Attachment 4 - MAHG211009 - Appendix C - MSS .xlsx
XLSX spreadsheet 43 KB Posted
- Solicitation number
- MAHG211009
About this file
This document is an attachment related to a federal contract opportunity for replacing Air Handling Units (AHUs) and Variable Air Volume (VAV) units in dormitory buildings at Keesler Air Force Base. The attachment contains a detailed schedule of material submittals required for the project, including items such as shop drawings, product data, samples, test reports, operations and maintenance data, and closeout submittals across mechanical, environmental, and general categories. The required submission dates, review/approval process, and remarks are provided for each submittal item.
The related federal contract opportunity has a solicitation number of MAHG211009 and a total estimated value between $5,000,000 and $10,000,000. It is a HUBZone set-aside acquisition issued by the Department of the Air Force Air Education and Training Command. The project involves replacing AHUs and VAVs in Phase 1 of the dormitory replacement work at Keesler AFB in Mississippi. An organized site visit is scheduled for August 1, 2024, and proposal preparation instructions are provided in Sections L and M of the solicitation.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MSS GENERAL
| STATUS | 0 complete of 22 for a total percentage complete of 0.00% | |||
| SCHEDULE OF MATERIAL SUBMITTALS | PROJECT NUMBER | PROJECT TITLE | SOLICITATION/CONTRACT NUMBER | |
| MAHG 21-1009 | REPLACE AHU’S AND VAV’S IN NPS DORMS PH-1 BLDGS 6950 AND 7404 | FA301024R0008 - Attachment 4 | ||
| TO BE COMPLETED BY PROJECT ENGINEER | TO BE COMPLETED BY CONTRACT ADMINISTRATOR | |||
| LINE NUMBER | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL |
*INDICATES ITEMS THAT REQUIRE ENGINEER OF RECORD REVIEW
'CB' INDICATES ITEMS THAT ARE REQUIRED ON THE COLOR BINDER SUBMITTAL
| See SOW Section VIII for detailed requirements. | REQUIRED INDICATED BY "X" | ||||||||||||||||||||||||
| Shop Drawings/Plans/Forms | Product Data | Color Selection | Samples | Design Data | Test Reports | Certificates | Manufacturer's Instructions | Manufacturer's Warranty | Operation and Maintenance Data | Closeout Submittals | REQUIRED SUBMISSION DATE | DATE RECEIVED IN CONTRACTING | DATE TO CIVIL ENGINEERING | RETURN SUSPENSE DATE | SUBMITTAL NUMBER | DATE CONTRACTOR NOTIFIED | CONTRACTOR RESUBMITTAL | FINAL APPROVAL | REMARKS | ||||||
| GENERAL | APPROVED | DISAPPROVED | |||||||||||||||||||||||
| Column2 | Column1 | ||||||||||||||||||||||||
| G1 | WORK CLEARANCE REQUEST (AF FORM 103) | X | Ph 1 NTP+10 DAYS | ||||||||||||||||||||||
| G2* | AS-BUILT DATA | X | FINAL + 21 Days | ||||||||||||||||||||||
| G3 | CONSTRUCTION PROGRESS SCHEDULE | X | Ph 1 NTP+ 3 DAYS | ||||||||||||||||||||||
| G4 | INITIAL PROJECT SCHEDULE | X | Ph 1 NTP+ 10 DAYS | ||||||||||||||||||||||
| G5 | TESTING LABORATORY IDENTIFICATION | X | 95% Design + 10 days | ||||||||||||||||||||||
| G6 | WARRANTIES | X | 10 DAYS BEFORE Final | ||||||||||||||||||||||
| G7 | OPERATION AND MAINTENANCE MANUALS | X | 10 DAYS BEFORE Final | ||||||||||||||||||||||
| G8 | PROJECT SPECIFIC SAFETY PLAN | X | Ph 1 NTP+20 DAYS | ||||||||||||||||||||||
| G9* | 65% DESIGN | SEE SCHEDULE | |||||||||||||||||||||||
