Attachment 4 Schedule of Items.pdf
PDF 52 KB Posted
- Solicitation number
- 12441926R0002
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a Schedule of Items for the Fort Simcoe Water System Renovation project dated August 5, 2024. The document outlines 24 base contract line items and 3 optional items required for the comprehensive renovation of the water system infrastructure.
Base items include mobilization, erosion controls, utility locates, and construction signage. The primary work involves constructing approximately 8,798 linear feet of 6-inch PVC C-900 waterline using open excavation or approved alternative methods, with all associated trench excavation, pipe installation, backfill, fittings, thrust blocks, disinfection, and testing included. Water service replacements are required for 18 buildings including duplexes, Nation Hall, Student Services, Student Health, Education, Gym, Maintenance, Brick Trade, WPO, Dental Storage, Auto, Fuel, Heavy Equipment, Trucking, Warehouse, Admin, and Carpentry facilities. Additional base items specify 7 fire hydrants, 37 six-inch gate valves with restrained joints, 4 eight-inch gate valves with restrained joints, 9 three-inch and 2 four-inch backflow prevention valves for irrigation, pavement restoration (2,450 square feet), sidewalk replacement (80 square feet), asbestos cement pipe removal and disposal, instrumentation upgrades for three wells and the reservoir, 2 water sampling stations, upgrades to Wells 1, 2, and 3, reservoir improvements, fill station improvements, and a 3 percent TERO fee. Optional items include an additional 828 linear feet of 6-inch PVC C-900 waterline, 1 six-inch gate valve with restrained joints, and 81 square feet of pavement restoration. Unit prices and total costs are to be completed by bidders.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation Questions and Answers 04-14-2026.docx | DOCX document | |
| 12441926R0002 Amendment 0004.pdf | ||
| 12441926R0002 Amendment 0003.pdf | ||
| 12441926R0002 Amendment 0002.pdf | ||
| Solicitation Questions and Answers.docx | DOCX document | |
| Amendment 1.rtf | RTF text file | |
| UPDATED FTS WaterSystemReno Specs 20260327.pdf | ||
| Attachment 2 Drawings.pdf | ||
| Attachment 3 Specifications.pdf | ||
| Attachment 5 Davis-Bacon Wage Determinations.pdf | ||
| Attachment 1 - Solicitation Terms and Conditions.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Fort Simcoe Water System Renovation Schedule of Items
8/5/2024 Item No Description Pay Unit
Pay Quantity and (Estimated Quantity) Unit Price Total
Base Items
0001 Mobilization LS 1
0002 Erosion Controls LS 1
0003 Utility Locates LS 1
0004 Construction Signage LS 1
Construct 6" PVC C-900 Waterline - Open Excavation or other approved method (Includes trench excavation, pipe, backfill, fittings, thrust blocks, disinfection and testing, and other miscellaneous work associated with installation and interconnection of new water main with existing and new lines.)
LS 1 (8798 LF)
Water Service Replacement - Building (All Sizes)Includes connection to water main, indicated pipe sizes, corporation stops & boxes, connection to existing building service entrance, and when indicated curb valves & boxes. 2 duplexes, Nation Hall, Student Services, Student Health, Education, Gym, Maintenance, Brick Trade, WPO, Dental Storage, Auto, Fuel Bldg, Heavy Equipment, Trucking, Warehouse, Admin, Carpentry
EA 18
Pavement Restoration - Quantity is based upon open excavation pipe installation.
LS 1 (2450 SF)
Sidewalk Replacement - Quantity is based upon open excavation pipe installation.
LS 1 (80 SF)
Fire Hydrant - Includes connection to main, pipe, joints, gate valve, valve box, hydrant.
EA 7
6" Gate Valve with Restrained Joint - Valves for hydrants are included in fire hydrant assembly item.
EA 37
Backflow Prevention Valve for Irrigation - up to 3-Inch (Includes all pipe, elbows, restraints and appurtenances)
EA 9
Backflow Prevention Valve for Irrigation - 4-Inch (Includes all pipe, elbows, restraints and appurtenances)
EA 2
0015 Asbestos Cement Pipe Removal and Disposal LS 1
Instrumentation Upgrades - Includes Wells 1,2,3, Reservoir, and Maintenance Bldg.
LS 1
Water Sampling Stations - Includes connection to main, curb valve & box,indicated fittings, riser, vent, housing, and tap.
EA 2
0018 Well 1 Upgrades LS 1
0019 Well 2 Upgrades LS 1
0020 Well 3 Upgrades LS 1
0021 Reservoir Improvements LS 1
Fill Station Improvements - Includes replacement of valves and valve boxes, connection of existing, fire fill to new water main, and installation of discharge screen.
LS 1
0023 8" Gate Valve With Restrained Joints EA 4
0024 TERO Fee (3% of Subtotal) LS 1
TOTAL BASE ITEMS:
Optional Items
1001 Construct 6" PVC C-900 Waterline (Includes trench excavation, backfill, fittings, thrust blocks, disinfetion and testing)
LS 1 (828 LF)
1002 6" Gate Valve With Restrained Joints EA 1 1003 Pavement Restoration LS 1 (81 SF)
TOTAL OPTIONAL ITEMS:
TOTAL BASE + OPTIONAL ITEMS:
Schedule of Items