Attachment_4_SOW_FOVA_BLDG_405_Roof_Maintenance_78pgs.pdf
PDF 675 KB Posted
- Attached to
- FOVA MAINTAIN BLDG 405 ROOF
- Solicitation number
- 140P8326Q0053
About this file
This is a Statement of Work (SOW) for a roof replacement project at Fort Vancouver National Historic Site in Vancouver, Washington, under the National Park Service.
The project involves complete demolition of the existing asphalt shingle roof system and installation of a new Styrene-Butadiene-Styrene (SBS) Modified Bituminous Membrane Roofing system on Building 405, a non-historic masonry aircraft maintenance facility constructed in 1983. The work is designed to achieve LEED Certification Level compliance. The SOW is organized into multiple sections covering general requirements (summary of work, submittal procedures, safety requirements, quality requirements, temporary facilities, product requirements, cutting and patching, execution, and closeout procedures); selective demolition; and the thermal and moisture protection system. Key specifications require the roofing system to meet FM Approvals 4450 and 4470 standards with a Class 1A-90 fire/windstorm classification and MH hail resistance rating. The roofing assembly must achieve a Solar Reflectance Index of not less than 78 and demonstrate resistance to uplift pressures of 83 lbf/sq. ft. at corners, 55 lbf/sq. ft. at perimeters, and 33 lbf/sq. ft. in the field. The basis of design product is Paradiene 20 TG/30 CRFRTG Torchable Roof System by Siplast, Inc., specified with detailed performance requirements for both base and finish plies. The contractor must submit an Accident Prevention Plan, Quality Control Plan, Waste Management Plan achieving 75 percent diversion rates, and Project Record Documents prior to construction. Work is restricted to normal business hours (7:00 a.m. to 5:30 p.m., Monday through Friday) with 48-hour advance notice required for weekend/holiday work. A 20-year manufacturer warranty is required from the date of Substantial Completion. The project emphasizes environmental sustainability with requirements for recycled content materials, low-VOC adhesives and sealants, and comprehensive waste management and diversion protocols.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
FY26 Re-Roof Building 405
Fort Vancouver National Historic Site
Vancouver, Washington
National Park Service
February 2026
TABLE OF CONTENTS
DIVISION 1 - GENERAL REQUIREMENTS
011100 Summary of Work 012700 Definition of Line Items 013300 Submittal Procedures 013523 Safety Requirements 014000 Quality Requirements 015000 Temporary Facilities 016700 Product Requirements 017340 Execution 017419 Construction Waste Management and Disposal 017000 Project Closeout
DIVISION 2 – SELECTIVE DEMOLITION
004101 Selective Demolition
DIVISION 7 - THERMAL AND MOISTURE PROTECTION
075216 SBS Modified Bituminous Membrane Roofing
01 11 00 - 1
SUMMARY OF WORK
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Work covered by the Contract Documents.
2. Work under other contracts.
3. Contractor use of premises.
4. Public use of site.
5. Work Restrictions.
6. Additional Reports.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: Fort Vancouver National Historic Site, South Barracks, Vancouver, Washington 98661. From Interstate 5, travel east on E. Mill Plain Boulevard to Fort Vancouver Way. Turn south onto Fort Vancouver Way and proceed through the turning circle to Alvord Road. Turn left on Alvord Road to Barracks Road.
B. The Work consists of the following:
The Work includes the installation of STYRENE-BUTADIENE-STYRENE (SBS) Modified Bituminous Membrane Roofing on Building 405. This building is a non-historic masonry structure constructed as an aircraft maintenance facility in 1983.
1. Project is designed to comply with a Certification Level according to the U.S. Green
Building Council's Leadership in Energy & Environmental Design (LEED) Rating System, as specified in Division 01 Section "Sustainable Design Requirements."
01 11 00 - 2
C. Project will be constructed under a single prime contract.
1.3 WORK UNDER OTHER CONTRACTS
A. General: Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate the Work of this Contract with work performed under separate contracts.
B. Concurrent Work: Government will award separate contract(s) for the following construction operations at Project site. Those operations will be conducted simultaneously with work under this Contract.
1.4 CONTRACTOR USE OF SITE
A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Limits: Confine construction operations to areas within the Contract limits.
2. Limit site disturbance, including clearing of vegetation, to areas indicated or approved by the Contracting Officer.
B. Storage of Materials: Confine storage of materials to facility provided by the NPS.
C. Preservation of Natural Features:
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
2. Provide temporary barriers to protect existing trees and plants and root zones.
3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with
Contracting Officer and remove agreed-on branches that interfere with construction.