| G10* | 95% DESIGN | SEE SCHEDULE | |||||||||||||||||||||||
| G11* | 100% DESIGN | SEE SCHEDULE | |||||||||||||||||||||||
| G12 | DRAFT DD FORM1354 | X | 95% Design | ||||||||||||||||||||||
| G13 | INTERIM DDFORM 1354 | X | Upon request of Pre-Final Inspection | ||||||||||||||||||||||
| G14 | FINAL DD FORM1354 | X | FINAL + 30 Days | ||||||||||||||||||||||
| G15 | PRE-CONSTRUCTION PHOTOS | X | PH 1 NTP + 10 Days | ||||||||||||||||||||||
| G16 | POST-CONSTRUCTION PHOTOS | X | FINAL + 21 Days | ||||||||||||||||||||||
| G17 | CONSTRUCTION GANTT CHART | X | PH 1 NTP + 10 Days | ||||||||||||||||||||||
| G18 | QUALITY CONTROL PLAN | X | PH 1 NTP + 10 Days | ||||||||||||||||||||||
| G19 | DRAFT PROJECT SCHEDULE | X | 5 DAYS BEFORE PRECON | ||||||||||||||||||||||
| G19 | TEMPORARY AIRFIELD CONSTRUCTION WAIVER (APPLICATION WITH SUPPORTING DOCUMENTATION) |
: CATIZONE, GAGE CTR AMC 6 CES/CENME:
| Use ONLY if work is on or adjacent to airfield. | X | 65% Design + 5 Days | ||
| G20 | FAA OBSTRUCTION EVALUATION (APPLICATION WITH SUPPORTING DOCUMENTATION) |
: Author:
| Use ONLY if FAA Evaluation is required. May be required on the flightline or for work requiring cranes in close proximity to flightline. | X | 65% Design + 5 Days | ||
| G21 | RESTRICTED/CONTROLLED AREA FREE ZONE (APPLICATION WITH SUPPORTING DOCUMENTATION) |
: Author:
Use ONLY if Free Zone is required, primarily airfield work.
: CATIZONE, GAGE CTR AMC 6 CES/CENME:
Use ONLY if work is on or adjacent to airfield. X 60 Days prior to PH 2 Start
MSS ENVIRONMENTAL
| STATUS | 0 complete of 39 for a total percentage complete of 0.00% | |||
| SCHEDULE OF MATERIAL SUBMITTALS | PROJECT NUMBER | PROJECT TITLE | SOLICITATION/CONTRACT NUMBER | |
| MAHG 21-1009 | REPLACE AHU’S AND VAV’S IN NPS DORMS PH-1 BLDGS 6950 AND 7404 | |||
| TO BE COMPLETED BY PROJECT ENGINEER | ||||
| LINE NUMBER | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL |
*INDICATES ITEMS THAT REQUIRE ENGINEER OF RECORD REVIEW
'CB' INDICATES ITEMS THAT ARE REQUIRED ON THE COLOR BINDER SUBMITTAL
| See SOW Section VIII for detailed requirements. | REQUIRED INDICATED BY "X" | ||||||||||||||||||||||||
| Shop Drawings/Plans/Forms | Product Data | Color Selection | Samples | Design Data | Test Reports | Certificates | Manufacturer's Instructions | Manufacturer's Warranty | Operation and Maintenance Data | Closeout Submittals | REQUIRED SUBMISSION DATE | DATE RECEIVED IN CONTRACTING | DATE TO CIVIL ENGINEERING | RETURN SUSPENSE DATE | SUBMITTAL NUMBER | DATE CONTRACTOR NOTIFIED | CONTRACTOR RESUBMITTAL | FINAL APPROVAL | REMARKS | ||||||
| ENVIRONMENTAL | APPROVED | DISAPPROVED | |||||||||||||||||||||||
| Column2 | Column1 | ||||||||||||||||||||||||
| V1 | CONTRACTOR HAZARDOUS MATERIALS USAGE TRACKING FORM AND SDS SHEETS FOR NON-EXEMPT HAZMAT | X | 95% Design + 10 days | ||||||||||||||||||||||
| V2 | GREEN PROCUREMENT COMPLIANCE FOR FINISHING MATERIALS | X | NTP Ph 2 + 10 Days | ||||||||||||||||||||||
| V3 | CONSTRUCTION AND DEMOLITION DEBRIS TRACKING FORM | X | 50% Construction Complete Stage | ||||||||||||||||||||||
| V4 | CONSTRUCTION AND DEMOLITION DEBRIS TRACKING FORM | X | 100% Construction Complete Stage | ||||||||||||||||||||||
| V5 | ASBESTOS NESHAP SURVEY AND LEAD-BASED PAINT SCREENING RESULTS |
: Author:
