Attachment 4 - MAHG211009 - Appendix C - MSS .xlsx

XLSX spreadsheet 43 KB Posted

Attached to
FA301024R0008 Replace AHUs & VAVs in NPS Dorms Ph1
Solicitation number
MAHG211009
Issued by

About this file

This document is an attachment related to a federal contract opportunity for replacing Air Handling Units (AHUs) and Variable Air Volume (VAV) units in dormitory buildings at Keesler Air Force Base. The attachment contains a detailed schedule of material submittals required for the project, including items such as shop drawings, product data, samples, test reports, operations and maintenance data, and closeout submittals across mechanical, environmental, and general categories. The required submission dates, review/approval process, and remarks are provided for each submittal item.

The related federal contract opportunity has a solicitation number of MAHG211009 and a total estimated value between $5,000,000 and $10,000,000. It is a HUBZone set-aside acquisition issued by the Department of the Air Force Air Education and Training Command. The project involves replacing AHUs and VAVs in Phase 1 of the dormitory replacement work at Keesler AFB in Mississippi. An organized site visit is scheduled for August 1, 2024, and proposal preparation instructions are provided in Sections L and M of the solicitation.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MSS GENERAL

STATUS0 complete of 22 for a total percentage complete of 0.00%
SCHEDULE OF MATERIAL SUBMITTALSPROJECT NUMBERPROJECT TITLESOLICITATION/CONTRACT NUMBER
MAHG 21-1009REPLACE AHU’S AND VAV’S IN NPS DORMS PH-1 BLDGS 6950 AND 7404FA301024R0008 - Attachment 4
TO BE COMPLETED BY PROJECT ENGINEERTO BE COMPLETED BY CONTRACT ADMINISTRATOR
LINE NUMBERITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL

*INDICATES ITEMS THAT REQUIRE ENGINEER OF RECORD REVIEW

'CB' INDICATES ITEMS THAT ARE REQUIRED ON THE COLOR BINDER SUBMITTAL

See SOW Section VIII for detailed requirements.REQUIRED INDICATED BY "X"
Shop Drawings/Plans/FormsProduct DataColor SelectionSamplesDesign DataTest ReportsCertificatesManufacturer's InstructionsManufacturer's WarrantyOperation and Maintenance DataCloseout SubmittalsREQUIRED SUBMISSION DATEDATE RECEIVED IN CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERDATE CONTRACTOR NOTIFIEDCONTRACTOR RESUBMITTALFINAL APPROVALREMARKS
GENERALAPPROVEDDISAPPROVED
Column2Column1
G1WORK CLEARANCE REQUEST (AF FORM 103)XPh 1 NTP+10 DAYS
G2*AS-BUILT DATAXFINAL + 21 Days
G3CONSTRUCTION PROGRESS SCHEDULEXPh 1 NTP+ 3 DAYS
G4INITIAL PROJECT SCHEDULEXPh 1 NTP+ 10 DAYS
G5TESTING LABORATORY IDENTIFICATIONX95% Design + 10 days
G6WARRANTIESX10 DAYS BEFORE Final
G7OPERATION AND MAINTENANCE MANUALSX10 DAYS BEFORE Final
G8PROJECT SPECIFIC SAFETY PLANXPh 1 NTP+20 DAYS
G9*65% DESIGNSEE SCHEDULE
G10*95% DESIGNSEE SCHEDULE
G11*100% DESIGNSEE SCHEDULE
G12DRAFT DD FORM1354X95% Design
G13INTERIM DDFORM 1354XUpon request of Pre-Final Inspection
G14FINAL DD FORM1354XFINAL + 30 Days
G15PRE-CONSTRUCTION PHOTOSXPH 1 NTP + 10 Days
G16POST-CONSTRUCTION PHOTOSXFINAL + 21 Days
G17CONSTRUCTION GANTT CHARTXPH 1 NTP + 10 Days
G18QUALITY CONTROL PLANXPH 1 NTP + 10 Days
G19DRAFT PROJECT SCHEDULEX5 DAYS BEFORE PRECON
G19TEMPORARY AIRFIELD CONSTRUCTION WAIVER (APPLICATION WITH SUPPORTING DOCUMENTATION)

: CATIZONE, GAGE CTR AMC 6 CES/CENME:

Use ONLY if work is on or adjacent to airfield.X65% Design + 5 Days
G20FAA OBSTRUCTION EVALUATION (APPLICATION WITH SUPPORTING DOCUMENTATION)

: Author:

Use ONLY if FAA Evaluation is required. May be required on the flightline or for work requiring cranes in close proximity to flightline.X65% Design + 5 Days
G21RESTRICTED/CONTROLLED AREA FREE ZONE (APPLICATION WITH SUPPORTING DOCUMENTATION)

: Author:

Use ONLY if Free Zone is required, primarily airfield work.

