Attachment 4 SOO FSS Airfield Copper to Fiber Upgrade ATCALS.pdf
PDF 12 MB Posted
- Attached to
- Airfield FOC Upgrade
- Solicitation number
- FA466123Q0056
About this file
This Statement of Objectives (SOO) outlines requirements for upgrading airfield fiber optic cable infrastructure at an Air Force base. The solicitation seeks proposals to replace aging copper cable with new fiber optic cable across runways, taxiways, and other airfield surfaces. Offerors must have experience deploying fiber optic cable in airfield environments. The work includes installing conduit, pulling cable, splicing connections, and testing/validating the upgraded system. Proposals are due by January 15th, 2023 and the contract is expected to be awarded by March 1st, 2023. The period of performance is 365 days following the award date. The SOO provides technical requirements but does not include pricing, legal terms, or other solicitation details. The related opportunity was issued by the Global Strike Command of the Department of the Air Force.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
38 ES 2/10/2023 Page 1 of 62
SOO- FSS System Copper to Fiber Optic Cable (FOC) Transport Upgrade. Dyess AFB TX
FOR OFICIAL USE ONLY
CONTROLLED UNCLASSIFIELD INFORMATION (CUI)
DEPARTMENT OF THE AIR FORCE
38TH CYBERSPACE ENGINEERING INSTALLATION GROUP (ACC)
TINKER AIR FORCE BASE OKLAHOMA
STATEMENT OF OBJECTIVES (SOO)
FSS System Copper to Fiber Optic Cable (FOC) Transport Upgrade Dyess AFB TX
13 March 2023
Prepared By
38 ES/ENII
4064 Hilltop Road
Tinker AFB OK 73145-2713
38 ES 2/10/2023 Page 2 of 62
FOR OFICIAL USE ONLY
1.0 SCOPE.
This SOO defines the requirement for the Contractor to engineer, furnish, install and test (EFI&T) the followings at Dyess AFB TX:
1. Install new FOC from Air Traffic Control Tower (ATCT), B4300 to ILS Glideslopes, Localizers and TACAN.
2. Install new FOC from OPS/Weather (B9001) to FMQ-19s, and the RLIM sensor at the lighting vault (B4101).
3. Install Air Force Flight Safety Agency (AFFSA) approved interface equipment at each location to transfer the circuits from copper to fiber.
2.0 REQUIREMENTS.
2.1 GENERAL REQUIREMENTS.
2.1.1 Safety Requirements.
The contractor shall remain in compliance with all Federal, State, county, and base security and safety laws, regulations, policies, and requirements.
2.1.2 Site Coordination.
The Contractor shall meet with the base safety officer immediately upon arrival on site for review of the specific safety requirements prior to installation.
2.1.2.1 Confined Space.
The Contractors and Sub-contractors entering spaces on Dyess AFB TX are responsible for the safety of their personnel and for their own permit space program as outlined in AFMAN 91-203. All confined space operations must be coordinated with the Base Safety Office prior to start of work. The primary Contractor is responsible for all Sub-contractor confined space operations.
2.1.2.2 Accident/Incident Reporting and Investigation.
The Contractor shall record and report all available facts relating to each instance of injury to either Contractor or Government personnel. Notification shall be provided to the 7 CS/SCXP Project Manager and the Base Safety Office unless otherwise stated in the SOO. The Contractor shall secure the scene of any accident and wreckage until released by the accident investigative authority through the Base POC. If the Government elects to conduct an investigation of the incident, the Contractor shall cooperate fully and assist the Government personnel until the investigation is completed.
2.1.2.3 Work Area(s).
At day’s end, the Contractor shall remove all debris and surplus materials from the workplace. Safety barriers shall be in place to protect unfinished work site at the end of the day. All open holes or trenches shall be completely enclosed by flexible orange construction safety fencing, or other safety barriers, at the end of the workday. Equipment and materials required to complete the work effort may remain on site as long as they are organized/stored in a manner that does not cause a safety hazard. The contractor shall coordinate with the 7 CS/SCXP to ensure that any locking manhole covers are put back in place at the end of each workday. For work performed in the flight line area: Under no circumstances shall any equipment or materials be left unattended within the designated Dyess AFB Controlled Movement Area (CMA). The Contractor’s designated on-site project manager shall always maintain two-way radio contact with the Dyess AFB Air Traffic Control Tower (ATCT)
38 ES 2/10/2023 Page 3 of 62 during construction work within the CMA. Two-way radios/LMRs will be provided by the government.
2.1.2.4 Traffic control.
In the event base vehicular traffic is to be disrupted by trenching or horizontal directional boring, the Contractor shall notify the 7 CS/SCXP PM NLT 10 calendar days in advance to inform base Security Forces and Emergency Services personnel of the planned disruptions.
2.1.2.5 Airfield Driving.
Any person operating a motor vehicle inside the airfield area on Dyess AFB shall coordinate with airfield management to obtain the required training/certifications IAW local procedures.
2.1.3 Security Requirements.
The Contractor shall process and provide a Site Visit Request Letter to 7 CS/SCXP within 5 calendar days after contract award. This letter shall identify the names (as shown on the driver’s license), driver’s license numbers and state of issue, and birth date of the personnel who will be performing work under this SOO. This information is required to grant access to the base. If required by the base, the Contractor shall provide identification badges for their employees. All Contractor personnel shall wear these badges while on duty on the Government site. The badges shall identify the individual, company name, and be clearly and distinctly marked as Contractor and be in accordance with base regulations.
2.1.3.1 Security Clearances.
Stated work and associated products shall be performed at the UNCLASSIFIED level.
However, some of this work may take place in secure areas where Contractor employees must be escorted at all times. The Contractor must coordinate access to secure areas at least five (5) calendar days ahead of time. It is the Government’s responsibility to provide escorts.
2.1.3.2 Country Clearances. “Reserved”.
2.1.3.3 Operational Security (OPSEC).
Network infrastructure drawings (MHDS, MH/HH locations, fiber paths, etc.) are on the 7 CS/SCXP Critical Information List and must be protected. The Contractor shall take appropriate measures to protect detailed information pertaining to the EFI&T effort, to include appropriate marking of documents as “Controlled Unclassified Information” (CUI),” and ensuring limited distribution of documents and schematics/drawings to only those individuals with a valid need to know. IAW AFI 10-701, OPSEC Considerations, the contractor shall develop an OPSEC plan to ensure the protection of CUI data either furnished by the government or produced by the contractor. The contractor’s OPSEC plan provided in the RFP shall be incorporated into the SOO in accordance with (IAW) CDRL A007.