| Required for projects where asestos containing material or suspect material is present | X | 65% DESIGN | ||
| V6 | ASBESTOS RENOVATION OR DEMOLITION NOTIFICATION FORM |
: Author:
| Required for all facility demolition projects; and for any renovation projects that involve asbestos containing materials | X | 95% Design + 10 days | ||
| V7 | POST ABATEMENT REPORT |
: Author:
| Required for all projects where asbestos removal/abatement is required | X | 10 DAY AFTER ABATEMENT | ||
| V8 | CONTRACTOR UNINTERRUPTIBLE POWER SUPPLY (UPS) TRACKING FORM |
: Author:
| Required for any project that involves installation of a UPS | X | 100% Construction Complete Stage | ||
| V9 | GENSET/FIRE PUMP PRODUCT DATA/TECHNICAL SPECIFICATION SHEETS |
: Author:
| Required for any project that involves installation of an internal combustion engine. | X | 65% DESIGN | ||
| V10 | ENGINE PERFORMANCE DATA SPECIFICATIONS WITH CERTIFIED EMISSION DATA |
: Author:
| Required for any project that involves installation of an internal combustion engine. | X | 65% DESIGN | ||
| V11 | DOCUMENTATION THAT THE ENGINE CONTROLS INCLUDE A NON-RESETABLE HOUR METER |
: Author:
| Required for any project that involves installation of an internal combustion engine. | X | 65% DESIGN | ||
| V12 | USEPA CERTIFICATE OF CONFORMITY FOR INTERNAL COMBUSTION ENGINE |
: Author:
| Required for any project that involves installation of an internal combustion engine. | X | X | 65% DESIGN | |||||
| V13* | PERMIT APPLICATION AND FEE - AIR CONSTRUCTION | X | X | 65% DESIGN | ||||
| V14 | VISIBLE EMISSIONS TEST (METHOD 9) AND COMPLIANCE REPORT |
: Author:
| Must be completed after installation - a requirement for Air Operating Permit | X | 10 DAYS PRIOR TO FINAL INSPECTION | |||||
| V15* | PERMIT APPLICATION AND FEE - AIR OPERATING | X | X | 10 DAYS PRIOR TO FINAL INSPECTION | |||
| V16 | POL STORAGE TANK APPLICATION AND SUPPORTING DOCUMENTATION |
: Author:
| Required for the installation of any POL storage tank >550 gallons in capacity | X | 65% DESIGN | ||||
| V17 | POL STORAGE TANK APPROVED PERMIT, INCLUDING RESPONSES TO REGULATOR COMMENTS | X | 95% DESIGN | |||
| V18 | POL STORAGE TANK FINAL INSPECTION (TEST RESULTS) |
: Author:
| Inspection by County, to include review of test results must be completed for generator to be operated | X | X | X | PRIOR TO FINAL INSPECTION | ||
| V19 | REFRIGERANTS SUBMITTAL FORM |
: Author:
| Required for any projects that remove or replace refridgerant (eg HVAC repair) | X | X | 100% Construction Complete Stage | ||
| V20* | SWFWMD (STORMWATER) PERMIT APPLICATION AND SUPPORTING DOCUMENTATION |
: Author:
| Required for any projects that add/increase impervious surfaces (eg. parking lots, buildings, roadways). | X | 65% DESIGN | ||||
| V21 | SWFWMD (STORMWATER) APPROVED PERMIT, INCLUDING RESPONSES TO REGULATOR COMMENTS | X | 95% DESIGN | |||
| V22* | SWFWMD CERTIFICATE OF COMPLETION (REDLINE AS-BUILTS) |
: Author:
| Required to close out SWFWMD permit. Some type a as-builts are required, and must be signed by EOR | X | X | X | PRIOR TO FINAL INSPECTION | ||
| V23* | HCEPC (WASTEWATER) PERMIT APPLICATION AND SUPPORTING DOCUMENTATION |
: Author:
| Required for projects that install or replace lift stations or sewer mains. | X | 65% DESIGN | ||||
| V24 | HCEPC (WASTEWATER) APPROVED PERMIT, INCLUDING RESPONSES TO REGULATOR COMMENTS | X | 95% DESIGN | |||
