This document is a preventive maintenance schedule from Modula Inc. detailing different maintenance levels required for their Vertical Lift Module systems.
The maintenance program consists of four levels: Level 1 requires annual maintenance to be performed by Certified Technicians at least once per year or before 15,000 missions, involving routine inspections, calibration, lubrication, and adjustments. Levels 2-4 involve specific parts replacement at different mission intervals: Level 2 (every 30,000 missions) requires replacement of sprockets, chains, pawls, guides, and door parts; Level 3 (every 45,000 missions) requires replacement of wheel-tubes and external bay slides; and Level 4 (every 150,000 missions) requires replacement of vertical belt, vertical pulleys, vertical E-Chain, cradle movement cables, motors, and gear motors. The document appears to be part of a Defense Logistics Agency Distribution solicitation (SP3300-25-Q-0030) for maintenance services on Modula equipment.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 0002.pdf | ||
| Amendment 0001.pdf | ||
| Attachment 9 - DL1818 Visitor Notification Form.pdf | ||
| Attachment 14 - QASP_ DDRV.docx | DOCX document | |
| CSS.pdf | ||
| Attachment 1 - Schedule of Services.xlsx | XLSX spreadsheet | |
| Attachment 3 - Equipment List.pdf | ||
| Attachment 7 - DL0584 Visitor Register Form.pdf | ||
| Attachment 6 - DD2875 System Authorization Access Request.pdf | ||
| Attachment 8 - DL1591 Supervisor Mishap Report.pdf | ||
| Attachment 10 - TE 1.1 Contractor Personnel Sec.pdf | ||
| Attachment 11 - TE_1.2_CAC_Procedures.pdf | ||
| Attachment 12 - QASP - CAP - VLM Maint.pdf | ||
| Attachment 13 - QASP - COSR - VLM Maint.pdf | ||
| Attachment 2 - PWS.pdf | ||
| Attachment 5 - Wage Determination No 2015-4331 Rev 29 dtd 12.23.2024.pdf |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PREVENTIVE MAINTENANCE LEVELS
Annual LVL 1 PM Maintenance The Scheduled LVL 1 Maintenance recommended by MODULA INC must be performed at least ONE a YEAR and not beyond No. 15,000 Missions.
During the LVL 1 PM the Certified Technicians will perform all routine inspections, calibration, lubrication, and adjustment activities to ensure the proper operation and increase the longevity of the machines.
Level 2,3,4 - PM parts replacement
The Maintenance KIT replacement program is design to ensure to the machine the proper operation during the years and to max its longevity, replacing some consumable parts at certain time.
• PM LVL 2 Every 30,000 missions (Replace Sprocket, Chains, Pawls, Guides, and Door parts if it is present)
• PM LVL 3 Every 45,000 missions (Replace Wheel-tubes, and external bay slides if an EB is present)
• PM LVL 4 Every 150,000 missions (Replace Vertical Belt, Vertical Pulleys, Vertical E-Chain, Cradle Movement
Cables, Motors, Gear motors)