just provide the 4" SCHEDULE 40 PVC CONDUIT only?
Spare Innerducts are needed to be provided.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet E604, Section Details 1 thru 6 |
Can the VA clarify if the intent is all “A” side and “B” side conduits are to be vertically separated by 12” earth fill material?
Yes
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet E604, Section Detail 8 |
Can the VA clarify if the intent is that all “A” side and “B” side, and spare conduits are to enter the exterior wall- with as many as 18 conduits, using a single line box? If so is the line box to mirror the duct bank conduit configurations, IE 6 conduits wide x 3 deep as worst case?
Each side shall be maintained separately entering the building, so one building transition for each side.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet E601, Keynote #6 |
The note states: “EXISTING ELEVATIONS SHOWN FOR REFERENCE ONLY. THE GENERAL CONTRACTOR SHALL REVIEW THE EXISTING RACK CONDITIONS, EVALUATE AND INCLUDE ANY ADJUSTMENT NEEDED BEFORE PROJECT BID ISSUANCE.” Can the VA confirm that the site visit will include the bidders getting into each of the spaces existing racks are located in order to review per this note?
The site visit happened and the contractors were permitted to look, measure, and take pictures.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet E601, Keynote #6 |
The note states: “WORK IN THIS ROOM SHALL BE PERFROMED WHILE ESCORTED BY VA PERSONNEL. CONTRACT SHALL INCLUDE IN BID ANY ADDITIONAL COORDINATION NEEDED TO DEVELOP WORK IN COMPLIANCE WITH THIS REQUIREMENT.” Can the VA expand on what the coordination would look like; IE one VA escort would be available per Bldg, per room etc.?
Contractors will need to submit documents for employee backgrounds to receive badges. Only a select few of competent personnel will need to go through additional background to be able to become escorts for IT closets.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet E600, GROUNDING AND BONDING RISER |
Can the VA confirm this project uses NON-FUSED DISCONNECTS in lieu of terminating in a hard-wired junction box?
Non fused disconnect shall be provided.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet ET109, ROOM NEXT TO ROOM 1505 |
The drawing has a note that the existing TR room to the left of 1505 is to be transitioned. Drawing sheet AE does not reflect that room as being transitioned. Can the VA confirm if this room is in the scope of work and is to be transitioned?
Space transitioning indicates to remove all OIT equipment (as directed by OIT) and leave all Non OIT equipment fully functioning. No significant architectural scope on the rooms to remain.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet AE113, Enlarged Plan RM 244 TR |
Which Keynote is applicable to the door, #7 or #10 or neither; as there is no demo plan and keynote #4 says “THE ARCHITECTURAL SCOPE IN THIS ROOM IS LIMITED TO PATCHING AND REPAIRING NEW PENETRATIONS”?
Per keynote 7 & 10, the GC shall remove the existing door and frame and install a new door and frame.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet AE103, RM 1451A DEMO PLAN |
Keynote 12 indicates removing flooring, keynote 15 indicates patch & repair floor. Keynote 12 is only shown in room 1451A. Can the VA clarify if room 1451B flooring is to be removed, which has keynote 15?
Keynote #12 applies to room 1451A, see demo and new work plan for extent.
Keynote #15 applies to room 1451B, PATCH AND REPAIR FLOOR FINISH, BASE, AND CEILING AS REQUIRED FOR TR MODIFICATION.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet AE104, RM 1451A TR |
This enlarged plan has a keynote to demo the ceiling. The demo plan does not indicate the limits of which the ceiling is to be removed in rooms 145 and room 1451B since new walls need to be installed to create the new TR. Can the VA provide the limits for the ceiling demo and what is required for patching the ceiling(s) in the adjacent room(s) of this new TR?
The limit of the demo is indicated by the dashed lines. And the ceiling in the adjacent room shall be patched to a finished condition.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet AE105, 1605 & RM 1607A DEMO PLAN |
Room 1605A has keynote #14. Keynote 14 is not used on this sheet. Can the VA clarify what keynote #14 is for room 1605A?