4. Do not fasten ropes, cables, or guys to existing trees.
5. Carefully supervise construction operations near trees to prevent damage.
D. Driveways and Entrances: Keep driveways, roads, and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
E. Construction Camp: Establishment of a camp within the park will not be permitted.
F. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for
01 11 00 - 3 vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
1.5 PUBLIC USE OF SITE
A. The building and parking area around each building will be closed to the public during construction.
1.6 OCCUPANCY REQUIREMENTS FOR BUILDINGS
A. Areas Within Buildings
1. Government Occupancy of Completed Areas of Construction: Government reserves the right to occupy and to place and install equipment in completed areas of building, provided such occupancy does not interfere with completion of the Work. Such placement of equipment and partial occupancy shall not constitute acceptance of the roof project.
a. Contracting Officer will prepare a Beneficial Occupancy letter for each specific portion of the Work to be occupied before Government occupancy.
b. Obtain a Certificate of Occupancy from the NPS before Government occupancy.
c. Before partial Government occupancy, mechanical and electrical systems shall be fully operational, and required tests and inspections shall be successfully completed.
On occupancy, Government will operate and maintain mechanical and electrical systems serving occupied portions of building.
d. On occupancy, Government will assume responsibility for maintenance and custodial service for occupied portions of building.
1.7 CONDUCT OF OPERATIONS
A. At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent from the Contracting Officer. Submit requests 48 hours in advance of the work to the Contracting Officer for approval.
C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
1.8 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7:00 a.m. to 5:30 p.m., Monday through Friday, except when otherwise indicated.
B. Existing Utilities
01 11 00 - 4
1. Existing Utilities: Notify Contracting Officer and utility companies of conflict with overhead power and data lines.
2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
C. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor air intakes.
1.9 ADDITIONAL REPORTS
A. The following reports are available:
B. Hazardous Materials Survey Report – April 20, 2015, Kelsay Environmental Consulting.
C. If conflicts occur between the report and drawings or specifications, the drawings and specifications govern.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00
01 27 00
DEFINITION OF CONTRACT LINE ITEMS
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
1.1 SUMMARY
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item No.0001 - Replace Roof Building 405
1. This item consists of all materials and labor required to demo the existing roof material and replace with Styrene-butadiene-styrene (SBS) modified bituminous membrane roofing on building 405.
2. Measurement for payment will be by on site review.
3. Payment will be made at the contract lump sum price
END OF SECTION 01 27 00
FOVA - 01 33 23 - 1
SUBMITTAL PROCEDURES
SECTION 01 33 23 - SUBMITTAL PROCEDURES
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other submittals.
1.2 DEFINITIONS
A. Action Submittals: Written and graphic information that requires Government’s responsive action.
B. Informational Submittals: Written information that does not require Government’s responsive action. Submittals may be rejected for not complying with the requirements.
1.3 GENERAL SUBMITTAL PROCEDURES
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities. Review them for legibility, accuracy, completeness, and compliance with Contract Documents.
1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.
2. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.
a. Contracting Officer reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
B. Submittal List: A submittal list has been attached to the end of this Specification Section. The intent is to provide an overall summary of submittal requirements and not a comprehensive list.
The requirements of the individual Specification Sections, terms and conditions of the Contract still apply regardless of what is shown on the submittal list.
C. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on Contracting Officer’s receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including re-submittals.
1. Action Submittals
a. Initial Review: Allow 30 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required.
b. Re-submittal Review: Allow 30 calendrer days for review of each re-submittal.
FOVA - 01 33 23 - 2
2. Informational Submittals
a. Review: Allow 15 days for review of each submittal.
D. Approved Equals:
1. For each item proposed as an “approved equal,” submit supporting data, including:
a. Drawings and samples as appropriate.
b. Comparison of the characteristics of the proposed item with that specified.
c. Changes required in other elements of the work because of the substitution.
d. Name, address, and telephone number of vendor.
e. Manufacturer’s literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists. Describe availability of maintenance service, and state source of replacement materials.
2. A request for approval constitutes a representation that Contractor:
a. Has investigated the proposed item and determined that it is equal or superior in all respects to that specified.
b. Will provide the same warranties for the proposed item as for the item specified.
c. Has determined that the proposed item is compatible with interfacing items.
d. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.
e. Waives all claims for additional expenses that may be incurred as a result of the substitution.
E. Additional Copies: Unless additional copies are required for final submittal, and unless Contracting Officer observes noncompliance with provisions in the Contract Documents, initial submittal may serve as final submittal.
1. Additional copies submitted for maintenance manuals will not be marked with action taken and will be returned.
F. Transmittal: Package each submittal individually and appropriately for transmittal and handling.
Transmit each submittal using a transmittal form. Contracting Officer will return submittals, without review, received from sources other than Contractor.
1. CM-16 Transmittal Form: All material submittals shall be transmitted using National Park Service form CM-16. (This form can be downloaded from the Workflows website at http://www.nps.gov/dscw/con_subreview21.htm.) No action will be taken on a material submittal item unless accompanied by the transmittal form.