: CATIZONE, GAGE CTR AMC 6 CES/CENME:

Use ONLY if work is on or adjacent to airfield. X 60 Days prior to PH 2 Start

MSS ENVIRONMENTAL

STATUS0 complete of 39 for a total percentage complete of 0.00%
SCHEDULE OF MATERIAL SUBMITTALSPROJECT NUMBERPROJECT TITLESOLICITATION/CONTRACT NUMBER
MAHG 21-1009REPLACE AHU’S AND VAV’S IN NPS DORMS PH-1 BLDGS 6950 AND 7404
TO BE COMPLETED BY PROJECT ENGINEER
LINE NUMBERITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL

*INDICATES ITEMS THAT REQUIRE ENGINEER OF RECORD REVIEW

'CB' INDICATES ITEMS THAT ARE REQUIRED ON THE COLOR BINDER SUBMITTAL

See SOW Section VIII for detailed requirements.REQUIRED INDICATED BY "X"
Shop Drawings/Plans/FormsProduct DataColor SelectionSamplesDesign DataTest ReportsCertificatesManufacturer's InstructionsManufacturer's WarrantyOperation and Maintenance DataCloseout SubmittalsREQUIRED SUBMISSION DATEDATE RECEIVED IN CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERDATE CONTRACTOR NOTIFIEDCONTRACTOR RESUBMITTALFINAL APPROVALREMARKS
ENVIRONMENTALAPPROVEDDISAPPROVED
Column2Column1
V1CONTRACTOR HAZARDOUS MATERIALS USAGE TRACKING FORM AND SDS SHEETS FOR NON-EXEMPT HAZMATX95% Design + 10 days
V2GREEN PROCUREMENT COMPLIANCE FOR FINISHING MATERIALSXNTP Ph 2 + 10 Days
V3CONSTRUCTION AND DEMOLITION DEBRIS TRACKING FORMX50% Construction Complete Stage
V4CONSTRUCTION AND DEMOLITION DEBRIS TRACKING FORMX100% Construction Complete Stage
V5ASBESTOS NESHAP SURVEY AND LEAD-BASED PAINT SCREENING RESULTS

: Author:

Required for projects where asestos containing material or suspect material is presentX65% DESIGN
V6ASBESTOS RENOVATION OR DEMOLITION NOTIFICATION FORM

: Author:

Required for all facility demolition projects; and for any renovation projects that involve asbestos containing materialsX95% Design + 10 days
V7POST ABATEMENT REPORT

: Author:

Required for all projects where asbestos removal/abatement is requiredX10 DAY AFTER ABATEMENT
V8CONTRACTOR UNINTERRUPTIBLE POWER SUPPLY (UPS) TRACKING FORM

: Author:

Required for any project that involves installation of a UPSX100% Construction Complete Stage
V9GENSET/FIRE PUMP PRODUCT DATA/TECHNICAL SPECIFICATION SHEETS

: Author:

Required for any project that involves installation of an internal combustion engine.X65% DESIGN
V10ENGINE PERFORMANCE DATA SPECIFICATIONS WITH CERTIFIED EMISSION DATA

: Author:

Required for any project that involves installation of an internal combustion engine.X65% DESIGN
V11DOCUMENTATION THAT THE ENGINE CONTROLS INCLUDE A NON-RESETABLE HOUR METER

: Author:

Required for any project that involves installation of an internal combustion engine.X65% DESIGN
V12USEPA CERTIFICATE OF CONFORMITY FOR INTERNAL COMBUSTION ENGINE

: Author:

Required for any project that involves installation of an internal combustion engine.XX65% DESIGN
V13*PERMIT APPLICATION AND FEE - AIR CONSTRUCTIONXX65% DESIGN
V14VISIBLE EMISSIONS TEST (METHOD 9) AND COMPLIANCE REPORT

: Author:

Must be completed after installation - a requirement for Air Operating PermitX10 DAYS PRIOR TO FINAL INSPECTION
V15*PERMIT APPLICATION AND FEE - AIR OPERATINGXX10 DAYS PRIOR TO FINAL INSPECTION
V16POL STORAGE TANK APPLICATION AND SUPPORTING DOCUMENTATION

: Author:

Required for the installation of any POL storage tank >550 gallons in capacityX65% DESIGN
V17POL STORAGE TANK APPROVED PERMIT, INCLUDING RESPONSES TO REGULATOR COMMENTSX95% DESIGN
V18POL STORAGE TANK FINAL INSPECTION (TEST RESULTS)

: Author:

Inspection by County, to include review of test results must be completed for generator to be operatedXXXPRIOR TO FINAL INSPECTION
V19REFRIGERANTS SUBMITTAL FORM

: Author:

Required for any projects that remove or replace refridgerant (eg HVAC repair)XX100% Construction Complete Stage
V20*SWFWMD (STORMWATER) PERMIT APPLICATION AND SUPPORTING DOCUMENTATION

: Author:

Required for any projects that add/increase impervious surfaces (eg. parking lots, buildings, roadways).X65% DESIGN
V21SWFWMD (STORMWATER) APPROVED PERMIT, INCLUDING RESPONSES TO REGULATOR COMMENTSX95% DESIGN
V22*SWFWMD CERTIFICATE OF COMPLETION (REDLINE AS-BUILTS)

: Author:

Required to close out SWFWMD permit. Some type a as-builts are required, and must be signed by EORXXXPRIOR TO FINAL INSPECTION
V23*HCEPC (WASTEWATER) PERMIT APPLICATION AND SUPPORTING DOCUMENTATION

: Author:

Required for projects that install or replace lift stations or sewer mains.X65% DESIGN
V24HCEPC (WASTEWATER) APPROVED PERMIT, INCLUDING RESPONSES TO REGULATOR COMMENTSX95% DESIGN
V25*HCEPC (WASTEWATER) CLEARANCE (TEST RESULTS, AS-BUILTS)

: Author:

Testing of system and preparation of as-builts (even if redlines) required to close out WW permitsXXPRIOR TO FINAL INSPECTION
V26*TAMPA PORT AUTHORITY PERMIT (IN WATER WORK) APPLICATION AND SUPPORTING DOCUMENTATION

: Author:

Required for projects that disturb the bay bottom.X65% DESIGN
V27TAMPA PORT AUTHORITY APPROVED PERMIT (IN WATER WORK), INCLUDING RESPONSES TO REGULATOR COMMENTSX95% DESIGN
V28*USACE/FDEP (WETLANDS) PERMIT APPLICATION AND SUPPORTING DOCUMENTATION

: Author:

Required for projects that disturb wetlandsX65% DESIGN
V29USACE/FDEP (WETLANDS) APPROVED PERMIT, INCLUDING RESPONSES TO REGULATOR COMMENTSX95% DESIGN
V30*HCEPC (WETLANDS) PERMIT APPLICATION AND SUPPORTING DOCUMENTATION

: Author:

Required for projects that disturb wetlandsX65% DESIGN
V31HCEPC (WETLANDS) APPROVED PERMIT, INCLUDING RESPONSES TO REGULATOR COMMENTSX95% DESIGN
V32*SWFWMD (WETLANDS) PERMIT APPLICATION AND SUPPORTING DOCUMENTATION

: Author:

Required for projects that disturb wetlandsX65% DESIGN
V33SWFWMD (WETLANDS) APPROVED PERMIT, INCLUDING RESPONSES TO REGULATOR COMMENTSX95% DESIGN
V34NPDES PERMIT APPLICATION AND SUPPORTING DOCUMENTATION

: Author:

Required for projects that disturb 1 acre of land or more. Contractor will secure this permit.X65% DESIGN
V35NPDES APPROVED PERMIT, INCLUDING RESPONSES TO REGULATOR COMMENTSX95% DESIGN
V36*DEPT OF HEALTH (DRINKING WATER) PERMIT APPLICATION AND SUPPORTING DOCUMENTATION

: Author:

Required for projects installing potable water mains or lateral lines >2-inches in diameter : Author:

Required for projects where asestos containing material or suspect material is present : Author:

Required for all facility demolition projects; and for any renovation projects that involve asbestos containing materialsX65% DESIGN
V37DEPT OF HEALTH (DRINKING WATER) APPROVED PERMIT, INCLUDING RESPONSES TO REGULATOR COMMENTSX95% DESIGN
V38*DEPT OF HEALTH (DRINKING WATER) CLEARANCE (TEST RESULTS, AS-BUILTS)

: Author:

Bac-T results and as-built drawings are required as part of permit close-out documents : Author:

Required for all projects where asbestos removal/abatement is requiredXXXPRIOR TO FINAL INSPECTION
V39SHPO CONSULTATION DESIGN DOCUMENTS

: Author:

Required for projects involving historic buildings. CEIE will prepare consultation letters but requires design details including facility elevation drawings to complete consultation letters. Project cannot begin construction until SHPO approval is received.