Existing telecommunication equipment to remain functional until the New TR / TE is constructed and operational. See MPE for additional info.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet AE105, General Note #14 (and many other sheets) |
This note states: “CONTRACTOR SHALL EVALUATE INTEGRITY OF ALL PARTITIONS INDICATED BY SYMBOLS ON THE LIFE SAFETY PLAN(S) WITHIN THE PROJECT SCOPE AND UPGRADE AS REQUIRED.” Where are the LS plans? Also, what is the intent of this statement. “ALL partitions” appear to be an open-ended statement. Can the VA please clarify?
The GC shall upgrade the walls associated with the scope of work as identified with wall tags and or keynotes at the TR rooms.
The VA shall provide the latest edition of the joint commission drawings.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet AE113, Keynote #4 |
This note states: “THE ARCHITECTURAL SCOPE IN THIS ROOM IS LIMITED TO PATCHING AND REPAIRING NEW PENETRATIONS.” However, detail for the RM 244 TR has keynotes 7 & 10 at the door. These notes indicate remove & replacing the door. Can the VA confirm which is correct?
244 should include replacing the door and frame due to the current door/frame not allowing us to do electronic access control.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet AE107, BLDG_500_RM 101 DEMO PLAN |
Keynote 12 states: “DEMOLISH EXISTING BASE AND FLOOR FINISH”
Looking at the extents of where this note is located and at the new wall locations for TR room 101A, shouldn’t the removal of the flooring extend into room 102 just beyond grid line “R”?
The extent of keynote #12 is limited by the new TR room. See new room layout for extent.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet AE107, BLDG_500_RM 101 DEMO PLAN |
Keynote 13 states: “DEMOLISH EXISTING CEILING, LIGHTS, DIFFUSERS, LOW VOLTAGE DEVICES AND ASSOCIATED COMPONENTS”
Looking at the extents of where this note is located and at the new wall locations for TR room 101A, shouldn’t the removal of these elements extend into room 102 just beyond grid line “R”?
The extent of keynote #13 is limited by the new TR room. See new room layout for extent.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet AE107, BLDG_500_RM 101 DEMO PLAN |
The keynotes are to remove and reinstall the existing double door 102 in the same location. It appears the door & frame would be 6’4” wide. The wall where this door would be reinstalled would be an inch or so larger than the full frame width. In otherwards not the normal width from frame to wall of 4” each side. Can the VA confirm that the frame may not have a double vertical stud on each side?
Bids should include removing and reinstalling the door and frame. See keynote #9, demolish existing wall and base. The existing frame will be rebuilt per the plans.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet AE108, BLDG_500_RM 101 TR RCP |
The new wall extending from room 101 appears to have a slight jog in that wall line. Is that intentional? If so, that would make the reinstallation of the double door difficult to fit what would be the new opening. Can the VA confirm the wall line will have the jog in it as shown?
No jog required.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet AE201, BLDG_501_RM 102B TE CLOSET |
It appears that where the new door 102A is to be installed there may be an existing roof access ladder on the hinge side that may interfere with the door opening. Can the VA confirm the door 102A location as shown on the drawing is consistent with RCP Keynote 45 on sheet AE202?
The door can be shifted to clear the roof access ladder.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet AE202, BLDG_501_RM 102A IMA OFFICE DEMO RCP |
Can the VA confirm the existing ceiling type of this room as being either drywall or plaster?
There are no existing as-built drawings for building 501. The ceiling is a hard lid ceiling. The GC shall verify the actual material on the site walk.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet AE401, BLDG_ 504_RM 102A TR |
There is no demolition indicated for existing flooring in order to build the new TR. Can the VA confirm no demo of flooring is required?
Demolish existing base and floor finish, typical. Patch and repair substrate. See finish schedule on sheet AE912.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet AE701, BLDG_517 NEW TE ENCLOSURE |
No keynote to demo flooring or ceiling for this room is identified. Can the VA confirm none is to be demolished?
This space is an open warehouse. Nothing is scheduled to be demolished.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet AE701, Keynote #17 |
Keynote states: “EXISTING FURNITURE / DESK TO BE RELOCATED, COORDINATE FINAL LOCATION WITH COR.” Can the VA clarify who will be relocating this furniture?
The GC will relocate per COR direction.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet AE601, BLDG_508_RM 116 TR |
Can the VA clarify this symbol near the door?
The symbol indicates card reader.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet AE601, BLDG_510_RM 110 OFFICE |
No keynote to demo flooring or ceiling for this room is identified. Can the VA confirm none is to be demolished?