2. Documents required in division 1 are to be delivered under separate cover letter. Do not use the CM-16 Transmittal form for these documents.
G. Identification: Place a permanent label 1 by 4 inches on each submittal for identification.
1. Include the following information on label for processing and recording action taken:
a. Project name, Park, PMIS number, Contract number.
http://www.nps.gov/dscw/con_subreview21.htm
FOVA - 01 33 23 - 3
b. Date.
c. Submittal number or other unique identifier, including revision identifier.
i. Submittal number shall be a sequential number (e.g., 001). Re-submittals shall include an alphabetic suffix after another decimal point (e.g., 001.A).
H. Re-submittals: Make re-submittals in same form and number of copies as initial submittal.
1. Note date and content of previous submittal.
2. Note date and content of revision in label or title block and clearly indicate extent of revision.
3. Re-submit submittals until they are marked “Approved” or “Approved with notations”.
I. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.
J. Use for Construction: Use only final submittals with mark indicating “Approved” or “Approved with notations.
PART 2 - PRODUCTS
2.1 ACTION SUBMITTALS
A. General: Prepare and submit Action Submittals required by individual Specification Sections.
1. Contracting Officer reserves the right to require submittals in addition to those called for in individual sections.
B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each copy of each submittal to show which products and options are applicable.
3. Include the following information, as applicable:
a. Manufacturer’s written recommendations.
b. Manufacturer’s product specifications.
FOVA - 01 33 23 - 4
c. Manufacturer’s installation instructions: When Contract Documents require compliance with manufacturer’s printed instructions, provide one complete set of instructions to Contracting Officer and keep another complete set of instructions at the project site until substantial completion.
4. Number of Copies: Submit one digital copy, unless otherwise indicated. Contracting officer will return one copy. Retain copy as a Project Record Document.
C. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual component as delivered and installed.
1. Transmit Samples that contain multiple, related components such as accessories together in one submittal package.
2. Identification: Attach label on unexposed side of Samples that includes the following:
a. Generic description of Sample.
b. Product name and name of manufacturer.
c. Sample source.
d. Submittal Number and title of appropriate Specification Section.
3. Disposition: Maintain sets of approved Samples at Project site, available for quality-control comparisons throughout the course of construction activity. Sample sets may be used to determine final acceptance of construction associated with each set.
4. Samples for Initial Selection: Submit manufacturer’s color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.
a. Number of Samples: Submit one set of Samples. COR will retain Sample set.
5. Samples for Verification: Submit full-size units or Samples of size indicated, prepared from same material to be used for the Work, cured and finished in manner specified, and physically identical with material or product proposed for use, and that show full range of color and texture variations expected. Samples include, but are not limited to, the following: partial sections of manufactured or fabricated components; small cuts or containers of materials; complete units of repetitively used materials; swatches showing color, texture, and pattern; color range sets; and components used for independent testing and inspection.
a. Number of Samples: Submit one set of Samples. COR will retain Sample set.
D. Construction Materials: The Contractor is encouraged to submit for approval products made out of recycled or environmentally responsible material. Every effort will be made by the National Park Service to approve these materials.
2.2 INFORMATIONAL SUBMITTALS
A. General: Prepare and submit Informational Submittals required by other Specification Sections.
1. Number of Copies: Submit one digital copy of each submittal, unless otherwise indicated.
FOVA - 01 33 23 - 5
2. Certificates and Certifications: Provide a notarized statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.
3. Informational submittals that do not comply with the requirements specified in the Contract Documents will be rejected and one copy will be returned.
B. Contractors Construction Schedule: Comply with the requirements specified in Section 01 32 16 “Construction Schedule.”
C. Accident Prevention Plan: Comply with the requirements specified in Section 01 35 23 “Safety Requirements.”
D. Schedule of Values: Comply with the requirements specified in Section 01 32 16 “Construction Schedule”.
E. Waste Recycling Plan: Comply with the requirements specified in Section 01 74 19 “Construction Waste Management and Disposal.”
F. Quality Control Plan: Comply with the requirements specified in Section 01 40 00 “Quality Requirements.”
G. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, names and addresses of architects and owners, and other information specified.
H. Installer Certificates: Prepare written statements on manufacturer’s letterhead certifying that Installer complies with the requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.
I. Manufacturer Certificates: Prepare written statements on manufacturer’s letterhead certifying that manufacturer complies with the requirements in the Contract Documents. Include evidence of manufacturing experience where required.
J. Product Certificates: Prepare written statements on manufacturer’s letterhead certifying that product complies with the requirements in the Contract Documents.
K. Material Certificates: Prepare written statements on manufacturer’s letterhead certifying that material complies with the requirements in the Contract Documents.
L. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency’s standard form, indicating and interpreting test results of material for compliance with the requirements in the Contract Documents.
M. Product Test Reports: Prepare written reports indicating current product produced by manufacturer complies with the requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency.
N. Research/Evaluation Reports: Prepare written evidence, from a model code organization acceptable to authorities having jurisdiction, that product complies with building code in effect for Project.
FOVA - 01 33 23 - 6
O. Manufacturer’s Instructions: Prepare written or published information that documents manufacturer’s recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturer.
P. Manufacturer’s Field Reports: Prepare written information documenting factory-authorized service representative’s tests and inspections. Include the following, as applicable:
1. Statement on condition of substrates and their acceptability for installation of product.
2. Summary of installation procedures being followed, whether they comply with the requirements and, if not, what corrective action was taken.
3. Results of operational and other tests and a statement of whether observed performance complies with the requirements.
3.1 CONTRACTOR’S REVIEW
A. Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions.
3.2 CONTRACTING OFFICER’S ACTION
A. General: Submittals will be returned disapproved without technical review if identification information is missing, not filled in, or if placed on the back of the submittal; an incorrect number or format of submittals is provided; the transmittal form is incorrectly filled out; submittals are not coordinated; or submittals do not show evidence of Contractor’s approval.
1. Any work done or orders for materials or services placed before approval shall be at the Contractor’s own risk.
B. Action Submittals: Contracting Officer will review each submittal, make marks to indicate corrections or modifications required, and return one copy. Contracting Officer will annotate the CM-16 Transmittal Form indicating the action taken, as follows:
1. The returned submittal will be marked in one of three ways as defined below:
a. APPROVED: Acceptable with no corrections.
b. APPROVED WITH NOTATIONS: Minor corrections or clarifications required.
All comments are clear and no further review is required. The Contractor shall address all review comments when proceeding with the work.
c. DISAPPROVED - RESUBMIT: Rejected as not in accordance with the contract or as requiring major corrections or clarifications. The Contracting Officer will identify the reasons for disapproval. The Contractor shall revise and resubmit with changes clearly identified.
FOVA - 01 33 23 - 7
C. Informational Submittals: Contracting Officer will review each submittal and will not return it, or will reject and return one copy if it does not comply with the requirements. Contracting Officer will forward each submittal to appropriate party.
D. Partial submittals are not acceptable, will be considered non-responsive, and will be returned without review.
END OF SECTION 01 33 23
FOVA 01 35 23 - 1
SAFETY REQUIREMENTS
SECTION 01 35 23 - SAFETY REQUIREMENTS
1.1 SUMMARY
A. This section includes establishing an effective accident prevention program and providing a safe working environment for all personnel and visitors.
1.2 SUBMITTALS
A. Accident Prevention Plan (APP): After contract award and before the Pre-Construction conference, submit for review, an Accident Prevention Plan. The Contracting Officer will review the proposed Plan. If the plan requires any revisions or corrections, the Contractor shall resubmit the Plan within 10 days. No work may progress on-site without a Contracting Officer approved Accident Prevention Plan. No progress payments will be made until the Plan is accepted.
1.3 QUALITY ASSURANCE
A. Comply with contract clauses entitled "Accident Prevention" and "Permits and Responsibilities".
In case of conflicts between Federal, State, and local safety and health requirements, the most stringent shall apply. Equipment or tools not meeting OSHA requirements will not be allowed on the project sites. Failure to comply with the requirements of this section and related sections may result in suspension of work.
B. Qualifications of Employees:
1. All employees must be physically and able to perform their assigned duties in a safe manner.
2. Do not allow employees to perform work whose ability or alertness is impaired because of prescription or illegal drug use, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
3. Operators of vehicles, hoisting equipment, and hazardous plant equipment shall be able to understand signs, signals, and operating instructions, and be fully capable of operating such equipment. Provide operating instructions for all equipment. Newly hired operators shall be individually tested by an experienced operator or supervisor to determine if they are capable of safely operating equipment. Retain copies of all operator’s licenses and/or certifications onsite.
1.4 ACCIDENT REPORTING
A. Reportable Accidents (per OSHA 29CFR 1904): A project reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, fires, and property damage by accident in excess of $100. Notify Contracting Officer immediately in the event of a reportable accident. Within 7 days of a reportable accident, fill out and forward to Contracting
FOVA 01 35 23 - 2
Officer an Accident/Property Damage Report (Form CM-22). Form may be obtained from the Contracting Officer.
2.1 ACCIDENT PREVENTION PLAN (APP)
A. The Plan shall be written to comply with OSHA and project requirements (a generic plan is not acceptable) including but not limited to the following:
1. Name of responsible supervisor to carry out the program. The responsible supervisor is to be separate individual from the site superintendent. The designated safety representative is be on site during all construction activities.