2.1.4 Environmental Compliance.
The Contractor shall comply with the most stringent environmental federal, state, and local laws and regulations, and Air Force policies, instructions, and plans.
The federal Government is not exempt from compliance with environmental regulations.
The Contractors are responsible to know and follow all applicable Federal, State, Local and Air Force regulations for environmental protection, including waste disposal, sewer discharge, air emissions, and storm water requirements. The
38 ES 2/10/2023 Page 4 of 62 contractor shall maintain an awareness of changing environmental regulatory requirements to avoid environmental deficiencies for activities on Dyess AFB. The Prime Contractor shall ensure that their subcontractors (if any) comply with these specifications.
2.1.5 Permits.
The Contractor shall be responsible to coordinate, complete and process all permits required to complete the installation prior to any trenching, horizontal directional boring or modifications to a facility, maintenance hole (MH) or hand-hole (HH). For example:
Digging permit, AF Form 103 shall be submitted through BCE 14 calendar days in advance of digging activities. The Contractor is responsible for maintaining all markings and for ensuring AF Form 103 remains current.
Confine space entry permit, AF Form 1024 shall be coordinated through base safety office. The Contractor shall be prepared to provide proof of their Confined Space Training Program along with the AF Form 1024 to base safety.
Base Civil Engineering Work Clearance Request, AF Form 332 shall be submitted through BCE 14 calendar days in advance of planned work in any building/infrastructure.
The Contractor shall trench, excavate, and mark and barricade open trenches IAW OSHA Standards.
All utility markings, flags, etc. shall be maintained by the contractor after the responsible work center/shop identifies/locates them and ensure that the AF Form 103 remains current. The contractor shall take precautions to protect existing infrastructure. If a utility is severed or damaged due to neglect or if attributed to the fault of the contractor, then the contractor shall repair and return the utility back to the same condition it was in prior to the damage.
2.1.6 Integrated Process Team (IPT).
The Contractor shall chair a weekly IPT meeting that includes Contractor representatives, the Government Contracting Officer (CO), the CSI-B, the System Engineer(s), the Government Project Manager, and other base personnel as required.
The Contractor shall provide an agenda NLT 1 working day prior to the scheduled meetings. The Contractor shall provide worldwide “Meet Me” teleconference capability for the duration of the project. The purpose of the IPT meeting is to discuss project progress, problems being encountered, and other information necessary/beneficial to ensure success and timely completion of contract requirements. The Contractor shall record meeting minutes and distribute to the attendees NLT 1 working day after each meeting (CDRL A004).
2.1.7 Quality Assurance.
The Contractor shall provide Quality Assurance Support for the entire life of the project. The Contractor’s quality assurance evaluator shall assist the Government representative in performing random spot checks and system acceptance tests. The Contractor shall be responsible for identifying system and outside plant deficiencies and/or discrepancies throughout the life of the project. A weekly report (soft copy) shall be submitted indicating progress/status and listing any deficiencies/discrepancies found and actions to correct them (CDRL A003).
38 ES 2/10/2023 Page 5 of 62
2.1.8 Contractor Personnel.
2.1.8.1 Project Management.
The Contractor shall provide a Project Manager (PM) and alternate(s) responsible for contract performance and continuity. The Contractor shall identify the Project Manager’s or alternate's range of authority to act for the Contractor relating to daily contract operation.
2.1.8.2 Site Point of Contact (POC).
The Contractor shall designate the Contractor's on-site team leader and alternate(s) as the Site POC for individual projects in their Site Visit Request Letter. The Site POC or alternate(s) shall be on site during duty hours for the duration of the project, up to and until final acceptance by the Government PM and shall oversee all facets of the installation tasks. The Site POC shall be the interface for all work site communications with the Government, including quality, safety, and discrepancy matters.
2.1.8.3 Personnel Requirements.
The Project Manager, Site POC, and respective alternate(s) shall be able to read, write, speak, and understand English and shall be on site to coordinate permits, clearances, and receive shipments/material related to the task order.
2.1.8.4 Minimum Contractor Qualifications.
All work shall be performed by an experienced Telecommunications Contractor. The Contractor shall have a minimum of 3 years of experience in Telecommunications Systems installations.
2.1.8.5 System for Award Management (SAM).
The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for Installation via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address https://www.sam.gov SAM replaces the previous ECMRA application that was hosted on https://www.ecmra.mil.
Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30.
While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year. Contractors may direct questions to the SAM help desk.
2.1.9 Warranty
The contractor shall provide any OEM pass through warranty and standard commercial warranties applicable to the products being purchased at no cost. This shall apply to new, refurbished and remanufactured equipment.
The warranty shall be at a minimum One year or/and manufacturers standard warranty, whichever is longer. The warranty period shall start from the date of system and/or project acceptance. The Contractor shall provide written procedures and required information for warranty services at or prior to site acceptance.
38 ES 2/10/2023 Page 6 of 62
2.1.10 Manuals and Practices.
The Contractor shall provide the latest version of operation, installation, and maintenance manuals and practices/users guide for each system installed as provided by the original manufacturer with all new equipment.
2.2 SPECIFIC REQUIREMENTS.
The Contractor shall EFI&T new fiber optic cables (FOC) and associate Manhole Duct Bank System (MHDS) infrastructure required to provide service to the following locations at Dyess AFB, Texas.
1. New 12 Strands Single Mode (SM) FOC from Air Traffic Controller (ATC), B4300 to the following location:
TACAN (B3202).
ILS Runway 34 Localizer (B3019) (North end of runway).
ILS Runway 16 Glideslope (B3010) (North end of runway) ILS Runway 16 Localizer (B3238/ B3239) (South end of runway).
This building has two different number (outside and inside) ILS Runway 34 Glideslope (B3225/ B3235) (South end of runway).
This building has two different number (outside and inside)
2. New 12 Strands Single Mode (SM) FOC from OPS/Weather (B9001) to the following location:
FMQ-19 Primary (North, B3005).
FMQ-19 RLIM (Central, B4101).
FMQ-19 Discontinuity (South, B3220).
3. Provide and install all AFFSA approved fiber multiplex equipment and cables to connect the ATCALS facilities above to the Dial Central office (DCO) B7318 and the ATCT B4300.