Room 110 is an office that will house the TE. No demolition required.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference 2014 Asbestos - Survey LB bldg 3132.pdf |
The results list asbestos in “conference rooms 2, 7 & 8. None of the design drawing floor plans have such room names. Can the VA please specify the rooms on the floor plans that match the rooms list in the asbestos report?
Latest asbestos documents have been provided.
See keynote 42 on sheet AE902.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference 2014 Asbestos - Survey LB bldg 3132.pdf |
Section 7.0 Drawings appear to be missing from the report. Can the VA provide the missing drawings?
The latest Asbestos Documentation was provided in the Solicitation posted to SAM.gov on 9/3/2024.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference 2014 Asbestos - 3133.pdf |
Section 7.0 Drawings appear to be missing from the report. Can the VA provide the missing drawings?
The latest Asbestos Documentation was provided in the Solicitation posted to SAM.gov on 9/3/2024.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference 2014 Asbestos - 3133.pdf |
The results list asbestos in “SUPERVISOR/STORAGE ROOM. None of the design drawing floor plans have such room names. Can the VA please specify the rooms on the floor plans that match the rooms list in the asbestos report?
The latest Asbestos Documentation was provided in the Solicitation posted to SAM.gov on 9/3/2024.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Can the VA provide the floor to deck heights of each building and floor? |
| See EHRM drawings. Contractor responsible to verify all heights. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Can the VA provide the deck type of each building and floor IE; concrete, bar joists? |
| See EHRM drawings. Contractor responsible to verify all heights. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Can the VA the most recent Geotechnical reports for the campus? |
| No reports available. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Are there any open EPA cleanup actions currently on the campus? If so, can the reports be provided prior to bid. |
| No reports available. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Are there any subsurface site conditions that need to be remediated under this project, if so please clarify? |
| See EHRM documents. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Does the VA have an existing Storm Water Pollution Prevention Permit for the entire campus? |
| If available to be provided post award. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Can the VA provide the location for the stabilized construction entrance? |
| This will be provided post award. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet C6.0, DUCTBANK ENTRANCE IDENTIFICATION SIGN DETAIL |
The notes states: “DUCTBANK IDENTIFICATION FROM SCHEDULES ON SHEETS
H-ES7.001 - H-ES7.003.” It does not appear that the referenced sheets were provided. Can the VA provide these missing sheets?
See electrical site plan and sheet E604 for duct bank details.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Did the Engineer of Record perform underground locates for determining the underground ductbank route? |
| The GC shall perform underground utility locating to confirm all duct bank locations. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Can the VA provide the Underground utilities located during design to include any storm sewer, sanitary sewer, water gas, communication, fiber optic, electrical, fuel, irrigation, and chilled water and steam lines? |
| Site survey provided. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Can the VA provide the MH invert elevations at all new MH’s? |
| Site survey provided. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Can the VA provide the utility-owned communication demarcation entrance room locations? |
| Site survey provided. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Can the VA provide the utility-owned communication service paths for the campus? |
| Site survey provided. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| If the route of the UG ductbank as shown on the drawings needs to be re-routed due to below surface obstacles, who is responsible for the added costs? |
| This would have to be discussed with the CO at the time that it happens to determine a solution. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Can the VA provide the profiles of the UG duct banks? |
| Refer to sheet E604 for details |
| 1. |
| 9-23-24 |
| 10-9-24 |
| The PSRDM mentions that pathways entering buildings must not be exposed on the building exterior. The SCHEMATIC DUCTBANK TRANSITION DETAIL on Drawing Sheet E604 reflects the transitioning conduit above ground and up the side of the wall. Can the VA confirm that each entrance conduit to the various buildings will follow that detail? And if so, what is the minimum height should the conduit enter above grade or finish floor elevation? |
| Install per detail. Assume 10 feet above finished floor. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Per the VA’s Physical Security and Resiliency Design Manual, para Table 8-3 Protection of Utilities and Equipment |
“Access points (such as manholes) At grade: The VA facility must assess the risk at each location of the at-grade utility structure. If determined to be high risk, it must comply with section 3.3 Standoff Requirements and section 3.6 Anti-Ram Rated Vehicular Barriers and be provided a fence as a pedestrian barrier and electronic security system for access control, intrusion detection, and monitoring of the critical equipment in accordance with Chapter 10.” Can the VA confirm that the MH’s have been evaluated and are not at high risk, therefore the above paragraph is not applicable to the project?