2. Weekly and monthly safety meetings shall be documented with topic and attendees.
3. First aid and rescue procedures.
4. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to provide for property protection and safety of the public, National Park Service personnel, and Contractor's employees. Identify the work included under each phase, with an Job Hazard Analysis (JHA)/Job Safety Analysis (JSA), etc.
5. Training, both initial and continuing.
6. Planning for possible emergency situations, such as cave-ins, earthquake, explosions,, fires, floods, power outages, slides, and wind storms. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure of persons and property.
2.2 FIRST AID FACILITIES
A. Provide adequate facilities for the number of employees and appropriate to the hazards associated with the types of ongoing construction work at the site.
2.3 PERSONNEL PROTECTIVE EQUIPMENT
A. Meet requirements of applicable ANSI standards. Selection shall conform to OSHA 29CFR
1926.95 Subpart E.
3.1 EMERGENCY INSTRUCTIONS
A. Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.
3.2
FIRE AND LIFE SAFETY
A. Comply with the requirements of NFPA 241 (Standard for Safeguarding Construction, Alteration, and Demolition Operations).
FOVA 01 35 23 - 3
B. Store hazardous materials in accordance with manufacturer’s and OSHA 29CFR1926 Subpart D requirements. Maintain readily available, on site, MSDS/Safety Data Sheets (SDS) for each chemical.
1. Immediately report all spills of hazardous materials to the park.
2. Maintain a spill emergency response kit.
3. Train employees how to respond to a spill and use the emergency response kit.
3.3 PROTECTIVE EQUIPMENT
A. Inspect personal protective equipment daily and maintain in a serviceable condition. Clean, sanitize, and repair personal items, as appropriate, before issuing them to another individual.
B. Inspect, maintain, and document other protective equipment and devices before use and on a periodic basis to ensure safe operation. Retain inspection documentation onsite.
3.4 SAFETY MEETINGS
A. As a minimum, conduct one weekly 15-minute "toolbox" safety meetings. These meetings shall be conducted by a foreman or supervisor and attended by all construction personnel at the worksite. Topics need to coincide with work scheduled for the following week. Document and submit meeting minutes to the Contracting Officer within one day after the meeting.
B. Conduct monthly safety meetings for all levels of supervision. Meetings shall be attended by all contractors and subcontractors performing work on the site. Notify the Contracting Officer of meeting dates and times. These meetings shall be used to review the effectiveness of the Contractor's safety effort, to resolve current health and safety problems, to provide a forum for planning safe construction activities, and for updating the Accident Prevention Plan. The Contracting Officers Representative will attend the meeting and enter the results of the meetings into the daily log.
3.5 HARD HATS AND PROTECTIVE EQUIPMENT AREAS
A. A hard hat use area shall be designated by the Contractor. The area within the Work Limits Boundary is to be a hard-hat area for the duration of the project. The hard hat area shall be posted by the Contractor in a manner satisfactory to the Contracting Officer.
B. It is the Contractor's responsibility to require all those working on or visiting the site to wear hard hats and other necessary personal protective equipment in good repair at all times. As a minimum, maintain six hard hats and all other APP required equipment.
3.6 TRAINING
A. First Aid: Provide adequate training to an adequate number of personnel to ensure prompt and efficient first aid.
B. Hazardous Material: Train and instruct each employee exposed to hazardous material in safe and approved methods of handling and storage. Hazardous materials are defined as explosive, FOVA 01 35 23 - 4 flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury.
END OF SECTION 01 35 23
FOVA 01 40 00 - 1
QUALITY REQUIREMENTS
SECTION 01 40 00 - QUALITY REQUIREMENTS
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for quality assurance and quality control.
B. Testing and inspecting services are required to verify compliance with requirements specified or indicated. These services do not relieve Contractor of responsibility for compliance with the Contract Document requirements. The quality of all work shall be the responsibility of the Contractor.
1. Specified tests, inspections, and related actions do not limit Contractor's other quality assurance and control procedures that facilitate compliance with the Contract Document requirements.
C. See Divisions 02 through 49 Sections for specific test and inspection requirements.
A. Quality Assurance Services: Activities, actions, and procedures performed before and during execution of the work to guard against defects and deficiencies and substantiate that proposed construction will comply with requirements.
B. Quality Control Services: Tests, inspections, procedures, and related actions during and after execution of the work to evaluate that actual products incorporated into the work and completed construction comply with requirements.
C. Preconstruction Testing: Tests and inspections that are performed specifically for the project before products and materials are incorporated into the work to verify performance or compliance with specified criteria.
D. Product Testing: Tests and inspections that are performed by a Nationally Recognized Testing Laboratory (NRTL), a National Voluntary Laboratory Accreditation Program (NVLAP), or a testing agency qualified to conduct product testing, to establish product performance and compliance with industry standards.