4. Provide and install required fiber modem equipment in the Field Data Collection Unit (FDCU) of the FMQ-19 Weather equipment, and the RLIM, to connect to the Terminal Data Acquisition Unit (TDAU)weather equipment in B9001.
The Contractor shall provide all equipment, tools, materials, supplies, transportation, labor, supervision, management, and other incidentals necessary to meet the requirements as stated in this SOO. The Contractor shall comply with the current TIA telecommunication installation and testing commercial standard and base installation standards. All equipment, supplies, and materials provided shall be new and not refurbished. See Sketch-00 for a logical diagram of the requirement.
2.2.1 Backboards.
Any newly installed backboards shall be AF-standard 0.75”-thick plywood, with two coats of white, fire-retardant paint. If a new backboard is required in an ILS shelter except for the TACAN, they shall be attached to the shelter wall using Closed End Blind Rants© (Rivet Nut).
38 ES 2/10/2023 Page 7 of 62
2.2.2 Equipment Cabinets. “Reserved.”
2.2.2.1 Grounding and Bonding
All new and existing racks/cabinets housing equipment for this project, as well as all ladder rack/and cable tray shall be bonded and grounded to the Equipotential Ground Plane IAW TIA-607-B. All Equipment racks and cabinet rails shall be Telecommunications style rails that are unpainted and have drilled and tapped mounting holes IAW DISN Implementation Standards, Ch. 2.7.20 to 2.7.26. Equipment cabinets shall be capable of containing any standard equipment shelves for communications equipment per the current revision of EIA/ECA-310. The Contractor shall test any new or extended ground at the cabinet/rack and at the new grounding/bonding points. The government reserves the right to test and validate newly installed grounds to ensure they meet compliance.
2.2.2.2 Bushings
All penetrations into the rack/cabinet must be reamed, filed and have an installed bushing or grommet material. No exposed metal edges shall come in contact with telecommunication cabling.
2.2.3 Outside Plant Requirements.
2.2.3.1 Existing Maintenance Holes.
The Contractor shall be responsible for pumping out maintenance holes/handholes.
Water from maintenance holes/handholes shall be pumped into the storm drain system unless it is not available; then it may be pumped out onto the surrounding ground, as long as there is no impact to roads, driveways, or vehicle traffic. Mud and debris shall be disposed of IAW base requirements. If Contractor comes across a manhole with contaminated water, the Contractor shall coordinate with the environmental office in Base CE.
2.2.3.2 Measurements.
Any distances provided in this SOO are approximations and should NOT be used for ordering materials or determining duct lengths.
2.2.3.3 Underground Utilities Markings.
The Contractor shall coordinate with base agencies to ensure markings are placed over existing base infrastructure prior to digging or horizontal directional boring and shall take precautions to protect existing infrastructure. The Contractor is responsible for repair of any damage caused during installation when the infrastructure is clearly marked. The Contractor is responsible for maintaining all markings and for ensuring AF Form 103 (Dig Permit) remains current.
2.2.3.4 Outside Plant Multi-pair Cable. “Reserved”.
2.2.3.5 Closures for Cable Splicing in Maintenance Holes.
2.2.3.5.1 Fiber Optic Splices.
Intermediate cable splices shall be minimized and consist of fusion splices in a high quality re-enterable splice case. Only splice closures intended for underground applications shall be used in the underground system. The Contractor shall use standard re-enterable fiber splice closures. The closures shall have adequate strength to protect the splice and maintain cable shield electrical continuity in the below ground environment. The Government quality inspector shall have the
38 ES 2/10/2023 Page 8 of 62 opportunity to inspect the inside of the splice case before closure pressure testing and encapsulation is performed. A coil of 25 feet of cable shall be provided on each cable entering and leaving a splice case in a MH or HH.
2.2.3.5.2 Copper Splices. “Reserved”.
2.2.3.6 Splice Connectors.
All fiber splicing shall be performed in accordance with RUS Bulletin 1735F-401.
The Core Alignment fusion splice method shall be used for all splicing and terminations of fiber optic cable.
2.2.3.7 Labeling.
The Contractor shall label all equipment and cables they install, and cables identified for re-use in accordance with TIA-606-B and as directed by the 7 CS/SCXP.
2.2.3.7.1 Cable Tags.
All tags shall be permanently labeled, easily visible and corrosion resistant.
Install cable tags in all maintenance holes/hand-holes, cable vaults, pull boxes and building entrance terminal locations. When cables pass through a maintenance-hole, put a tag on the cable, approximately 2 feet from each duct entrance. Information on the cable tag shall identify cable by size, type, cable number and count. Tagging and labeling of new cables shall be IAW the following:
Fiber Optic Tags:
A36L8.3F
FO B241-B100, 1-12 +
FO B241-B101, 13-24 +
FO B241-B102, 25-36
Line One: A = Armored Sheath (otherwise leave blank) 36 = Fiber Count. L = Loose Tube Buffer or (T) Tight Tube Buffer. 8.3 = Single Mode. F = Filled core (otherwise leave blank).
Lines Two, three and four: 241-100 = From-To Building numbers. 1-12 = Cable/strand Count.
Copper Tags: “Reserved”.
2.2.3.7.2 Fiber Optic Distribution Panel (FODP) Marking.
Each FODP shall be stenciled/marked with black ink or paint, or adhesive backed decals in letters and numbers. The cover of all new fiber optic distributions (FODPs) shall be labeled to conform to the system used by local maintenance personnel to identify FODPs that terminate fiber. If the manufacturer has not identified the sequence in which ports on FODPs (pigtail modules) are counted, the Contractor shall provide designation labels/strips to identify the sequence in which they are counted.
Each splice tray shall be marked to identify the fiber count contained in the splice tray. The marking shall identify the FODP by number (building number), cable number, and count.
FODP-B3
38 ES 2/10/2023 Page 9 of 62
FO B3-B1038, 1-12
FO B3-B1400, 13-24
2.2.3.7.3 New Ducts.
New ducts shall be permanently labeled on the wall of each building/Maintenance Hole (MH)/Handhole (HH) indicating the connecting building/Maintenance hole/Handhole at the other end of the duct (for example, “To MH-306H”). The same information shall appear on the Contractor’s completed as-built-drawings.