Contractor to verify and report to the VA if any are found.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Can the VA provide the inter-building A/B side fiber conduit/cabling routing from the entrance rooms of each building to the TR or TE rooms in order to meet the PDSM of 50’ separation? |
| Current spacing has been DCIE and VA approved |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Per the PDSM “Pathways must not be located closer than 50 feet (15 m) to each other; pathways must enter served buildings at different locations and must not be exposed on the building exterior.” Can the VA provide the room locations for the OSP entrances per building meeting the PDSM having two entrances 50’ apart? |
| Service provider entrances are existing to remain. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Are all new utilities across roads, parking lots to be open cut installations? |
| See civil and electrical drawings. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Is the VA going to provide each of the HH and MH designations, to include the RIM elevation, Inverts in & out on the duct banks; as the MH details on drawing C6.0 suggests the depth to bottom of MH from the conduit “varies”? |
| Contractor responsible to verify conditions. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Are the MH and HH covers to be lockable? |
| Contractor to meet VA design requirements. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Is the contractor responsible for any re-marking of parking stalls or other directional markings disturbed during UG construction? |
| Yes |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Are the Manhole / Hand Hole covers to be H-20 rated? |
| Contractor to meet VA design requirements. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet E0000, Contractor Notes |
These notes state that the contractor can request the project design narrative as part of this design documentation package. Can the VA provide the design narrative as stated?
Documents were provided.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet E0000, Contractor Notes |
The following note states: “FOR NEW CONDUIT PENETRATIONS LEADING INTO ROOM 1128, THE DESIGN INTENT IS TO PROVIDE A 90 DEGREE BEND UNDERGROUND AND RUN CONDUITS ALONG THE EXTERIOR OF THE BUILDING, THEN PENETRATING INTO THE ROOM AT A HIGH ELEVATION FOR EASE OF TRANSITION: UTILIZING CABLE TRAYS TO THE TERMINATION LOCATION. NO UNDERGROUND/CUTTING OF EXISTING SLAB WITHIN ROOM 1128 SHALL BE PERFORMED FOR NEW CONDUIT PENETRATIONS.”
Is the SCHEMATIC DUCTBANK TRANSITION DETAIL on E604 the only location the detail is applicable?
No, every building in the project needs a transition for A/B fiber.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Draying ES100 |
What branch distribution duct bank detail on E604 is applicable that runs from the MH to building 3128?
Run (2) 4-inch conduit and provide a minimum separation no less than 48 inches between or as wide as the tunnel/ crawl space allows, whichever is the most. Match wiring and innerduct of detail 1, sheet E604
| 1. |
| 9-23-24 |
| 10-9-24 |
| Can the VA provide the topographic survey of the campus? |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Can the VA provide the referenced existing service tunnel as builts as identified on ES100 Keynote #4? |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet ES100, Keynote #4 |
Can the VA provide the conduit count & configuration thru the service tunnel?
Run (2) 4-inch conduit and provide a minimum separation no less than 48 inches between or as wide as the tunnel/ crawl space allows, whichever is the most. Match wiring and innerduct of detail 1, sheet E604
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet ES100, General Note A |
The note states: “ENCASE UNDERGROUND DUCTS AND CONDUITS IN CONCRETE OR AS DESCRIBED IN PDSM.” While the PDSM requires conduits be encased in concrete, the manual also states that there should be a minimum of two spare four-inch (100 mm) conduits between buildings. SECTION - 1 BY 2 DUCTBANK on sheet E604 does not reflect any spares. Can the VA confirm that the detail is correct and spares for SECTION - 1 BY 2 DUCTBANK are not required?
Spare innerduct provides spare paths.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet C0.0, Sheet List Table |
This list reflects C6.1 CONSTRUCTION DETAILS. This sheet does not appear to have been provided. Can the VA provide this sheet?
C6.1 should not be in the civil index, C6.1 is not listed on the main project sheet index on GI002
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Specification Section 26 05 41 para 2.3 DUCTS, C Ducts (direct-burial) |
The specs include direct burial duct, can the VA confirm that we can use the direct burial method?