E. Source Quality Control Testing: Tests and inspections that are performed at the source, i.e., plant, mill, factory, or shop.
F. Field Quality Control Testing: Tests and inspections that are performed on-site for installation of the work and for completed work.
G. Testing Agency or Laboratory: An entity engaged to perform specific tests, inspections, or both.
Testing laboratory shall mean the same as testing agency.
H. Installer/Applicator/Erector: Contractor or another entity engaged by Contractor as an employee, Subcontractor, or Sub-subcontractor, to perform a particular construction operation, including installation, erection, application, and similar operations.
FOVA 01 40 00 - 2
1. Using a term such as “carpentry” does not imply that certain construction activities must be performed by accredited or unionized individuals of a corresponding generic name, such as “carpenter.” It also does not imply that requirements specified apply exclusively to trades people of the corresponding generic name.
1.3 CONFLICTING REQUIREMENTS
A. Reference Standards: If compliance with two or more standards is specified and the standards establish different or conflicting requirements for minimum quality levels, comply with the most stringent requirement. Refer uncertainties and requirements that are different, but apparently equal, to Contracting Officer for a decision before proceeding.
B. Minimum Quality Levels: The quality level shown or specified shall be the minimum provided or performed. The actual installation may comply exactly with the minimum quality specified, or it may exceed the minimum within reasonable limits. To comply with these requirements, indicated numeric values are minimum or maximum, as appropriate, for the context of requirements. Refer uncertainties to Contracting Officer for a decision before proceeding.
1.4 SUBMITTALS
A. Quality Control Plan:
1. After contract award and before the Pre-Construction conference, submit for approval a written Contractor Quality Control (CQC) plan.
2. If the plan requires any revisions or corrections, the Contractor shall resubmit the plan within 10 days.
3. The Government reserves the right to require changes in the plan during the contract period as necessary to obtain the quality specified.
4. No change in the approved plan may be made without written concurrence by the Contracting Officer.
B. Qualification Data: For testing agencies specified in “Quality Assurance” Article to demonstrate their capabilities and experience. Include proof of qualifications in the form of a recent report on the inspection of the testing agency by a recognized authority.
C. Contractor's Quality Control Daily Reports: Submit showing all inspections and tests on the first workday following the date covered by the report. Quality Control Supervisor shall utilize the DSC forms available by accessing the DSC Workflows website, http://www.nps.gov/dscw/publicforms.htm.
1. Review CMR Dailies and reconcile any differences prior to posting CQC Dailies on the SharePoint Project Website.
D. Test Reports
1. Test reports shall be completed by the person performing the test.
2. Submit Daily Test Information Sheets with Quality Control Daily Reports.
3. Submit failing test results and proposed remedial actions within four hours of noted deficiency.
4. Submit three copies of complete test results no later than one calendar day after the test was performed.
E. Accessibility Inspection Report:
http://www.nps.gov/dscw/publicforms.htm
FOVA 01 40 00 - 3
1. Fill out the applicable sections of the Accessibility Inspection Report and attach to the Quality Control Daily Report.
2. Utilize the attached Accessibility Inspection form to document compliance with the Architectural Barriers Act Accessibility Standards (ABAAS).
3. Inspect at various stages of construction as needed to insure the finished product meets the standards.
4. Submit report not later than one calendar day after the inspection was performed.
5. Accessibility Inspection Report and Scoping Form must also be completed and submitted by the Contractor prior to the Final Inspection.
F. Off-Site Inspection Reports: Submit prior to shipment.
G. If the CQC plan and Quality Control Daily Reports are not submitted as specified, the Contracting Officer may retain all payments until such time a plan is accepted and implemented, or may retain payments for work completed on days there are no Quality Control Daily Reports.
H. Permits, Licenses, and Certificates: For NPS records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations bearing on performance of the work.
1.5 QUALITY ASSURANCE
A. General: Qualifications paragraphs in this Article establish the minimum qualification levels required; individual Specification Sections specify additional requirements.
B. Contractors Quality Control Staff:
1. The Contractor's Quality Control Supervisor may not perform superintendent duties, but may be the site safety representative.
2. The Contractor's designated Quality Control Supervisor shall be on the project site whenever contract work is in progress.
3. The Contractor's job supervisory staff may be used to assist the Quality Control Supervisor supplemented, as necessary, by additional certified testing technicians.
C. Installer Qualifications: A firm or individual experienced in installing, erecting, or assembling work similar in material, design, and extent to that indicated for this Project, whose work has resulted in construction with a record of successful in-service performance.
D. Manufacturer Qualifications: A firm experienced in manufacturing products or systems similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.
E. Fabricator Qualifications: A firm experienced in producing products similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.