2.2.3.8 Cable Terminations.
2.2.3.8.1 Fiber Optic Terminations.
Newly installed fiber optic cables shall be terminated on new fiber optic distribution panels using fusion spliced pigtails with LC (per UFC 3-580) connectors or LC fusion splice direct connectors. Distribution panels shall be designed for rack mounting in 19-in (48 cm) racks or wall mounted as required. Panels shall be sized accordingly to cable and method of termination. Fiber cassettes will be required for fiber terminations within new FOPPs.
2.2.3.8.2 Copper Cable Terminations. “Reserved”.
2.2.3.8.3 Grounding and Bonding.
In the Equipment room/Mechanical room in which the cable is to be terminated, there is either a telecommunications main grounding busbar (TMGB) or a telecommunications grounding busbar (TGB). If a grounding busbar doesn’t exist in the equipment room/mechanical room, then the Contractor shall provide it and bond it to the electrical service equipment (power) ground. The grounding conductor shall be tagged with a nonmetallic tag as close as practicable to the point of termination in a readable position. The information on the tag shall contain the following information “If this connector or wire is loose or must be removed, please call Base Communications Office” or some similar wording. Although it is not anticipated that any splicing will be required in a Maintenance hole, should there be some practical reason that a splice be made, the cable shield (armor) shall be bonded and continuous throughout the cable length. In addition, the splice case shall be bonded to the Maintenance hole bonding ribbon, if it exists. Grounding hardware such as corrosion resistant wire, bonding ribbon, clamps, ground rod, etc. necessary to properly bond/ground the cable in MHs/HHs shall be provided by the contractor. Reference TIA 607.
2.2.3.9 FOC Maintenance Loop.
The Contractor shall install a minimum of a 50-foot fiber optic cable maintenance loop at the first MH from the building, at each splice point MH location and at every third manhole (if possible or as directed by 7 CS/SCXP). The maintenance loop shall be properly labeled and securely supported by two cable hooks. Cable hooks are to be positioned so the highest one supports the underside of the top of the coil and the bottom hook supports the underside of the bottom of the coil. The maintenance loop shall have a cable tag. The same information shall appear on the Contractor’s completed as-built-drawings.
2.2.3.10 New Maintenance Holes (MH)/Hand-holes (HH)/Pull box (PB).
Pull Box installed under this Task Order shall have an American Association of State Highway and Transportation Officials (AASHTO) rating of H-20. Unless otherwise stated, PBs shall have minimum interior dimensions of 2’W x 2’L x 2’H (Width, Length, 38 ES 2/10/2023 Page 10 of 62
Height, the installer must coordinate/verify with 7 CS/SCXP for the final dimensions of the new PB).
Prefabricated PB are preferred. PB shall be installed so that they are reasonably level on a gravel bed of 6 inches to allow drainage of water from the walls. The gravel bed should extend 8 inches to 12 inches beyond the outer edges of the PB. PB covers shall be labeled with 1/8” raised letters stating “COMMUNICATIONS”.
2.2.3.10.1 Cable Racks and Cable Rack Supports.
Cable racks shall be installed in MH/HH as required - this includes new and existing MHs/HHs. Splices shall not be supported by the cables that enter each end of the splice case. The splices shall be supported by cable hooks under the splice case.
Telecommunications industry standard cable hooks of the appropriate length shall be provided to support cables and splice cases. The cable hooks shall be secured using cable rack locking clips. All cables shall be supported using racking clips, cable racks, and cable hooks.
2.2.3.11 Underground Conduit System.
The Contractor shall be responsible for any required trenching and/or boring necessary to lay the duct system. Contractor is also responsible for backfilling ditch lines and compaction of fill materials with appropriate compaction tools.
Provide a minimum of 12" cover of clean fill above the conduit. Backfill material shall be clean and free from all organic material, clay, marl or unstable materials, debris, lumps, or broken paving. No rocks or stones larger than 3 inches in diameter shall be allowed in backfill. Material for backfill may be material resulting from excavation if it meets the above requirements. Directional drilling will be used for major road crossings. Otherwise, crossing of paved surfaces may be performed by pavement cuts and resurfacing with appropriate matching road material. This does not prevent the Contractor from using directional drilling if it is more cost effective. Ducts will be appropriately protected when placed under paved surfaces.
2.2.3.11.1 Composition.
The ducts shall be corrosion resistant and 4-inch inside diameter (I.D.) round or metric equivalent. The ducts shall be made of EPC-40 Polyvinyl Chloride (PVC) (Schedule 40) IAW NEMA TC-2. For unique situations the ducts shall be EPC-80-PVC (Schedule 80) IAW NEMA TC-2, high density polyethylene (HDPE) SDR 11.5, Galvanized Iron Pipe (GIP) or “thickwall” stainless steel. Schedule 80 PVC shall be limited to risers. High density polyethylene (HDPE) SDR 11.5 shall be used when directional boring is used. GIP or stainless steel shall be used under taxiways and runways.
The ducts shall be appropriately labeled indicating the composition material. Ducts shall have a sleeve or bell end type coupling and shall be watertight when assembled.
In addition, the Contractor shall adhere to any additional Host Base/site specific requirements.
2.2.3.11.2 Installation.
Installation of underground conduits/ducts shall be IAW RUS Bulletin 1751F-643 and RUS Bulletin 1753F-151. Ducts installed beneath roads, sidewalks, parking areas, other paved surfaces or areas to be paved, etc. shall be installed a minimum of 36" below grade. Ducts installed beneath roads and parking areas shall be protected IAW Para. 2.2.3.11.10. It is understood that in some locations, especially at paved surface crossings, the Contractor may bore and substitute 4-inch I.D. HDPE conduit (Roll pipe, suitable for the application) for 4-inch PVC conduit. This substitution is acceptable. However, do not terminate the HDPE directly in a MH/HH but instead install 4-inch I.D. PVC stub out(s), a minimum of 5-10 feet out of the manhole and
38 ES 2/10/2023 Page 11 of 62 couple the HDPE to the PVC. Also, if HDPE is used, it shall be SIDR 11.5 so that the inside diameter of the HDPE will match the inside diameter of the PVC. All ducts not installed across roads, sidewalks, parking areas, or areas to be paved, etc. shall have a minimum of 36 inches ground cover, where possible. The Contractor shall provide other protective measures, concrete cap, etc., in those areas where the minimum ground cover cannot be achieved. Grading of ducts and drain slope of ducts shall be accomplished IAW BICSI “Outside Plant Design Reference Manual” (OSPDRM) and RUS Bulletin 1751F-643.