No direct burial is allowed.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Specification Section 26 05 41 para 3.1 MANHOLE AND PULLBOX INSTALLATION, D & E |
The specs include Manhole Lighting and Sump Pump. Can the VA confirm that the manholes are to have these and if so, can the VA please provide the dedicated direct-buried conduit and conductors to nearest electrical panelboard information for each MH?
As basis of bid provide 1/2HP sump pump per manhole and controls for each manhole. Include pump piping. Assume power to be provided from Mail Electrical room in building 500, and writing (sized for voltage drop) routing following the duct bank. Assume new 2 pole 208V brakers for each pump. Include one 120 V circuit feeding all light fixtures, from same location above. Light fixtures lr spec. No direct burial conductors are allowed
| 1. |
| 9-23-24 |
| 10-9-24 |
| Can the VA provide the MH and HH AASHTO Load Category rating for the covers or are we to assume all to be H-20 Rated? |
| Contractor to meet VA design requirements. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| To confirm; based on sheet ET900, currently the 2 existing service providers enter bldg 500 room 1128 correct? |
| Correct |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference all architectural new work plans |
The drawings do not specify the wall type at walls where the door is to be removed and infilled. Can the VA clarify which wall type we should use for all the doors being removed and infilled?
If the wall type is not identified, the GC shall patch and repair the existing wall to match. It is highly recommended that the GC do a site walk to clearly understand the scope of work.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet AE105, 1605 IT & 1607A TR |
Can the VA provide the new wall dimensions?
Yes
| 1. |
| 9-23-24 |
| 10-9-24 |
| Can the VA clarify that it is acceptable to run loose 6A cabling in the wall space at locations that do not have conduits to a backbox? |
| Install wiring as specified on drawings |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Can the VA clarify that it is acceptable to install the new 6A cabling in the existing conduit provided the fill rate is not exceeded? |
| No. Intent is to have the existing Data drop fully functional, until transition is completed. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Can the VA clarify that all existing conduit drops to the backbox are ½” EMT therefore that is why the drawings reflect installing and new drop next to the existing? |
| Install wiring as specified on drawings |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Can the VA clarify that that if the existing EMT is ¾” to a backbox the existing can be used for the 2 data cables required per the drawings even though this would exceed the max fill rate? |
| Install wiring as specified on drawings |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Can the VA clarify if there is any furniture system cabling required on this project, if so can the VA please identify each location? |
| No furniture system cabling required. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Can the VA clarify if the use of flex conduit can be used for the new data drop locations? |
| Refer to project specifications for and drawings for allowed means and methods. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet AE111 |
Can the VA confirm that the existing door frame 1713D does not require to be modified for access control?
Door frames will need to be modified.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Can the VA provide the locations that currently have Fireproofing? |
| Please reference specific drawings and specs. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet AE201, BLDG_501_RM 102A IMA OFFICE DEMO |
Room 102B specifies to remove ceiling etc. However, it does not mention 102A as having the ceiling removed, just 102B being removed. Can the VA clarify if the entire room 102A is to have the ceiling completely removed, not just the area for room 102B?
See AE202
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet AE201, BLDG_501_RM 102B TE |
Can the VA clarify if Room 102B requires the walls to be extended to the deck?
Existing walls to remain
| 1. |
| 9-23-24 |
| 10-9-24 |
| Can the VA confirm that when the fiber enters into the buildings the fiber must be separated and routed diversely, if so, can the VA provide the diverse fiber route for each building? |
| Contractor shall provide on shop drawing submittal. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Can the VA confirm that when routing fiber inside buildings a minimum of 50’ separation to be maintained, with the possible exception of routing being next to each other if the fiber is in opposite directions? |
| Current spacing has been DCIE and VA approved |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Can the VA clarify if the contractor is responsible for installing any 25 Pair Phone cable to each TR room 110 block? |
| Existing phone lines shall remain and kept fully functional. Project does not include any 25 pair phone work. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Can the VA clarify if the new 30 AMP 2 POLE/NEMA 3R, NON FUSIBLE DISCONNECTS for the multiple condensing units are to be motor-rated switches? |
| YES |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet ET901B, B3136 -OVERALL -ELECTRICAL |
Can the VA confirm the location of the card reader for this room?