| V25* | HCEPC (WASTEWATER) CLEARANCE (TEST RESULTS, AS-BUILTS) |
: Author:
| Testing of system and preparation of as-builts (even if redlines) required to close out WW permits | X | X | PRIOR TO FINAL INSPECTION | ||
| V26* | TAMPA PORT AUTHORITY PERMIT (IN WATER WORK) APPLICATION AND SUPPORTING DOCUMENTATION |
: Author:
| Required for projects that disturb the bay bottom. | X | 65% DESIGN | ||||
| V27 | TAMPA PORT AUTHORITY APPROVED PERMIT (IN WATER WORK), INCLUDING RESPONSES TO REGULATOR COMMENTS | X | 95% DESIGN | |||
| V28* | USACE/FDEP (WETLANDS) PERMIT APPLICATION AND SUPPORTING DOCUMENTATION |
: Author:
| Required for projects that disturb wetlands | X | 65% DESIGN | ||||
| V29 | USACE/FDEP (WETLANDS) APPROVED PERMIT, INCLUDING RESPONSES TO REGULATOR COMMENTS | X | 95% DESIGN | |||
| V30* | HCEPC (WETLANDS) PERMIT APPLICATION AND SUPPORTING DOCUMENTATION |
: Author:
| Required for projects that disturb wetlands | X | 65% DESIGN | ||||
| V31 | HCEPC (WETLANDS) APPROVED PERMIT, INCLUDING RESPONSES TO REGULATOR COMMENTS | X | 95% DESIGN | |||
| V32* | SWFWMD (WETLANDS) PERMIT APPLICATION AND SUPPORTING DOCUMENTATION |
: Author:
| Required for projects that disturb wetlands | X | 65% DESIGN | ||||
| V33 | SWFWMD (WETLANDS) APPROVED PERMIT, INCLUDING RESPONSES TO REGULATOR COMMENTS | X | 95% DESIGN | |||
| V34 | NPDES PERMIT APPLICATION AND SUPPORTING DOCUMENTATION |
: Author:
| Required for projects that disturb 1 acre of land or more. Contractor will secure this permit. | X | 65% DESIGN | ||||
| V35 | NPDES APPROVED PERMIT, INCLUDING RESPONSES TO REGULATOR COMMENTS | X | 95% DESIGN | |||
| V36* | DEPT OF HEALTH (DRINKING WATER) PERMIT APPLICATION AND SUPPORTING DOCUMENTATION |
: Author:
Required for projects installing potable water mains or lateral lines >2-inches in diameter : Author:
Required for projects where asestos containing material or suspect material is present : Author:
| Required for all facility demolition projects; and for any renovation projects that involve asbestos containing materials | X | 65% DESIGN | ||||
| V37 | DEPT OF HEALTH (DRINKING WATER) APPROVED PERMIT, INCLUDING RESPONSES TO REGULATOR COMMENTS | X | 95% DESIGN | |||
| V38* | DEPT OF HEALTH (DRINKING WATER) CLEARANCE (TEST RESULTS, AS-BUILTS) |
: Author:
Bac-T results and as-built drawings are required as part of permit close-out documents : Author:
| Required for all projects where asbestos removal/abatement is required | X | X | X | PRIOR TO FINAL INSPECTION | ||
| V39 | SHPO CONSULTATION DESIGN DOCUMENTS |
: Author:
Required for projects involving historic buildings. CEIE will prepare consultation letters but requires design details including facility elevation drawings to complete consultation letters. Project cannot begin construction until SHPO approval is received.
: Author:
Required for any project that involves installation of a UPS : Author:
Required for any project that involves installation of an internal combustion engine.
: Author:
Required for any project that involves installation of an internal combustion engine.
: Author:
Required for any project that involves installation of an internal combustion engine.
: Author:
Required for any project that involves installation of an internal combustion engine.