2.2.3.11.3 Bends and Sealing.
All bends between MHs/HHs shall be a minimum of ten times (10X) the diameter of the duct size (i.e, 4-inch duct = 40 inches) with the sum of bends in all directions not exceeding a total of 90 degrees where practical. Coordinate with 7 CS/SCXP if runs have bent that total more than 90 degrees is required. Ducts shall have bell ends and enter a MH/HH perpendicular to the surface of the wall through which it is entering. All ducts/inner-ducts entering MH/HH shall be sealed. Universal duct plugs or removable putty sealants may be used. Upon completion of conduit sections, a rigid test mandrel ¼” (6.4mm) smaller than the inside diameter of the conduit shall be pulled through two diagonally opposite ducts to ensure proper alignment.
In addition, all ducts shall be cleared of loose materials such as concrete, mud, dirt, stones, etc.
2.2.3.11.4 Utility Separation.
When communications ducts cross either power duct or buried power cable, maintain a minimum separation of 3 inches of concrete or 12 inches of well-tamped earth between the two or 12 inches of well tamped earth when parallel; for pipes (e.g., gas, water, oil) maintain 6 inches when crossing or 12 inches when parallel.
2.2.3.11.5 Spacers and Tracer Wire.
Along the length of the duct run, if the ducts are installed by trenching, spacers shall be placed at five (5) foot intervals. At least one duct or roll pipe shall have tracer wire or be otherwise locatable from the surface. All new tracer wire installed for this project needs to have a wire nut and label installed at all wire ends, and those wire ends secured but not connected to grounds. The tracer wire shall be exposed; free from the conduit and capped (insulated). The tracer shall be secured and routed to the maintenance hole or hand-hole neck to a point where maintenance personnel may access the wire without having to enter the maintenance hole/hand-hole and tagged with a label so indicating it as a “Duct Tracer Wire to xxx – Do Not Remove (where xxx is the other end of the wire).” Tracer wires shall not be connected to any grounding system. Tracer wire shall be pulled back from building entrances until it is underground to prevent lightning damage.
2.2.3.11.6 Warning Tape.
Cable warning tape shall be buried one (1) foot below the surface and shall follow the duct route. The tape shall be a minimum of three inches wide and orange in color with the appropriate warning message.
2.2.3.11.7 Entrance Conduits into Existing Maintenance Holes.
When new entrance conduits/ducts or sleeves are required, the Contractor shall bore and install the necessary holes and install the ducts or sleeves, if knockout doesn’t exist. Penetration shall not be in such a location through the wall as to block use of existing ducts in the maintenance hole. New ducts will be a minimum of 18 inches from either the floor or ceiling of the maintenance hole if practical. Ducts shall
38 ES 2/10/2023 Page 12 of 62 have bell ends and enter the maintenance hole perpendicular to the surface of the wall through which it is entering and shall be installed flush with the interior wall of the maintenance hole. Ducts and openings around ducts shall be sealed to prevent moisture from entering the maintenance holes.
2.2.3.11.8 Pull Boxes/NEMA 4 Enclosures. “Reserved”.
2.2.3.11.9 Excavation/Building Penetrations.
All wall penetrations, including inside buildings, shall be restored to meet the required base fire ratings.
2.2.3.11.10 Conduit Protection.
The Contactor shall install the appropriate physical protection required [(concrete encasement, steel tube (casing)] for buried PVC conduits or HDPE Roll pipe, consistent with commonly accepted telecommunications industry practices relative to the task and to the environment in which they are installed and the loads (H-5, H- 10, H-20, railroads, flight line, etc.) to which they are expected to be exposed.
Type of protection may be dependent upon the specific application and shall be IAW applicable federal, state or local (Dyess AFB Civil Engineering construction requirements) procedures. However, at a minimum, nonmetallic conduits shall be encased in concrete of minimum 3000 lb. /in2 compressive strength where vehicular traffic is above the pathway. The encasement shall be concrete of a wet type of mix and shall be placed in such a manner as to ensure the concrete completely surrounds all conduits and no air voids are trapped in the mix a bend or sweep is placed in PVC nonmetallic duct bank between maintenance holes, the duct bank must be encased in concrete with a minimum compressive strength of 3000 pounds per square inch (psi).
2.2.3.11.11 Pull Tape.
All newly installed ducts left vacant shall be provided with a pull tape with a waterproof, corrosion resistant, pre-lubricated flat woven polyester pull tape with sequential footage markings, (1250 lb. pulling strength) for future cable installations. The pull tape shall extend into the maintenance holes/handholes and be secured to a cable rack or pulling iron, etc.
2.2.4 New Outside Plant Installation.
This section describes the underground maintenance hole/conduit system, flexible geotextile multiple cell fabric inner-duct and copper and fiber optic cable installation requirements. The Contractor shall design and install Customer-Owned “Outside Plant Telecommunications Infrastructure” in according with TIA-758-B. Each cable installation shall be coordinated with the 7 CS/SCXP so that the impact on the building users is properly coordinated. The sequence of installation is at the Contractor’s discretion.
See Project Sketches for reference and estimated distances of existing and proposed infrastructure and cables routes. This is only a proposed solution. The Contractor is free to make any recommendations pertaining to the accomplishment of this requirement in their proposal.
The Contractor shall install underground outside plant infrastructure as described below.
38 ES 2/10/2023 Page 13 of 62
2.2.4.1 New Infrastructure Installation.
The contractor shall install the following new infrastructure. All new locations and distances are approximate. (See Project Sketches for additional information).
2.2.4.1.1 New Manholes/Hand-holes/Pull Box (PB).
Install three new PB as shown on Sketch-4, 11 and 20.
Note: Approximate locations are shown on the project sketches. Coordinate with 7 CS/SCXP for final maintenance-hole placement and numbering scheme.
2.2.4.1.2 New Duct bank Infrastructure.
Provide and install one (1), 4-inch conduit as shown at the following table.
Distances (Dist.) are approximate and shown in feet.
Install the following 1, 4” conduit
From To Dist. Sketch Comment
MH 6 New PB-1 30’ 11 & 20 N/A New PB-1 New PB-2 70’ 11 & 20 N/A New PB-2 Existing PB 11 & 20 There in an existing PB at the exterior wall of B4101. Install the new conduit up to the existing PB.
MH WT35 New PB-3 75 4 N/A New PB-3 FMQ-19 (Primary, B3005) 30 4 & 13 Install the new conduit up to the concrete base of the FMQ-19. Install a new weather cap on the open end of the new conduit.