Right side of the Rack. Key #2 is pointing to it.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Can the VA clarify whether 1-1/4" Flex Conduit can be used in existing walls for communication cabling? |
| Refer to project specifications for allowed means and methods. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Can the VA clarify if all new WAO’s are Standard Density? |
| Yes, unless otherwise noted on drawings |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet AE401, BLDG_504_RM 102A TR |
Can the VA confirm that the existing flooring is not to be removed for this new TR room?
See previous response
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet AE301, BLDG_502_RM 03 TE CLOSET |
Can the VA confirm that there is no existing ceiling to be removed for this new TE room as no demo note indicated on the RCP?
See detail 2, keynote 12 &13
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet AE301, BLDG_502_RM 03 TE CLOSET |
Can the VA confirm that there are no walls to be extended to the deck?
Existing walls to remain
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet AE301, BLDG_502_RM 03 TE CLOSET |
Can the VA clarify if all walls are to receive ¾” FRT plywood backing or just the wall of which the wall mounted rack is shown?
See detail 2, keynote 29
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet ET300, FUTURE MOP SINK AREA IMAGE |
Can the VA clarify where this detail 4 is located on the sheet?
Key Note 8 indicates the general area
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet ET300, FUTURE MOP SINK AREA IMAGE |
Can the VA provide a clear picture of this image See source imagery
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet ET300, KEYNOTE #10 |
The note states: “ALL EXISTING EQUIPMENT, DEVICES AND ITEMS LOCATED ON THIS WALL SHALL BE RELOCATED TO A NEW LOCATION. COORDINATION WITH VA PRIOR TO RELOCATION.”
The image isn’t very clear, can the VA provide more details as to the scope of which the contractor has to relocate and to where?
See source imagery. For bidding purposes assume that items will be relocated not farther than 200 feet from the current location.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet AE115, BLDG_500_RM 440 TR |
The room label has 445, however the detail says the room is 440. Can the VA clarify which is correct?
The room number per plan is 445.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet AE701, BLDG_517 NEW TE ENCLOSURE |
Can the VA indicate what the new TE room number assignment would be?
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet AE701, BLDG_517 NEW TE ENCLOSURE |
I understand the keynote states to coordinate the actual location and size of the fencing, however can the VA provide what we should use as the basis of design for sizes in order to price?
10x7
| 1. |
| 9-23-24 |
| 10-9-24 |
| Several of the TE rooms as an example reflect a card reader next to the wall rack within the room, other TE’s reflect the card reader outside the room near the door. Can the VA clarify the differences in locations shown for these readers? |
| Car reader functionality would be the same in either location. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Can the VA provide which building(s) and which floors have interstitial space? |
| No interstitial space between floors. There is a crawl space below TR zones 1 thru 4. |
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing AE903, 3126 -NEW ROOM 107 CARD READER |
The keynote #5 says to remove and replace reader. Keynote #6 was not used at this room. Can the VA clarify if note #6 was the intent for this reader and not note #5?
Keynote 5 is correct.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet AE912, Finish Schedule |
Can the VA clarify that “CS” in the schedule is really “SC” to match the finish legend?
Yes, CS is SC.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet AE912, Finish Schedule |
Can the VA clarify that ceilings for rooms 116 (506), 116, 116 (508) in the schedule are to be GWB or Open?
Yes, GYP Per plans
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet AE912, Finish Schedule |
Many of the floor plans indicate the rated plywood locations for each of the rooms that seem to differ from the finish schedule. Can the VA clarify if all walls in the rooms listed are to receive rated plywood or as the floor plans indicate?
Provided plywood per plans. TR rooms will get full plywood and TE rooms will only get plywood behind the new equipment per the plans.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Can the VA provide the basis of design for the RB-1 |
RUBBER FLOORING called out in the room finish schedule?
Contractor to meet VA design requirements.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Specification for RB-1 Rubber Flooring |
Can the VA provide the specifications for this material?
For bidding purposes only, The specification can be found https://www.cfm.va.gov/TIL/spec.asp
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference SECTION 09 66 00 STATIC DISSIPATIVE SEALER FOR CONCRETE SUBSTRATES |
Can the VA clarify if this specification is appliable to the project and if so, provide the location(s) of which it applies?
Yes, this spec is provided for all TR rooms. See finish schedule on AE 912.