F. Professional Engineer Qualifications: A professional engineer who is legally qualified to practice in jurisdiction where Project is located and who is experienced in providing engineering services of the kind indicated (including Structural Tests and Special Inspections (STSI). Engineering services are defined as those performed for installations of the system, assembly, or products that are similar to those indicated for this Project in material, design, and extent.
FOVA 01 40 00 - 4
G. Specialists: Certain sections of the Specifications require that specific construction activities shall be performed by entities who are recognized experts in those operations. Specialists shall satisfy qualification requirements indicated and shall be engaged for the activities indicated.
1. Requirement for specialists shall not supersede building codes and regulations governing the work.
H. Testing Agency Qualifications: An NRTL, an NVLAP, or an independent agency with the experience and capability to conduct testing and inspecting indicated, as documented according to ASTM E 329; and with additional qualifications specified in individual Sections; and where required by Contract, is acceptable to the Contracting Officer.
1. NRTL: A nationally recognized testing laboratory according to 29 CFR 1910.7.
2. NVLAP: A testing agency accredited according to NIST's National Voluntary Laboratory
Accreditation Program.
3. All measuring devices, laboratory equipment, and instruments shall be calibrated at established intervals against certified standards in accordance with NIST requirements.
Upon request, measuring and testing devices shall be made available for use by the Government for verification tests.
I. Factory-Authorized Service Representative Qualifications: An authorized representative of manufacturer who is trained and approved by manufacturer to inspect installation of manufacturer's products that are similar in material, design, and extent to those indicated for this Project.
J. Mockups: Before installing portions of the work requiring mockups, build mockups for each form of construction and finish required to comply with the following requirements, using materials indicated for the completed work:
1. Build mockups in location and of size indicated or, if not indicated, as directed by Contracting Officer.
2. Notify Contracting Officer seven days in advance of dates and times when mockups will be constructed.
3. Demonstrate the proposed range of aesthetic effects and workmanship.
4. Obtain Contracting Officer’s approval of mockups before starting work, fabrication, or construction.
5. Maintain mockups during construction in an undisturbed condition as a standard for judging the completed work.
1.6 QUALITY CONTROL
A. The Contractor is responsible for all testing and inspections, including Structural Tests and Special Inspections (STSI), as identified in the attached STSI. Inspect and test work as needed to ensure that the quality of materials, workmanship, construction, finish, and functional performance are in compliance with applicable specifications, drawings, and those required by the Building Code.
1. Engage a qualified testing agency to perform these quality-control services.
2. Submit the appropriate report, for each quality-control service.
3. Testing and inspecting requested by Contractor and not required by the Contract
Documents are Contractor's responsibility.
4. The Contracting Officer may designate test locations.
FOVA 01 40 00 - 5
B. Manufacturer's Field Services: Where indicated, engage a factory-authorized service representative to inspect field-assembled components and equipment installation, including service connections. Report results in writing.
C. Re-testing/Re-inspecting: Regardless of whether original tests or inspections were Contractor's responsibility, provide quality-control services, including retesting and re-inspecting, for construction that replaced work that failed to comply with the Contract Documents.
D. Testing Agency Responsibilities: Cooperate with NPS and Contractor in performance of duties.
Provide qualified personnel to perform required tests and inspections.
1. Notify Contracting Officer and Contractor promptly of irregularities or deficiencies observed in the work during performance of its services.
2. Determine the location from which test samples will be taken and in which in-situ tests are conducted.
3. Conduct and interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from requirements.
4. Submit 3 copies of the certified written report of each test, inspection, and similar quality-control service through Contractor.
5. Do not release, revoke, alter, or increase the Contract Document requirements or approve or accept any portion of the work.
E. Associated Services: Cooperate with agencies performing required tests, inspections, and similar quality-control services, and provide reasonable auxiliary services as requested. Notify agency sufficiently in advance of operations to permit assignment of personnel. Provide the following:
1. Access to the work.
2. Incidental labor and facilities necessary to facilitate tests and inspections.
3. Adequate quantities of representative samples of materials that require testing and inspecting. Assist agency in obtaining samples.
4. Facilities for storage and field curing of test samples.
5. Delivery of samples to testing agencies.
6. Preliminary design mix proposed for use for material mixes that require control by testing agency.
7. Security and protection for samples and for testing and inspecting equipment at Project site.
F. Coordination: Coordinate sequence of activities to accommodate required quality assurance and control services with a minimum of delay and to avoid necessity of removing and replacing construction to accommodate testing and inspecting.
1. Schedule times for tests, inspections, obtaining samples, and similar activities.
2.1 QUALITY CONTROL PLAN
A. The Quality Control Plan shall include:
1. Provide a letter designating the Quality Control Representative, from the company president, clearly stating that Quality Control Representative has the authority to stop work, direct re-work and "over-ride" the site superintendent on matters of quality.