New PB-3 N-End Glideslope (B3010)
50 4 & 14 There in an existing PB/HH at the exterior wall of B3010. Install the new conduit up to the existing PB.
2.2.4.1.3 New Metallic Conduit Infrastructure
B9001 (AMOPS/Weather), install one new 2-Inch electric metal tube (EMT) conduits over the false ceiling as shown at the following table. The exact placement/route of the new conduit will be coordinated with 7 CS/SCXP during implementation.
Distances are approximate and shown in feet.
From To Distance Sketch Comment Building entry conduit Rm. Comm. Rm. 100’ 22 N/A
2.2.4.1.4 New Geotextile Fabric Inner-duct (or Innerduct).
Each new 3-cell shall have a separate thread color and one shall be detectable.
Distances (Dist.) are approximate and shown in feet.
38 ES 2/10/2023 Page 14 of 62
Install the following Geotextile Fabric Inner-ducts (Equivalent to Maxcell) From To Quantity Dist. Sketch Comment MH20 MH18 1-Pack (3) 130’ 1 New innerduct will be installed inside a conduit with existing cable (Cable Override)
MH20 MH18 1-Pack (3) 170’ 1 Same MH18 MH16 1-Pack (3) 170’ 1 Same MH16 MH15 1-Pack (3) 210’ 1 Same MH15 MH14 1-Pack (3) 300’ 1 Same MH14 MH13 1-Pack (3) 220’ 1 Same MH13 MH12 1-Pack (3) 270’ 1, 2 Same MH12 MH11 1-Pack (3) 195’ 2 Same MH11 MH10 1-Pack (3) 185’ 1 Same
MH WT13 B3202 (TACAN) 1-Pack (3) 500’ 7, 10 Same MH Wind 02 FMQ-19
(Discontinuity, South (B3220))
1-Pack (3) 350’ 12 Install new 3, fabric innerduct inside existing conduit.
MH WT01 MH WT02 3-Pack (9) 1050’ 2 New Innerduct will be installed inside vacant 4-inch conduit
MH WT02 MH WT03 3-Pack (9) 290’ 2, 3 Same MH WT03 MH WT04 3-Pack (9) 350’ 3 Same MH WT04 MH WT05 3-Pack (9) 195’ 3 Same MH WT05 MH WT06 3-Pack (9) 600’ 3 Same MH WT06 MH WT08 3-Pack (9) 425’ 3 Same MH WT08 MH WT37 3-Pack (9) 850’ 3 Same MH WT37 MH WT36 3-Pack (9) 850’ 3, 4 Same MH WT36 MH WT35 3-Pack (9) 850’ 4 Same MH WT35 16GS (North)
B3010 3-Pack (9) 200’ Same
MH WT35 MH WT34 3-Pack (9) 820’ 4, 5 Same MH WT34 MH WT33 3-Pack (9) 820’ 5 Same MH WT33 MH WT32 3-Pack (9) 820’ 5 Same MH WT32 MH WT31 3-Pack (9) 820’ 5 Same MH WT31 34Loc (N) B3019 3-Pack (9) 200’ 5 Same MH WT08 MH WT09 3-Pack (9) 880’ 3, 6 Same MH WT09 MH WT10 3-Pack (9) 880’ 6 Same MH WT10 MH WT11 3-Pack (9) 850’ 6 Same MH WT11 MH WT12 3-Pack (9) 820’ 6 Same MH WT12 MH WT13 3-Pack (9) 500’ 6, 7 Same MH WT13 MH WT14 3-Pack (9) 850’ 7 Same MH WT14 MH WT15 3-Pack (9) 820’ 7 Same MH WT15 MH WT16 3-Pack (9) 820’ 7 Same MH WT16 MH WT17 3-Pack (9) 820’ 7, 8 Same MH WT17 MH WT18 3-Pack (9) 750’ 8 Same MH WT18 MH WT19 3-Pack (9) 850’ 8 Same MH WT19 MH Wind01 3-Pack (9) 280’ 8 Same MH Wind01 34GS(S)
B3235/B3225 3-Pack (9) 250’ 8 Same
MH WT19 MH WT20 3-Pack (9) 850’ 8 Same MH WT20 MH WT21 3-Pack (9) 700’ 8, 9 Same MH WT21 MH WT22 3-Pack (9) 750’ 9 Same MH WT22 MH WT23 3-Pack (9) 630’ 9 Same MH WT23 S-End Localizer
(B3239/B3238) 3-Pack (9)
150’ 9 Same
38 ES 2/10/2023 Page 15 of 62
2.2.4.2 New Fiber Optic Cable Installation
The Contractor shall install single mode (SM), loose buffer tube, water blocked, outside plant (OSP) cable suitable for underground applications. The intent is to install the cable in one continuous length, to the extent that it is practical. The cable shall meet RUS 7 CFR 1755.900 criteria; shall comply with industry standards with regard to manufacturers’ cable marking, jacket, rip cords, water blocking, fiber color coding, jacketing materials, etc. In addition, the fibers shall comply with industry standards with regard to mode field diameter, core cladding concentricity, attenuation, and dispersion characteristics at 1310 nm and 1550nm.
All fiber optic cables shall be installed in new or existing geotextile innerduct/innerduct. Distances are approximate and shown in feet.