: Author:

Required for any project that involves installation of a UPS : Author:

Required for any project that involves installation of an internal combustion engine.

: Author:

Required for any project that involves installation of an internal combustion engine.

: Author:

Required for any project that involves installation of an internal combustion engine.

: Author:

Required for any project that involves installation of an internal combustion engine.

: Author:

Must be completed after installation - a requirement for Air Operating Permit : Author:

Required for the installation of any POL storage tank >550 gallons in capacity : Author:

Inspection by County, to include review of test results must be completed for generator to be operated : Author:

Required for any projects that remove or replace refridgerant (eg HVAC repair) : Author:

Required for any projects that add/increase impervious surfaces (eg. parking lots, buildings, roadways). X X 65% DESIGN + 10 DAYS

AF66 MECHANICAL

STATUS0 complete of 20 for a total percentage complete of 0.00%
SCHEDULE OF MATERIAL SUBMITTALSPROJECT NUMBERPROJECT TITLESOLICITATION/CONTRACT NUMBER
MAHG 21-1009REPLACE AHU’S AND VAV’S IN NPS DORMS PH-1 BLDGS 6950 AND 7404
TO BE COMPLETED BY PROJECT ENGINEERTO BE COMPLETED BY CONTRACT ADMINISTRATOR
LINE NUMBERITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL

*INDICATES ITEMS THAT REQUIRE ENGINEER OF RECORD REVIEW

'CB' INDICATES ITEMS THAT ARE REQUIRED ON THE COLOR BINDER SUBMITTAL

See SOW Section VIII for detailed requirements.REQUIRED INDICATED BY "X"
Shop Drawings/Plans/FormsProduct DataColor SelectionSamplesDesign DataTest ReportsCertificatesManufacturer's InstructionsManufacturer's WarrantyOperation and Maintenance DataCloseout SubmittalsREQUIRED SUBMISSION DATEDATE RECEIVED IN CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERDATE CONTRACTOR NOTIFIEDCONTRACTOR RESUBMITTALFINAL APPROVALREMARKS
MECHANICALAPPROVEDDISAPPROVED
Column2Column1
M1*T & B CERTIFICATION*XXX95% DESIGN + 10 DAYS
M2*DUCT WORK, DUCT INSULATION AND DUCT SEALANTS AND ACCESSORIES*XXXX95% DESIGN + 10 DAYS
M3*DUCT ACCESS DOORS*XXXX95% DESIGN + 10 DAYS
M4*VAV BOXES WITH REHEAT COILS*XXXXXXX95% DESIGN + 10 DAYS
M5*CONTROLSXXXXXXX95% DESIGN + 10 DAYS
M6*AIR HANDLERS, FAN COIL UNITS AND ASSOCIATED COMPONENTS (THERMOSTATS, ETC)*XXXXXX95% DESIGN + 10 DAYS
M7*CONDENSATE PIPING*XXXX95% DESIGN + 10 DAYS
M8*CALCULATIONS: OUTSIDE AIR, HEATING/COOLING LOAD, BUILDING PRESSURIZATION, SPACE AIR BALANCE CRITERIA*XXWITH 65% DESIGN
M9*DUCT LEAKAGE TESTINGXPRIOR TO INSULATION
M10*START UP & TESTING OF HVAC SYSTEMS, CONTROLS,*XXX15 DAYS BEFORE PRE-FINAL INSPECTION
M11*T & B REPORT*XX10 DAYS BEFORE PRE-FINAL INSPECTION
M12*COMMISSIONING AGENT CERTIFICATIONXWITH 65% DESIGN
M20*CONTROLS COMMISSIONING NARRATIVE*XWITH 65% DESIGN
M21*CONTROLS COMMISSIONING PLAN*XX95% DESIGN + 10 DAYS
M13*COMMISSIONING REPORT*XX5 DAYS BEFORE FINAL INSPECTION
CHILLED WATER AND HOT WATER SYSTEMS
M14*CHILLED WATER PIPING, FITTINGS AND INSULATION*XXX95% DESIGN + 10 DAYS
M15*HOT WATER PIPING AND FITTINGS*XXX95% DESIGN + 10 DAYS
SITE INSPECTION
M16*SIGNED SITE VISIT FIELD NOTESXXX65% DESIGN + 10 DAYS

File details come from the government source that posted it. Updated .