: Author:
Must be completed after installation - a requirement for Air Operating Permit : Author:
Required for the installation of any POL storage tank >550 gallons in capacity : Author:
Inspection by County, to include review of test results must be completed for generator to be operated : Author:
Required for any projects that remove or replace refridgerant (eg HVAC repair) : Author:
Required for any projects that add/increase impervious surfaces (eg. parking lots, buildings, roadways). X X 65% DESIGN + 10 DAYS
AF66 MECHANICAL
| STATUS | 0 complete of 20 for a total percentage complete of 0.00% | |||
| SCHEDULE OF MATERIAL SUBMITTALS | PROJECT NUMBER | PROJECT TITLE | SOLICITATION/CONTRACT NUMBER | |
| MAHG 21-1009 | REPLACE AHU’S AND VAV’S IN NPS DORMS PH-1 BLDGS 6950 AND 7404 | |||
| TO BE COMPLETED BY PROJECT ENGINEER | TO BE COMPLETED BY CONTRACT ADMINISTRATOR | |||
| LINE NUMBER | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL |
*INDICATES ITEMS THAT REQUIRE ENGINEER OF RECORD REVIEW
'CB' INDICATES ITEMS THAT ARE REQUIRED ON THE COLOR BINDER SUBMITTAL
| See SOW Section VIII for detailed requirements. | REQUIRED INDICATED BY "X" | ||||||||||||||||||||||||
| Shop Drawings/Plans/Forms | Product Data | Color Selection | Samples | Design Data | Test Reports | Certificates | Manufacturer's Instructions | Manufacturer's Warranty | Operation and Maintenance Data | Closeout Submittals | REQUIRED SUBMISSION DATE | DATE RECEIVED IN CONTRACTING | DATE TO CIVIL ENGINEERING | RETURN SUSPENSE DATE | SUBMITTAL NUMBER | DATE CONTRACTOR NOTIFIED | CONTRACTOR RESUBMITTAL | FINAL APPROVAL | REMARKS | ||||||
| MECHANICAL | APPROVED | DISAPPROVED | |||||||||||||||||||||||
| Column2 | Column1 | ||||||||||||||||||||||||
| M1* | T & B CERTIFICATION* | X | X | X | 95% DESIGN + 10 DAYS | ||||||||||||||||||||
| M2* | DUCT WORK, DUCT INSULATION AND DUCT SEALANTS AND ACCESSORIES* | X | X | X | X | 95% DESIGN + 10 DAYS | |||||||||||||||||||
| M3* | DUCT ACCESS DOORS* | X | X | X | X | 95% DESIGN + 10 DAYS | |||||||||||||||||||
| M4* | VAV BOXES WITH REHEAT COILS* | X | X | X | X | X | X | X | 95% DESIGN + 10 DAYS | ||||||||||||||||
| M5* | CONTROLS | X | X | X | X | X | X | X | 95% DESIGN + 10 DAYS | ||||||||||||||||
| M6* | AIR HANDLERS, FAN COIL UNITS AND ASSOCIATED COMPONENTS (THERMOSTATS, ETC)* | X | X | X | X | X | X | 95% DESIGN + 10 DAYS | |||||||||||||||||
| M7* | CONDENSATE PIPING* | X | X | X | X | 95% DESIGN + 10 DAYS | |||||||||||||||||||
| M8* | CALCULATIONS: OUTSIDE AIR, HEATING/COOLING LOAD, BUILDING PRESSURIZATION, SPACE AIR BALANCE CRITERIA* | X | X | WITH 65% DESIGN | |||||||||||||||||||||
| M9* | DUCT LEAKAGE TESTING | X | PRIOR TO INSULATION | ||||||||||||||||||||||
| M10* | START UP & TESTING OF HVAC SYSTEMS, CONTROLS,* | X | X | X | 15 DAYS BEFORE PRE-FINAL INSPECTION | ||||||||||||||||||||
| M11* | T & B REPORT* | X | X | 10 DAYS BEFORE PRE-FINAL INSPECTION | |||||||||||||||||||||
| M12* | COMMISSIONING AGENT CERTIFICATION | X | WITH 65% DESIGN | ||||||||||||||||||||||
| M20* | CONTROLS COMMISSIONING NARRATIVE* | X | WITH 65% DESIGN | ||||||||||||||||||||||
| M21* | CONTROLS COMMISSIONING PLAN* | X | X | 95% DESIGN + 10 DAYS | |||||||||||||||||||||
| M13* | COMMISSIONING REPORT* | X | X | 5 DAYS BEFORE FINAL INSPECTION | |||||||||||||||||||||
| CHILLED WATER AND HOT WATER SYSTEMS | |||||||||||||||||||||||||
| M14* | CHILLED WATER PIPING, FITTINGS AND INSULATION* | X | X | X | 95% DESIGN + 10 DAYS | ||||||||||||||||||||
| M15* | HOT WATER PIPING AND FITTINGS* | X | X | X | 95% DESIGN + 10 DAYS | ||||||||||||||||||||
| SITE INSPECTION | |||||||||||||||||||||||||
| M16* | SIGNED SITE VISIT FIELD NOTES | X | X | X | 65% DESIGN + 10 DAYS |