38 ES 2/10/2023 Page 16 of 62
Insert new FOC as shown at the following table
From To Count Dist. Sketch
MH22 B4300 (FODP) 60 200’ 1, 21
MH22 MH21 60 430’ 1
MH21 MH20 60 330’ 1
MH20 MH18 60 130’ 1
MH18 MH16 60 170’ 1
MH16 MH15 60 210’ 1
MH15 MH14 60 300’ 1
MH14 MH13 60 220’ 1
MH13 MH12 60 270’ 1, 2
MH12 MH11 60 195’ 2
MH11 MH10 60 185’ 2
MH10 MH9 60 250’ 2
MH9 MH8 60 195’ 2
MH8 MH7 60 290’ 2
MH7 MH6 60 25’ 2
MH6 MH WT01 60 175’ 2
MH WT01 MH WT02 60 1050’ 2
MH WT02 MH WT03 60 290’ 2, 3
MH WT04 MH WT05 60 195’ 3
MH WT05 MH WT06 60 600’ 3
MH WT06 MH WT08 60 425’ 3
MH WT08 Splice
MH WT08 MH WT37 24 850’ 3
MH WT37 MH WT36 24 850’ 3, 4
MH WT36 MH WT35 24 850’ 4
MH WT35 Splice - - 4
MH WT35 North End GS (B3010) 12 125’ 4, 14
MH WT35 MH WT34 12 820’ 4, 5
MH WT34 MH WT33 12 820’ 5
MH WT33 MH WT32 12 820’ 5
MH WT32 MH WT31 12 820’ 5
MH WT31 North End Localizer (B3019) 12 200’ 5, 15
MH WT08 MH WT09 36 880’ 3, 6
MH WT09 MH WT10 36 880’ 6
MH WT10 MH WT11 36 850’ 6
MH WT11 MH WT12 36 820’ 6
MH WT12 MH WT13 36 500’ 6, 7
MH WT13 Splice
MH WT13 B3202 (TACAN) 12 500’ 7, 10, 16
MH WT13 MH WT14 24 850’ 7, 10
MH WT14 MH WT15 24 820’ 7
MH WT15 MH WT16 24 820’ 7
MH WT16 MH WT17 24 820’ 7, 8
38 ES 2/10/2023 Page 17 of 62
From To Count Dist. Sketch
MH WT17 MH WT18 24 750’ 8
MH WT18 MH WT19 24 850’ 8
MH WT19 Splice - - 8
MH WT19 MH Wind01 12 280’ 8 MH Wind01 S-End GS(B3235/B3225) 12 250’ 8, 18
MH WT19 MH WT20 12 850’ 8, 9
MH WT20 MH WT21 12 700’ 9
MH WT21 MH WT22 12 750’ 9
MH WT22 MH WT23 12 630’ 9
MH WT23 S-End Localizer(B3239/B3238) 12 150’ 9, 19 B9001(Weather) MH4 36 100’ 11
MH4 MH5 36 275’ 11
MH5 MH6 36 275’ 2, 11
MH6 Splice
2, 11
MH6 New PB-1 12 30’ 11
New PB-1 New PB-2 12 70’ 11
New PB-2 Exterior PB (B4001), FMQ-19 (Central), then inside FMQ-19
12 30’ 20, 11
MH6 MH WT1 24 175’ 2, 11
MH WT1 MH WT2 24 1050’ 2, 11
MH WT2 MH WT3 24 290’ 2, 3
MH WT3 MH WT4 24 350’ 3
MH WT4 MH WT5 24 195’ 3
MH WT5 MH WT6 24 600’ 3
MH WT6 MH WT8 24 425’ 3
MH WT8 Splice - - 3
MH WT8 MH WT37 12 850’ 3
MH WT37 MH WT36 12 850’ 3, 4
MH WT36 MH WT35 12 850’ 4
MH WT35 FMQ-19 Primary (B3010) 12 150’ 4, 14
MH WT8 MH WT9 12 880’ 3, 6
MH WT9 MH WT10 12 880’ 6
MH WT10 MH WT11 12 850’ 6
MH WT11 MH WT12 12 820’ 6
MH WT12 MH WT13 12 500’ 6, 7
MH WT13 MH WT14 12 850’ 7
MH WT14 MH WT15 12 820’ 7
MH WT15 MH WT16 12 820’ 7
MH WT16 MH WT17 12 820’ 7, 8
MH WT17 MH WT18 12 750’ 8
MH WT18 MH WT19 12 850’ 8
MH WT19 MH Wind01 12 280’ 8
MH Wind01 MH Wind02 12 575’ 8 MH Wind02 FMQ-19 Discontinuity, South
(B3220) 12 350’ 12, 17
38 ES 2/10/2023 Page 18 of 62
Note: South End GS(B3225/B3235) and South End Localizer(B3238/B3239) has different number inside and outside of the buildings.
2.2.4.2.1 FODP and FOC termination at the ATC Tower (B4300), AMOPS/Weather (B9001) and ILS locations.
B3005. FMQ-19 Primary (North): New FOC will terminate at a new FODP. For additional information see Sketch-13.
B3010. (North End Glideslope): New FOC will be installed by installing a Back- Board (BB), next to the existing BB. The size of the new BB will be determined by the installer and approved by 7 CS/SCX. For additional information see Sketch-14.
B3019. (North End Localizer): New FOC will be installed by installing a Back-Board (BB), next to the existing BB. The size of the new BB will be determined by the installer and approved by 7 CS/SCX. For additional information see Sketch-15.
B3202. (TACAN): New FOC will be installed by installing a Back-Board (BB), next to the existing BB. The size of the new BB will be determined by the installer and approved by 7 CS/SCX. For additional information see Sketch-16.
B3220. FMQ-19 Discontinuity (South): New FOC will terminate at a new FODP. For additional information see Sketch-17.
B3235/B3225. 34 Glideslope (South End of Runway): New FOC will be installed by installing a Back-Board (BB), next to the existing BB. The size of the new BB will be determined by the installer and approved by 7 CS/SCX. For additional information see Sketch-18. This location has two different number inside/outside the building, the installer must verify the correct building number with 7 CS/SCXP.
B3239/B3228.16 Localizer (South End of Runway): New FOC will be installed by installing a Back-Board (BB), next to the existing BB. The size of the new BB will be determined by the installer and approved by 7 CS/SCX. For additional information see Sketch-19. This location has two different number inside/outside the building, the installer must verify the correct building number with 7 CS/SCXP.
B4101. Lighting Vault, FMQ-19 RLIM: New FOC will terminated at a new FODP inside the existing pull-box (outside wall of B4101). For additional information see Sketc- 20.
B4300. ATCT: New FOC will terminate at a new FODP on a new backboard in Rm. G103.
For additional information see Sketc-21.
B9001. AMOPS/Weather: New FOC will terminated at a new FODP on the existing backboard in the Communications Room. For additional information see Sketc-22.
2.2.4.3 Copper Telephone Cable Installation. “Reserved”.
2.2.5 Interface Equipment Requirements.
The contractor shall EFI&T all TC Communications Inc fiber multiplexer equipment and required cables to connect the ATCALS facilities (Glideslopes, Localizers and TACAN) to the Control Tower and the Weather Equipment (FMQ-19) to Base Weather Ops
38 ES 2/10/2023 Page 19 of 62 over fiber optic cable. In addition, contractor shall provide equipment to extend the phone lines from the DCO to the ATCT and cross-connect them to the interface equipment going to the ATCALS shelters. See the “TC Communications: ILS TC8800/TC8801/TC8805 Navaids Solution” for a system diagram at the end of the Appendix. Cutover of circuits shall be coordinated with the 7 CS/SCXP and 7 OSS/RAWS so that the impact on the Runway operations is properly coordinated. The sequence of installation is at the Contractor’s discretion.