Note: CS in the finish schedule is SC in the legend.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet AE912, Finish Schedule - GENERAL FINISH NOTES #2 |
The note specifies to match the campus standard. Can the VA provide a copy of the campus standard?
To be provided post award.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet AE912, Finish Schedule – Bldg 510, RM 110 and 505, RM 112 |
The schedule reflects ACT for these TE rooms, is this correct?
Yes
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet AE912, Door Legend “Accessories” |
The legend provides accessories such as door plates and an example designation. Can the VA provide where on the drawings these designations are used?
Door plates are not required on TR doors.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet AE912, Door Schedule “Legend” |
The legend states “ALL DOORS WITH CARD READERS MUST HAVE DOOR CLOSERS.”
Can the VA clarify if this is applicable to doors not included in the door schedule but are to receive a card reader; as there is nothing indicating this on the drawings for providing closures on existing doors to remain or frames to be modified to receive access control?
VA Handbook 0730/4 requires doors into secured spaces have a door closer. If an existing room/door is being used and does not have a door closer, then one must be added.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet AE912, CMU WALL HEADER DETAIL |
The Lintel Schedule provides the various “Marks”, can the VA provide which “Mark” is applicable to which door location on the floor plans?
See Door schedule and legend note #6 for location.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing Sheet AE912, CONTROL JOINT AT DOOR FRAMES |
Can the VA provide where CJ’s are applicable on the floor plans?
These are typical details and shall be installed at all new doors. See door schedule for new doors and frame.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing AE701, Floor Plan Note #33 |
Please provide additional details for the 7' CHAINLINK FENCE WITH SWING GATE AND LOCKING HARDWARE, Example: 9 gauge chain link with a 2 inch diamond pattern; high security fences with more substantial 6 gauge wire; anchorage method, etc..
No special requirements are required. The fence is used to keep the space separated from the storage area. Provide a bid for basic chain link fence and hardware per plans.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing AE701, Floor Plan Note #33 |
Can the VA clarify if the fence needs to go to the underside of the roof?
Per Keynote #33, the fence is 7’-0”.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Section 10 22 13 Wire Mesh Partitions from the TIL |
Wouldn’t this section be a better suited product/material to use vs. chain-link fencing? Locking mechanisms are available for wire partitions. Suggestion Only.
Bid per the plans and notes.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference Drawing AE201, Floor Plan Note #19 |
Building 501, room 102A calls out for a new floor finish and base. The room finish schedule does not include this specific room, and the only flooring specifications provided is Static Dissipative Sealer for Concrete Substrates. Can the VA clarify what floor finish is applicable to this room and provide the specifications?
Provide Static dissipative sealer for concrete.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference VA Lake Baldwin - Specification Addendum 01 June 21, 2024 “1.2 General Intention (D): Updated, the spec section 01 45 29 / laboratory services were not provided and will not be required. “ |
Per “SECTION 32 12 16 ASPHALT PAVING - Laboratory and field-testing requirements: Section 01 45 29, TESTING LABORATORY SERVICES” was retained as a related specification. Can the VA confirm that Testing Laboratory Services for concrete, pavements, compaction etc. are not required to be performed and document test results?
Testing Laboratory Services is not required.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference SECTION 32 12 16 ASPHALT PAVING, para 1.2 RELATED WORK “C” |
The related Section 32 17 23, PAVEMENT MARKINGS was retained however not provided. Can the VA provide section 32 17 23?
For bidding purposes only, the specification can be found https://www.cfm.va.gov/TIL/spec.asp
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference SECTION 32 12 16 ASPHALT PAVING, para 1.4 ALIGNMENT AND GRADE CONTROL |
This para states: “The Contractor’s Registered Professional Land Surveyor shall establish and control the pavement (aggregate or asphalt base course and asphalt surface course) alignments, grades, elevations, and cross sections as shown on the Drawings.” None of the above has been provided on the drawings. Can the VA clarify how we are to meet this requirement if there is missing information for a surveyor to base controls on?
This question is unclear. The pavement work is all patch and repair for trenching.
| 1. |
| 9-23-24 |
| 10-9-24 |
| Reference SECTION 31 20 11 EARTHWORK, para 1.3 RELATED WORK Section 01 45 29, TESTING LABORATORY SERVICES was retained in this section. |
Can the VA confirm the section is…
This is the start of the file's text. The full file is on GovTribe.