Replace Air Handler Units, Azalea Dining Hall, B6960 at Keesler AFB Federal contract opportunity
Solicitation number
FA301025R0025
Issued by
Department of the Air Force Air Education and Training Command

About this file

This document is a Material Submittals Schedule for a federal construction project to replace Air Handler Units at Azalea Dining Hall, Building 6960 at Keesler Air Force Base. The project is valued between $500,000 and $1,000,000 and is set aside exclusively for Service-Disabled Veteran-Owned Small Businesses under solicitation FA301025R0025.

The detailed schedule outlines 25 specific material submittal requirements with varied submission deadlines, including hazardous material documentation, warranties, technical drawings, and compliance certificates. Key submission timelines include 5 days prior to Phase 2 start, 10 days following Notice to Proceed, and end of contract dates for final documentation. A mandatory site visit is scheduled for 14 August 2025 at 08:00 AM CDT, requiring participants to bring valid identification, vehicle registration, and proof of insurance. The solicitation notes that funds are not currently available, and the government reserves the right to cancel the solicitation at any time without reimbursing offeror costs.

View the file

Other files for this federal contract opportunity

Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Material Submittals Schedule

Project Number:
241052Project Title:
MAHG241052 Repair AHU's Azalea Dining Hall B6960Solicitation / Contract Number:

FA301025R0025

Line Number(To be completed by Project Engineer)(To be completed by Contract Administrator)
Number of Copies Required (if not electronically submitted)Remarks
Item or Description of Item, Contract Reference, Type of SubmittalCertificate of ComplianceShop DrawingsSamplesColor SelectionManufacturer's RecommendationWarranty-Manufacturer and/or WorkmanshipCatalog DataOperating InstructionsSchedules, Listings, Reports, PlansTechnical DataTest ReportsField ReportsRequired Submission DateDate Received in ContractingDate to Civil EngineeringReturn Suspense DateSubmittal NumbersDate Contractor
NotifiedContractor ResubmittalFinal Approval
ApprovedDisapproved
1HazMat Questionnaire335 Days Prior to start of Phase 2
2HazMat MSDS335 Days Prior to start of Phase 2
3HazMat Reporting Entry Form335 Days Prior to start of Phase 2Submit Final Quantities
4HazMat Reporting entry Form33End of Contract
5Recycling and Landfill Report33End of Contract
6Warranty (Manufacture's)33End of Contract
71-Year Warranty (Contractor's)33End of Contract
21Section 23 05 93 TAB33314 Days Following HVAC complete
22Section 23 09 00 Control3333310 Days Following EMS Control complete
23Section 23 30 00 Air Distribution System33310 Days Prior to start of Phase 2
24SECTION 26 20 00
INTERIOR DISTRIBUTION SYSTEM119 Days prior to start of Phase 2
25Shop Drawings, Equipment Data Sheet (Cutsheet)3Prior to start of Phase 2
8Section 061000-Rough Carpentry11110 Days Following NTP
9Section 062000-Finish Carpentry General111110 Days Following NTP
10Section 064020-Interior Architectural Woodwork111110 Days Following NTP
10Section 082000-Wood Doors111110 Days Following NTP
11Section 081113-Steel Frames1111110 Days Following NTP
12Section 082000-Wood Doors1111110 Days Following NTP
13Section 084010-Aluminum Doors and Frames1111110 Days Following NTP
11Section 079200-Joint Sealants111110 Days Following NTP
15Section 093013-Tile and Grout1111110 Days Following NTP
16Section 093050-Tile Setting Materials and Accessories1111110 Days Following NTP
1210 Days Following NTP
12111110 Days Following NTP
131111110 Days Following NTP
14Section 099100-Paint111110 Days Following NTP
15111110 Days Following NTP
20Section 099323-Stains and Transparent Finishes1111110 Days Following NTP
14
15
16
17
18
19
20
21
22
23
24
25

&L&"Verdana,Bold"&12Schedule of Material Submittals&C&12Print on Legal size paper ( 8 x 14 ).

&R&P of &N Enter the due date from the Contractor (MM/DD/YY) Enter the date received from the Contractor. (MM/DD/YY) Enter the date submittal was given to CE for review. (MM/DD/YY) Enter the date the submittal is due back from CE

(MM/DD/YY)

Enter the Submittal Number Enter date the Contractor was notified of submittal approval

(MM/DD/YY)

Enter date the Contractor was notified of submittal disapproval

(MM/DD/YY)

Enter Resubmittal Number Enter the submittal final approval date

(MM/DD/YY)

File details come from the government source that posted it. Updated .