2.2.5.1 Dial Central Office (DCO) B7318
Install the equipment in Table 1 in the 2nd fiber distribution rack in the DCO.
Install a connectorized RJ-11 to RJ21 patch panel (such as ICMPP024T4) above the equipment. Install connectorized 110 or Krone block on the Main Distribution Frame (MDF) and tie back to the RJ-11 patch panel. Male Cross connects to the telephone lines in the table as the circuits are cutover.
Provide two fiber jumpers from the TC Communications fiber connectors to the FODP for the two diverse paths as shown in Sketch 23.
2.2.5.2 Air Traffic Control Tower (ATCT) B4300
Extend the FOC installed in Para. 2.2.4.2.1 above to G106 of the ATCT. Install a 36 pair patch panel on the backboard and a 36 pair FODP in the 8th Floor equipment room at the bottom of the SELEX RCSU cabinet. Install 72 strand indoor Plenum rated cable between the two FODPs. Install fiber jumpers to the two FODP going to B6015 and B7320 as shown in Sketch 23.
Install the equipment listed in Table 1 for the ATCT, in the 8th Floor Equipment Room in the RCSU cabinet. Provide Cross connect RJ-11 cables from shelf one to shelf two for the telephone lines in the table as the circuits are cutover. See the “TC Communications: ILS TC8800/TC8801/TC8805 Navaids Solution” for a system diagram at the end of the Appendix.
As the shelters are cut-over install RJ-11 cables from the second shelf’s 600ohm audio cards to the SELEX RCSU unit’s status lines. Connection is made on the back of the RCSU to terminal blocks on the modem cards.
2.2.5.3 34 Localizer Shelter B3019 and 34 Glideslope B3225
Install equipment listed in Table 1 of the Appendix on the backboard. All equipment on the backboard can be temporarily removed until cutover. The Digi PortServer TS will be the only remaining item that is currently installed.
Install equipment IAW the TC Communications s Drawings In Appendix. Install all Fiber jumpers required and connect phone lines and status lines.
2.2.5.4 TACAN Shelter B3202
Install equipment listed in Table 1 of the Appendix on the backboard. Install equipment IAW the TC Communications s Drawings in the Appendix. Install all Fiber jumpers required and connect phone lines and status line.
2.2.5.5 16 Localizer Shelter B3238 and 16 Glideslope B3010
Install equipment listed in Table 1 of the Appendix on the backboard. All equipment on the backboard can be temporarily removed until cutover. The Digi
38 ES 2/10/2023 Page 20 of 62
PortServer TS will be the only remaining item that is currently installed.
Install equipment IAW the TC Communications s Drawings in the Appendix. Install all Fiber jumpers required and connect phone lines and status line.
2.2.5.6 FMQ-19 Primary Sensor B3005.
Install liquid-tight conduct from the bottom of the FODP into the fiber entry Knockout in the FDCU housing. Contractor shall purchase the conversion kit (S74822 or latest version) from the manufacturer for the conversion from copper to fiber. See Sketches 24 to 29 for a weather systems overview. The Contractor shall install the following Coastal Environmental Industries equipment within the Sensor Equipment Enclosure:
One (1) 1205130229 Line Driver, FO, SM, 1310nm, 115 V
One (1) 1205130272 Cable, IFS FOM to SSEM
Install two jumper cables from the FODP through the Liquid-tight conduit to the FDCU (one active and one spare). Base personnel will install the Line Driver within the Sensor Equipment Enclosure and connect the cable from the Line Driver to the SSEM module.
2.2.5.7 FMQ-19 Discontinuity Sensor B3220.
Install liquid-tight conduct from the bottom of the FODP into the fiber entry Knockout in the FDCU housing. Contractor shall purchase the conversion kit (S74822 or latest version) from the manufacturer for the conversion from copper to fiber. The Contractor shall install the following Coastal Environmental Industries equipment within the FDCU Sensor Equipment Enclosure:
One (1)1205130229 Line Driver, FO, SM, 1310nm, 115 V
One (1)1205130272 Cable, IFS FOM to SSEM
Install two jumper cables from the FODP through the Liquid-tight conduit to the FDCU (one active and one spare). Base personnel will install the Line Driver within the Sensor Equipment Enclosure and connect the cable from the Line Driver to the SSEM module.
2.2.5.8 FMQ-19 Runway Light Intensity Monitor (RLIM) at Lighting Vault, B4101
Contractor shall purchase the conversion kit (S78105 or latest version) from the manufacturer for the conversion from copper to fiber. The Contractor shall install the following Coastal Environmental Industries equipment within the RLIM Equipment Enclosure:
One (1)1205130229 Line Driver, FO, SM, 1310nm, 115 V (Part of S78105 Kit)
One (1)1205130272 Cable, IFS FOM to SSEM (Part of S78105 Kit)
The Contractor shall install a fiber optic jumper cable and duct from the RLIM Equipment Enclosure to the FODP installed in SOO Para. 2.2.4.2.1 above.
The Contractor shall connect the cable from the Line Driver to the RLIM module.
2.2.5.9 Base Ops/Wax B9001
Contractor shall purchase the conversion kit (S74842 or latest version) from the manufacturer for the conversion from copper to fiber. The Contractor shall install the following Coastal Environmental Industries equipment within the TDAU in the Communications/Computer Room (See Sketches 24 to 29:
38 ES 2/10/2023 Page 21 of 62
One (1)1205130188 Card Rack, FO Line Driver, 115V Power Supply (Part of S74842).
Three (3)1205130231 Line Driver, FO, SM, 1310nm, Rack Card (Part of Kit S74822 and S78105)
The Contractor shall install three (3) fiber optic jumper cables to connect from the three Line Drivers to the new FODP (to the Primary Sensor, Discontinuity Sensor and RLIM) installed in SOO Para. 2.2.4.2.1 above.
The Contractor shall refer to Sketches 16 and 17 and provide and install RJ-45 CAT 6 patch cables from the Line Drivers to the Cross Connect Panel at the back of the TDAU cabinet. Existing cables may be reused if in good condition.
2.2.6 Project Residue.
All residue from this project shall be disposed of off base and in accordance with Federal, State, local and base environmental laws, and regulations.