2. A list of personnel responsible for quality control and assigned duties. Include each person's qualifications.
FOVA 01 40 00 - 6
3. A copy of a letter of direction to the Contractor's Quality Control Supervisor outlining assigned duties.
4. Names, qualifications, and descriptions of laboratories to perform sampling and testing, and samples of proposed report forms.
5. Methods of performing, documenting, and enforcing quality control of all work.
6. Methods of monitoring and controlling environmental pollution and contamination as required by regulations and laws.
3.1 OFF-SITE CONTROL
A. Items that are fabricated or assembled off-site shall be inspected for quality control at the place of fabrication.
3.2 ON-SITE CONTROL
A. Notification:
1. Notify the Contracting Officer at least 48 hours in advance of the preparatory phase meeting.
2. Notify the Contracting Officer at least 24 hours in advance of the initial and follow-up phases.
3. Preparatory meeting and initial phase meeting for the same feature of work cannot be on the same date and/or that the meetings cannot be combined.
4. The preparatory meeting will be held a minimum of 24 hours in advance of initial phase.
B. Preparatory Phase: Perform before beginning each feature of work.
1. Review control submittal requirements with personnel directly responsible for quality assurance and quantity control of the work. As a minimum, the Contractor's Quality Control Supervisor and the foreman responsible for the feature of work shall be in attendance.
2. Review all applicable specifications sections and drawings related to the feature of work.
3. Ensure that copies of all referenced standards related to sampling, testing, and execution for the feature of work are available on site.
4. Ensure that provisions have been made for field control testing.
5. Examine the work area to ensure that all preliminary work has been completed.
6. Verify all field dimensions and advise the Contracting Officer of discrepancies with contract documents.
7. Ensure that necessary equipment and materials are at the project site and that they comply with approved shop drawings and submittals.
8. Document all preparatory phase activities and discussions on the Contractor's Quality
Control Daily Report.
C. Initial Phase:
1. As soon as work begins, inspect and test a representative portion of a particular feature of work for quality of workmanship.
2. Review control testing procedures to ensure compliance with contract requirements.
FOVA 01 40 00 - 7
3. Document all initial phase activities and discussions on the Contractor's Quality Control Daily Report. Exact location of initial phase shall be indicated for future reference and comparison with follow-up phases.
D. Follow-Up Phase: Inspect and test as work progresses to ensure compliance with contract requirements until completion of work.
E. Additional Preparatory and Initial Phases: Additional preparatory and initial phases may be required on the same feature of work for the following reasons:
1. Quality of on-going work is unacceptable.
2. Changes occur in the applicable quality control staff, on-site production supervision, or work crew.
3. Work on a particular feature of work is resumed after a substantial period of inactivity.
3.3 DOCUMENTATION
A. Maintain Quality Control Daily Reports, Daily Test Report Information Sheets, and Accessibility Inspection Reports (Forms may be downloaded from the DSC Workflows website, http://www.nps.gov/dscw/publicforms.htm.) of quality control activities and tests.
B. Quality Control Daily Reports may not be substituted for other written reports required under clauses of the contract, such as Disputes, Differing Site Conditions, or Changes.
3.4 ENFORCEMENT
A. The Contractor shall stop work on any item or feature pending satisfactory correction of any deficiency noted by the quality control staff or the Contracting Officer.
3.5 REPAIR AND PROTECTION
A. General: On completion of testing, inspecting, sample taking, and similar services, repair damaged construction and restore substrates and finishes.
1. Comply with the Contract Document requirements for Division 01 Section “Cutting and
Patching.”
B. Protect construction exposed by or for quality-control service activities.
C. Repair and protection are Contractor's responsibility, regardless of the assignment of responsibility for quality-control services.
END OF SECTION 01 40 00
http://www.nps.gov/dscw/publicforms.htm
FOVA 01 50 00 - 1
TEMPORARY FACILITIES AND CONTROLS
SECTION 01 50 00 - TEMPORARY FACILITIES AND CONTROLS
1.1 SUMMARY
A. This Section includes requirements for temporary utilities, support facilities, and security and protection facilities.
A. Permanent Enclosure: As determined by Contracting Officer, permanent or temporary roofing is complete, insulated, and weathertight; exterior walls are insulated and weathertight; and all openings are closed with permanent construction or substantial temporary closures.
1.3 USE CHARGES
A. General: Cost or use charges for temporary facilities shall be included in the Contract Sum as required.
B. Field Office: The contractor will provide a field office for use their use. The contractor will maintain these temporary facilities in a condition acceptable to NPS. The NPS will not provide potable water or restrooms. The contractor will provide temporary communications connections as necessary.
This is the start of the file's text. The full file is on GovTribe.